Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 15

BILL OF QUANTITY

PROJECT :
BILL NO :
DATE :

Item No Description Unit Quantity

GENERALLY :

The following bill of Quantities are guide only. Is the


responsibility of the tenderer to measure and satisfy
themselves as to the accuracy of all The quantities for
work requiring payment. The descriptions provided
herein are for a quide only as to the required scope of
work which from part of this contract and should be
cross referenced with all drawings and specification. The
format provided in these bill should be followed in order
to assist in tender evaluation.

SITE WORKS, SUBSTRUCTURE & STRUCTURE WORK

A SITE AND PREPARATION WORKS


1 Site Clearance
Allow for site clearence, including removal of grass, trees,
vegetable soil, dispose off site
Around building area plus 1500 mm out around

a. Site clearance, cutting shrubs and small trees complate M2 587.58


cleaning and disposal

b. Cutting tree complete take a root, cleaning and disposal Item Include in external works -

2 Setting out & Timber Bouwplank

a. Setting Out Ls
b. Meranti or similar timber bouwplank as specified M1

B EARTH WORK & SUBSTRUCTURE WORK


1 Excavation Works
Excavation (top and hard fill) of any ground encountered for
foundation, levelling, etc

a. Bulk excavation and filling work to achieve pad level M3


b. to footplate foundation M3
c. to trence for riverstone masonry M3
d. to trench for tie beam M3
e. Pool Bowl M3

2 Soil Fill

Backfilling with Excavated material available including


- M3
compaction as specified in the technical specification
- Leveling & Compaction M3
imported limestone or similiar filling material in layer off 20 cm
- max, thickness to be as specified in the technical M3
specification - if any
Excavated earth filling in layers of 20 cm Max thickness to be
- compacted to build up platform as specified in technical M3
specification
Compaction as specified to underside of the following
- M2
compacting for pad ground slab

3 Sand Filling M3
Backfilling with sand 100mm thick
a. Under footplate foundation
b. under Tie beam & ground slab

Material
Sand Urug / Sand Concrete M3

Manpower
Laborer 1 p/d
Foreman 1 p/d

4 Termite Control
Termite treatment wit chemical premise (Ex Mika and similar)
product as specified in technical specification

- Underground Slab and tie beam include drying area &


M2
refuse

5 Plastic Membrane M2
Plastick membrane 0.2 mm Thick (Ex Mika or similar) on
compacted soil, Flat surface, or lean concrete without any
waves to avoid damage to membrane including cost of
material, labour Etc complete
'- Under ground Slab or above lean concreteground (if Any) M2
C LEAN CONCRETE FOUNDATION WORK M3
1 Lean Concrete K-100 Lev -6,400 M3 17.21
Lean concrete 100 mm thick including cost of all material,
labour, tool equipment, etc complete as specified

Lean Concrete Foundation Lev -6,400 M3 17.21

Monolithic MF-1 M3 1.68


Monolithic MF-2 M3 0.23
Monolithic MF-3 M3 12.1
Monolithic MF-4 M3 3.2

Material

Concrete Ready Mix K-100 @ Jaya Mix M3 17.21

Manpower
Laborer 1p/d 17
bricklayer 1p/d 2
Foreman 1p/d 1

Equipment

Concrete Pump Capacity 4 M3 Day 1


Concrete Vibrator Day 1

2 Lean Concrete K-100 Lev -5,900 M3 -

D MONOLITHIC FOUNDATION
1 Foundation Lev -6,400 M3 74.04
Monolithic Mf-1 M3 7.2
Monolithic Mf-2 M3 0.84
Monolithic Mf-3 M3 53.1
Monolithic Mf-4 M3 12.9

a. Concrete Work K-250 M3 74.04


Material
Concrete Ready Mix K-250 @ Jaya Mix M3 74.04

Manpower
Laborer 1p/d 33
bricklayer 1p/d 10
Foreman 1p/d 2
Equipment
Concrete Pump Capacity 4 M3 Day 3
Concrete Vibrator Day 3
b. Rebar Work Kg 8494
Material
Rebar A500C - Ǿ16 mm Kg 5340.06
Rebar A500C - Ǿ18 mm Kg 3154.0
Manpower
Laborer 1p/d 85
Metal Working 1p/d 85
Foreman 1p/d 3
Equipment
Bar Bending Day 9
Bar Cutter Day 9
c. Formwork M2 442.9225
Foundation Formwork
Monolithic Mf-1 M2 19.2
Monolithic Mf-2 M2 4.2
Monolithic Mf-3 M2 294.5
Monolithic Mf-4 M2 125.02
Material
Wooden Block @Kruing Wood Size 5cm x 5 cm x 400 cm Pcs 62
Wooden Block @Kruing Wood Size 10 cm x 10 cm x 400 cm Pcs 62
Multiplek 12 mm Sheet 35
Nail 3 Inch Kg 11
Nail 6 Inch Kg 11
Formwork oil Ltr 89

