0. ENGINEERING
A. DIRECT MATERIALS
1. Pipe Materials
Page 1 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
5) U-clamp X
8) Stiffener rings X
Page 2 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
B. DIRECT LABOR
1) Wages X
2) Overtime Premiums X
3) Camp X
4) Catering X
5) Insurance X
6) Taxes X
7) Transportation X
8) Recruitment X
9) Others X
Page 3 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
5) Threaded compound X
Gasket compound and anti-seizing
6) X
solvent for bolts/nuts
Tools, consumables, test materials for
7) NDE and PWHT work such as film, X
chemical, magnetic particles and etc
8) Welding Rod X
4) Threaded compound X
Materials for temporary access road for
5) X
piping work
Materials for welding qualification and
6) X
welder test
7) Test materials for WPS and PQR X(*) * Note 2
3. Tools & Consumables, Temporary Materials for
Pressure Test
Tools and consumables for pressure test
1) X
such as hydro pump, test recorder, etc.
2) Temporary blinds and spacers X
Page 4 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
2) Demin. Water X
3) Drinking water X
4) Electric power X
6) Others, if any X
6. Scaffolding
E. GENERAL WORK
Page 5 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
2. Material Handling
Receiving, unpacking, unloading of the
(*) Bidder shall complete
piping material supplied by SECL at
1) X(*) unpacking within 3day
SECL’s warehouse, and/or lay-down area
after SECL request.
and/or prefabrication shop
Loading and transportation from SECL’s
2) warehouse to Jobsite and/or pre- X
fabrication shop
Transportation from the prefabrication
3) shop to jobsite, and loading/unloading at X
prefabrication shop and jobsite
Transportation from SECL’s warehouse
and/or lay down area to painting shop,
4) X
loading/unloading of raw pipe materials
and pipe support
Transportation from painting shop in lay-
5) down area to jobsite, loading/unloading of X
raw pipe materials and pipe support
Transportation between valve test area to
6) jobsite include loading/unloading at valve X
test area and jobsite
Transportation between Safety valve
Popping test area to jobsite include
7) X
loading/unloading at safety valve popping
test area and jobsite
Surplus and scrap materials to be
returned to designated area by SECL (i.e.
8) SECL warehouse) or removed to out of X
jobsite conforming to local regulation, if
requested by SECL
9) Control and handling of received materials X
Material storing, protection and custody in
10) X
BIDDER's warehouse
Cleaning the spool and providing the
11) protection device of opened ends such as X
beveled end, flange and tools
① Capping end of pipe & valve X
③ Rust prevention X
Page 6 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
Page 7 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
Page 8 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
Page 9 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
Page 10 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
Page 11 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
① Supply of oil X
② Disposal of oil X
Cleaning of suction pipe of compressor
9) X
and air blower
10) N2 seal after chemical cleaning X
10. Reinstatement X
11. Commissioning X
12. Others
Marking the spool piece number and color
on fabricated piping and supports in
1) accordance with SECL’s instruction X
(Marking the spool piece number and
color material coding)
Mark spools to be galvanized by hard
2) X
stamping
Providing temporary access road for
3) X
piping Work
Page 12 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
F. SPECIFIC WORK
1) Site cleaning(Housekeeping) X
Other required works for the completion of
2) X
work
Coordination & cooperation for all
3) X
interface works with other subcontractors
Safety scaffolding, safety net and other
4) X
necessary facilities for inspection & test
Any modification during punch work due
5) to BIDDER's fault or not completed by X
BIDDER
Acceleration work to recover delayed
6) X
progress due to BIDDERS's fault
Maintaining & monitoring the quality of
7) test water according to project X
requirement.
8) Water drain & air dry work after hydro test X
Providing temporary road for equipment
9) X
access for piping work
Install scaffolding for piping work at all
10) X
floor of pipe rack
G. FMCS(Field Material Control System)
*Monthly Base of
Operating FMC System for piping Payment shall be
1) X(*) calculated based on
construction management. data entered in FMC
System.
2) Input all Weld Joint, Pipe Spool, and Pipe X
Support data in FMC system
3) Input all Fit-Up, Welding, Welder data in X
FMC System.
All personnel and equipment(PC) for *SECL shall provide
4) X(*) ID/PW for FMC System
Operating system
to Subcontractors.
PC utilized only for FMC in order to
5) X
protect Data and security reasons.
H. Field work Related Module Installation
Tie-in work between modules and * Including edge
1) module-to-stick built, including alignment X(*) preparation, if required
of pre-installed piping inside module * Including pipe support
Page 13 of 14
Project : Vietnam Yen Binh WtE Project
Scope of Direct Work & Supply Job No. : PE6946
(Piping Work) ITB No. : PE6946-ITB-001
Rev No. : 0
In-line components such as control valve, on-off valve, PSV and instruments shall be installed two(2)
times for hydro-testing and Water flushing / Air blowing. For hydro-testing and water flushing / air
3.
blowing, the installed in-line components shall be replaced with temporary pipe spools and after hydro-
testing and water flushing / air blowing, the in-line components shall be re-installed.
Welding procedure qualification test shall be performed under applicable standards and regulation,
4.
and the BIDDER shall submit the procedure to SECL for approval prior to test
The BIDDER shall understand above scope of work completely, and comply that the cost incurred by
5. above items shall be included in BIDDER's quotation and/or contract amount irrespective of being not
shown as line items (work items) on BOQ in ITB and/or indirect scope of work.
The BIDDER shall consider for the preservation of foundation after receiving the foundation from other
6.
Subcontractor until handover to Contractor.