Professional Documents
Culture Documents
SFD-CTE-SAPF1-G08-00003 rev R01
SFD-CTE-SAPF1-G08-00003 rev R01
SFD-CTE-SAPF1-G08-00003 rev R01
R01
Revision Philosophy
All documents for review will be issued at R01 as required, with subsequent R02….
If the document is for information, it will also be issued as R01.
All revisions Issued for Review / approval will be issued at A01, with subsequent A02, A03, etc as
required.
All revisions approved for design will be issued at D01, with subsequent D02, D03, etc as required.
Documents approved for Construction will be issued at C01, C02, and C03 respectively.
Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc.
Narrative sections revised from previous approved issues are to be noted in the table below and/or
highlighted in the RH margin (using the appropriate revision status) thus: | A02
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected
areas and by the use of a triangle containing the revision status.
Revision History
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
RECORD OF AMENDMENT
It is certified that the amendments listed below have been incorporated in this copy of the publication.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
PARAGRAPH
SECTION DESCRIPTION OF HOLD
NO.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Table of Contents
ABBREVIATIONS/DEFINITIONS .............................................................................................13
1.0 EXECUTIVE SUMMARY...............................................................................................14
1.1 Introduction ........................................................................................................14
1.2 Sapele Flowstation Existing Configuration .........................................................14
1.3 Debottlenecking Study Conclusions ...................................................................15
2.0 INTRODUCTION...........................................................................................................18
2.1 Background........................................................................................................18
2.2 Objective............................................................................................................18
2.3 Study Scope ......................................................................................................18
2.4 Study Execution .................................................................................................19
3.0 STUDY BASIS AND APPROACH ................................................................................20
3.1 Study Basis........................................................................................................20
3.1.1 Production Forecast ...............................................................................20
3.1.2 Water Cut forecast .................................................................................20
3.1.3 Oil production composition .....................................................................20
3.1.4 Sapele Flowstation Configuration ...........................................................21
3.1.5 Sapele Flowstation Pressure Profile (on site records) ............................22
3.1.6 Sapele Flow Station Flow Diagram.........................................................22
4.0 INLET MANIFOLD / HEADERS ....................................................................................24
4.1.1 Description and assessment Parameters ...............................................24
4.1.2 Results ...................................................................................................24
4.1.3 Analysis..................................................................................................29
4.1.4 Recommendation ...................................................................................30
5.0 SEPARATORS .............................................................................................................31
5.1 Assessment Method ..........................................................................................31
5.1.1 Liquid Handling Capacity........................................................................31
5.1.2 Gas Handling Capacity...........................................................................32
5.1.3 Nozzle Assessment Criteria....................................................................32
5.1.4 Control Valves ........................................................................................32
Seplat doc SFD-CTE-SAPF1-G08-00003 Final Report
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Figures
Figure 1-1. Extra Capacity from Sapele Flowstation (Amukpe-LTF online)................................16
Figure 3-1. Process flow diagram of current plant .....................................................................23
Figure 4-1. XHP Manifold Capacity (Erosional Velocity)............................................................26
Figure 4-2. HP Manifold Max Capacity (Erosional Velocity) ......................................................27
Figure 4-3. LP Manifold Max Capacity (Erosional Velocity) .......................................................28
Figure 4-4. LP Header Pressure Drop (bar) ..............................................................................29
Figure 5-1. XHP Horizontal vessel, V-105 .................................................................................33
Figure 5-2. On site XHP Separator V-105 .................................................................................33
Figure 5-3. XHP Separator V-105 Operation Envelope .............................................................35
Figure 5-4. HP Separator, V-102/202........................................................................................36
Figure 5-5. On site HP Separator 2, V-202................................................................................37
Figure 5-6. HP Separator V-102/202 Operating Envelope.........................................................39
Figure 5-7. LP Separator V-103/203 .........................................................................................40
Figure 5-8. On site LP separator 2, V-203.................................................................................41
Figure 5-9. LP separator V-103/203 Operating Envelope..........................................................43
Figure 5-10. Surge Vessel, V-104/204 ......................................................................................45
Figure 5-11. On site Surge vessels V-104/204.........................................................................46
Figure 5-12. Surge Drum V-104/204 Operating Envelope .........................................................48
Figure 6-1. Export system Operating Envelope. Amukpe LTF in operation. ..............................53
Figure 6-2. System Operating Envelope, LTF in Operation, pipeline remediated ......................54
Figure 6-3. Export system Operating Envelope, LTF bypassed.................................................56
Figure 6-4. Export System Operating Envelope. LTF Bypassed. Line Remediated ...................57
Figure 6-5. NPSHa vs NPSHr ...................................................................................................58
Figure 6-6. Metering capacity when Amukpe LTF is in operation ..............................................61
Figure 6-7. Metering capacity when Amukpe LTF is bypassed..................................................61
Figure 7-1. Sapele flowstation PSV's capacity ..........................................................................65
Seplat doc SFD-CTE-SAPF1-G08-00003 Final Report
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Figure 7-2- Vapour Flowrate vs. Distance for the allowable thermal radiation level ...................70
Figure 7-3 Radiation for different vapour flow rates at different distances .................................71
Figure 7-4 Total flaring Flowrate vs. Distance for the allowable thermal radiation ....................72
Figure 7-5 Radiation for different total flaring flow rates at different distances ...........................73
Figure 7-6. Sapele Flowstation Flarenet model .........................................................................75
Figure 7-7. Existing LP Manifold Flare System..........................................................................81
Figure 7-8. Modifications recommended for LP header and LP manifold PSVs tailpipes...........82
Figure 7-9. New LP manifold relief system configuration...........................................................82
Figure 7-10. New Surge Vessel relief system configuration ......................................................83
Figure 7-11. New LP separator relief system configuration .......................................................84
Figure 8-1. Pressure drop across each fitting in the separator section ......................................87
Figure 8-2. Pressure drop across each fitting in the header section ..........................................88
Figure 8-3. LP compressor capacity based on suction pressure ...............................................89
Figure 8-4. LP compressor capacity, with Debottlenecking. ......................................................90
Figure 10-1. Liquid Capacity Bottlenecks at Sapele Flowstation ...............................................95
Figure 10-2. Extra Capacity from Sapele Flowstation (Amukpe LTF Bypassed)........................96
Figure 10-3. Extra Capacity from Sapele Flowstation (Amukpe-LTF online)..............................97
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Tables
Table 3-1. Gross Production Forecast.......................................................................................20
Table 3-2. Water Cut Forecast ..................................................................................................20
Table 4-1. Inlet Manifolds Calculation Summary .......................................................................24
Table 6-1. Oil Export Pump Detail-Model Ref Sulzer 4x8x10.5B ...............................................50
Table 6-2. Current pipeline vs Remediated Pipeline..................................................................51
Table 6-3. Summary of Oil Export System Capacities ...............................................................59
Table 7-1. Sapele Flowstation Relief Valve Detail .....................................................................63
Table 7-2. Base Case. PSV rated capacity vs 68,000 BPD.......................................................64
Table 7-3. Max Production Case. PSV rated capacity vs 82,000BPD production ......................66
Table 7-4 Recommended design total radiation ........................................................................68
Table 7-5 Flarenet summary .....................................................................................................76
Table 7-6. XHP and HP Relief systems (82,000 BPD) ..............................................................77
Table 7-7. LP Relief System (82,000 BPD) ...............................................................................77
Table 7-8 LP Manifold Relief for 82,000BPD.............................................................................82
Table 7-9 Surge Vessel Relief for 82,000BPD...........................................................................83
Table 7-10 LP Separator Relief for 82,000BPD.........................................................................84
Table 8-1. Compressor unit PSVs .............................................................................................86
Table 9-1. Sapele Flowstation Control Valves ...........................................................................92
Table 9-2. Compressor Station Control Valves..........................................................................93
Table 11-1. Sapele export pipeline capacity summary ..............................................................99
Table 14-1. Long Lead Item List..............................................................................................104
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
ABBREVIATIONS/DEFINITIONS
Term Definition
API American Petroleum Institute
BPD Barrel of oil per day
BWPD Barrel of Water Per Day
CFD Computational Fluid Dynamics
CITHP Closed In Tubing Head Pressure
DCS Distributed Control System
GOR Gas Oil Ratio
HP High Pressure
HYSYS Proprietary Simulation Tool
LCV Level Control Valve
LP Low Pressure
LTF Liquid Treatment Facility
MAOP Maximum Allowable Operating Pressure
MMSCFD Million standard cubic feet of gas per day
NA Not Applicable
NGC Nigerian Gas Company
NPSHa Net positive suction head available
NPSHr Net positive suction head required
P&ID Piping and Instrumentation Diagram
PCV Pressure Control Valve
PFD Process Flow Diagram
PVT Pressure, Volume, Temperature
PSV Pressure Safety Valve
SEPLAT Seplat Petroleum Development Company
SG Specific Gravity
SPDC Shell Petroleum Development Company
XHP Extra High Pressure
Seplat doc SFD-CTE-SAPF1-G08-00003 Final Report
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
compressor unreliability and operational issues, at the moment most of the gas is being
flared.
