Packaged MBBR units

Number of Units 2 Nos. for Ph1 & 2Nos. for future expansion (Ph2).

Average Flow rate 100 m3/day (per unit)

Design BOD (1) 1160 mg/l

Each unit consists of three - Anoxic Chamber


main chambers (2)(3)
-Aerobic Chamber

-Clarification (settling) Chamber

Each Packaged unit is - Vertical mixer for the anoxic chamber


complete with (4)
-MBBR Media for both anoxic and aerobic chambers.

-Medium/Coarse Bubble Air distribution system for aerobic chamber.

-Rotary Displacement Air Blowers (duty standby)

-Sludge Transfer pumps (Submersible or Air Lift)

-Lamella plates or tube settlers for clarification tank.

-Necessary pipes and fittings

-Local control panel

- 2 Years spare parts

(1) The BOD is expected to be reduced in the DAF unit; however, this should not be
considered in the design of the Packaged MBBR units in order to be able to accommodate
any future or unexpected increase in the BOD load.

(2) The required volume of each chamber within the packaged units is to be determined by
the packaged unit manufacturer according to the design criteria they use to meet the
required effluent quality.

(3) The aerobic chamber may consist of more than one stage in series depending on the
packaged unit’s manufacturer design and standards.

(4) Any additional (parts /components/equipment) that the packaged unit manufacturer
deems necessary to complete the works and meet the required effluent quality should be
included in their offer.