Professional Documents
Culture Documents
Estimation and Costing
Estimation and Costing
ON
“CASE STUDY OF HIGH LEVEL BRIDGE OVER MULVAAGU IN
VEMULAWADA”
Submitted in partial fulfillment of the requirements for the award of the degree of
BACHELOR OF TECHNOLOGY
IN
CIVIL ENGINEERING
Submitted by
E. LOKESH (23285A0104)
K . VENKATESH (23285AO116)
Mr. S. RAJASHEKAR
Assistant Professor
(Approved by AICTE New Delhi, Affiliated to JNTUH-Hyderabad and Accredited by NAAC with A++)
CERTIFICATE
This is to certify that the project report entitled
E. LOKESH (23285A0104)
K . VENKATESH (23285AO116)
In the partial fulfilment of the requirement for the award of the Bachelor of Technology in
Civil Engineering by the Jawaharlal Nehru Technology University, Hyderabad during the
academic year 2023-2024.
No part of these is copied from books, journals, internet and wherever the portion is taken,
the same has been duly referred to in the text. The report is based on the project work done
entirely by me and not copied from any other source.
E. LOKESH (23285A0104)
K. VENKATESH (23285AO116)
ACKNOWLEDGEMENT
We would like to add few heartfelt words for the people who gave complete support right
from the stage of this project idea was considered.
We take this opportunity to express our deep sense of gratitude and respect to our project
guide Mr. K. Rajashekar, Asst. prof. of Civil Engineering, Kamala Institute of Technology
and Science, for her valuable suggestion’s sagacious guidance, scholarly advice and
comprehensive critical remarks during the course of investigation. We express unfeigned
gratitude towards our project guide for her valuable guidance in completion of field-based
project work.
Our sincere thanks to Dr. M. ANIL, Head of the department of Civil Engineering, for his
suggestions and wholehearted support.
Finally, we are thankful to one and all that have directly or indirectly rendered this valuable
guidance and encouragement during our project work.
E. LOKESH (23285A0104)
K . VENKATESH (23285AO116)
ABSTRACT
With meticulous attention to detail, the study meticulously analyzes the planning
and construction phases of the bridge, offering comprehensive insights. It
thoroughly explores various components of the bridge, including deck slabs,
columns, piles, beams, and arches, elucidating their respective roles in upholding
the bridge's structural integrity.
CHAPTER 1 INTRODUCTION
1 General 1
1.1 Estimation 2
1.3 Costing 4
CHAPTER 2 METHODOLOGY
2
ARCH BRIDGE
An arch bridge is a bridge with abutments at each end shaped as a curved arch.
Arch bridges work by transferring the weight of the bridge and its loads
partially into a horizontal thrust restrained by the abutments at either side. A
viaduct (a long bridge) may be made from a series of arches, although other
more economical structures are typically used today.
Arch bridges are bridges with a curved underside. Arch bridges distribute the
load (weight) instead of just pushing it straight down. They have abutments,
supports on the ground at both ends, on either side of the arch for added
support.
It can take up to triple the time to build this structure, which may not be
available to some communities if a span is needed immediately. This
disadvantage is also why the cost of building is so much higher with an arch-
based design, since there is more labor involved in the project.
List of the Advantages of Arch Bridges
Pile foundation
o Pile and pile cap
Substructures
o Pier &pier cap,
Pedestal,Bearing,
Abutment
Superstructures
o Beams, slab,
columns,
arch, tie
beams
Grade of concrete:
Pile & pile cap: RCC M35
Pier & pier cap: RCC M35
Pedestals: RCC M35
RC Beams: RCC M45
Deck Slab : RCC M45
Columns,Arch&Tiebeams : RCC M45
Sub structure
Earth face : 50mm
Other face : 40mm
Foundation : 75mm
Super structure : 40mm
1. The construction starts by drilling a vertical hole into the soil using
the bored piling machine. The machine is outfitted with
accessories like drilling tools, buckets, and grabs that help remove
soil and rocks during the drilling process.
4. After this, a rebar cage for the pile is inserted into the hole
and, subsequently, filled with concrete.
