Professional Documents
Culture Documents
Contract documentation
Contract documentation
Contract documentation
0 CONTRACT DOCUMENTATION
A construction contract is a mutual and legally binding agreement between a building contractor
and a client based on certain policies and conditions generally recorded in documentation form in
a contract document. The roles of each party in the contract are also highlighted in the contract
document.
Key Parties involved in Contract
• Client/Employer
• Architect
• Contractor
• Subcontractor
• Engineer
• Manufacturer of Materials
• Project Financiers.
Client/Employer
The person named as the employer in the appendix to tender and the legal successor in tittle to
this person.
Contractor
Person(s) named as Contractor in the letter of Tender accepted by the employer and the legal
successor in tittle to this person(s).
Subcontractor
Any person (s) named in the contract as a subcontractor or any person appointed as a
subcontractor for a part of the works and the legal successor in tittle to each of these people
Engineer
Person appointed by the employer to act as the Engineer for the purposes of the Contract and
named in the Appendix to Tender or other person appointed from time to time by the Employer
and notified to the Contractor.
Architect
Architect is a person appointed by the client, who develops a facility as per the design concept
and the requirements specified by the client.
Project Financiers
An entity that provides funding for long-term infrastructure, industrial projects, and public
services using a non-recourse or limited recourse financial structure. Eg. Government of Kenya,
ADB, JICA, World Bank, etc
• Government funding
• Grants
• Bonds
• Public Private partnerships
Manufacturer of Materials
Material manufacturers are mainly companies that manufacture various materials/components
and employment is based on the engineer’s knowledge of the qualities, performance and uses of
the building materials.
Specification: This amplifies the information given in the contract drawings and bill of
quantities, and describes in detail the work to be executed under the contract and the nature and
quality of the materials, components and workmanship.
Bill of Quantities: This consists of a schedule of items of work to be carried out under the
contract with quantities entered against each item, prepared in accordance with the Standard
Method of Measurement of Building Works (refer to SMM7).
Contract Drawings: These depict the details and scope of the works to be executed under the
contract. They must be prepared in sufficient detail to enable the contractor to satisfactorily price
the bill of quantities.
Organization of General Building Project
Organization of General Civil Engineering Project
Roles of Client/Employer
i. Giving right of access to site to the contractor and possession of all parts of the site
within the contract period.
ii. Shall provide assistance (whenever in a position to do so) to the contractor to obtain
permits, licences, and approvals.
iii. Assistance in delivery of goods and clearance through customs.
iv. Export of contractor’s equipment when removed from site.
v. Ensuring employers personnel cooperate with the contractor.
vi. Facilitate payment to the contractor.
vii. Giving notices to the contractor regarding any claims that he feels entitled to.
Roles of Engineer
i. Shall act on behalf of the employer
ii. Approve materials and plant.
iii. Approve contractors site superintendence unless otherwise stated in the contract.
iv. Issue instructions to the contractor.
v. Checking and review of payment certificates.
vi. Inspection and approval of completed works sections.
vii. Issuance of notices to the contractor.
viii. Request for any relevant tests for materials used for works as he/she deems fit.
ix. Provision of and modification of drawings.
General roles include;
Contractor shall make no alterations in design, scope, or methodology without notifying the
Engineer
Roles of Nominated Subcontractors
Nominated subcontractor is a subcontractor whom the contractor has been instructed by the
engineer to employ as a subcontractor.
• Roles similar to the contractor except that they don’t report directly to the employer and
have specified works which is a portion of the contractor’s scope.
Roles of Material Manufacturers
i. Research and development on ways to improve the material in view of the conditions or
to come up with other uses of the materials in order to increase the market.
ii. Testing of the material-this will be to guarantee the quality of the material and to ensure
that it meets the local and international standard.
iii. Supply to contractors.
Roles of Architect
• Extension of time (EOT) for work delays caused by the employer or his representative
• Financial claim (Payment of cost incurred plus reasonable profit)
Failure of the employer to give the contractor possession of site within the stipulated time in the
contract. eg. 14 dyas after order to commence.
Delay or cost implications due to errors that arise as a fault of the employer and an experienced
contractor could not possibly have discovered such error.
Cause of delays that warranty EOT
i. Variation—Change of quantity of an item of work.
ii. Adverse climatic conditions
iii. Unforeseeable shortages in availability of personnel or material caused by epidemic or
government actions.
iv. Any delay attributable to the employers such as
• Failure of the employer to give the contractor possession of site within the
stipulated time in the contract. eg. 14 dyas after order to commence.
• Delay or cost implications due to errors that arise as a fault of the employer and
an experienced contractor could not possibly have discovered such error.
• Suspension of works
Suspension of Work
The contractor or the employer can suspend works.
Engineer may suspend part or all works through a notification to the contractor.
Consequences of Suspension of works by the employer
Generally the contract will set out what those breaches are, but they might include:
Contracts may allow party open to significant claims by the other party in case of breech.
Termination for convenience is only provided for in some forms of contract, and is often only
available to the client.
5.0 TERMINATION BY EMPLOYER
i. Abandons site
ii. Subcontracts the whole of the works without prior agreement
iii. Becomes bankrupt
iv. Gives or offers to give bribe, gift, commission, as an inducement or reward.