ID Task Name Duration Start Finish April May June July August Septembe BME BM E BME BM E BME BM 1 PREJECT PERIOD 133 days Sat 20/04/24 Sat 31/08/24 2 Site clearance and excavation 4 days Sat 20/04/24 Wed 24/04/24 3 Trench cleaning and trench leveling4 days Sun 21/04/24 Thu 25/04/24 4 Blinding for bases and footing 7 days Sun 21/04/24 Sun 28/04/24 5 Steel fixing for bases and footing 10 days Mon 29/04/24 Thu 09/05/24 6 Concrete casting to footing and 14 days Fri 10/05/24 Fri 24/05/24 bases 7 Foundation walling 14 days Sat 25/05/24 Sat 08/06/24 8 Formwork to columns 7 days Mon 10/06/24 Mon 17/06/24 9 Casting concrete to columns 7 days Thu 20/06/24 Thu 27/06/24 10 Backfilling with murram and 14 days Sat 29/06/24 Sat 13/07/24 compaction 11 Bolt setting 7 days Mon 15/07/24 Mon 22/07/24 12 Hardcore packing to level 14 days Tue 23/07/24 Tue 06/08/24 13 Gladiator spraying, DPM 7 days Fri 09/08/24 Fri 16/08/24 spreading and BRC fixing and side formwork to slab 14 Concrete casting to slab 14 days Sat 17/08/24 Sat 31/08/24