METHOD STATEMENT TITLE
TABLE OF CONTENTS
1. Introduction
2. Purpose
3. Scope
4. References
5. Definitions
6. Responsibilities
7. Safety Precautions
9. Installation Procedure
11. Documentation
12. Appendices
MS REF NO.:
R08-HE4C33-ATL-MTS-
PROJECT:
Method of Statement for Installation FE-0001
Shura East
of Domestic Kitchen Appliances REV : C0
Hotel – HE4
DATE : 04.06.2024
PAGE 3 OF 10
1. Introduction
This Method of Statement (MOS) details the procedure for the installation of domestic kitchen appliances,
including stoves, hoods, ovens, built-in fridges, ice makers, and coffee machines, at the Shura Island Villas.
All appliances are electrical and intended for use in domestic kitchens.
2. Purpose
The purpose of this MOS is to ensure the correct, safe, and efficient installation of kitchen appliances in
compliance with the project specifications and manufacturer's guidelines.
3. Scope
This MOS covers the installation of the following electrical kitchen appliances in the villas at Shura Island:
- Stove
- Hood
- Oven
- Built-in fridge
- Ice maker
- Coffee machine
4. References
- Project Specifications
- Manufacturer's Installation Manuals
- Health, Safety, and Environmental (HSE) Regulations
- Electrical Codes and Standards
5. Definitions
6. Responsibilities
7. Safety Precautions
9. Installation Procedure
1. **Positioning:**
- Place the stove in its designated location.
- Ensure it is level using a spirit level.
2. **Electrical Connection:**
- Connect the stove to the electrical outlet as per the manufacturer’s instructions.
- Secure the appliance to prevent movement.
3. **Testing:**
- Switch on the power and test the stove to ensure it is working correctly.
2. **Electrical Connection:**
- Connect the hood to the electrical supply following the manufacturer’s instructions.
MS REF NO.:
R08-HE4C33-ATL-MTS-
PROJECT:
Method of Statement for Installation FE-0001
Shura East
of Domestic Kitchen Appliances REV : C0
Hotel – HE4
DATE : 04.06.2024
PAGE 5 OF 10
3. **Testing:**
- Test the hood's operation to ensure proper ventilation and lighting.
1. Positioning:**
- Slide the oven into the cabinet space.
- Ensure it is level and fits snugly.
2. Electrical Connection:
- Connect the oven to the electrical outlet.
- Secure the oven in place as per the installation guide.
3. Testing:
- Switch on the power and test the oven’s functions.
1. Positioning:
- Place the fridge in its designated built-in space.
- Ensure it is level and has adequate ventilation clearance.
2. Electrical Connection:
- Connect the fridge to the electrical outlet.
- Secure the appliance to prevent any movement.
3. Testing:
- Switch on the power and check the cooling operation.
2. Electrical Connection:
- Connect the ice maker to the electrical outlet.
- Secure the appliance.
3. Testing:
- Test the ice maker to ensure it produces ice correctly.
1. Positioning:
- Place the coffee machine in its designated spot.
- Ensure it is stable and level.
2. Electrical Connection:
- Connect the coffee machine to the electrical outlet.
- Secure any loose parts.
3. Testing:
- Test the coffee machine’s functions.
- Inspect all installations to ensure compliance with the manufacturer’s guidelines and project
specifications.
- Conduct functional tests for each appliance to verify proper operation.
- Document all inspection and test results.
11. Documentation
- Maintain a record of all installations including date, installer’s name, and any issues encountered.
- Submit installation reports to the QA/QC Manager and Client Representative.
12. Appendices
Hood:
1. Mark mounting points on the wall.
2. Drill holes and install mounting brackets.
3. Secure the hood to the brackets.
4. Connect to the electrical supply and ductwork.
5. Test operation (ensure proper ventilation).
Coffee Machine:
1. Position the machine according to the design.
2. Connect to water supply and electrical outlet.
3. Secure the machine as per the manufacturer’s instructions.
4. Test operation (run a cycle to ensure functionality).
Built-in Fridge:
1. Position the fridge in the allocated space.
2. Level the appliance using adjustable feet.
3. Connect to the water supply if it has a water/ice dispenser.
4. Connect to the electrical outlet.
5. Secure the fridge to the cabinetry.
6. Test operation (ensure cooling and ice/water dispensing).
Ice Maker:
1. Position the ice maker in the allocated space.
2. Connect to the water supply and drain.
3. Connect to the electrical outlet.
4. Secure the appliance as per the manufacturer’s instructions.
5. Test operation (ensure ice production).
7. Safety Measures
- PPE: gloves, safety glasses, ear protection.
MS REF NO.:
R08-HE4C33-ATL-MTS-
PROJECT:
Method of Statement for Installation FE-0001
Shura East
of Domestic Kitchen Appliances REV : C0
Hotel – HE4
DATE : 04.06.2024
PAGE 8 OF 10
- Electrical safety: turn off power before installation, use insulated tools.
- Manual handling procedures: use lifting aids or team lifts for heavy appliances.
8. Emergency Procedures
- Contact details for emergency services.
- First aid kit location.
- Procedures for gas leaks, electrical shocks, or injuries.
9. Quality Control
- Inspection and testing criteria.
- Sign-off procedures.
Risk Assessment
MS REF NO.:
R08-HE4C33-ATL-MTS-
PROJECT:
Method of Statement for Installation FE-0001
Shura East
of Domestic Kitchen Appliances REV : C0
Hotel – HE4
DATE : 04.06.2024
PAGE 9 OF 10
1. Identified Hazards
- Electric Shock
- Gas Leak
- Manual Handling Injuries
- Fire Hazard
- Trip and Fall
3. Mitigation Actions
- **Training**: Ensure all workers are trained in safe installation procedures and emergency response.
- **Supervision**: Ensure work is supervised by a competent person.
- **Regular Inspections**: Conduct regular inspections to ensure compliance with safety procedures.
- **Emergency Preparedness**: Ensure all team members are familiar with emergency procedures.
- Verify specifications.
- Ensure power and gas supplies are off.
2. Positioning
- Move appliances into place.
- Level as needed.
3. Connecting
- Connect to electrical supply.
- Connect to gas supply (if applicable) and check for leaks.
4. Testing
- Turn on power and gas.
- Test functionality.
5. Completion
- Secure appliances.
- Clean the work area.
Hood
1. Preparation
- Ensure the mounting area is clear.
2. Installation
- Mark and drill mounting points.
- Install brackets and secure the hood.
- Connect to electrical supply and ductwork.
3. Testing
- Turn on the hood.
- Ensure proper operation.
4. Completion
- Secure the installation.
- Clean the work area.