Project : Vietnam Yen Binh WtE Project

Scope of Direct Work & Supply Job No. : PE6946


(Steel Structure Work) ITB No. : PE6946-ITB-001
Rev No. : 0

02_req_att_02_04

SCOPE OF DIRECT WORK & SUPPLY

(Steel Structure Work)


Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Steel Structure Work) ITB No. : PE6946-ITB-001
Rev No. : 0

SCOPE OF DIRECT WORK & SUPPLY


(STEEL STRUCTURAL WORK)

Description Bidder SECL Remarks

A. DIRECT MATERIALS

1. Structural Steel Materials


i.e) profiles & tubular
1) Structural steel X
steel
2) Plates and built-up shapes X

3) High tension bolt with nuts X

4) Common bolt with nuts X


i.e) Grating, Checkered
5) Floorings including fixing accessories X
plate
Miscellaneous steel items including fixing i.e) ladder, handrail, stair
6) X
accessories etc.
7) Painting on steel structures X
Touch up painting on steel structures at
8) X
field
Structural steel and Misc. steel supplied * Field touch up paint is
9) X(*)
by SECL’s vendor under Bidder’s scope
2. Cladding Materials(Roofing & Siding)
i.e) Un-insulated Single
Roof & Wall metal claddings including
1) X panels, Insulated
fixing materials
sandwich panels
i.e) Gutter, Flashing,
2) Miscellaneous cladding materials X Splash block, Down Spot
etc.
3. Others
Anchor bolt & nuts for steel structure
1) X(*) * by civil contractor
foundations
Grouting material for steel structure
2) X
foundations
3) Fire-proofing material for steel structures X(*) * by other contractor
Other materials necessary for the
4) X
installation work
B. DIRECT LABOR

1) Wages X

Page 1 of 7
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Steel Structure Work) ITB No. : PE6946-ITB-001
Rev No. : 0

SCOPE OF DIRECT WORK & SUPPLY


(STEEL STRUCTURAL WORK)

Description Bidder SECL Remarks

2) Overtime Premiums X

3) Camp X

4) Catering X

5) Insurance X

6) Taxes X

7) Transportation X

8) Recruitment X

9) Others X

C. DIRECT CONSTRUCTION EQUIPMENT

1) Construction equipment / operator X


- Mob. & Demob. charge of construction
X
Equipment.
- Valid construction equipment test
X
certificate to SECL.
2) Maintenance / Repair Work / Spare Parts X

3) Fuel for construction equipment X

D. TOOLS AND CONSUMABLE

1. Tools & Consumable for Steel Structural erection X

2. Tools & Consumable for Cladding Works X

3. Utilities

1) Filtered water (For Construction & Test) X

2) Demin. Water X

3) Drinking water X

4) Electric power X

Page 2 of 7
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Steel Structure Work) ITB No. : PE6946-ITB-001
Rev No. : 0

SCOPE OF DIRECT WORK & SUPPLY


(STEEL STRUCTURAL WORK)

Description Bidder SECL Remarks

5) Air (I.e. N2, Arc etc.) X

4. Scaffolding

1) Scaffolding Materials X

2) Erection / Removal X

3) Maintenance & Repair X

5. Others X

E. GENERAL WORK

1. Material Handling
Receiving, unpacking, unloading of the
Steel Structure material supplied by
1) X
Bidder at warehouse, and/or laydown
area
Loading, Unloading and transportation
2) X
from Bidder’s warehouse to Jobsite
3) Control and handling of received materials X
Surplus and scrap materials to be
4) returned to storage area or removed to X
designation area confirmed by SECL
Custody of all materials required for the
5) X
work
6) Storage and preservation of all materials X
2. Transportation For Direct Materials Supplied By
Bidder
1) Export Packing X
Inland transportation inside exporting
2) X
country
Forwarding charge such as acquisition
clearance, preparation of shipping
3) X
documents, warehousing. handling and
similar
4) Ocean/Air freight including surcharge X

Page 3 of 7
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Steel Structure Work) ITB No. : PE6946-ITB-001
Rev No. : 0