The LTF (Liquid Treatment Facility) operational mode in the Amukpe Station affects the
processing capacity of the Sapele Flowstation. This debottlenecking study will look into
this two operational modes:
1. Amukpe LTF station is in operation
2. Amukpe LTF is bypassed and the Sapele export pipeline discharges at a higher
backpressure.
If the Amukpe LTF is operational, the pipeline limits the flow from Sapele to
78-81,000BPD.
If the Amukpe LTF is bypassed, the pipeline backpressure limits the flow from
Sapele to 58-60,000BPD (current pipeline). This capacity could be increased to
67,000 BPD if the pitted sections of the pipeline are remediated and its design
pressure increased to 66 barg.
The mode of operation of the Amukpe LTF affects the maximum production from Sapele
by 20,000 BPD (current pipeline) or 14,000 BPD if the pipeline is remediated.
It should be possible to debottleneck the existing surface facilities at the Sapele
flowstation to achieve a production up to the pipeline capacity limit of 81,000BPD.
The current mode of operation of the Sapele Flowstation is different from the original
design. The majority of the wells are aligned to the LP manifold and LP separators. Most
of the new wells are LP wells. The LP separators are currently overloaded. As part of the
debottlenecking scope, the LP separator capacity needs to be increased. This can be
achieved by realigning redundant HP Separator V-202 to LP Separator duty and
installing additional piping from the LP manifold to the LP separators.
The flowstation was built in the early 1970s. The current design of the overpressure
protection system does not comply with current industry standards (API 521) at current
production rates. The current installed relief system will not protect the LP Separators
and Surge Vessels from overpressure. As part of the debottlenecking scope, the relief
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
and flare system needs to be modified. (If no debottlenecking is carried out, the relief
system will still need to be modified).
One key bottleneck is the Surge Vessels, V-104, and V-204. These are operating with
high inlet nozzle velocities. Using standard vessel sizing evaluation methods, these
vessels have a combined capacity of 61,000BPD; however it may be possible to expand
the capacity by retrofitting internals. It is recommended that a computational fluid
dynamics (CFD) study be carried out to determine the capacity of the current vessels:
and if the vessels are a bottleneck, to determine if vessel internals can be retrofitted to
increase the capacity.
In the oil export system a fourth oil export pump has already been purchased by Seplat;
an additional metering run will be required to be purchased.
Pipeline capacity
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
In summary, there are several improvements that need to be made to the Sapele
flowstation facilities to debottleneck the production capacity to match the pipeline limit of
81,000BPD. These are shown in Figure 1-1.
This study will recommend that the Sapele flowstation be debottlenecked up to the
maximum pipeline capacity of 81,000BPD. It will also recommend that the uptime of the
Amukpe LTF and its water disposal system be reviewed as that has a significant impact
on the production achievable from Sapele.
A more comprehensive list of recommendations is given in section 12.0.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
2.0 INTRODUCTION
2.1 Background
Sapele field is located about 40 km north of Warri in OML 41, and was discovered by the
original operator Shell Petroleum Development Company (SPDC) in October 1969. The
flowstation was commissioned in 1972 with an installed capacity of 60,000 BPD. The
facility receives and treats well fluids from Sapele Deep, Sapele Shallow and Ovhor
Fields. Current gross production from the flowstation is about 47,000 BPD.
The execution of the Sapele Field Development Plan is expected to increase production
from the Sapele and Ovhor reservoirs. Well fluids from third party facilities (Okweke
field) are also expected to be routed to the Sapele flowstation for treatment. Production
forecasts show that the installed capacity of the Sapele flowstation will be exceeded with
the contributions from these developments.
This additional production will come in phases, and it is anticipated that the first phase
will increase the flowstation throughput to about 86,000 BPD in 2015.
2.2 Objective
SEPLAT intends to execute a debottlenecking project to enable the facility originally
designed for 60,000 BPD to handle the approximately 86.000BPD predicted for 2015.
The debottlenecking study has the following objectives:
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
PSVs.
Control Valves.
Compressor system (Gas handling system).
Out of this scope of work are the following equipment and systems that have not been
evaluated:
Test manifold/header.
Test separator.
Fuel Gas system.
Utilities System.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
the fluid composition and properties for different headers entering Sapele Flowstation.
Heat and Material balance has been generated for the purpose of extracting the stream
composition and properties. The flowrate would be different and changing based on the
specific case and option selected.
3.1.4 Sapele Flowstation Configuration
Production from Sapele and Ovhor fields as well as future third parties production will be
split between XHP, HP and LP headers.
The plant configuration is 2x100% trains. Three headers enter the flowstation, XHP
header routes fluid to one XHP separator, HP header routes fluid to two HP separators
and LP header routes fluid to two LP separators.
The liquids from XHP separator are routed to the only operational HP separator (V-102),
the other HP separator (V-202) is currently offline. Liquids from HP separator (V-102)
are routed to both LP separators V-103 and V-203. Genesis has assumed that both HP
separators are in operation for the HYSYS simulation. Ref [2]
Liquids from the XHP, HP and LP separators are routed to the Surge Vessels (V-104
and V-204)
Liquid from surge vessels is routed to the pump suction header that feeds 3 export
pumps, two operational and one standby.
Gas from XHP is routed to Gas Lift Manifold via 105-PCV-001 and/or 105-PCV-002. If
needed this gas can be routed to flare via 100-PCV-125 or to the compressor station.
Gas from HP Separators is routed to the HP Gas Header. From there it is sent to the
Flare system via dedicated 100-PCV-120. A T branch line is sent to the compressor HP
station.
Gas from LP Separators is routed to the LP Gas Header. This gas can be split and
routed to both the flare system and/or LP compressor station. It is confirmed by Seplat
that most of this gas currently is being flared. P&ID C-201-G04-0011-001 is not showing
this line to the flare and shows LP compressor as the only destination. Genesis has
assumed that there is a line connecting the LP Gas header to the Flare system.
Gas from Surge Vessel is routed to the Flare via dedicated 100-PCV-010.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
3.1.5.1 Separators
Vessels Operating Pressure, Temperature
barg (psig) °C (°F)
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
4.1.2 Results
Table 4-1 summarises the current velocity versus the maximum velocity recommended
in two-phase flow lines.