Manpower
Laborer 1p/d 91
Carpenter 1p/d 91
Foreman 1p/d 4

E FOUNDATION MONOLITHIC VERTICAL


1 Foundation Lev -5,900 M3 136.57
Monolithic Vertical Elements M3 136.57

a. Concrete Work K-250 M3 136.57

Material
Concrete Ready Mix K-250 @ Jaya Mix M3 136.57

Manpower
Laborer 1p/d 61
bricklayer 1p/d 19
Foreman 1p/d 3
Equipment
Concrete Pump Capacity 4 M3 Day 6
Concrete Vibrator Day 6
b. Rebar Work Kg 1078

Material
Rebar A500C - Ǿ18 mm Kg 11347.4
Rebar A500C - Ǿ16 mm Kg 104.3
Rebar A500C - Ǿ12mm Kg 6486.6
Rebar A240C - Ǿ8 mm Kg 973.5
Manpower
Laborer 1p/d 11
Metal Working 1p/d 11
Foreman 1p/d 1
Equipment
Bar Bending Day
Bar Cutter Day 2
c. Formwork M2 0
Rates (Rp) Amou

Material, Tool & Material, Tool &


Labour Total
Equipment Equipment

IDR 20,000.00

Include in external works - if any


Rp 1,400,000.00 Rp 1,400,000.00 Rp 24,094,000.00

Rp 219,000.00
Rp 250,000.00 Rp 749,000.00
Rp 280,000.00

Rp 4,700,000.00 Rp 4,700,000.00
Rp 4,750,200.00
Rp 50,200.00 Rp 50,200.00

Rp 1,400,000.00 Rp 1,400,000.00 Rp 103,656,000.00

Rp 219,000.00
Rp 250,000.00 Rp 749,000.00
Rp 280,000.00

Rp 4,700,000.00 Rp 14,100,000.00
Rp 4,750,200.00
Rp 50,200.00 Rp 150,600.00
Rp 16,200.00
Rp 16,200.00 Rp 86,508,972.00
Rp 32,400.00
Rp 16,200.00 Rp 51,094,800.00

IDR 145,000.00
IDR 135,000.00 IDR 435,000.00
IDR 155,000.00

Rp 172,500.00 Rp 172,500.00 Rp 1,552,500.00

Rp 330,000.00 Rp 20,463,019.50
Rp 350,000.00 Rp 21,703,202.50
Rp 231,990.00 Rp 8,220,287.26
Rp 1,001,990.00
Rp 30,000.00 Rp 332,191.87
Rp 30,000.00 Rp 330,000.00
Rp 30,000.00 Rp 2,657,535.00

IDR 219,000.00
IDR 215,000.00 Rp 684,000.00
IDR 250,000.00

Rp 1,400,000.00 Rp 1,400,000.00 Rp 191,198,000.00

Rp 219,000.00
Rp 250,000.00 Rp 749,000.00
Rp 280,000.00

Rp 4,700,000.00 Rp 28,200,000.00
Rp 4,750,200.00
Rp 50,200.00 Rp 301,200.00
Rp 284,256.04
Rp 16,200.00 Rp 183,827,880.00
Rp 16,200.00 Rp 1,689,660.00
Rp 64,800.00
Rp 16,200.00 Rp 105,082,920.00
Rp 16,200.00 Rp 15,770,700.00

IDR 145,000.00
IDR 135,000.00 IDR 435,000.00
IDR 155,000.00

Rp 172,500.00 Rp 172,500.00 Rp 345,000.00


Amount

Remarks
Labour Total IDR (Rp)

IDR 11,751,524.80 IDR 11,751,524.80

0
IDR -

Rp 33,486,935.00
Rp 24,094,000.00

Rp 3,768,990.00
Rp 593,745.00 Rp 4,642,735.00
Rp 280,000.00

Rp 4,750,200.00

NOT DESIGN LEAN CONCRETE

Rp 385,880,228.93

Rp 128,193,600.00

Rp 103,656,000.00

Rp 7,227,000.00
Rp 2,500,000.00 Rp 10,287,000.00
Rp 560,000.00

Rp 14,250,600.00

IDR 163,466,271.72
Produktivitas Equipment :
Bar Bending / Day =1000 Kg/day
Rp 137,603,772.00
Bar Cutter / Day =1000 Kg/day

Rp 12,316,387.00
Rp 11,466,981.00 Rp 24,309,999.72
Rp 526,631.72

Rp 1,552,500.00

Rp 91,470.00 IDR 94,220,357.21

Rp 53,706,236.14

Rp 19,885,005.64
Rp 19,521,809.19 Rp 40,514,121.08
Rp 1,107,306.25

Rp 238,648,200.00

Rp 191,198,000.00

Rp 13,359,000.00
Rp 4,750,000.00 Rp 18,949,000.00
Rp 840,000.00

Rp 28,501,200.00

IDR 309,951,160.00

Produktivitas Equipment :
Bar Bending / Day =1000 Kg/day
Bar Cutter / Day =1000 Kg/day
Rp 306,371,160.00

Rp 1,595,000.00
Rp 1,485,000.00 Rp 3,235,000.00
Rp 155,000.00

Rp 345,000.00

#DIV/0! IDR -

You might also like