Project : Kalselteng 2 Coal Fired Steam Power Plant (2x100MW)


PT Truba Jaya Engineering – Hyundai Engineering Co. Ltd. – Itochu Corporation as a
Consortium is installing the 2 x 100 MW Coal Fired Power Plant at Asam-Asam, South
Kalimantan Tengah on an EPC basis. The Owner of the project is PT. Perusahaan Listrik Negara
(Persero).

December 29, 2021


Letter No. : IKCP-HEC.SITE-RFQ-L00XX
Reference No.:

To : PT. RZ
Jl. Sesama
Jakarta

Subject : Request for Quotation of Heavy Equipment (Rent Price Estimate)

Dear Sir,

In concern with the needs of project installation in Kalselteng-2 CFSPP (2×100 MW) Project, w e, Hyundai
Engineering (herein after HEC), would be grateful if you could send us a quote of rent price estimate for the
following:
a) #1 and #2 Steam Turbine Generator Lifting Device
(Please see Attachment.1 Purchase Request/Subontract Request)

b) #2 Boiler Drum Lifting Device


(Please see Attachment.2 Lifting Plan of ………)

*Note:
 Request of Quotation for ….. with control driver/operator includes mobilization, demobilization and
installation.
 Rent Price Estimate is 7 days for ….. and 5 days for ……..

We are looking forward to hearing back from you.

Yours sincerely,

_____________________
Kim Hee Chul
Project Manager