Professional Documents
Culture Documents
6-Stationary Equipment Inspection Frequency Guideline
6-Stationary Equipment Inspection Frequency Guideline
TABLE OF CONTENTS
1. INTRODUCTION...........................................................................................................2
3. DEFINITIONS............................................................................................................... 2
5. RESPONSIBILITIES...................................................................................................13
6. REFERENCES............................................................................................................14
7. ATTACHMENTS.........................................................................................................14
8. APPENDICES.............................................................................................................14
TE-STA-GLN-00-0017 Page 1 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
1. INTRODUCTION
This guideline outlines the requirements for inspection of stationary equipment categorized as
MICE (Mechanical Integrity Covered Equipment). Periodic in-service and out of service
inspections of stationary equipment are essential for maintaining the mechanical and
environmental integrity. Establishing appropriate frequency of such periodic inspections is
required to insure the integrity of the equipment as well as for economical considerations in
order to avoid overdoing such inspections which usually results into extra maintenance costs,
un-necessary effort and Plant down time and production loss.
This guideline establishes the maximum interval between internal, on-stream, external and
supplemental inspections for stationary equipment, based on the requirements of API 510, API
570 and API 653 inspection codes and / or Risk Based Inspection and for changing the
established inspection frequency. API Certified Inspectors are authorized to apply at their
discretion, the latest API inspection codes that may be published during the validity period of
this Guideline.
3. DEFINITIONS
CUI: Corrosion under insulation, including stress corrosion cracking under insulation.
Dead-Legs: Components of a piping system that normally have no significant flow.
Examples include the following: blanked branches, lines with normally closed block
valves, lines with one end blanked, pressurized dummy support legs, stagnant control
valve bypass piping, spare pump piping, level bridles, relief valve inlet and outlet header
piping, pump trim bypass lines, high-point vents, sample points, drains, bleeders, start up
lines and instrument connections.
External Inspection: A thorough formal inspection of the exterior of the equipment to
assess all aspects of the equipment as possible without suspending operations or
requiring equipment shutdown.
Injection Point: Locations where relatively small quantities of materials are injected into
process streams to control chemistry or other process variables. Injection points do not
include locations where two process streams join (mixing tees).
Inspector: Stationary Equipment Inspector/Engineer who perform visual inspection along
with NDE to ascertain the vessel, storage tank or piping condition.
Internal Inspection: The direct examination of the inside of the equipment to determine
the thickness, condition and overall suitability for continued safe operation. Thickness
measurement taken at all inspection points and a complete visual examination are
required to fulfill this type of inspection.
MICE: Mechanical Integrity Covered Equipment as per EHS 6160.
On-Stream Inspection: Used to establish the suitability of equipment for continued
operation. Non-destructive examination procedures are used to establish the suitability of
the equipment, and the vessel may or may not, be in operation while the inspection is
being carried out. An on-stream inspection means essentially that the vessel is not
entered for internal inspection.
TE-STA-GLN-00-0017 Page 2 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
Piping Circuit: A section of piping that has all points exposed to an environment of
similar corrosivity and that is of similar design conditions and construction material.
Complex process units or piping systems are divided into piping circuits to manage the
necessary inspections, calculations, and record keeping. When establishing the boundary
of a particular piping circuit, the Inspector may also size it to provide a practical package
for record keeping and performing field inspection.
Pressure Vessel: A container designed to withstand internal or external pressure. This
pressure may be imposed by an external source, by the application of heat from a direct
or indirect source, or by any combination thereof. This definition includes unfired steam
generators and other vapor generating vessels which use heat from the operation of a
processing system or other indirect heat source.
RBI: Risk Based Inspection.
Soil-to-Air (S/A) Interface: An area in which external corrosion may occur on partially
buried pipe. The zone of the corrosion will vary depending on factors such as moisture,
oxygen content of the soil, and operating temperature.
Storage Tank: A stationary container, usually cylindrical in shape, consisting of a
metallic roof, shell, bottom, and support structure used for storing water, liquid chemicals
and hydrocarbons.
Supplemental Inspection: These inspections are periodic examinations other than
external, internal, or on-stream. Supplemental inspections might include thermography, or
additional UT thickness readings etc. It is sometimes called a manual or call file inspection
TML: Thickness Monitoring Location.