XHP
10” 19,477 311.57 0.37 6.91 0.003
Header
HP
8” 29,993 101.51 2.79 12.11 0.11
Header
LP
8” 384,119 60.91 59.46 15.63 8.9
Header
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Following graphics Figure 4-1, Figure 4-2 and Figure 4-3 represent the maximum liquid and gas
capacity of the headers based on the maximum allowable erosional velocity.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
40
30
25
Gas (MMSCFD)
15
10
XHP operating
0
0 10,000 20,000 30,000 40,000 50,000 60,000
Liquids (BPD)
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
40
35
30
25
HP Liquid Capacity
Gas (MMSCFD)
20
15
HP Gas capacity
10
5
HP operating
0
0 10,000 20,000 30,000 40,000 50,000 60,000
Liquids (BPD)
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
40.00
35.00
30.00
20.00
15.00
10.00
LP Gas Capacity
5.00
0.00
0 10,000 20,000 30,000 40,000 50,000 60,000
Liquids (BPD)
Figure 4-4 below shows the total pressure drop of the LP header line for different
throughputs. The pressure drop is evaluated from the tee at the LP manifold to the inlet
of the separator.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
7
Operating Point
6 at 2015 Forecast
Pressure drop (bar)
5
Current Operating
4 Point
0
15,000 20,000 25,000 30,000 35,000 40,000 45,000 50,000 55,000 60,000 65,000 70,000
Liquids ( BPD)
4.1.3 Analysis
XHP and HP inlet headers are not a concern, due to the low number of wells lined up to
these headers. The mass flow is relatively low for the size of the headers, as a result,
low erosional velocity and pressure drop are experienced across the line. There is free
capacity in these headers.
LP Inlet Header has a high erosional velocity and pressure drop.
– Pressure drop is 4.5 bar at current production of 47,000BPD, expected to
increase at higher throughputs
– This would put excessive backpressure on wells (6.6 bar additional pressure at
60,000BPD)
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
This is an understandable finding: compared to the original design, most of the wells at
the Sapele flowstation are aligned to the LP manifold.
In summary, the existing LP manifold/header is overloaded with high pressure drop and
high erosional velocities. Adding additional wells/production to the LP header is not
recommended.
As part of the debottlenecking, additional LP headers are recommended along the length
of the LP manifold. This would reduce the velocity (and the pressure drop) along each
section of the LP manifold and the LP headers. As well as allowing for future expansion,
running 3 LP headers would reduce the backpressure on the existing wells and enhance
current production.
With a total Sapele throughput of 82,000 BPD and 3 LP headers; the flow through each
LP header would be 27,300 BPD and the pressure drop would be 2 bar. This is a
reduction in pressure on the existing wells of 2.5 bar, which would be expected to
enhance production.
With a total Sapele throughput of 60,000 BPD and 3 LP headers; the flow through each
LP header would be 20,000 BPD and the pressure drop would be 1 bar. This is a
reduction in pressure on the existing wells of 3.5 bar, which would be expected to
enhance production.
In summary, installing 2 additional LP headers from the LP manifold to the separators is
recommended not only as a debottlenecking exercise to free up capacity for new wells
but is also recommended to enhance production from existing LP wells.
The easiest configuration would be to run one new 8” header from the LP manifold to
V-202**; one new 8” LP header to either V-103 or V-203 and reconfigure the existing LP
header to feed only one of V-203 or V-103.
4.1.4 Recommendation
– Install two new 8” LP headers from the manifold to V-202 and V-103 and
reconfigure the existing 8” LP header to feed to V-203 only. This will dedicate a
separate 8” header line to each of V-103, V-203, V-202.
** Note: V-202 is the unused HP separator, which is recommended to be reallocated to
LP Separator service, see section 5.4 below.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
5.0 SEPARATORS
5.1 Assessment Method
The following has been assessed for each separator based on SHELL DEP 31.22.05.11-Gen
[Ref 4] :
Required liquid hold up time: LALL to LAL: 5mins (for action outside the control
room)
Required liquid hold up time LAL to LAH: 3mins (on total product outflow for
separator trains)
Required liquid hold up time LAH to LAHH: 5mins (for action outside the control
room)
Vertical Vessels
Required liquid hold up time: LALL to LAL: 5mins (for action outside the control
room)
Required liquid hold up time LAL to LAH: 10mins (on total product outflow for
separator trains)
Required liquid hold up time LAH to LAHH: 5mins (for action outside the control
room)
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Inlet Nozzle (No Inlet Device) : 1400 Pa (Based on Shell DEP 31.22.05.11)
Liquid Outlet Nozzle : 3m/s (In line with general liquid velocity criteria)
Inlet Nozzle and liquid Outlet Nozzle Erosion Velocity: use the method of API RP
14E (see equation in Section 4.1.1)
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Length 6096mm
Thickness 38.1mm
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
5.2.2 Results
5.2.2.1 Liquid Holdup Capacity and Response Times
Note: the above control bands are based on assumed level settings and are indicative
only. The total hold-up time LALL to LAHH conforms to the Shell DEP recommendations.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
50
(LALL to LAL) Liquid Hold Up (2 mins)
(LALL to LAL) Liquid Hold Up (5 mins)
40
Inlet nozzle
30
20
22,424
Inlet Nozzle (Vapour)
10
Operating Point
0
0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 20,000
Liquids (BPD)
5.2.3 Analysis
The operating envelope for the XHP shows a Gas handling capacity of 52MMSCFD and
a liquid capacity based on the liquid outlet nozzle of ~18000BPD.
Current operating point is within the limits of gas and liquid handling capacity.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Length 6096mm
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
5.3.2 Results
5.3.2.1 Limiting Factor
Note: the above control bands are based on assumed level settings and are indicative
only. The total hold-up time LALL to LAHH conforms to the Shell DEP recommendations.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
30
Vapour Handling
Capacity
20
10
5
Inlet Nozzle (Vapour)
Operating Point
0
0 2,000 4,000 6,000 8,000 10,000
Liquids (BPD)
5.3.3 Analysis
The operating envelope for the HP Separator shows a Gas handling capacity of
21MMSCFD and a liquid capacity based on the liquid inlet nozzle of ~7000BPD.
Current operating point is within the limits of gas and liquid handling capacity.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Length 6096mm
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
5.4.2 Results
5.4.2.1 Limiting Factor
Note: the above control bands are based on assumed level settings and are indicative
only. The available response time is significantly less than the 90s or 300s
recommended. This would result in a high probability of low or high level trips; for non-
steady operations.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Vapour Handling
14 Capacity
12
Operating Point
LALL to LAL Liquid Hold Up (2 mins)
Gas (MMSCFD)
10
Liquid Outlet Nozzle
Inlet Nozzle (liquids)
0
0 5,000 10,000 15,000 20,000 25,000 30,000 35,000
Liquids (BPD)
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
the current operating point is 11.3 MMscf/d per separator. There is capacity for
2x1.7MMscfd = 3.4MMscf/d of additional gas capacity.
HP Separator V-202 is currently not used and is of identical size and design pressure to
V-103/V-203. Re-piping the inlet and outlet of V-202 to reconfigure it to LP Separator
duty is highly recommended. The proposed additional wells for the Sapele flowstation
are mostly LP wells. Moreover, the new wells will be gas lifted. With V202 realigned to
LP service, the total vapour handling capacity between the three separators V-202
/V-103/V-203 is 39MMscf/d; the current gas throughput 22.6MMscf/d. This would allow
16.4MMscf/d of additional lift gas.
In summary, reallocating V202 to LP service will not only give increased liquid handling
capability but also allow for a significantly higher flow of additional lift gas (16.4 MMscf/d
vs 3.4 MMscf/d).
It is also recommended that two new LP headers (three in total, one 8” header to each
LP separator) are installed if the full gas lift capacity is to be utilized (see section 4.1.4).
5.4.5 Recommendation
HP Separator V-202 is currently offline. This should be reconfigured as a third LP
Separator, both to maximize liquid handling capacity and to allow for 16.4 MMscf/d of
additional lift gas.