5. The top of the pile is capped either with a footing or a pile cap near
the ground level so that the structure above can be constructed.
Stages in Bored Pile Construction
It is usual for a pile cap to be of a greater depth than a comparable pad footing
as it is typically subject to higher bending moments and shear forces. The pile
cap achieves greater rigidity from the increased depth, which enables it to
evenly spread the load to all piles in the group. The factors that determine the
depth of the pile cap include:
As it is very difficult to bore or drive piles exactly vertically, the pile cap
should be able to accommodate some deviation in the final position of the
pile heads. The pile cap should overhang the outer piles, typically by a
distance of 100-150 mm on all sides, depending on the size of the piles.
Pile caps are constructed by excavating an area around the group of piles to
enable formwork to be inserted. The pile tops may be trimmed to ensure they
are at the same height. A reinforcement cage is then built and positioned in
the formwork cast box and fastened to the piles. The concrete is then poured
and left to cure, after which the formwork is removed.
Pier and pier cap:
Piers are most commonly made of concrete, masonry or treated timber, and
installed into prepared holes or shafts.
Piers can serve a similar purpose to piles, but are not installed by hammers
and have the potential, if based on a stable substrate, to support a greater
load. Pier shafts have been excavated with widths of more than 1.8 m and
depths of more than 30 m , capable of supporting high-rise buildings.
Uncontrolled drainage from the approach may wash around abutment wings
and underneath stub abutments, leaving the foundations exposed. Improving
drainage at approach will help . Another option is to excavate the fill and
install a drainage system adjacent to the abutment. This may by a proprietary
backwall drain system or a section of drained aggregate from which water is
piped away. Excavation may also allow for the installation of granular backfill
material to relieve excess pressure on the abutment.
Beams :
A beam structure, sometimes simply referred to as a beam, is a type of
structure used in construction and engineering to provide a safe and
efficient load path that effectively distributes weight throughout the
foundation of a building. These beams support the load by resisting
being bent under the load's pressure. The construction of beams follows
as
Formwork
Bending and Binding Steel Bars
Positioning of steel bars
Placement of cement concrete
Deck Slab :
Approach slabs serve to reduce the step which can result from settlement of
approach embankments caused by consolidation of embankment fills and the
underlying material. The smooth transition provided by approach slabs
reduces dynamic vehicle loads on bridges. It is unlikely that approach slabs
will fail structurally because of their thickness (typically 15-inches) and the
large amount of reinforcing steel in the bottom. The surface may spall or
scale like a bridge deck; in these cases, recommended repairs are similar to
those for bridge decks.
Columns :
A column or pillar in architecture and structural engineering is a structural
element that transmits, through compression, the weight of the structure
above to other structural elements below. … Columns are frequently used to
support beams or arches on which the upper parts of walls or ceilings rest.
Columns are essentially required with the primary longitudinal reinforcement
and lateral ties to avoid buckling of the primary bars. … The spacing of the
longitudinal reinforcement should not be more than 300 mm. The maximum
and minimum values of the pitch of helical reinforcement is restricted to 75
mm and 25 mm.
Arch:
Arch bridges have a curved underside. … Actually, the arch is what makes
the bridge strong. The arch allows the load to spread out instead of pushing
straight down. The load spreads out to the abutments, which are supports on
the ground at both ends, which keeps the ends of the arch bridge from
breaking apart. Arches work by transferring the load through the arch to the
supporting foundation via the abutments.
TIE BEAMS:
The tie beam is under tension and connects the end joints of a structure,
which are subject to horizontal thrust forces. By tightening the ends of the
structures, the tie beam absorbs the thrust, relieving the supports of the
horizontal force. The tie beams are beams whose function is not to carry the
slab load but just to act as a stiffener to the columns and thereby reduce the
long column effect.
Conclusion
This internship has helped us in knowing a lot about the civil engineering
works which we weren’t aware of. I personally observed many of the major
differences between the things we learned theoretically in our classroom and
at the site. We have come to know that their is a lot of process in handlesuch a
huge project. It’s also a long procedure to get these government various
project constructions. Finally I can say that I learnt about each and every
minute process in construction procedure.