Professional Documents
Culture Documents
2024.05.18_09_51_22am
2024.05.18_09_51_22am
2024.05.18_09_51_22am
(Appellate Jurisdiction)
IA No.525 OF 2024
APPEAL NO.157 OF 2024
VERSUS
Matrugupta Mishra
Swagitika Sahoo
Ritika Singhal
Nipun Dave
Sonakshi
Akanksha V. Ingole
Shashwat Dubey
Ananya Mishra for Res. 4
ORDER
1. The present IA No. 525 of 2024 has been filed by Appellant, M/s
Uttarakhand Jal Vidyut Nigam Ltd (“UJVNL”) in Appeal No 157 of 2024
against the Order dated 02.02.2024 in Petition No. 02 of 2024 and Order
dated 15.03.2024 in Misc. Application No. 10 of 2024 in Petition No 02 of
2024 passed by Uttarakhand Electricity Regulatory commission
(“Respondent No 1/ UERC”), seeking ex parte ad interim relief in the form
of interim connectivity to its Suringad SHP ( 5MW).
2. Learned Counsel for the Appellant submitted that UERC has only
partially allowed its prayer, granting interim connectivity of its Suringad SHP
to 33/11 KV Darati substation of UPCL from 15th December to 15th March till
the commissioning of Baram Sub-station, though it has sought interim
Page 2 of 8
IA No.525 OF 2024
APPEAL NO.157 OF 2024
connectivity from December till end of May, considering Low Flow Season (
LFS). M/s Himalaya Hydro Pvt Ltd, the (“Respondent No4 / HHPL”) has
its two hydro projects, namely, Motighat (5 MW) and Tanga (5 MW) SHP
connected to 33/11 KV Darati Substation. Learned Counsel of Appellant
further submitted that UERC vide its order dated 20.02.2023 in Misc.
Application No. 21 of 2022 has allowed ad interim connectivity to the
Suringad SHP up to 31.05.2023 subject to the fulfillment of following
directions:
ii) 1st Right of evacuation shall vest with Respondent No. 3 and
in case of evacuation constraints, Suringad SHP shall be
backed down automatically using the SPS.”
and Respondent No.4 and submit its report to this Tribunal . Appeal No. 275
of 2023 was eventually dismissed by this Tribunal on 01.06.2023 on
becoming infructuous after the expiry of interim connectivity on 31.05.2023.
Page 4 of 8
IA No.525 OF 2024
APPEAL NO.157 OF 2024
9. Learned counsel for the Appellant affirmed that during the period of
interim connectivity of its Suringad SHP upto 15th March 2024, there was no
evacuation constraints from all the three SHPs, namely, Motighat, Tanga
and Suringad, so there was no requirement of SPS operation and that SPS
was never operated. Learned counsel for the Respondent UERC submitted
Page 6 of 8
IA No.525 OF 2024
APPEAL NO.157 OF 2024
10. From the deliberations, it emerged that since SPS operation was not
warranted, it has not operated when interim connectivity to Suringad SHP
was provided up to 15th March 2024. In our opinion, efficacy of SPS and
other measures, so put in place after technical deliberations, should not be
questioned/doubted based on apprehensions that when required it will not
operate, as contended by learned counsel for Respondent No 4. The efficacy
of SPS would be an important factor while deciding the IA or the main
Appeal or the Appeal preferred by Respondent No 4.
May, 2024 till 25th May 2024. We direct the Respondent-UERC to get the
power evacuation from these three SHPs (Motighat, Tanga, Suringad)
including operation of SPS, monitored by UPCL on daily basis and a
detailed report submitted to this Tribunal by 27th May, 2024. Thereby we
shall also have the benefit of the report while deciding the rival submissions
urged by both the learned counsel for the Appellant and the 4th Respondent
in the I.A. As long as their first right of evacuation is ensured, the 4th
Respondent cannot claim to suffer prejudice on the Appellant being granted
interim connectivity. We are also of the considered view that, in case,
SPS does not operate the way it should and first right of evacuation gets
denied for the SHPs of Respondent No 4, then UPCL may disconnect the
Appellant’s Suringad HEP after recording detailed justification.
REPORTABLE / NON-REPORTABLE
ts/ag/dk
Page 8 of 8