Thickness Unknown mm
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
5.5.2 Results
5.5.2.1 Limiting Factor
Note: the above control bands are based on assumed level settings and are indicative
only. The available response time is significantly less than the 300s recommended. This
would result in a high probability of low or high level trips; for non-steady operations.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
4.5
2.5
1.5
5.5.3 Analysis
It is concluded that the inlet nozzles on the Surge Vessels are undersized for current flowrates;
the response time is also very low for local operation (not from a centralised control room). This
would lead to a risk of overfilling from downstream upsets such as oil export pump trips. The
inlet nozzle criteria is exceeded which may lead to liquid mist formation and excess droplet
carryover.
These are soft constraints, a hard constraint is the liquid outlet nozzle criterion: high velocities in
the liquid outlet could lead to vortexing and vapour carryunder to the oil export pumps. Vapour
carryunder to the oil export pumps is a known cause of pump cavitation leading to impeller
damage. This could happen at lower velocities if the liquid level in V-104/204 was low.
The original nameplate design for V-104/204 was 30,000BPD; the highest flowrate through one
surge vessel in actual service was reported as 30,500BPD.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
The Surge Vessels are a key unit operation for the Sapele flowstation and cannot be bypassed,
this would limit the maximum production through Sapele.
For the purposes of this debottlenecking exercise, the maximum capacity of V-104/204 is taken
as 30,500BPD per vessel; 61,000BPD combined. This is proven in operational service although
it is significantly above some of the “soft constraints” in vessel capacity calculations.
It may be possible to fit internals (for example, a vortex breaker) to V-104/204 which would allow
a higher production than 30,500BPD per vessel. It is recommended that this be examined by a
computational fluid dynamics (CFD) study which would do a detailed 3-dimensional model of the
vessel; examine which flowrates would lead to vapour carryunder and if a vortex breaker or
other internal would allow operation at higher flowrates.
5.5.4 Recommendation
The Surge Vessels V-104/204 are a bottleneck for the overall Sapele flowstation
production and would limit flow through the flowstation to 61,000BPD (both online).
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
No of stages - 11
When exporting the liquids from Sapele flowstation to Amukpe LTF, there are two
different operational scenarios that need to be considered. It has been reported that
Amukpe LTF has operational problems due to the availability of the water injection wells.
In this event, the Amukpe LTF plant is bypassed and the export pumps at Sapele have
to operate at a higher pressure to feed the oil into the pipeline system that connects to
the Forcados terminal.
The pipeline from Sapele to Amukpe was derated by the previous operator to 55 barg,
with a high pressure trip at Sapele set at 45 barg. Seplat have carried out intelligent
Seplat doc SFD-CTE-SAPF1-G08-00003 Final Report
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
pigging of the Sapele export pipeline and have confirmed that part of the pipeline is
pitted. Seplat are considering repairing the pitted section of the pipeline which would
enable the maximum allowable operating pressure (MAOP) to be raised to 66 barg.
Two separate pipeline conditions have been reviewed: current pipeline (MAOP 55 barg)
and “remediated” pipeline (66 barg).
Table 6-2. Current pipeline vs Remediated Pipeline
Pipeline (current) 45 50 55
Pipeline remediated 54 60 66
Note that the high pressure trip setpoint of 54 barg is an assumption based on a similar
percentage below MAOP to the existing pipeline.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Pump net positive suction head required (NPSHr) versus NPSH available
(NPSHa) at higher flows in each pump suction line
Pump curves and NPSH curves were supplied by the pump vendor, Sulzer. As-built
datasheets for the pumps were supplied by Seplat. It is notable that the maximum power
rating for the gas engine driving the pumps is rated at 372kW whereas the gearbox is
rated at 295kW. The gearbox is therefore the limiting constraint for the maximum power
able to be supplied to each oil export pump.
The roughness of the pipe walls will affect the pressure drop between Sapele and
Amukpe. Two different pipe roughnesses have been investigated: 0.06mm (roughness
used in the Pipesim model supplied by Seplat for the pipeline network) and 0.15mm.
There is limited data to back-calibrate the actual pipeline roughness: the pipeline is
known to be pitted and would be expected to have a roughness greater than that for new
pipe (0.05mm).
For the two operational scenarios, pipeline system curves were generated to show
required discharge pressure at Sapele versus flowrate for two different pipe
roughnesses. These system curves were superimposed on the pump curves to identify
which constraint was hit first: pipeline high pressure trip, pump curve or gearbox power
limit.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
With three pumps online, the gearbox power again limits the maximum flow: the power
line from the pump curve intersects the pipeline system curve at 78,000 to 81,000BPD
(dependent on pipeline roughness).
In both cases with the Amukpe LTF operational, the discharge pressure at Sapele is
below the current pipeline trip setpoint of 45 barg, so remediated the pipeline would not
permit a higher export flowrate (although it would increase the margin between the
operating pressure and the trip setpoint and reduce the likelihood of spurious trips).
With the pipeline remediated (see Figure 6-2) the capacity is constrained by the three
pumps so there is no change in capacity. There is marginal benefit in adding a fourth
pump online with the pipeline remediated: the system curve is steep at this point and is
constrained by the pipeline high pressure trip.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
450.00
Gearbox 3 pumps
400.00
Roughness 0.15
350.00
Roughness 0.06
300.00
250.00 Op. Point 2 ppumps 2650rpm
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
With three pumps online, the constraint on maximum capacity is not the pump (or
gearbox power); it is the design pressure of the pipeline. For the current pipeline with a
trip set at 45 barg, the built-up backpressure from the pipeline is at 45 barg at flows of
58,000 to 60,000BPD (depending on pipeline roughness).
If the pipeline is remediated and has a trip set at 54 barg, the constraint is again the high
pressure trip setpoint: in this case the pressure would limit the flows to 65,000 to
67,000BPD.
In summary, if Amukpe LTF is not operational and is bypassed, the capacity of the
current pipeline is reduced from a maximum of 81,000BPD to a maximum of
60,000BPD.
If the pipeline is remediated to have a MAOP of 66 barg, there is no impact if the
Amukpe LTF is operational, but if Amukpe LTF is bypassed, the capacity is now a
maximum of 67,000BPD.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Figure 6-4. Export System Operating Envelope. LTF Bypassed. Line Remediated
P Trip
500 Op. Point
450 Max Design P
400
Relief P
350
300 2 pumps 2650rpm
250
200 3 pumps 2650rpm
150
Gearbox 2 pumps
100
50 Gearbox 3pumps
0
0 10000 20000 30000 40000 50000 60000 70000 80000 90000 100000
Liquid Flow (BPD)
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
3
2.8
2.6 2650rpm
2.4
1656rpm
2.2
1822rpm
2
1.8 1987rpm
NPSHr (m)
1.6
2153rpm
1.4
2319rpm
1.2
1 2484rpm
0.8 NPSHa
0.6
0.4
0.2
0
0 20 40 60 80 100 120 140 160 180 200 220
FLow (m3/h)
6.1.4 Analysis
1) When Amukpe LTF is in operation:
If 2 pumps are running in parallel, the power rating on the pump gearbox is
limiting the maximum oil export capacity to 55,000BPD.
If 3 pumps are running in parallel, the backpressure from the pipeline will build-up
until the Pump Gearbox power rating is reached. This gives a maximum export
capacity of 78,000BPD to 81,000BPD depending on pipeline roughness.
As the pumps gearbox becomes the limiting factor before the built-up
backpressure reaches the pipeline high pressure trip setpoint, remediating the
pipeline to increase the pipeline MAOP will not have an impact on the maximum
oil export capacity of Sapele if Amukpe LTF is online.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
2) When the Amukpe LTF is bypassed, the pipeline backpressure and system operation
is very different:
If 2 pumps are running in parallel, the power rating on the pump gearbox is
limiting the maximum oil export capacity to 53,000BPD. The pumps will hit the
power limit before the pipeline high pressure trip is reached.
If 3 pumps are running in parallel, the built-up backpressure from the pipeline
reaches the high pressure trip setpoint of 45barg at a flowrate of 58,000BPD to
60,000BPD depending on pipeline roughness.