The frequency with which equipment should be inspected depends on several factors. The
most important factor is the rate of deterioration and the remaining corrosion allowance.
Corrosion rates will vary markedly with the types of feed stock processed, the temperature of
exposure, and the materials of construction. Each condition must be individually appraised to
establish the initial inspection period for new equipment. A service history record should be
established after the first inspection by on-stream methods or internal examination. On the
basis of this history, an inspection interval based on time, condition, or risk-based factors shall
be set in accordance with the applicable inspection code (API 510 for pressure vessels, API
570 for piping or API 653 for storage tanks) or RBI assessments.
The Thickness Monitoring Location (TML) program of Meridium determines the Long-term
and short-term corrosion rates of the Stationary Equipment (pressure vessels / Piping /
Storage tanks) based on the thickness monitored at the specified TMLs. The determination
of corrosion rate may include thickness data collected at more than two different times. The
remaining life of the stationary equipment is calculated in Meridium based on respective
formulae given in API 510, API 570 and API 653 for Pressure vessels, Piping and Storage
Tanks respectively. The inspection frequency of TML is determined at half of the calculated
remaining life.
TE-STA-GLN-00-0017 Page 3 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
RBI assessment may be applied in determining the inspection frequency when an extension
of the frequency beyond this guideline or as defined in API 510, 570 and 653 is required.
When applied, it must include a systematic evaluation of both the likelihood of failure and the
associated consequence of failure, in accordance with API RP 580. The likelihood
assessment must be based on all forms of degradation, both internally and externally, that
could reasonably be expected to affect a Equipment in any particular service.
Other factors that should be considered in a RBI assessment conducted in accordance with
API RP 580 include: appropriateness of the materials of construction; equipment design
conditions, relative to operating conditions; appropriateness of the design codes and
standards utilized; effectiveness of corrosion monitoring programs; and the quality of
maintenance and inspection quality assurance/quality control programs. Equipment failure
data and information will also be used for this assessment. The consequence assessment
must consider the potential incidents that may occur as a result of fluid release, including
explosion, fire, toxic exposure, environmental impact, and other health effects associated
with a failure of equipment.
All RBI assessments shall be thoroughly documented in accordance with API RP 580, clearly
defining all the factors contributing to both the likelihood and consequence of a failure of the
equipment. After an effective RBI assessment is conducted, the results shall be used to
establish the equipment inspection strategy and more specifically better define the following:
i. The most appropriate inspection methods, scope, tools and techniques to be utilized
based on the expected forms of degradation.
ii. The appropriate frequency for internal, external, and on-stream inspections.
iii. The need for pressure testing after damage has been incurred or after repairs or
modifications have been completed.
iv. The prevention and mitigation steps to reduce the likelihood and consequence of
equipment failure.
A RBI assessment will be used to establish the appropriate inspection intervals for internal
and on-stream inspections, including a potential increase in the inspection interval limit, as
well as the external interval. When used to increase the inspection interval limit, the RBI
assessment shall be reviewed and approved by an appropriate engineer (as applicable) and
Inspector at intervals not to exceed inspection intervals defined based on corrosion
rates/remaining life as detailed in this document, or more often if warranted by process,
equipment, or consequence changes.
There are several types of inspection intervals that must be considered for each piece of
pressure vessel. These inspections are internal, on-stream, external, and supplemental.
They can each be performed individually or in conjunction with each other. To insure vessel
integrity, all vessels shall be inspected at the frequencies provided in this section. The term
pressure vessels is intended to cover towers, drums, reactors, heat exchangers, re-boilers,
air-cooled exchangers and condensers.
TE-STA-GLN-00-0017 Page 4 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
ii. Inspection for corrosion under insulation (CUI).shall be carried out as per “Corrosion
Under Insulation and Corrosion Under Fireproofing Inspection Guideline” TE-STA-GLN-
00-0007. Inspections for CUI shall be carried out based on RBI analysis
recommendations (if performed) on vessels prone to CUI.
iii. Vessels that are known to have a remaining life of over 10 years or that are protected
against external corrosion—for example,
a) Vessels insulated effectively to preclude the entrance of moisture,
b) Jacketed cryogenic vessels,
c) Vessels installed in a cold box in which the atmosphere is purged with an inert gas,
d) Vessels in which the temperature being maintained is sufficiently low or sufficiently
high to preclude the presence of water do not need to have insulation removed for
the external inspection.
