1) First of all press UPS green button and see A.C Input and Inverter output green lights are ON .
2) Now ON mains of Air Dryer and ensure that air temperature should be in green zone i.e 0 to 15 ºC .
3) Clean the machine and surface plate properly ,use acetone to clean the surface plate and use soft ,rashes
free cloth.
4) Ensure room temperature should be maintained at 20 ± 2 º C.
6) Before starting the machine ensure that air pressure should be above or equal to 60 PSI .
10) After completion of work switch off controller and room lights.