If 3 pumps are running in parallel and Amukpe LTF is bypassed, remediating the
pitted section of the pipeline to increase the MAOP to 66 barg will result in an
increase in pipeline capacity. In this case, the built-up backpressure will reach
the maximum gearbox power constraint before the pipeline high pressure trip
setpoint is reached. The maximum oil export capacity from Sapele would be
65,000BPD to 67,000BPD depending on pipeline roughness.
NPSH of the pump does not represent any constraints for the export capacity. Each
pump has its own suction line which is rated for the end-of-pump-curve flowrate.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
6.1.5 Recommendations
Seplat have purchased a fourth oil export pump for the Sapele flowstation. This
needs to be installed to have three pumps running with one standby. The
addition of a third operational pump is essential to maximising the capacity of the
Sapele oil export system and needs to be installed with the other debottlenecking
modifications in this report.
With a third oil export pump operational, the uptime of the Amukpe LTF has a
significant impact on the Sapele oil export system capacity. Production is
reduced from ~80,000BPD to 60,000BPD when the Amukpe LTF is not-
operational and has to be bypassed. It is recommended to review the causes and
frequency of Amukpe LTF outages.
The roughness of the pipeline affects the maximum capacity by about 2,000BPD
if roughness is reduced from 0.15 to 0.06. It is recommended that pipeline
pressure drop information from the existing operation be collected and analysed
before and after the latest intelligent pigging/pipeline cleaning campaign. If there
is a reduction in pipeline pressure drop after the pipeline was cleaned,
consideration could be made to a regular pipeline cleaning pig operation to
minimise the pipeline roughness.
If the pipeline is remediated and the MAOP increased, a pipeline hydraulic study
is recommended to advise the correct setting of the high pressure trip.
Metering Specifications:
Vendor: FMC Technologies
Model: Smith Meter 6” Steel Model G6
Continuous Rating: 3.75l/min (33.950BPD)
Meter Gearing: One barrel per revolution of meter calibrator output shaft
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
6.2.2 Results
110000
100000
90000
80000 pumps capacity
Oil Net Flow (BPD)
70000
metering capacity
60000
50000
40000
30000
20000
10000
0
2 pumps/2metering 3 pumps/3metering
110000
100000
90000
80000
pumps capacity
Oil Net Flow (BPD)
70000
50000
40000
30000
20000
10000
0
2 pumps/2metering 3 pumps/3metering
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
6.2.3 Analysis
The capacity constraints for the oil export metering are as follows
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
7.1.2 Results
Two different cases have been studied as result of the capacities that have come out
from previous calculation presented in this final report.
1) The base case shows the relief system when the Sapele flowstation is processing
68,000BPD. This is the forecast production for end of 2014. See Ref [2]
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
2) The Max Capacity case is based on maximum export capacity with 3 pumps in
operation, 82,000BPD. [Ref 2]
Following table represents the current relieving flow with 68,000BPD of gross production against
the rated capacity of the existing PSVs.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
65000
60000
55000
50000
Gross Relieving Capacity (BPD*)
45000
40000
35000
Max capacity
30000
Existing load
25000
20000
15000
10000
5000
0
XHP HP LP Surge Pump HP1 LP manifold XHP
Separator separator separator vessel manifold manifold
*Note: mass flow has been converted to BPD for a better understanding.
It can be highlighted that the LP system (manifold and LP separators) together with the
Surge drums PSV’s are undersized for the current production at Sapele flowstation. This
is a safety risk and requires special attention.
The same calculations were made in order to evaluate the existing PSV system when
higher gross production is received at Sapele (82,000BPD). The Table 7-3. Max
Production Case. PSV rated capacity vs 82,000BPD productionshows the orifice size
needed to handle the new relief scenario.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Table 7-3. Max Production Case. PSV rated capacity vs 82,000BPD production
Calculated
Existing Orifice Relieving flow Rated capacity
Name Service Orifice
(cm2) (kg/h) (kg/h)
(cm2)
105-RV-001 XHP Separator 3.149 23.225(M) 2.39E+04 1.76E+05
7.1.3 Analysis
• XHP separator and manifold, HP separator and manifold, pump PSVs are not of
concern.
• LP Manifold relief capacity is 14,700 BPD equivalent.
– Currently this is not a concern as the wells with CITHP over 1250 psig only make
up 22% of LP production (8,950 BPD gross).
– Concern is the future production with new LP wells with higher CITHP
• LP Separator installed relief capacity is 14,300 BPD equivalent per separator.
– This is a concern both for current operation (23,500 BPD per LP separator) as
well as future debottlenecking.
Seplat doc SFD-CTE-SAPF1-G08-00003 Final Report
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
– In the event of a full flow relief event trying to relieve through the undersized
PSV, the expected pressure in the LP separators is 170% of the design pressure
– There is a high level trip (LZAHH) but this is off the same instrument as the level
controller, hence failure of this level transmitter could both cause the
overpressure event as well as disable the high level trip (“common mode
failure”).
– There is an independent high pressure trip (PZAHH) which is the current
protection on the LP separators
• Surge Vessel installed relief capacity is 7,200 BPD equivalent per surge vessel
– This is also a concern for current operation (23,500 BPD per surge vessel) as
well as future debottlenecking.
– In the event of a full flow relief event trying to relieve through the undersized
PSV, the expected pressure in the surge vessel is 320% of design pressure.
– System is currently protected only by the high level trips 104-LZA-001 and 204-
LZA-001
– At current flow rates, holdup time is low. There is a high risk of overfilling from
downstream upsets.
7.1.4 Recommendations
Permanent Solution:
Review if new PSVs need to be installed to protect the LP manifold (see 7.3.3).
The LP separators are protected solely by the high pressure trip and the Surge
Vessels solely by a high level trip. The maintenance and last function test of
these instruments must be checked as a priority action.
Perform wall thickness analysis on surge vessels and confirm burst pressure
(“fitness for service”). Evaluate if expected overpressure would rupture
V-104/V-204.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Vapour only:
Flare load is considered to be all vapour. Any carryover liquid gets separated
in flare knock out drum. The radiation is calculated based on different
predicted associated gas flow rate from year 2014-2019.
The flare thermal radiation level is calculated based on API 521 [Ref 5]
7.2.2 Results
7.2.2.1 Vapour only flare load
Figure 7-2 Represents the relation between the vapour flow rate and the distance from
the centre of the flame where the thermal radiation level is at the limit of 4.73 KW/m2
(1500 Btu/hr. ft2) and 6.31 Kw/m2 (2000 Btu/hr.ft2).
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Figure 7-2- Vapour Flowrate vs. Distance for the allowable thermal radiation level
90
80
Distance From Center of Flame ( m)
70
60
50
K=4.73 KW/m2
40 K=6.31 KW/m2
30
20
10
0
0 20 40 60 80 100
Vapor Flowrate ( MMSCFD)
Figure 7-3 represents the thermal radiation for different vapour flow rates at different
distances. The maximum allowable thermal radiation to generate this plot is assumed to
be 4.73 Kw/m2.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Figure 7-3 Radiation for different vapour flow rates at different distances
25.00
20.00
D=35 m
D=50 m
Radiation ( K-KW/m2)
15.00
D=70 m
D=90 m
10.00
D=110 m
D=130 m
5.00 D=160 m
K= 4.73 KW/m
0.00
20 30 40 50 60 70 80 90
Vapor Flowrate ( MMSCFD)
To generate these two plots, the thermal radiation level from both vapour and liquid is
considered. However, for the purpose of comparison, the x-Axis is only showing the
vapour flow rate.
