REKAPITULASI

RENCANA ANGGARAN BIAYA (RAB)


KEGIATAN : PENGINAPAN
LOKASI : BLORA , JAWA TENGAH

NO. URAIAN PEKERJAAN JUMLAH HARGA

A PERSIAPAN Rp. 97.925.705,83


B PEKERJAAN URUGAN DAN GALIAN Rp. 154.257.324,90
C PEKERJAAN PASANGAN Rp. 357.841.800,00
D PEKERJAAN BETON Rp. 302.340.384,21
E PEKERJAAN PLESTERAN Rp. 493.067.217,65
F PEKERJAAN LANTAI DAN PELAPIS DINDING Rp. 379.364.122,96
G PEKERJAAN KUSEN, DAUN PINTU, DAN JENDELA Rp. 281.673.570,00
H PEKERJAAN RANGKA DAN PENUTUP ATAP Rp. 407.076.360,00
I PEKERJAAN PLAFOND Rp. 118.130.000,00
J PEKERJAAN PENGECATAN Rp. 256.674.616,28
K PEKERJAAN LISTRIK Rp. 178.579.317,50
L PEKERJAAN SANITASI Rp. 255.900.022,30
M PEKERJAAN FAÇADE & EKSTERIOR Rp. 120.855.000,00
SUB TOTAL + PROVIT Rp. 3.744.053.985,80
JUMLAH TOTAL Rp. 3.744.050.000,00
RENCANA ANGGARAN BIAYA
PEMBANGUNAN PENGIANAPAN 40 UNIT

Pemilik : Penginapan 40 unit


Lokasi : Blora, Jawa Tengah

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN + MATERIAL VOL. SAT.
(Rupiah) (Rupiah)

A PEKERJAAN PERSIAPAN
1 Bouwplank 812,00 m' 18.315,00 14.871.780,00
2 Pengadaan Listrik dan Air Kerja 12,00 bln 500.000,00 6.000.000,00
3 Pembersihan Lokasi 812,00 m2 32.355,00 26.272.260,00
4 Pembuatan Papan Nama Proyek 1,00 unit 781.665,83 781.665,83
5 Mobilisasi & demobilisasi 1,00 ls 50.000.000,00 50.000.000,00

SUB-TOTAL 97.925.705,83

B PEKERJAAN URUGAN DAN GALIAN


1 Pek. Galian Pondasi Batu kali 586,67 m3 61.250,00 35.933.537,50
2 Pek. Urugan Pasir Bawah Pondasi T = 5 cm 24,36 m3 300.250,00 7.314.090,00
3 Pek. Pondasi Batu Kali 117,33 m3 860.850,00 101.006.973,90
4 Pek. Urugan Tanah Kembali 195,56 m3 51.150,00 10.002.723,50
SUB-TOTAL 154.257.324,90

C PEKERJAAN PASANGAN
A Lantai Dasar
1 Pekerjaan Pasangan 1/2 Bata 1 Pc : 5 Ps 2.736,38 m2 130.000,00 355.729.400,00
2 Pekerjaan Openingan / Skonengan 105,62 m1 20.000,00 2.112.400,00
SUB-TOTAL 357.841.800,00

D PEKERJAAN BETON
1 Sloof S1 15x20 cm 24,36 m3 5.049.692,94 123.010.520,12
2 Kolom Praktis 15x15 cm 17,88 m3 4.550.188,48 81.340.306,87
3 RB 15x20 cm 24,36 m3 4.022.559,82 97.989.557,22
SUB-TOTAL 302.340.384,21

E PEKERJAAN PLESTERAN
A Lantai Dasar
1 Pekerjaan Plesteran 1 Pc : 5 Ps 5472,76 m2 55.904,80 305.953.553,25
2 Acian 5472,76 m2 34.190,00 187.113.664,40
SUB-TOTAL 493.067.217,65

F PEKERJAAN LANTAI DAN PELAPIS DINDING


1 Pekerjaan keramik 60x60 glossy u/ interior 881,00 m2 338.718,00 298.410.558,00
2 Pekerjaan Lantai Keramik 40 x 40 (km/wc) 164,00 m2 182.531,18 29.935.112,86
3 Pekerjaan Dinding Keramik 20 x 25 (km/wc) 225,00 m2 226.748,68 51.018.452,10
SUB-TOTAL 379.364.122,96

