Name of Project: Titavi Storage Tank Tq. Soygaon Dist.

Aurangabad
S.No Items Details
Latest Estimated Cost for AIBP/BJSY 13.80
1 Component (Rs in crore)
9.13
2 Latest Expenditure including ETP (Rs in Crore)
(Upto Dec. - 2021) as per Division

4.67
3 Balance Cost (1-2) (Rs in Crore)
4 Financial Capacity of Project authorities 7.34
during last 3 years (FY 2018-21)
(Rs in Crore)
5 Estimated cost of running tenders 2.29
(Rs in Crore)
6 Estimated time of completion of tenders Jun-22
under item No 5
7 i.Balance amount of tenders to be invited (Rs 0.24
in crore)
ii.Time required for completion Jun-22
8 Irrigation Potential under BJSY 0.255
(Th ha)
9 Irrigation Potential created upto date (Th ha) 0

10 Balance Potential to be created 0.255


(Th ha)
11 i. Total Land required to be acquired under
project (Ha) 25.36
ii. Total Land acquired (Ha) 4.9 (Forest Land)
iii. Balance land required to be acquired 20.46
12 Rehabilitation and Resettlement No. of families to be shifted Due to construction of the project, No villages
No. of families shifted are being affected. Hence, no necessity of
Resettlement & Rehabilitation.
Balance
13 Status of progress of Major Component in % 61.15%
14 Balance Major works to be executed Poondy type Spillway of length of 117 m ( RD 43 to 160 m) is completed. Excavation and filling
of COT (Cut of Trench) of dam is completed and balance work ( Embankment in RD 43-160m &
160-405m and pitching) is under progress which is planned to be completed by June, 2022.

15 Bottlenecks including issues due to which Land Aquisition by direct purchase of balance 20.46 Ha private land is in progress. Proposal
potential creation getting affected Submitted to District Collector for final award.
16 Efforts made in resolving issues To resolve balance land acquisition problem, several meeting has been conducted with
Revenue department Land acquisition officer and nessesory data has been provided.

17 Likely date of Completion Jun-22


Name of Project: Banoti Storage Tank Tq. Soygaon Dist.Aurangabad
S.No Items Details

1 Latest Estimated Cost for AIBP/BJSY 35.826


Component (Rs in crore)

2 Latest Expenditure including ETP (Rs in Crore) 16.00


(Upto Dec. - 2021) as per Division

3 Balance Cost (1-2) (Rs in Crore) 19.826


4 Financial Capacity of Project authorities 5.21
during last 3 years (FY 2018-21)
(Rs in Crore)
5 Estimated cost of running tenders 1.93
(Rs in Crore)
6 Estimated time of completion of tenders Jun-22
under item No 5
7 i.Balance amount of tenders to be invited (Rs 1.74
in crore)
ii.Time required for completion Jun-22
8 Irrigation Potential under BJSY 0.265
(Th ha)
9 Irrigation Potential created upto date (Th ha) 0

10 Balance Potential to be created 0.265


(Th ha)
11 i. Total Land required to be acquired under 49.67
project (Ha)
ii. Total Land acquired (Ha) 0
iii. Balance land required to be acquired 49.67
12 Rehabilitation and Resettlement No. of families to be shifted Due to construction of the project, No villages
No. of families shifted are being affected. Hence, no necessity of
Resettlement & Rehabilitation.
Balance
13 Status of progress of Major Component in % 60%
14 Balance Major works to be executed One flank work is completed and one is under progres, Waste weir.is completed
15 Bottlenecks including issues due to which Land Aquisition by direct purchase of balance 49.67 Ha private land is in progress. Proposal
potential creation getting affected Submitted to District Collector for final award.
16 Efforts made in resolving issues To resolve balance land acquisition problem, several meeting has been conducted with
Revenue department Land acquisition officer and nessesory data has been provided.

