Professional Documents
Culture Documents
33KV Substation Design
33KV Substation Design
Design of 33kV switchyard (equipment, SLD, and layout) for small hydro-power plant
Voltage level
Power carrying capability of transmission lines increases roughly as the square of the volt
Therefore in order to obtain lower structures and facilitate maintenance it is important to d
Site considerations
Practical site consideration at a particular location e.g. lack of adequate flat area for layou
At some locations completely indoor substations may be required.
ain single line diagram and switching scheme for a substation are voltage level, site limitation and general a
ro-power plant
e square of the voltage. Accordingly disconnection of higher voltage class equipment from bus bars get incr
e it is important to design such substations preferably with not more than two levels of busbars.
e flat area for layout of equipment in the substation may also influence the choice in such locations. Pollution
unit on the high-voltage side only, is shown in Figure 1. The unit scheme is well suited to power systems where loss of large blocks of gene
ultiple units, as could occur using other arrangements. The “unit” scheme makes maintenance outages simp
ro-power plant
ation and general and special considerations.
m bus bars get increasingly less desirable with increase in voltage levels. High structures are not desirable in
busbars.
locations. Pollution caused by location near to sea or some other contaminated atmosphere may also affec
s of large blocks of generation is difficult to tolerate. The loss of a transformer or transmission line in all other arrangements may mean the
nance outages simpler to arrange.
rrigation and power manual on SubStation layout for 36 kV and above.
tion layout.
normally done by the powerhouse crane and for large transformer rails are laid from powerhouse to the site
g other equipment is required and also affects layout. In order to reduce the chances of spread of fire, transf
d in between the transformers and also between the transformer and roads within the substation.
are not desirable in earthquake prone areas.
ngements may mean the loss of more than a single generating unit.
erhouse to the site of installation in switchyard.
pread of fire, transformers are provided with a soaking pit of adequate capacity to contain the total quantity o
n the total quantity of oil.