G PEKERJAAN KUSEN, DAUN PINTU, DAN JENDELA


1 Pekerjaan Kusen Alumunium 81,00 M' 115.000,00 9.315.000,00
2 Pemasangan pintu kamar semi panel 42,00 unit 1.300.000,00 54.600.000,00
3 Pemasangan pintu pvc kamar mandi 48,00 unit 830.000,00 39.840.000,00
4 Pintu Type PJ1 ( 2.2 x 1.45) 133,98 m2 721.500,00 96.666.570,00
5 Pintu P1 (2.20 x 0,9) 95,04 m2 721.500,00 68.571.360,00
6 Jendela Type BV (0.70 x 0.50) 16,80 m2 754.800,00 12.680.640,00
SUB-TOTAL 281.673.570,00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN + MATERIAL VOL. SAT.
(Rupiah) (Rupiah)

I PEKERJAAN RANGKA DAN PENUTUP ATAP


1 Pemasangan Kuda2 Baja Ringan 864,00 m2 250.815,00 216.704.160,00
2 Pasang Atap zincalum 864,00 m2 129.675,00 112.039.200,00
3 Pemasangan Woodplank 20 Cm 600,00 M' 55.000,00 33.000.000,00
4 Bubungan atap zincalum 216,00 M' 100.890,00 21.792.240,00
5 Pemasangan talang zincalum 216,00 M' 108.985,00 23.540.760,00
SUB-TOTAL 407.076.360,00

J PEKERJAAN PLAFOND
A Lantai Dasar
1 Pemasangan plafon gypsum 864,00 m2 120.000,00 103.680.000,00
2 Celling droop 170,00 m2 85.000,00 14.450.000,00
SUB-TOTAL 118.130.000,00

K PEKERJAAN PENGECATAN
A Lantai Dasar
1 Pekerjaan Cat Dinding Eksterior 2736,38 m2 50.838,00 139.112.086,44
2 Pekerjaan Cat Dinding Interior 2.736,38 m2 30.868,00 84.466.577,84
3 Pekerjaan Cat Plafond 864,00 m2 38.305,50 33.095.952,00
SUB-TOTAL 256.674.616,28

L PEKERJAAN LISTRIK
1 Instalasi titik penerangan 347 Ttk 210.347,50 72.990.582,50
2 Instalasi titik stop kontak 85 Ttk 204.180,00 17.355.300,00
3 Down light LED 7 W dia 150 Cm,Recessed Mounted 347 Bh 130.000,00 45.110.000,00
4 Lampu Sorot LED 20 Watt 40 Bh 116.050,00 4.642.000,00
5 Saklar tunggal 45 Bh 46.125,00 2.075.625,00
6 Saklar ganda 42 Bh 62.625,00 2.630.250,00
7 Instalasi Outlet Televisi 40 Bh 255.000,00 10.200.000,00
8 Instalasi Stop Kontak AC 42 Bh 204.180,00 8.575.560,00
9 Instalasi Box Zikring 15 Bh 1.000.000,00 15.000.000,00
SUB-TOTAL 178.579.317,50

M PEKERJAAN SANITASI
1 Pemasangan pipa air bersih 200,00 M' 34.000,00 6.800.000,00
2 Pemasangan pipa air kotor 300,00 M' 34.000,00 10.200.000,00
3 Pemasangan pipa air bekas 300,00 M' 34.000,00 10.200.000,00
4 Accesoris Pemipaan (Fiting) 1,00 Ls 500.000,00 500.000,00
5 Hanger & Support 1,00 Ls 500.000,00 500.000,00
6 Pipa PVC Dia.100(4") + Air Hujan 200,00 M' 106.395,00 21.279.000,00
7 Septic Tank 4,00 unit 3.815.818,08 15.263.272,30
8 Pas. Closet duduk + acc 48,00 bh 2.498.607,50 119.933.160,00
9 Kran Dinding 48,00 bh 97.700,00 4.689.600,00
10 Pas. Jet Washer 20,00 bh 404.337,00 8.086.740,00
11 Pas. Wastafel Meja 4,00 bh 1.720.500,00 6.882.000,00
12 Pas. Floor Drain 48,00 bh 137.625,00 6.606.000,00
13 Pas. Roof Drain 42,00 bh 177.625,00 7.460.250,00
14 Pas. Torn + Accesoris Pemipaan 10,00 Unit 3.750.000,00 37.500.000,00
SUB-TOTAL 255.900.022,30

FAÇADE & EKSTERIOR


O PEKERJAAN FAÇADE & EKSTERIOR
1 Pekerjaan batu Alam Depan façade 420,00 m2 287.750,00 120.855.000,00
TOTAL FAÇADE & EKSTERIOR 120.855.000,00
TOTAL 3.403.685.441,64

MARGIN PROFIT = 10% 340.368.544,16

GRAND TOTAL 3.744.053.985,80

Blora, 26 juni 2024

Keterangan :
*Pembayaran Dp & Progres wajib CASH DI AWAL
*Apabila ada permintaan desain maka WAJIB melakukan pembelian desain

You might also like