DAILY REPORT 0
Owner: Columbia SM Ltd 18.06.2024 Date:
m/v Name: CAPE FERROL 9359325 IMO:
Engine Maker: STX MAN 7L23/30H Engine Type:
Engine Number: DG2 SB7L23-6344 Engine Serial №:

PERSONEL & WORKING HOUR


Name Position Working Hours Over time Travel/Waiting
Huvir Valentyn Service Engineer 10
Protsenko Valerii Technician 10
0 Technician

SCOPE OF WORK (intermediate overhaul 16000 hours) DAY 9

1. All high-pressure fuel injection pumps were disassembled, and all parts were cleaned.

2. All rocker arms were disassembled, and clearance between the shaft and bushes was measured. The measurements are
attached in a separate table.

1/2 Designed by Technical Department


S.M.RAPIDTECH LTD
A.G. Leventi, 5 Company code:
The Leventis Gallery VAT code: 60014411F
Tower, 13th Floor, service@rapidtech-marine.com
Office 1301, 1097 www.rapidthech-marine.com
Nicosia, Cyprus Tel. +35799875892
DAILY REPORT 0
Owner: Columbia SM Ltd 18.06.2024 Date:
m/v Name: CAPE FERROL 9359325 IMO:
Engine Maker: STX MAN 7L23/30H Engine Type:
Engine Number: DG2 SB7L23-6344 Engine Serial №:

3. All high-pressure fuel injection pumps were overhauled and installed. O-rings, barrels, and plungers IMO 36.02 were replaced.

Note: Since the injector test machine on board is out of order, the injectors will be installed as they are without overhauling.
This can cause deviation during the performance test, similar to what occurred during the initial performance test before the
overhaul.
Job plan for: 19.06.2024
• Installing rocker arms.
• Adjusting tappet clearance.
• Tightening connecting rod studs.