One Month Look ahead Schedule - JUL-2024

Depth of the
Sl. Rig
Location Bore hole Plan Start Plan Finish Duration 01 02 03 04 05 06 07 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
No Machine
(m)
SOIL INVESTIGATION WORK

1 AP-11 25 RIG - 1 10-Jul 11-Jul 2

2 AP-10 25 RIG - 1 14-Jul 15-Jul 2

3 AP-20 25 RIG - 1 16-Jul 17-Jul 2


N-17717 - 400kV OHL Reinforcement Works Between Al Ain South West (ASWG) - Sweihan (SWHG) Grid Station and Related Remote End Works

One Month Look ahead Schedule - JULY-2024


Sl. Tower Rig Plan
Location Premit Plan Start Duration 01 02 03 04 05 06 07 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
No Type Machine Finish
PILING & PILECAP WORK - 1
1 33/16 S-1 No LAP Required RIG - 1 3-Jul 5-Jul 3

2 33/15 S+6 No LAP Required RIG - 1 8-Jul 10-Jul 3

3 33/14 S+6 No LAP Required RIG - 1 11-Jul 12-Jul 2

4 33/13 S+4 No LAP Required RIG - 1 14-Jul 15-Jul 2

5 33/12 S+9 No LAP Required RIG - 1 16-Jul 17-Jul 2

6 33/11 S+6 No LAP Required RIG - 1 18-Jul 19-Jul 2

7 33/10 AT+3 No LAP Required RIG - 1 21-Jul 24-Jul 3

8 33/9 S-1 No LAP Required RIG - 1 24-Jul 26-Jul 2

9 33/8 S+4 No LAP Required RIG - 1 28-Jul 29-Jul 2

10 33/7 S+4 No LAP Required RIG - 1 30-Jul 31-Jul 2

PILING & PILECAP WORK - 1

1 AP-18 AT+6 LAP not required RIG - 2 30-Jul 31-Jul 4

2 18/1 S+6 LAP not required RIG - 2 28-Jul 29-Jul 2

3 18/2 S+4 LAP not required RIG - 2 23-Jul 24-Jul 2

4 18/3 S+6 LAP not required RIG - 2 21-Jul 22-Jul 2

5 18/4 S+6 LAP not required RIG - 2 18-Jul 19-Jul 2

6 18/5 S+4 LAP not required RIG - 2 16-Jul 17-Jul 2

7 18/6 S+5 LAP not required RIG - 2 14-Jul 15-Jul 2

8 18/7 S+6 LAP not required RIG - 2 11-Jul 12-Jul 2

9 AP-19 AT+6 LAP not required RIG - 2 8-Jul 10-Jul 3

10 19/1 S+6 LAP not required RIG - 2 3-Jul 5-Jul 3


N-17717 - 400kV OHL Reinforcement Works Between Al Ain South West (ASWG) - Sweihan (SWHG) Grid Station and Related Remote End Works

One Month Look ahead Schedule - JULY-2024


Plan
Sl. No Location Tower Type Team Plan Start Duration 01 02 03 04 05 06 07 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Finish
TOWER PAINTING

1 AP37C AT+0 Team-1 3-Jul 5-Jun 3


2 37/6 S-3 Team-2 3-Jul 5-Jun 3
3 37/3 S+4 Team-1 8-Jul 10-Jul 3
4 37D/1 S-3 Team-2 8-Jul 10-Jul 3
5 37/2 S-1 Team-1 9-Jul 14-Jul 4
6 36/39 S+2 Team-2 9-Jul 14-Jul 4
7 36/23 S+4 Team-1 15-Jul 17-Jul 3
8 36/25 S+2 Team-2 15-Jul 17-Jul 3
9 36/26 S+4 Team-3 15-Jul 17-Jul 3
10 36/28 S+5 Team-1 18-Jul 21-Jul 4
11 36/30 AT-3 Team-2 18-Jul 21-Jul 4
12 36/2 S+6 Team-1 22-Jul 24-Jul 3
13 36/3 S+6 Team-2 22-Jul 24-Jul 3
14 AP35 AT+3 Team-1 25-Jul 28-Jul 4
15 AP36 AT+3 Team-2 25-Jul 28-Jul 4
16 AP34 AT+6 Team-1 29-Jul 31-Jul 3
17 33/17 S+6 Team-2 29-Jul 31-Jul 3