17 Likely date of Completion Jun-22


Name of Project: Deogaon Rangari L.M.I Tank Tq. Kannad Dist.Aurangabad
S.No Items Details
Latest Estimated Cost for AIBP/BJSY
1 99.40
Component (Rs in crore)

Latest Expenditure including ETP (Rs in Crore)


2 93.29
(Upto Dec. - 2021) as per Division

3 Balance Cost (1-2) (Rs in Crore) 6.11


4 Financial Capacity of Project authorities 14.43
during last 3 years (FY 2018-21)
(Rs in Crore)
5 Estimated cost of running tenders 0
(Rs in Crore)
6 Estimated time of completion of tenders Jun-22
under item No 5
7 i.Balance amount of tenders to be invited (Rs 12.45
in crore)
ii.Time required for completion Jun-22
8 Irrigation Potential under BJSY 1.012
(Th ha)
9 Irrigation Potential created upto date (Th ha) 0.458

10 Balance Potential to be created 0.554


(Th ha)
11 i. Total Land required to be acquired under 415.36
project (Ha)
ii. Total Land acquired (Ha) 409.98
iii. Balance land required to be acquired 5.38
12 Rehabilitation and Resettlement No. of families to be shifted 210
No. of families shifted 0
Balance 210
13 Status of progress of Major Component in % 93%
14 Balance Major works to be executed Dam earth work and canal work is completed, Only storage is restricted due to
Rehabilitation is balance.

15 Bottlenecks including issues due to which Kanadgaon village comes under submergence of the project hence rehabilitation of this
potential creation getting affected village is proposed. At this stage, registry of land required for kanadgaon is completed in
March 2021. The tender process of works of Civic Amenities in rehabilited village is in
progress.

16 Efforts made in resolving issues


17 Likely date of Completion Dec-22
Name of Project: Vangaon Pohari Storage Tank Tq. Soygaon Dist.Aurangabad
S.No Items Details

1 Latest Estimated Cost for AIBP/BJSY 61.44


Component (Rs in crore)

2 Latest Expenditure including ETP (Rs in Crore) 54.23


(Upto Dec. - 2021) as per Division

3 Balance Cost (1-2) (Rs in Crore) 7.21


4 Financial Capacity of Project authorities 43.79
during last 3 years (FY 2018-21)
(Rs in Crore)

5 Estimated cost of running tenders 10.05


(Rs in Crore)
6 Estimated time of completion of tenders Dec-21
under item No 5
7 i.Balance amount of tenders to be invited (Rs 1.73
in crore)
ii.Time required for completion Dec-21

8 Irrigation Potential under BJSY 0.473


(Th ha)
9 Irrigation Potential created upto date (Th ha) 0

10 Balance Potential to be created 0.473


(Th ha)
11 i. Total Land required to be acquired under 150.96
project (Ha)
ii. Total Land acquired (Ha) 150.96

iii. Balance land required to be acquired 0

12 Rehabilitation and Resettlement No. of families to be shifted Due to construction of the project, No villages
are being affected. Hence, no necessity of
No. of families shifted Resettlement & Rehabilitation.
Balance
13 Status of progress of Major Component in % 72%

14 Balance Major works to be executed Earthwork and Revetment of Right flank (Rd 1560 to 2550) and Waste weir(Rd 180 to
350) completed , Earthwork of remaingdam length is under progress.

15 Bottlenecks including issues due to which Final award of land Aquisiton by direct purchase of 7.45Ha Private land has been
potential creation getting affected declared and registry process is in progress

16 Efforts made in resolving issues -


17 Likely date of Completion Jun-22
Name of Project: Savaladbara Storage Tank Tq. Soygaon Dist.Aurangabad
S.No Items Details

1 Latest Estimated Cost for AIBP/BJSY 21.96


Component (Rs in crore)

2 Latest Expenditure including ETP (Rs in Crore) 20.39


(Upto Dec. - 2021) as per Division

3 Balance Cost (1-2) (Rs in Crore) 1.57


Financial Capacity of Project authorities 12.07
4 during last 3 years (FY 2018-21)
(Rs in Crore)
Estimated cost of running tenders 0
5 (Rs in Crore)
Estimated time of completion of tenders Work Completed
6 under item No 5
i.Balance amount of tenders to be invited (Rs 1.75
7 in crore)
ii.Time required for completion Jun-21
Irrigation Potential under BJSY 0.302
8 (Th ha)

