POLAVARAM H.E.

PROJECT ( 12 X 80 MW)
Action taken report on Minutes of 37th CCM Dt: 24.05.2024 and Agenda for 38th CCM Dt: 28.06.2024
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM

A E&M ISSUES (HEAD QUARTERS)


27B(1) The works are being hampered due to Unit-11 DT Elbow liner will be Not yet received MEIl to update the status on the
lack of E&M equipment. M/s MEIL has dispatched at BHEL by 7th June. Unit- remaining material supplies.
to expedite the materials supplies. 12 DT Elbow liner will be supplied by
31st August.

36A(2) EOT and stay ring erection schedule is Unloading bay EOT crane erection by Latest status of works need to be
to be furnished August end. 1No. Service bay EOT- updated MEIL to respond
crane by October - 2024

37A(3) The status of Civil and H&M drawings is


also to be updated in the monthly
Not incorporated in the Monthly
progress report in line with the E&M MEIL accepted to incorporate MEIL to respond
Progress report of May 24
status of drawings

37A(5) Supply details of embedments for the


runner pit in maintenance bay shall be
submitted at the earliest as the MEIL informed that embedments will be
maintenace bay floor concreting is supplied duly consulting BHEL Not yet received MEIL to respond
being planned.

38A(1) In accordance to the 28th CCM and


35th CCM, it was agreed to scruplously
follow the procedure of furnishing the
inspection calls after obtaining the
Approved drawings. Even though it was
repeatedly informed again inspection
call was raised for runner blades and New Point MEIL to respond
subsequently R0 drawings for the same
were furnished.
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM

38A(2) Drawings are being dispatched with


Saturday dates and submitted in this
office on mondays. However several
times it was instructed to furnish the New Point MEIL to respond
drawings from Monday onwards

38A(3) In compliance to the point 36A(1)


forecasted BHEL supplies for Q2 was
furnished in the monthly progress
report of May 24. However several
mistakes were observed in the unit
details, some of the material to be
received are not shown. Request to New Point MEIL to respond
cross check the details furnished by
BHEL before submission and adhere to
the supply schedule.

B E&M ISSUES (FIELD)


36 B(1) As per the approved drawing for pipes MEIL agreed to incorporate in Revision- Revised EMGA R-10 received on
and embedments in second Stage-R3, 10 EMGA drawing and revised EMGA 22.06.2024
layout of the Runner aeration pipes for drawing will be submitted by
all the 12 units shall be shown in EMGA 10.06.2024
drawings upto termination above
EL+35m

C WAPCOS
38C(1) It is noticed that the deputed E&M WAPCOS to update the latest
consultant was not available at New Point status
Vijayawada WAPCOS office.

D SITE CIVIL ISSUES:


36 D(1) Construction schedule for RCC works
for Unloading and service bay (Civil
works)
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM

21D(7) Construction schedule for Units 1,2&3


(Civil works).
35 D(1) Construction schedule for columns,
roof trusses, EOT crane girder for
Unloading & Service bay and for Units 1
to 3:

(i)Procurement of structural steel


(ii) Fabrication of structural steel MEIL agreed to submit comprehensive MEIL has not furnished the programs
(iii) erection of structural steel MEIL to respond
program by 15.06.2024. inspite of several requests.

35 D(3) Construction schedule for U/s side -


Intake pool & Intake structure for Units
1 to 3

35 D(2) Construction schedule for TRC


36 D(2) Submission of program for completion
of project Hostel.
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM

36 D(3) Submission of program for completion


of Storage sheds.
36 D(4) Augmentation of labour at all fronts to MEIL to improve 200 Nos progressively Not improved. MEIL to revert.
improve progress. The fronts such as by 15.06.2024.
U/s transition, U/s Intake arears, D/s
transition, raising of B&D line walls
etc., are available.

38 D(1) Fabrication of structural steel at site M/s MEIL is requested to fabricate the
fabrication yards. structural steel columns, crane girder
beams etc., for PH building at site
fabrication yard as it is lying vacant due
to completion of penstock steel liners
work.