Figure 7-4 represents the distance from the centre of the flame at the allowable thermal
radiation limit of 4.73 and 6.31 Kw/m2 for the vapour and liquid flaring.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Figure 7-4 Total flaring Flowrate vs. Distance for the allowable thermal radiation
100.00
90.00
80.00
Distance From Center of Flame ( m)
70.00
60.00 K=4.73
KW/m2
50.00
K=6.31
40.00 KW/m2
30.00
20.00
10.00
0.00
0 20 40 60 80 100
Vapor Flowrate ( MMSCFD)
Figure 7-5 represents the thermal radiation for different total flaring flow rates at different
distances. The maximum allowable thermal radiation to generate this plot is assumed to
be 4.73 Kw/m2.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Figure 7-5 Radiation for different total flaring flow rates at different distances
30.00
25.00
D=35 m
20.00
Radiation ( K-KW/m2)
D=50 m
D=70 m
15.00
D=90 m
D=110 m
10.00
D=130 m
5.00 D=160 m
K= 4.73 KW/m
0.00
20 30 40 50 60 70 80 90
Vapor Flowrate ( MMSCFD)
7.2.3 Analysis
For this study, it is assumed that the maximum allowable radiation limit including the
solar radiation is 4.73 Kw/m2.
During the peak associated gas of 82 MMCFD and net oil production flowrate of 42,389
BPD, the sterile area which needs to be blocked off for the personnel to enter is:
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
7.3.2 Results
7.3.2.1 Scenario 68,000BPD
Table 7-5 below represents current relieving flows at the production rate of 68,000BPD
Note: MABP = Maximum allowable back pressure, 10% for conventional PSVs.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
HP Sep
102-RV-001 0.52 4.9 29,180 65,200 Slug Flow (0.14) at tailpipe
#1
XHP
100-RV-004 0.28 1.6 23,860 72,000 Slug Flow (0.17) at tailpipe
Man
HP Man 100-RV-001 0.27 8.6 36,740 81,900 Slug Flow (0.26) at tailpipe
However the LP system was a bottleneck for the base case of 68,000BPD.
Recommendations to modify the system are given in this report (See section 7.4) and
have been applied in the new simulation. See Table 7-7. LP Relief System for results.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
7.3.3 Analysis
Three systems (Surge Vessels, LP Separators, LP Manifold) were found incapable of
relieving the required flow through the existing conventional relief valves. Two different
options were investigated for the installation of new relief valves:
1. The existing PSV (conventional type) is kept in operation and a new PSV
(conventional or balanced bellow type) is added in parallel. Both PSVs have the
same set point and their combined relieving rate provide the required relieving
rate for the system;
2. The existing PSV is isolated/replaced and a new PSV (conventional or balanced
bellow) is added to relieve the total required relieving rate;
The new PSV may be connected to the existing or a new header.
See Section 7.4 for more data.
Scenario 68,000BPD
For HP Separator 1 and 2 and the XHP manifold, the model shows several instances
of possible Slug flow in the PSV tailpipes and/or flare header, although these occur
at relatively low relieving velocities.
The HP manifold PSV has a high back pressure, it requires a change in the tailpipe
size from 3” to 4”, as well as the removal of the 6”x4” reducer in the downstream
header (see Figure 7-8).
The PSVs on the LP manifold, LP separators and Surge Vessels are undersized.
Scenario 82,000BPD
For XHP Separator, HP Separator # 1 and XHP and the HP manifold, the model
shows several instances of possible Slug flow in the PSV tailpipes and/or flare
header, although these occur at relatively low relieving velocities.
The Surge Vessels are modelled with a new PSV installed in parallel with the
existing PSV. In this case, the model also shows several instances of possible slug
flow, although these occur at relatively low relieving velocities.
For the new plant configuration where V202 is reconfigured to LP Separator service
giving three LP separators in operation, it is still necessary to add a new PSV in
parallel with the existing PSVs on the LP Separators. In this case, the model also
shows several instances of possible slug flow, at the existing tailpipes and headers
as well as in the new tailpipes and headers
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
For the case that all the new wells to be tied into the LP manifold have a closed in
tubing head pressure in excess of the PSV setpoint (1250 psig); two new PSVs will
be required in parallel to the existing PSV 100RV003. Modifications are required to
the tailpipe of the existing PSV 100RV003 as well as to the downstream header that
relieves the manifold PSVs (see Figure 7-9).
Note: if the new wells to be connected to the LP Manifold are sub-hydrostatic or the
CITHP is less than 1250psig and the maximum gas lift pressure is less than
1250psig; the installed PSV capacity on the LP manifold is adequate and no new
PSVs are required. It is still necessary to remove the bottleneck in the flare system,
see Figure 7-8.
There are no spare PSVs installed, and no locked open isolation is provided on
the flare network to allow isolation and maintenance of a single PSV (for example
after spurious opening). Hence any PSV maintenance requires a total shutdown
of the Sapele flowstation.
The setpoint of the PSV on the XHP Separator (48.9 barg) is too close to the
normal operating pressure (48 barg, as per site visit records) for the existing
relief valve which is a conventional type. This would lead to a high likelihood of
spurious opening.
Under the latest version of API 521 [Ref 5], PSV tailpipes and the flare header
should be sized for the “PSV rated flow” (the maximum flow able to be flowed
through the installed orifice size) not the calculated relieving flow.
The existing flare header does not slope down to the flare knockout drum. It
contains low lying pockets that will in time accumulate liquid. These liquid slugs
may increase the system backpressure and obstruct the relieving flow. Liquid
slugs in any flare network also have the potential to be pushed at high velocity
during the relieving event, with the risk of liquid hammer and damage of the
pipework.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
It is recommended that a piping review be carried out on the existing flare header
to confirm that the pipe supports are suitable for the reaction forces developed by
liquid slugs.
7.3.4 Flare Knockout Drum
The Flare KO Drum on the Sapele flowstation has a limited liquid holdup and would be
expected to fill up with liquid very quickly, crude oil would then be sent to the flare. A
sensitivity case was run on the Flarenet model to simulate the header system operating
in two-phase all the way to the flare tip; that is the operator is not able to shutdown
production before the flare KO drum fills full of liquid.
The effect of this increased backpressure was simulated by removing the drum from the
Flarenet model; results obtained are marginally worse than the results obtained with the
drum in operation. In summary, although it is not ideal, the increased backpressure was
not predicted to have an effect on the PSV relieving capacity.
N2
N3 J4
2100
N1
N4
291
600
M1
259
J 3A
J1A
487 360
J1B
J2A
350
360
N5
J2B 190
150 N6
60
549
J3A
N8
N7
280
Implicit in this modelling method was that the relieving event was assumed to be high
velocity and flow straight through the flare KO drum. The worst possible event would be
a low velocity release filling up the flare KO drum so that it was liquid full, followed by a
high velocity relieving event. There is no high level alarm or trip on the flare KO drum 46-
S-100, only a start for the air-driven pumps 46-P-100A/B.
Seplat doc SFD-CTE-SAPF1-G08-00003 Final Report
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Increase the existing 4” section to 6”, for common sub-header 6”-PL-0001; thus
eliminating reducer 6”x4”;
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
New RV 104
RV 104
New Tailpipe
Tailpipe
Surge #1
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Install a new PSV (Conventional, P-orifice, Rated Flow of 162,500 kg/hr) on each
separator to operate in parallel with the existing PSVs. The new PSVs will have a
new 10” tailpipe connected to a new 12” header.
New RV 103
RV 103
New Tailpipe
Tailpipe
LP Separator
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
8.3 PSV
Following Table 8-1. Compressor unit PSVssummarizes all the PSVs in the compressor
unit and relieving flows. Since the compressor unit is operated by NGC, Seplat did not
provide the PSV datasheets, hence the existing orifice sizes need to be confirmed by
Seplat.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
The performance of a reciprocating compressor is directly affected by the suction pressure. For
a given speed, reciprocating compressors are a “fixed volumetric throughput” machine: a lower
density of the gas at the suction will result in a reduction in the overall mass flow capacity (and
capacity in MMscf/d). The power required by a reciprocating compressor is higher at lower
suction pressures (i.e. higher compression ratios).
A lower suction pressure at the LP compressors will result in a lower mass flow capacity; there
is a constraint on minimum operating pressure due to maximum motor power.