9 Irrigation Potential created upto date (Th ha) 0.302


Balance Potential to be created 0
10 (Th ha)
i. Total Land required to be acquired under 84.10
project (Ha)
11
ii. Total Land acquired (Ha) 84.10
iii. Balance land required to be acquired 0
Rehabilitation and Resettlement No. of families to be shifted Due to construction of the project, No villages
are being affected. Hence, no necessity of
12 No. of families shifted Resettlement & Rehabilitation.
Balance
13 Status of progress of Major Component in % 100.00%
14 Balance Major works to be executed No any major works remain
Bottlenecks including issues due to which Nil
15 potential creation getting affected

16 Efforts made in resolving issues Not Applicable


Likely date of Completion Completed in Jun 2019.
17
Name of Project: Palaskheda L.M.I. Project Tq.Bhokardan Dist.- Jalna
S.No Items Details
Latest Estimated Cost for AIBP/BJSY 53.29
1 Component (Rs in crore)
55.11
2 Latest Expenditure including ETP (Rs in Crore)
(Upto Dec. - 2021) as per Division

3 Balance Cost (1-2) (Rs in Crore) -1.82


Financial Capacity of Project authorities 13.54
4 during last 3 years (FY 2018-21)
(Rs in Crore)
Estimated cost of running tenders 3.94
5 (Rs in Crore)
Estimated time of completion of tenders Jun-21
6 under item No 5
i.Balance amount of tenders to be invited (Rs 6.4
7 in crore)
ii.Time required for completion Jun-22
Irrigation Potential under BJSY 0.930
8 (Th ha)
Irrigation Potential created upto date (Th ha) 0.360
9
Balance Potential to be created 0.570
10 (Th ha)
i. Total Land required to be acquired under 304.5
project (Ha)
11
ii. Total Land acquired (Ha) 293.9
iii. Balance land required to be acquired 10.6
Rehabilitation and Resettlement No. of families to be shifted 147
12 No. of families shifted 147
Balance 0
13 Status of progress of Major Component in % Dam completed, waste weir completed, 97% Land acquisition completed
14 Balance Major works to be executed Rehabilitation related works to be completed
Bottlenecks including issues due to which Rehabilitation related issues and lack of supply of sand for works.
15 potential creation getting affected
Efforts made in resolving issues visited rehabilitation village hivra da. alongwith Tehsildar Badnapur for resolving their
16 issues regarding rehabilitation.
Likely date of Completion Jun-22
17
Name of Project: Barbada M.I. Tq. Mantha Dist. Jalna
S.No Items Details
Latest Estimated Cost for AIBP/BJSY 355.77
1 Component (Rs in crore)
62.03

2 Latest Expenditure including ETP (Rs in Crore)


(Upto Dec. - 2021) as per Division

3 Balance Cost (1-2) (Rs in Crore) 293.74


Financial Capacity of Project authorities 43.17
4 during last 3 years (FY 2018-21)
(Rs in Crore)
Estimated cost of running tenders 4.1
5 (Rs in Crore)
Estimated time of completion of tenders Jun-22
6 under item No 5
i.Balance amount of tenders to be invited (Rs 15.92
7 in crore)
ii.Time required for completion Jun-22
Irrigation Potential under BJSY 1.225
8 (Th ha)
Irrigation Potential created upto date (Th ha) 0
9
Balance Potential to be created 1.225
10 (Th ha)
i. Total Land required to be acquired under 523.21
project (Ha)
11 ii. Total Land acquired (Ha) 273.8
iii. Balance land required to be acquired 249.41
Rehabilitation and Resettlement No. of families to be shifted 713
12 No. of families shifted 0
Balance 713
13 Status of progress of Major Component in % Dam 80% completed, waste weir 80% completed, 52% Land acquisition completed
14 Balance Major works to be executed Gorge Filling , Construction of Waste weir
Bottlenecks including issues due to which Rehabilation of village Akani is not yet done. Second RAA is submitted to secretary level
15 potential creation getting affected sub committee for further approval

16 Efforts made in resolving issues


Likely date of Completion Jun-23
17
Name of Project: Hatwan L.M.I. Tq. Dist. Jalna
S.No Items Details
Latest Estimated Cost for AIBP/BJSY 297.39
1 Component (Rs in crore)
6.37

