eds-06-0001a-substation-end-to-end-earthing-processes
eds-06-0001a-substation-end-to-end-earthing-processes
eds-06-0001a-substation-end-to-end-earthing-processes
START
Send documents to
Review documents
earthing mailbox
Install earthing design
Send earthing design
in accordance with
to delivery
ECS 06-0022 Upload documents to
Document
Management System
Test earthing in
accordance with
ECP 11-0406
Submit spreadsheet to Process spreadsheet
Data Systems to add data to SAP
Commission post-
construction earth test Submit results to
via approved earthing UKPN
contractor Carry out post-
construction Resolve data errors Yes Data errors?
measurement/
verification in
accordance with No
ECS 06-0022
END
Produce earthing
report
Submit documents to
UKPN
Secondary Substation (Connection Projects and Network Planning) End-to-End Earthing Process
CONNECTIONS UKPN DELIVERY
CONNECTIONS / NETWORK PLANNING CUSTOMER ART ASSET MANAGEMENT
(Substation Design Team) (Network Ops or CPP)
New or Upgraded
Secondary Substation
Produce earthing
Send SAP substation Create substation in
design and
request to ART SAP CP1
construction forms
No
Yes
Measure earth
Update earthing study Yes Install earthing system
resistance
Reject or conditionally
Revise earthing
accept design
Design accepted? No design and resubmit to
submission with
UKPN
comments
Send design
Yes Install earthing system
acceptance to ICP
Create earthing
Send test form to ART Send test form to
equipment record in
mailbox UKPN
SAP CP1
Enter measurement
data from test form
into SAP CP1
Earthing
characteristics
Yes END
populated in SAP
CP1?
Enter earthing data
into SAP CP1
No