The pressure drop from the Sapele flowstation to the LP compression at the NGC compressor
station has a significant impact on the compressor performance: this is analysed below.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Figure 8-1. Pressure drop across each fitting in the separator section
4.5
4
No carry over
3.5
Pressure drop across (psi)
1% liquid carryover
3
2.5
1.5
0.5
0
Reducer Tee Flow element Tee Enlarger Valve
Name of fittings
Figure 8-1 depicts the pressure drop on the outlet of each LP Separator, before the gas
comingles to flow to the compressor station.
The flow element (103-F-0001) represents a high Pressure Drop in the line. This
calculation is made for one LP line. It is assumed that the LP separator 2 has the same
pressure drop across the line.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Figure 8-2. Pressure drop across each fitting in the header section
0.8
0.7
0.6
Pressure drop across (bar)
0.5
Dry Gas
0.3
0.2
0.1
0
Flow Ball valve Control Check valve Reducer Ball valve Enlarger Ball valve
element valve
Name of fittings
In the common LP header, going from the LP separators to the compressor station, the
Control Valve 100-PCV-186, represents the fitting with the higher pressure drop in the
line. Figure 8-2 is based on the control valve being fully open; it is “best case”.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
4 Suction Pressure
(dry gas)
Suction Pressure
3.5
(wet gas, 1%
carryover)
LP compressor suction pressure, Barg
Suction Pressure
3 (wet gas, 2%
carryover)
Compressor
Capacity (1 train
2.5 online)
Compressor
Capacity (2 trains
2 online)
Comopressor
Capacity (3 trains
online)
1.5 Compressor
Capacity (4 trains
online)
1 Maximum Power
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
Total flow to LP gas compressor, MMSCFD
Figure 8-3. LP compressor capacity based on suction pressureshows system curves for
the operation of the LP compressors. The horizontal line shows the minimum suction
pressure of the LP compressors before they trip out on high power. The angled lines
show the flows through 1, 2, 3, 4 compressors online: the flow through each compressor
in MMscfd increases with suction pressure.
The curves show the arrival pressure at the LP compressor suctions: as the flowrate
increases, the system pressure drop increases and the LP compressor suction pressure
is reduced.
The LP Separators V-103/V-203 are known to be running with high velocities in the inlet
nozzles and some mist carryover could occur into the gas outlets. The effect of liquid
mist carryover into the line to the LP compressors is examined in Figure 8-3. With 1-2%
mist carryover and 4 compressors running, the compressors would operate only 0.1 bar
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
above the power limit suction pressure; hence there is a high likelihood of tripping on
high power. Operation with 2 or 3 LP compressors online would give a larger margin.
3
Suction Pressure (wet
gas, 2% carryover)
Compressor Capacity
2.5
(1 train online)
Compressor Capacity
(2 trains online)
2
Comopressor Capacity
(3 trains online)
Maximum Power
1
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
Using 3rd separator
Total flow to LP gas compressor, MMSCFD and 33% bigger
control valve
Figure 8-4 shows a debottlenecked case: V-202 is converted to LP service and 100-
PCV-186 is replaced with a larger valve with CV over 1000. The pressure drop from the
LP Separators to the LP compressors is significantly reduced. For 4 compressors
running, there is now over 1 bar margin between the power constraint/trip suction
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
pressure and the operating pressure. This would allow margin for mist carryover or
operating pressure fluctuations.
.
8.4.1 Results
The LP compressors are currently operating close to the low suction pressure limits of
the compressors and any mist carryover would be expected to lead to tripping on low
pressure. The control valve 100-PCV-186 at the Sapele flowstation is an identified
bottleneck. Replacing this PCV and its associated reducers and expanders would
remove one of the major bottlenecks, realigning V202 to LP Separator service would
also reduce some of the pressure drop to the LP compressors.
Both of these modifications should allow the compressor station to operate with 4
compressors online with less risk of tripping.
8.4.2 Recommendations
Replace 8” Control Valve 100-PCV-186 with a larger valve of CV greater than
1000 (10” or 12” valve); replace the reducers and expanders associated with the
current 100-PCV-186
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
9.2 Analysis
Table 9-1. Sapele Flowstation Control Valves
Valve
Required Installed
Tag Service Service Size Comment
Cv Cv
(inches)
Fischer - Valve ET Actuator 667 - 3in
XHP (Equal %). Total XHP gas flow of
105-PCV-001 Gas 3 15 136
separator 1.958 MMSCFD. Assume valve dP
0.5bar
Fischer - Valve ET Actuator 657 - 1in
XHP (Equal %). Total XHP gas flow of
105-PCV-002 BYPASS 1 15 17.2
separator 1.958 MMSCFD. Assume valve dP
0.5bar
XHP Fischer - Valve ET Actuator 667 - 3in
105-LCV-001 liquid 3 3.8 136
separator (Equal %)
Masoneilan - Valve 10124 Actuator -
HP
102-LCV-001 liquid 6 21 450 37 - 6in (Oil). All HP liquids. Assume
separator
only one HP Separator in operation
HP Masoneilan - Valve 10124 Actuator -
202-LCV-001 liquid 6 N/A 450
separator 37 - 6in (Oil)
LP Masoneilan - Valve 10124 Actuator -
103-LCV-001 liquid 6 155 450
Separator 37 - 6in (Oil)
LP Masoneilan - Valve 10134 Actuator -
203-LCV-001 liquid 6 155 450
Separator 37 - 6in (Oil)
Surge
Masoneilan - Mintork II - Valve 37310
100-PCV-010 Gas Vessel Gas 6 28 1330
Actuator- 33 - 6in
to FKO
HP Gas to
Masoneilan - Valve 10174 Actuator -
100-PCV-120 Gas Flare KO 6 19 450
37 - 6in. All gas to Flare
vessel
Masoneilan - Valve 10122 Actuator -
XHP Gas
37 - 4in- (Equal %). All gas to flare.
100-PCV-125 Gas to Flare KO 4 2.9 195
Total XHP gas flow of 1.958
vessel
MMSCFD
XHP Gas Masoneilan - Camplex II - Valve
100-PCV-196 Gas header to 6 4.1 500 35202 Actuator - 35 - 6in. All gas to
NGC compression
Seplat doc SFD-CTE-SAPF1-G08-00003 Final Report
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Valve
Required Installed
Tag Service Service Size Comment
Cv Cv
(inches)
LP Gas Masoneilan - Camplex II - Valve
100-PCV-186 Gas header to 8 1000 850 35202 Actuator - 35 - 8in. Current gas
NGC flow of 2.371 MMSCFD
HP Gas Masoneilan - Camplex II - Valve
100-PCV-181 Gas header to 6 67 500 35202 Actuator - 35 - 6in. Current gas
NGC flow of 2.629 MMSCFD
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
9.3 Results
Only one control valve, 100-PCV-186, has been identified as a bottleneck (see detailed
analysis in section 8.2). This is corroborated by the site visit report, where no control
valves were observed operating at or close to 100% open (which is a good indication of
an undersized control valve).
Also of note is that the installed control valve on V-202, the non-utilised HP Separator
has the same CV as that installed on the LP Separators V-103 and V-203; this means
that the control valve does not have to be replaced as part of the proposed realignment
of V-202 to LP Separator Service.