2 Latest Expenditure including ETP (Rs in Crore)


(Upto Dec. - 2021) as per Division

3 Balance Cost (1-2) (Rs in Crore) 291.02


Financial Capacity of Project authorities 0
4 during last 3 years (FY 2018-21)
(Rs in Crore)
Estimated cost of running tenders 29.95
5 (Rs in Crore)
Estimated time of completion of tenders Jun-23
6 under item No 5
i.Balance amount of tenders to be invited (Rs 8.94
7 in crore)
ii.Time required for completion Jun-23
Irrigation Potential under BJSY 1.695
8 (Th ha)
Irrigation Potential created upto date (Th ha) 0
9
Balance Potential to be created 1.695
10 (Th ha)
i. Total Land required to be acquired under 714.15
project (Ha)
11
ii. Total Land acquired (Ha) 0
iii. Balance land required to be acquired 714.15
Rehabilitation and Resettlement No. of families to be shifted 266
12 No. of families shifted 0
Balance 266
13 Status of progress of Major Component in % works yet to be executed
Balance Major works to be executed Construction Work of Hatwan dam was started on 07/05/2010 but due to farmers
demand for acquiring land as per land acquisition rules-2013 ,the work was stopped in
14 initial stage in September 2010.

Bottlenecks including issues due to which Project has Administrative Approval of Rs. 53.37crore. on dated 11/03/2008 given by
potential creation getting affected GMIDC Aurangabad. Project has first Revised Administrative Approval of Rs. 297.39
15 crore on dated 08/07/2021. Process for acquisition of land reqired for rehabilited village
is in progress by direct purchase.

16 Efforts made in resolving issues -


17 Likely date of Completion Jun-23
Name of Project: Patoda Storage Tank Tq. Mantha Dist. Jalna
S.No Items Details
Latest Estimated Cost for AIBP/BJSY 130.66
1 Component (Rs in crore)
45.67
2 Latest Expenditure including ETP (Rs in Crore)
(Upto Dec. - 2021) as per Division

3 Balance Cost (1-2) (Rs in Crore) 84.99


Financial Capacity of Project authorities 18.01
4 during last 3 years (FY 2018-21)
(Rs in Crore)
Estimated cost of running tenders 7.42
5 (Rs in Crore)
Estimated time of completion of tenders Jun-22
6 under item No 5
i.Balance amount of tenders to be invited (Rs 17.88
7 in crore)
ii.Time required for completion Jun-22
Irrigation Potential under BJSY 1.199
8 (Th ha)
Irrigation Potential created upto date (Th ha) 0
9
Balance Potential to be created 1.199
10 (Th ha)
i. Total Land required to be acquired under 316.91
project (Ha)
11
ii. Total Land acquired (Ha) 288.37
iii. Balance land required to be acquired 28.54
Rehabilitation and Resettlement No. of families to be shifted 724
12 No. of families shifted 0
Balance 724
13 Status of progress of Major Component in % Dam 20% completed, waste weir 10% completed, 90% Land acquisition completed
Balance Major works to be executed Earth work,Gorge Filling , Construction of Waste weir and Rehabilation of one village
14 Limbewadgaon coming under submergence.

Bottlenecks including issues due to which Land acquisition in submergence of Village Limbewadgaon.
15 potential creation getting affected
Efforts made in resolving issues Villagers are convinced to abdone the village. proposal of valuation of village houses is
submitted to Govt. 1st RAA is submitted to Cabinet meeting for further approval
16

Likely date of Completion Jun-22


17
Name of Project: Name of Project: Sonkheda S.T., Tq. Jafrabad, Dist. Jalna
S.No Items Details
1 Latest Estimated Cost for AIBP/BJSY 55.48
Component (Rs in crore)
2 47.05
Latest Expenditure including ETP (Rs in Crore)
(Upto Dec. - 2021) as per Division

3 Balance Cost (1-2) (Rs in Crore) 8.43


4 Financial Capacity of Project authorities 25.62
during last 3 years (FY 2018-21)
(Rs in Crore)
5 Estimated cost of running tenders 7.95
(Rs in Crore)
6 Estimated time of completion of tenders Jun-22
under item No 5
7 i.Balance amount of tenders to be invited (Rs 0
in crore)
ii.Time required for completion Jun-22
8 Irrigation Potential under BJSY 0.445
(Th ha)
9 Irrigation Potential created upto date (Th ha) 0
10 Balance Potential to be created 0.445
(Th ha)
11 i. Total Land required to be acquired under 169.28
project (Ha)
ii. Total Land acquired (Ha) 152.72
iii. Balance land required to be acquired 16.56
12 Rehabilitation and Resettlement No. of families to be shifted NA
No. of families shifted NA
Balance NA
13 Status of progress of Major Component in % Dam 90% completed, waste weir 90% completed, 87% Land acquisition completed
14 Balance Major works to be executed Dam Geourge filling,Waste weir,Tail Channel,Devide wall,Construction of Toe Wall and
Protection Wall etc.
15 Bottlenecks including issues due to which Land Acquisition problem.
potential creation getting affected