E ENGINEERING ISSUES ( CIVIL):


11F(1) Designs and drawings of tail race pool MEIL agreed to submit by 27.05.2024. MEIL furnished the revised design and WAPCOS to furnish
including retaining walls. drawings on 05.06.2024 observations / comments.
9E(1) Submission of Tail Race Channel (TRC) MEIL agreed to submit by 30.05.2024. MEIL has not furnished. MEIL to furnish designs &
designs & drawings along with outfall drawings for TRC for initial rock
structure. portion (Ch: 596.50m to Ch:
TRC for initial rock portion (Ch: 656.50m).
596.50m to Ch: 656.50m).

19E(4) (i) Design of rope drum hoist for DT MEIL informed that to organise the (i) MEIL submitted revised drawings on ( i) WAPCOS to respond.
gates meeting at the earliest. 10.04.2024.Comments from WAPCOS yet
(ii) gantry crane for Stoplog gates. to be received.
(ii) Meeting held on 10.06.2024 with (ii) MEIL to review & confirm the
MEIL, APGENCO & WAPCOS maximum possible increase in
rail spacing of gantry crane
beyond 3m proposed in the
designs against the spacing of
5m as per the agreement.
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM

27E(2) Design and drawings for MEIL agreed to submit revised drawings (i.a) MEIL submitted the B-row wall cut ia. Wapcos to respond.
i. B-row wall with columns. of B-row wall cutouts & Downstream out drawings for Unit # 1 along with cut
ii. D/s annex building columns, beams floor cutouts to APGENCO by out drawings for drainage and Ib. APGENCO will issue approval
& floors. 31.05.2024. dewatering sump slab on 04.06.2024. on 25.06.2024.
Based on approval civil drawings will be Comments from WAPCOS to be
submitted received.
(i.b) MEIL submitted B-line wall cut out
details drawings for units 2 to 11on
12.06.2024. WAPCOS comments
received on 14.06.2024.
ii. MEIL has not submitted D/s Annex Ii. MEIL to respond.
building drawings.
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM

29E(2) Furnishing of Non-plant buildings layout MEIL agreed to submit by 06.06.2024. MEIL has not furnished. MEIL to respond.

29E(3) Furnishing of spiral casing drawings (i) MEIL to furnish revised drawings as i. MEIL has not furnished. i. MEIL to respond..
per discussions in virtual meeting
dt:22.05.2024 by 30.05.2024.

(ii) MEIL to construct a physical model Ii. MEIL not complied so far. Ii. MEIL to update status.
at site as agreed during the meeting.

29E(4) U/s Annexe building floor designs & MEIL agreed to submit by 10.06.2024. MEIL to submit comprehensive drawings MEIL to respond.
drawings as per approved EMGA of U/S annex building for all units (1 to
drawings. 12) duly relocating the staircase as per
the modified layout (Approved in 36th
CCM).

34E(1) Designs and drawings of Machine hall WAPCOS agreed to submit by WAPCOS has not yet furnished. WAPCOS to furnish observations.
floor at EL +26.00m between D&B lines 28.05.2024.

35E(2) Submission of revised and consolidated MEIL agreed to submit by 15.06.2024. MEIL has not furnished. MEIL to furnish the revised
drawings of Appproach channel and drawings.
intake pool drawings as per approved
intake structure Unit-1 and Unit-12,
drawings end pier layouts.

36 E (1) Revised drawings for service bay grids 9 MEIL agreed to submit by 30.05.2024 MEIL communicated the modified draft MEIL to respond.
to 12 between ch: 500.50m(B-line) to drawings vide email on 29.05.2024. The
519.40m (A-line) same were reviewed and accepted by
APGENCO & WAPCOS. MEIL to submit
the same officially for approval of
APGENCO.
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM

36 E (2) TRC outfall structure. MEIL to revert. MEIl to submit the proposals for MEIL to respond.
a) TRC right bank in the river course.
b) Outfall structure including planning &
designing of area between downstream
of ECRF GAP-1

MEIL WAPCOS APGENCO