However, the condition of their insulating system or their outer jacketing, such as the
cold box shell, shall be observed at least every 5 years and repaired if necessary.
iv. Buried vessels shall be inspected to determine their external environmental condition.
The inspection interval shall be based on corrosion-rate information obtained from one
or more of the following methods:
a) During maintenance activity on adjacent connecting piping of similar material;
b) From the interval examination (specified in 4.3.1(i) of similarly buried corrosion test
coupons of similar material;
c) From representative portions of the actual vessel; or
d) From a vessel in similar circumstances.
TE-STA-GLN-00-0017 Page 5 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
TE-STA-GLN-00-0017 Page 6 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
inspection should be performed no later than 3 years from unit start-up or commissioning
of the new equipment. The equipment should have a minimum of 2 internal inspections
at successive scheduled turnarounds in order to establish the most probable corrosion
rate and expected maximum inspection interval. In any case, the interval set shall not
exceed the limits indicated earlier.
TE-STA-GLN-00-0017 Page 7 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
d) Piping Class 4
Services that are essentially nonflammable and nontoxic are in Class 4, as are most
utility services. Inspection of Class 4 piping is optional and usually based on reliability
needs and business impacts as opposed to safety or environmental impact. Examples
of Class 4 service include, but are not necessarily limited to those containing the
following:
steam and steam condensate;
nitrogen;
water, including boiler feed water, stripped sour water;
ASME B31.3, Category D services;
Fire hydrants
ii. The interval between piping inspections shall be established and maintained using the
following criteria:
a) Corrosion rate and remaining life calculations per section 4.1.
b) Piping service classification (as per API 570).
c) Judgment of the Inspector, the piping engineer, or a corrosion specialist, based on
operating conditions, previous inspection history, current inspection results, and
conditions that may warrant supplemental inspections. Such inspections include
periodic use of radiography, thermography, ultrasonic, acoustic emission and acoustic
leak detection.
iii. Inspector shall establish inspection intervals for thickness measurements and external
visual inspections and, where applicable, for internal and supplemental inspections.
iv. Thickness measurements shall be scheduled based on the calculation of not more than
half the remaining life determined from corrosion rates indicated in section 4.1or at the
maximum intervals suggested in Table-1, whichever is shorter. Shorter intervals may be
appropriate under certain circumstances. Table-1 contains recommended maximum
inspection intervals for the three categories of piping services (as per API 570) described
in 4.4 .(i), as well as recommended intervals for injection points and soil/air interfaces.
TE-STA-GLN-00-0017 Page 8 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
vi. External visual inspections, including inspections for corrosion under insulation (CUI),
should be conducted at maximum intervals listed in Table-1. Alternatively, external visual
inspection intervals can be established by using a valid RBI assessment conducted in
accordance with API RP 580 and in line with section .
vii. Following the external visual inspection of susceptible systems, additional examination is
required for the inspection of CUI. The extent and type of the additional CUI inspection are
listed in Table 2. Damaged insulation at higher elevations may result in CUI in lower areas
remote from the damage.
NDE inspection for CUI should also be conducted as listed in Table-2 at suspect locations
meeting the temperature criteria for CUI. If the inspection of the damaged or suspect
areas has located significant CUI, additional areas should be inspected and, where
warranted, up to 100 percent of the circuit should be inspected. The extent of the CUI
program described in Table-2 should be considered as target levels for piping systems
and locations with no CUI inspection experience. It is recognized that several factors may
affect the likelihood of CUI to include: local climatic conditions, insulation design, coating
quality, and service conditions.
When CUI inspection is experienced, CUI inspection targets of Table-2 may be increased
or reduced. An exact accounting of the CUI inspection targets is not required. The
Inspector may confirm inspection targets with operational history or other documentation.
Piping systems that are known to have a remaining life of over 10 years or that are
adequately protected against external corrosion need not be included for the NDE
inspection recommended in Table-2. However, the condition of the insulating system or
the outer jacketing, such as a cold-box shell, should be observed periodically by operating
or other personnel. If deterioration is noted, it should be reported to the inspector.
viii. SBP Inspection: SBP(Small Bore Piping) that is primary process piping should be
inspected in accordance with all the requirements of this document. SBP that is secondary
process piping has different minimum requirements depending upon service classification.