16 Efforts made in resolving issues 90% Land Acquisition process is completed balance process for Land Acquisition is under way by
solving the disputes of land owner.

17 Likely date of Completion Jun-22


Name of Project: Khoradsawngi M.I. Tank Tq. Mantha Dist. Jalna
S.No Items Details
Latest Estimated Cost for AIBP/BJSY 22.58
1 Component (Rs in crore)
10.20

2 Latest Expenditure including ETP (Rs in Crore)


(Upto Dec. - 2021) as per Division

3 Balance Cost (1-2) (Rs in Crore) 12.38


Financial Capacity of Project authorities 3.65
4 during last 3 years (FY 2018-21)
(Rs in Crore)
Estimated cost of running tenders 2.26
5 (Rs in Crore)
Estimated time of completion of tenders Jun-22
6 under item No 5
i.Balance amount of tenders to be invited (Rs 2
7 in crore)
ii.Time required for completion Jun-22
Irrigation Potential under BJSY 0.254
8 (Th ha)
Irrigation Potential created upto date (Th ha) 0
9
Balance Potential to be created 0.254
10 (Th ha)
i. Total Land required to be acquired under 81.5
project (Ha)
11 ii. Total Land acquired (Ha) 70.42
iii. Balance land required to be acquired 11.08

Rehabilitation and Resettlement No. of families to be shifted 31


12 No. of families shifted 0
Balance 31
13 Status of progress of Major Component in % Dam 90% completed, waste weir 10% completed, 87% Land acquisition completed
14 Balance Major works to be executed Gorge Filling , Construction of Waste weir , Pickup weirs on D/S Side.
15 Bottlenecks including issues due to which Land acquisition in submergence of Village Malsawangi
potential creation getting affected Villagers are convinced to abdone the village. proposal of rehabiliation of village houses
Efforts made in resolving issues
and amenities is submitted to Government on datw 05/03/2020 by Divisional
16 Commissioner Office,Aurangabad March 2022

Likely date of Completion Jun-22


17
Name of Project: Maniramkhed LMI ,Dis Nanded
S.No Items Details
1 Latest Estimated Cost for AIBP/BJSY 97.29
Component (Rs in crore)
2 Latest Expenditure including ETP (Rs in crore) 68.90
(upto Dec -2021)

3 Balance Cost (1-2) (Rs in crore) 28.39

4 Financial Capacity of Project authorities 16.495


during last 3 years (FY 2017-20)
(Rs in crore)
5 Estimated cost of running tenders ( Dam+Rehabilitation+Road)18.97+6.29+6.45 = 31.71 Cr
(Rs in crore)
6 Estimated time of completion of tenders Jun-22
under item No 5
7 i.Balance amount of tenders to be invited (Rs 15.96
in crore)
ii.Time required for completion Jun-22
8 Irrigation Potential under BJSY 1.2
(Th ha)
9 Irrigation Potential created upto date (Th ha) 0.4

10 Balance Potential to be created 0.8


(Th ha)
11 i. Total Land required to be acquired under 310.84
project (Ha)
ii. Total Land acquired (Ha) 310.84
iii. Balance land required to be acquired 0
12 Rehabilitation and Resettlement No. of families to be shifted 234
No. of families shifted 234
Balance 0
13 Status of progress of Major Component in % Dam 100%,Waste weir and sluice 100%,Rehabilation 100%,Road in submergence 100%

