Column Estimator
Discription Sectional Area Height Perimeter Nos VOL(cuft) Area(sqft) No of storey
Up To Plinth
C1 1.36 4.75 4.67 9.00 58.19 199.50
Up To Top
C1 1.36 8.33 4.67 22.00 249.44 855.21
Slab Estimator
Discription Slab Area(sqft) Thickness Total Volume(cft) Area For formwork(sqft)
Ground Floor 777.000 0.417 323.750 777.000
First Floor 837.000 0.417 348.750 837.000
Second Floor 0.000 0.417 0.000 0.000
Top Floor 280.310 0.417 116.796 280.310
STAIRCASE 135.420 0.417 56.425 135.420
Total 845.72 2029.73
1320.900
Beam Estimator
S.N Strap Beam Lower Tie Beam Upper Tie Beam Ground Floor Beam First Floor Beam Second Floor Beam Stair Secondary Top Floor
Size 14 9 9 9 9 9 9 9
22 12 12 10 10 10 10 10
Section 2.139 0.750 0.750 0.625 0.625 0.625 0.625 0.625
Summary
S.N Description Qty (cuft) Formworks (sqft) Remarks
A Footing 540.00 360.00
B Beams 493.24 1256.03
C Columns 307.62 1054.71
D Slabs 845.72 2029.73
F Sill and Lintel 147.79 549.77
Total 2334.38 5250.25