SCOPE OF DIRECT WORK & SUPPLY


(STEEL STRUCTURAL WORK)

Description Bidder SECL Remarks


Unloading, landing, import expense,
5) storage or warehousing charges and X
similar
Inland transportation inside importing
6) X
country including cartage charges
Transportation between BIDDER’s
7) prefabrication yard and the location of X
installation and storage area
8) Others, if any X

3. General Work

1) Welding procedure qualification test X Note 1

2) Welder’s qualification test X Note 1


Preparation of work permit in the existing
3) X
area
Scaffolding works for erection, inspection
4) X
and test
Marking on fabricated steel members and
5) X
supports
Mark on members to be painting / coating
6) X
/ galvanizing
4. Steel Structural Work

1) Shop Fabrication X

2) Erection & Installation X


Installation of floorings
3) X
i.e) Grating, Checkered plate
Installation of miscellaneous steel items
4) X
i.e) ladder, handrail, stair etc.
5) Grouting work X
Touch up painting works for steel
6) X
structures
5. Cladding Works(*) * Roofing & Siding
Installation of metal cladding for roof and
1) X
walls

Page 4 of 7
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Steel Structure Work) ITB No. : PE6946-ITB-001
Rev No. : 0

SCOPE OF DIRECT WORK & SUPPLY


(STEEL STRUCTURAL WORK)

Description Bidder SECL Remarks

i.e) Flashings, Gutters,


2) Installation of misc. cladding materials X
downspouts, Etc.

6. Surveys

1) Topographic X By other contractor

2) Geological X By other contractor

3) Base bench mark X By other contractor

4) Foundation elevation & location check X

5) Sub bench mark X

7. Test and Inspection


All other testing and inspection required to
1) ensure that the Work meets the X
requirements of the SECL
8. Punch Clear Works X

9. Demolition Works

1) Demolition works. X

2) Restoration works of the demolished part X

10. Preservation

1) Required protection for the work X

2) Preservation X

11. PRECOMMISSIONING X By other contractor

12. COMMISSIONING X By other contractor

F. SPECIFIC WORK

1) Site cleaning(Housekeeping) X
Other required works for the completion of
2) X
work

Page 5 of 7
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Steel Structure Work) ITB No. : PE6946-ITB-001
Rev No. : 0

SCOPE OF DIRECT WORK & SUPPLY


(STEEL STRUCTURAL WORK)

Description Bidder SECL Remarks


Coordination & cooperation for all
3) X
interface works with other subcontractors
Safety scaffolding, safety net and other
4) X
necessary facilities for inspection & test
5) Fire-proofing work for steel structures X(*) * By other contractor
In cases where a minor
Other required minor work such as repair,
repair is not possible,
modification, adjustment, alignment, trail
BIDDER shall officially
6) excavation, etc. X
discuss with SECL and it
(BIDDER shall consider adequate cost for
shall be confirmed from
repair work in their proposed unit price)
SECL
In cases where a minor
Repair of hand rails, floors and stages
repair is not possible,
which have been damaged or holed by
BIDDER shall officially
7) other work X
discuss with SECL and it
(BIDDER shall consider adequate cost for
shall be confirmed from
repair work in their proposed unit price)
SECL
In cases where a minor
Minor repair caused during shipment or repair is not possible,
delivery by others BIDDER shall officially
8) X
(BIDDER shall consider adequate cost for discuss with SECL and it
repair work in their proposed unit price) shall be confirmed from
SECL
(High tension) bolt tightening work
In addition, the bolt tightening of all steel
9) X
structures shall be done by calibrated
torque wrench
Before the commencement of the steel
structure erection work, Bidder shall
10) X
inspect the location of anchor bolts and
the result shall be approved by contractor
G. NOTE
Welding procedure qualification test shall be performed under applicable standards and regulation,
1.
and the BIDDER shall submit the procedure to SECL for approval prior to test
The BIDDER shall understand above scope of work completely, and comply that the cost incurred by
2. above items shall be included in BIDDER's quotation and/or contract amount irrespective of being not
shown as line items (work items) on BOQ in ITB and/or indirect scope of work.

Page 6 of 7