14 Balance Major works to be executed pipe distribution system

15 Bottlenecks including issues due to which No Bottlenecks


potential creation getting affected

16 Efforts made in resolving issues No Bottlenecks

17 Likely date of Completion Dec-22

file:///conversion/tmp/activity_task_scratch/769723382.xlsx
Name of Project: Daresarsam S.T. Dis Nanded
S.No Items Details
1 Latest Estimated Cost for AIBP/BJSY 17.12
Component (Rs in crore)
2 Latest Expenditure including ETP (Rs in crore) 16.54
(upto Sep 2021)

3 Balance Cost (1-2) (Rs in crore) 0.58

4 Financial Capacity of Project authorities 5.84


during last 3 years (FY 2017-20)
(Rs in crore)
5 Estimated cost of running tenders 0.8
(Rs in crore)
6 Estimated time of completion of tenders Dec-22
under item No 5
7 i.Balance amount of tenders to be invited (Rs 0
in crore)
ii.Time required for completion 0
8 Irrigation Potential under BJSY 0.258
(Th ha)
9 Irrigation Potential created upto date (Th ha) 0.258

10 Balance Potential to be created 0


(Th ha)
11 i. Total Land required to be acquired under 109.35
project (Ha)
ii. Total Land acquired (Ha) 109.35
iii. Balance land required to be acquired 0
12 Rehabilitation and Resettlement No. of families to be shifted 0
No. of families shifted 0
Balance 0
13 Status of progress of Major Component in % DAM 100% WASTE WIER AND SLUICE 100 %,PICKUP WEIR 100%
14 Balance Major works to be executed NIL
15 Bottlenecks including issues due to which NIL
potential creation getting affected

16 Efforts made in resolving issues NIL

17 Likely date of Completion Project is physically completed.


Name of Project: Borsuri Storage Tank Tq.Nilanga Dist.Latur
S.No Items Details

1 Latest Estimated Cost for AIBP/BJSY Component 57.87


(Rs in crore)

2 Latest Expenditure including ETP(Rs in crore) 48.46


(upto December 2021)as per division

3 Balance Cost (1-2) (Rs in crore) 9.41


4 Financial Capacity of Project authorities during 42.68
last 3 years (FY 2017-20)
(Rs in crore)

5 Estimated cost of 4 running tenders 13.4


(Rs in crore)

6 Estimated time of completion of tenders under item Jun-22


No 5

7 i.Balance amount of tenders to be invited (Rs in 0


crore)

ii.Time required for completion 0


8 Irrigation Potential under BJSY 0.352
(Th ha)

9 Irrigation Potential created upto date (Th ha) 0


10 Balance Potential to be created 0.352
(Th ha)

11 i. Total Land required to be acquired under project 95.12


(Ha)

ii. Total Land acquired (Ha) 88.72


iii. Balance land required to be acquired 6.40
12 Rehabilitation and Resettlement No. of families to be shifted NIL
No. of families shifted NIL
Balance NIL
13 Status of progress of Major Component in % Excavation work 44.72 %, Earthwork 74.11 % are
completed and concrete work is in balance.

14 Balance Major works to be executed Excavation 173.78TCM, Earthwork 60.80 TCM &
Concrete work 14.87 TCM are tobe executed.

15 Bottlenecks including issues due to which The final award is to be declaired by the SDM Nilanga for
potential creation getting affected 6.40 Ha. on time. But there is delay due to non availlability
of valuation of trees by Agricultural Department.
16 Efforts made in resolving issues The valuation of civil works i.e. wells,Pipelines and
boerwells are being submitted to SDM Nilanga and there is
continuous correspondence to declare the award of 6.40
Hect.

17 Likely date of Completion June-2022


Name of Project: Vairagad Storage Tank Tq.Ahmedpur Dist.Latur

S.No Items Details


1 Latest Estimated Cost for AIBP/BJSY 43.375
Component (Rs in crore)

2 Latest Expenditure including ETP (Rs in crore) 30.91


(upto December 2021)as per division

3 Balance Cost (1-2) (Rs in crore) 12.47


4 Financial Capacity of Project authorities 21.75
during last 3 years (FY 2017-20)
(Rs in crore)

5 Estimated cost of 3 running tenders 20.16


(Rs in crore)

6 Estimated time of completion of tenders under June-2022


item No 5

7 i.Balance amount of tenders to be invited (Rs 0


in crore)

ii.Time required for completion 0


8 Irrigation Potential under BJSY 0.848
(Th ha)

9 Irrigation Potential created upto date (Th ha) 0

10 Balance Potential to be created 0.848


(Th ha)

11 i. Total Land required to be acquired under 64.95


project (Ha)

ii. Total Land acquired (Ha) 60.89


iii. Balance land required to be acquired 4.06
12 Rehabilitation and Resettlement No. of families to be shifted NIL
No. of families shifted NIL
Balance NIL
13 Status of progress of Major Component in % Excavation work 83.45 % and Concrete work 68.37%
completed.