Class 1 secondary SBP shall be inspected to the same requirements as primary process
piping. Inspection of Class 2 and Class 3 secondary SBP is optional. SBP deadlegs (such
as level bridles) in Class 2 and Class 3 systems should be inspected where corrosion has
been experienced or is anticipated. Deadlegs with TMLs should be tracked in a separate
piping circuit from the mainline piping. These deadlegs or low points are typically identified
and documented in the inspection record by the inspector. Deadlegs may be combined
into one circuit if their anticipated corrosion rates are similar. Inspections should include
profile radiography on small diameter deadlegs, such as vents and drains, and UT or RT
on larger diameter deadlegs.
TE-STA-GLN-00-0017 Page 9 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
The interval between inspections of a storage tank (both internal and external) shall be
determined by its service history unless special reasons indicate that an earlier inspection
must be made. On-stream, nondestructive methods of inspection shall be considered when
establishing inspection frequencies.
TE-STA-GLN-00-0017 Page 10 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
The interval from initial service date until the first internal inspection shall not exceed 10
years unless a tank has one or more of the leak prevention, detection, corrosion mitigation
or containment safeguards listed in Table 3 below. The initial internal inspection date shall
be based on incremental credits for the additional safeguards in Table 3 which are
cumulative.
For example, the maximum interval for a 1/4 in. bottom that has a release prevention
barrier and a fiberglass lining would be determined as follows:
10 years (initial) + 5 years (fiberglass lining) + 10 years (release prevention barrier) = 25
years.
The initial inspection interval shall not exceed 20 years for tanks without a Release
Prevention Barrier, or 30 years for tanks with a Release Prevention Barrier.
As an alternative to establishing the initial interval, initial internal inspection date and
reassessment can be established using Risk Based Inspection (RBI) assessment that
may exceed the initial 10 years interval but shall not exceed 20 years for tanks without a
Release Prevention Barrier, or 30 years for tanks with a Release Prevention Barrier
except as follows.
The initial RBI assessment shall be reviewed and approved by an Inspector and an
engineer(s), knowledgeable and experienced in tank design (including tank foundations)
and corrosion. The RBI assessment shall be subsequently reviewed and approved, at
intervals not to exceed 10 years, or more often if warranted by changes in service.
ii. Subsequent Inspection Interval
The interval between subsequent internal inspections shall be determined in accordance
with either the corrosion rate procedures of the latest cod edition or hired risk based
inspection procedures.
When using the corrosion rate procedures the maximum subsequent internal inspection
interval shall be 20 years for tanks without a Release Prevention Barrier, or 30 years for
tanks with a Release Prevention Barrier
If the minimum bottom thicknesses, at the end of the in-service period of operation, are
calculated to be less than the minimum bottom renewal thicknesses given in Table 4
below or less than the minimum bottom renewal
TE-STA-GLN-00-0017 Page 11 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
For tank in service with a product specific gravity of 1.0 or greater which require annular
plates for other than seismic loading considerations, the thickness of the annualr plates shall
be in accordance with API 650, Table 5-1A or 5-1b, plus any specified corrosion allowance.
Following each internal inspection, a Frequency Analysis shall be performed. The internal
inspection data for each piece of equipment is to be carefully analyzed. The Interval
TE-STA-GLN-00-0017 Page 12 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
Analysis should be performed as the inspections are made and prior to start-up to ensure
that data gathering has been done correctly.
The analysis includes a review of the corrosion rates, service, operating conditions,
equipment and operating history, calculated remaining equipment life, etc. The Interval
Analysis should result in one of the following recommendations:
5. RESPONSIBILITIES
TE-STA-GLN-00-0017 Page 13 of 14
TE-STA-GLN-00-0017
EQUIPEMENT RELIABILITY GROUP
Rev. 2
iii. Responsible for setting the appropriate inspection interval based on the equipment
design, operating conditions, past inspection history, and comparable service experience.
Carry out RBI on case to case basis.
6. REFERENCES
7. ATTACHMENTS
None
8. APPENDICES
None
TE-STA-GLN-00-0017 Page 14 of 14