PROJECT ( 12 X 80 MW)
Action taken report on Minutes of 37th CCM Dt: 24.05.2024 and Agenda for 38th CCM Dt: 28.06.2024
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM
36A(2) EOT and stay ring erection schedule is Unloading bay EOT crane erection by Latest status of works need to be
to be furnished August end. 1No. Service bay EOT- updated MEIL to respond
crane by October - 2024
C WAPCOS
38C(1) It is noticed that the deputed E&M WAPCOS to update the latest
consultant was not available at New Point status
Vijayawada WAPCOS office.
38 D(1) Fabrication of structural steel at site M/s MEIL is requested to fabricate the
fabrication yards. structural steel columns, crane girder
beams etc., for PH building at site
fabrication yard as it is lying vacant due
to completion of penstock steel liners
work.
19E(4) (i) Design of rope drum hoist for DT MEIL informed that to organise the (i) MEIL submitted revised drawings on ( i) WAPCOS to respond.
gates meeting at the earliest. 10.04.2024.Comments from WAPCOS yet
(ii) gantry crane for Stoplog gates. to be received.
(ii) Meeting held on 10.06.2024 with (ii) MEIL to review & confirm the
MEIL, APGENCO & WAPCOS maximum possible increase in
rail spacing of gantry crane
beyond 3m proposed in the
designs against the spacing of
5m as per the agreement.
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM
27E(2) Design and drawings for MEIL agreed to submit revised drawings (i.a) MEIL submitted the B-row wall cut ia. Wapcos to respond.
i. B-row wall with columns. of B-row wall cutouts & Downstream out drawings for Unit # 1 along with cut
ii. D/s annex building columns, beams floor cutouts to APGENCO by out drawings for drainage and Ib. APGENCO will issue approval
& floors. 31.05.2024. dewatering sump slab on 04.06.2024. on 25.06.2024.
Based on approval civil drawings will be Comments from WAPCOS to be
submitted received.
(i.b) MEIL submitted B-line wall cut out
details drawings for units 2 to 11on
12.06.2024. WAPCOS comments
received on 14.06.2024.
ii. MEIL has not submitted D/s Annex Ii. MEIL to respond.
building drawings.
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM
29E(2) Furnishing of Non-plant buildings layout MEIL agreed to submit by 06.06.2024. MEIL has not furnished. MEIL to respond.
29E(3) Furnishing of spiral casing drawings (i) MEIL to furnish revised drawings as i. MEIL has not furnished. i. MEIL to respond..
per discussions in virtual meeting
dt:22.05.2024 by 30.05.2024.
(ii) MEIL to construct a physical model Ii. MEIL not complied so far. Ii. MEIL to update status.
at site as agreed during the meeting.
29E(4) U/s Annexe building floor designs & MEIL agreed to submit by 10.06.2024. MEIL to submit comprehensive drawings MEIL to respond.
drawings as per approved EMGA of U/S annex building for all units (1 to
drawings. 12) duly relocating the staircase as per
the modified layout (Approved in 36th
CCM).
34E(1) Designs and drawings of Machine hall WAPCOS agreed to submit by WAPCOS has not yet furnished. WAPCOS to furnish observations.
floor at EL +26.00m between D&B lines 28.05.2024.
35E(2) Submission of revised and consolidated MEIL agreed to submit by 15.06.2024. MEIL has not furnished. MEIL to furnish the revised
drawings of Appproach channel and drawings.
intake pool drawings as per approved
intake structure Unit-1 and Unit-12,
drawings end pier layouts.
36 E (1) Revised drawings for service bay grids 9 MEIL agreed to submit by 30.05.2024 MEIL communicated the modified draft MEIL to respond.
to 12 between ch: 500.50m(B-line) to drawings vide email on 29.05.2024. The
519.40m (A-line) same were reviewed and accepted by
APGENCO & WAPCOS. MEIL to submit
the same officially for approval of
APGENCO.
Agenda Issue Minutes of 37th CCM Action taken on the MOM of 37th Agenda for 38th CCM Resolution
item No CCM
36 E (2) TRC outfall structure. MEIL to revert. MEIl to submit the proposals for MEIL to respond.
a) TRC right bank in the river course.
b) Outfall structure including planning &
designing of area between downstream
of ECRF GAP-1