14 Balance Major works to be executed Excavation 30.07 TCM, Earthwork 10.52 TCM &
Concrete work 9.96 TCM are to be executed.

15 Bottlenecks including issues due to which Due to heavy rains, there is river flowing full of water
potential creation getting affected which affsects the construction of central spillway.

16 Efforts made in resolving issues --


17 Likely date of Completion Jun-22
Name of Project: Chondi Storage Tank Tq.Udgir Dist.Latur

S.No Items Details


1 Latest Estimated Cost for AIBP/BJSY 23.56
Component (Rs in crore)

2 Latest Expenditure including ETP (Rs in crore) 18.44


(upto December 2021)as per division

3 Balance Cost (1-2) (Rs in crore) 5.12


4 Financial Capacity of Project authorities 11.51
during last 3 years (FY 2017-20)
(Rs in crore)

5 Estimated cost of running tenders 9.97


(Rs in crore)

6 Estimated time of completion of tenders under Jun-22


item No 5

7 i.Balance amount of tenders to be invited (Rs 0


in crore)

ii.Time required for completion


8 Irrigation Potential under BJSY 0.765
(Th ha)

9 Irrigation Potential created upto date (Th ha) 0

10 Balance Potential to be created 0.765


(Th ha)

11 i. Total Land required to be acquired under 68.51


project (Ha)

ii. Total Land acquired (Ha) 68.51


iii. Balance land required to be acquired 0
12 Rehabilitation and Resettlement No. of families to be shifted NIL
No. of families shifted NIL
Balance NIL
13 Status of progress of Major Component in % Excavation work 50.50%, Earthwork 65.07 %
completed and concrete work 31.79% is in Completed

14 Balance Major works to be executed Excavation 123.34 TCM, Earthwork 155.15 TCM &
Concrete work 10.51 TCM are tobe executed.

15 Bottlenecks including issues due to which -


potential creation getting affected

16 Efforts made in resolving issues --


17 Likely date of Completion Jun-22
Name of Project: -Satrapotra Storage Tank Ta.&Dist. Beed

S.No Items Details


1 Latest Estimated Cost for AIBP/BJSY 49.44
Component (Rs in crore)as per SLTAC

2 Latest Expenditure including ETP (Rs in 39.50


crore)
(upto December 2021)as per division

3 Balance Cost (1-2) (Rs in crore) 9.94


4 Financial Capacity of Project authorities 30.71
during last 3 years (FY 2017-20)
(Rs in crore)

5 Estimated cost of running tenders 16.58


(Rs in crore)

6 Estimated time of completion of tenders Jun-22


under item No 5

7 i.Balance amount of tenders to be invited 0


(Rs in crore)

ii.Time required for completion Jun-22


8 Irrigation Potential under BJSY 0.79
(Th ha)

9 Irrigation Potential created upto date (Th ha) 0

10 Balance Potential to be created 0.79


(Th ha)

i. Total Land required to be acquired under 190


project (Ha)

ii. Total Land acquired (Ha) 188


iii. Balance land required to be acquired 2
No. of families to be shifted 172
No. of families shifted 0
Balance 172
13 Status of progress of Major Component in E/Dam - 90% Rehabitation - 80%
%

14 Balance Major works to be executed Gorege Filling work, Tail Channel Balance work
15 Bottlenecks including issues due to which 1. Rehabilitation of Kumbhari gavthan under submergence of satrapotra
potential creation getting affected Storage tank.2. Reimbursement of affected house holders of Kumbhari Village
to be made .

16 Efforts made in resolving issues 1. Rehabilitation of Kumbhari gavthan under submergence of satrapotra
Storage tank.

2. Reimbursement of affected house holders of Kumbhari Village to be made


17 Likely date of Completion Proposal
Jun-22 Submitted to revenue department.