In summary, with the exception of 100-PCV-186, the installed control valve sizes are
appropriate for the equipment that they were designed for.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
100,000
90,000
2015 production target
80,000
70,000
Gross Liquid Capacity (BPD)
60,000
50,000
40,000
30,000
20,000
10,000
0
LP LP header Oil export Pipeline Pipeline Surge Vessel Remediated Metering One V202 as LP Pipeline Two Metering
Separators pumps (2 of) (Amukpe (Amukpe nameplate Pipeline (LTF Runs (2 additional Separator (Amukpe additional Runs (3
(2of) (with LTF LTF (with PSVs bypass) online) LP Header (3xLP) LTF online, 3 LP Headers online)
PSVs bypassed, 3 bypassed, 3 upgraded)? pumps)
upgraded) pumps) pumps, line
repaired)
Hard constraints
Soft Constraints
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Figure 10-2. Extra Capacity from Sapele Flowstation (Amukpe LTF Bypassed)
100,000
90,000
80,000
50,000
40,000
30,000
20,000
10,000
0
Current system (with V202 as 3rd LP Separator Additional oil export Revamp surge vessel
PSVs upgraded) with dedicated LP Header pump
The current system is operating off the original design point: the majority of wells are
aligned to the LP Manifold and LP Separators. The existing LP Separators are currently
overloaded. 47,000BPD has been shown as the nominal capacity of the existing system.
Realigning V-202 to LP Separator service will overcome this bottleneck and increase
capacity to 53,000BPD, the limits of two oil export pumps. If a fourth pump is installed to
allow 3 operating, then capacity would increase to 58-60,000 BPD; which is the limits of
the Sapele-Amukpe pipeline with Amukpe LTF bypassed.
If the pipeline is remediated to increase its MAOP and the surge vessel is revamped with
a vortex breaker (CFD study to confirm); the maximum possible capacity of the Sapele
flowstation with the Amukpe LTF bypassed would be 65-67,000 BPD. This is restricted
by the built-up backpressure from the pipeline.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
The current system is operating off the original design point: the majority of wells are
aligned to the LP Manifold and LP Separators. The existing LP Separators are currently
overloaded. 47,000BPD has been shown as the nominal capacity of the existing system.
Realigning V-202 to LP Separator service will overcome this bottleneck and increase
capacity to 55,000BPD, the limits of two oil export pumps. If a fourth pump is installed to
allow 3 operating, then capacity would increase to 61,000 BPD; which is the proven
capacity of the two Surge Vessels. Revamping the surge vessels by a vortex breaker
(CFD study to confirm) would increase the capacity to 67,900 BPD; the capacity of 2
metering runs. The final bottleneck reached before the pipeline capacity limit of 78-
81,000BPD is the LP header capacity; adding a third LP header would increase capacity
to the pipeline limit.
In summary, if the Amukpe LTF is operating, there is scope to increase the production
from the Sapele flowstation to 78-81,000 BPD; but there are several modifications
required to achieve this.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Revamp the surge vessels with new internals (CFD study to confirm)
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
11.0 CONCLUSIONS
The maximum capacity from the Sapele flowstation is dependent on the operation of the
Amukpe LTF. This determines the backpressure from the pipeline, which is the
constraint on current operation.
If the Amukpe LTF is operational, the pipeline limits the flow from Sapele to
78-81,000BPD.
If the Amukpe LTF is bypassed, the pipeline backpressure limits the flow from
Sapele to 58-60,000BPD (current pipeline), with an increase to 67,000 BPD if
the pitted section of the pipeline is remediated and its MAOP increased to 66
barg.
If the Amukpe LTF is bypassed, the maximum production from Sapele is reduced by
20,000 BPD (current pipeline) or by 14,000 BPD if the pipeline is remediated.
*Table is based on a pipe wall roughness of 0.06mm. If roughness of the pipe is 0.15, export
capacity is reduced by ~2,000BPD.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
The current mode of operation of the Sapele Flowstation is different from the original
design. The majority of the wells are aligned to the LP manifold and LP separators. Most
of the new wells are LP wells. The LP separators are currently overloaded. As part of the
debottlenecking scope, the LP separator capacity needs to be increased.
The flowstation was built in the early 1970s. The current design of the overpressure
protection system does not comply with current industry standards (API 521) at current
production rates. The current installed relief system will not protect the LP Separators
and Surge Vessels from overpressure. As part of the debottlenecking scope, the relief
and flare system needs to be modified. (If no debottlenecking is carried out, the relief
system will still need to be modified).
There is scope to debottleneck the surface facilities of the Sapele flowstation up to the
81,000BPD capacity of the export pipeline (based on Amukpe LTF being operational).
One key bottleneck is the Surge Vessels: V-104, V-204. These are operating with high
inlet nozzle velocities. It is recommended that a computational fluid dynamics (CFD)
study be carried out to determine the capacity of the current vessels: and if the vessels
are a bottleneck, to determine if vessel internals can be retrofitted to increase the
capacity.
This study will recommend that the Sapele flowstation be debottlenecked up to the
maximum pipeline capacity of 81,000BPD. It will also recommend that the uptime of the
Amukpe LTF be reviewed as that has a significant impact on production from Sapele.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
12.0 RECOMMENDATIONS
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
13.0 REFERENCES
1. Study Basis. Sapele Flowstation Debottlenecking Study. SFD-CTE-SAPF1-G08-
00001
2. Heat and Material Balance. Sapele Flowstation Debottlenecking Study. SFD-CTE-
SAPF1-G13-00001
3. Site visit report. EC038132-000-RT-0000-0003
4. SHELL DEP 31.22.05.11-Gen
5. API STD 521 Pressure Relieving and Depressuring Systems, Sixth Edition, January
2014.
6. Thermal Radiation from Large Pool Fires, Kevin B. McGrattan, Howard R. Baum,
Anthony Hamins, Fire Safety Engineering Division, Building and Fire Research
Laboratory, Nov. 2000, US Dept. of Commerce
7. API 14E, Recommended Practice for Design and Installation of Offshore Production
Platform Piping Systems, Fifth Edition, October 1991, Reaffirmed, January 2013.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
The table below shows a list of identified long lead piping and instrument items which are part of the
recommended debottlenecking scope.
PSVs
Flange Flange Set Pressure
Tag (hold 1) Description Size
Sizes Class (psig)
100-RV-005
4" x 6" 600# x 150# L orifice 1250 psig
Additional PSVs on LP
manifold (hold 3)
100-RV-006 4" x 6" 600# x 150# L orifice 1250 psig
Additional PSV on 241 psig
202-RV-002 4" x 6" 300# x 150# P orifice
V-202 (note 4)
Additional PSV on 241 psig
203-RV-002 4" x 6" 300# x 150# P orifice
V-203 (note 4)
Additional PSV on 241 psig
103-RV-002 4" x 6" 300# x 150# P orifice
V-103 (note 4)
Additional PSV on 42 psig
104-RV-002 6" x 8" 300# x 150# Q orifice
V-104 (note 5)
Additional PSV on 42 psig
204-RV-002 6" x 8" 300# x 150# Q orifice
V-204 (note 5)
Control Valves
Flange Flange
Tag Description Size Duty Notes
Sizes Class
1. Air fail
Replace PCV on LP line 10" closed
100-PCV-186 150# CV>=1000
to LP compression (hold 2) 2. Equal %
characteristic
ESD Valves
Flange Flange Design
Tag (hold 1) Description
Sizes Class pressure
ESD Valve on new LP
202-XZV-100 8" 600# 1250psig Air fail closed
header to V202
ESD Valve on new LP
103-XZV-100 8" 600# 1250psig Air fail closed
header to V103
Metering Run
See discussion in section 6.2.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
1. Use existing ESDV 100-XZV-104 on existing line to V203, two new ESDVs required for V103 and V202
3. LCV on V202 is same size as LCVs on V103, V203; so only new valve is inlet ESDV.
4. Second PSV on pressure vessel set at 105% of design pressure (241 psig), existing PCV set at 100%
of design pressure (230 psig).
5. Second PSV on pressure vessel set at 105% of design pressure (42 psig), existing PCV set at 100% of
design pressure (40 psig).
HOLDS
2. Flange size to be confirmed by control valve vendor; either 10" or 12" required.
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030
Document No. SFD-CTE-SAPF1-G08-00003 Rev. R01
Confidential – Do Not Disclose Without Authorization © Copyright Genesis North America - All Rights Reserved
Technip USA, Inc. d/b/a Genesis North America TBPE Firm Reg. No. F-3030