P & M department
Vehicle / Machinery type & REG. NO /ID No Fit Unfit
Note:if the space is not enough attach separate sheets and If found any unfit Vehicle / Machinery, send the relevant check list
Prepared by Authorized by
Nagarajan.V Annamalai.M
(AM – EHS) (AGM – EHS)
URC Construction (P) Ltd FLR-EHS- 010
Weekly Report on EHS Activities Rev 02/Jan15
Are there enough switchboards for the job?
Are ELCBs (safety Switches) fitted?
Are the correct type socket outlets being used?
Are portable outlet devices suitable?
Is construction cabling identified and protected from mechanical damage?
Are electric tools and flexible leads in a safe condition?
Has the electrical installation been tested?
Have ELCBs been tested?
Are portable generators suitable?
Are extension leads being used safely?
Are plant and temporary structures a safe distance from power lines?
Is electrical installation and repair work being done safely?
Earthling of electrically operated equipment?
Provision of Shed /Canopy/ cover of distribution board and sub-distribution
board?
Insulation of cables and joints?
Whether cables layed properly?
Fire extinguishers in main distribution board room?
Whether Men working don't switch on board and other related warning
boards and tags displayed on panels during maintenance?
Name: Name:
Name: Name:
Note: This report must be send to H.O on or before Tuesday of following week.
Prepared by Authorized by
Nagarajan.V Annamalai.M
(AM – EHS) (AGM – EHS)