Professional Documents
Culture Documents
issue_12_-_iq_2014
issue_12_-_iq_2014
Follow us on and for the latest construction and energy legal updates
Contract Corner:
A review of typical contracts and clauses Issue 12, 2014
should the court exercise its discretion and output was achieved was foreseeable from the procedure, even if more expensive and
order that the Council’s proceedings be stayed? outset, yet nevertheless the parties chose to extensive, than to take the real risk that this
incorporate the adjudication machinery in the will be required in any event in addition to an
On the first issue the Judge decided that FIDIC form of contract. Both parties therefore adjudication.
upon a proper interpretation of the Contract, agreed to the “rough and ready” adjudication
sub-clause 20.8 would only apply to give procedure. However in the Swiss case, the Supreme Court,
Peterborough a unilateral right to opt out of perhaps because the Swiss Civil Code, like that
DAB adjudication if the parties had agreed That said, in circumstances where the parties of Romania, makes provision for the parties to
to appoint a standing DAB at the outset. had not yet invested time or money in the DAB act in accordance with the principles of good
Accordingly, given that sub-clause 20.2 adjudication, the Judge was sympathetic to faith, looked at the whole circumstances of
provided for ad hoc DAB appointments, the Peterborough’s case that the court proceedings the disputes between the parties. Here the
Judge accepted EMS’s argument that the should not be supplanted by adjudication. Contractor spent some 18 months trying to
Contract required the determination of the bring about the appointment of a DAB before
dispute through DAB adjudication prior to However, the overriding principle, as illustrated resorting to arbitration. An Employer could
any litigation. The right to refer a dispute to by the English legal authorities, clearly showed not then in good faith insist on the mandatory
adjudication arises under sub-clause 20.4 as a presumption in favour of leaving parties to nature of the DAB procedure it had done so
soon as a DAB has been appointed, whether resolve their disputes in the manner they had much to frustrate in the first place. This is rather
under sub-clause 20.2 or 20.3. agreed to in their contract. Accordingly, the helpful for contractors who are faced with an
Judge ordered that the court proceedings employer who is apparently trying to prevent
Peterborough then argued that sub-clause 20.8 were to be stayed. what is seen as a legitimate dispute from being
provided an opt-out from DAB adjudication resolved through the DAB process.
but that if reference of a dispute to a DAB was The Swiss and English decisions compared
mandatory, the court proceedings should be
Although the circumstances of the cases were Footnotes
allowed to continue on the grounds that:
very different, both the English and the Swiss 1. [2014] EWHC 3193 (TCC)
(i) what was a complex dispute was courts emphasised that DAB procedures must
unsuitable for a “rough and ready” DAB be treated as mandatory.
adjudication procedure; and
One of the main differences between the two
(ii) any DAB adjudication would be an decisions was the attitudes of the parties. In
expensive waste of time as it was the Swiss case, the Employer was essentially
inevitable that the losing party would go trying to frustrate the entire dispute resolution
to court. process, first by moving very slowly when it
came to the appointment of the DAB and
Peterborough submitted that any decision
then using the lack of a DAB to allege that the
by the DAB would almost inevitably provoke
arbitration tribunal did not have jurisdiction.
a notice of dissatisfaction from one or other
In the English case, the Employer did not really
party. Accordingly, to embark on the fairly
want to have a DAB, preferring to go straight
lengthy (and therefore expensive) adjudication
to a final resolution of the case. This may, to a
procedure under the contract would be a
limited degree, have had an influence on the
wholly or at least largely unproductive exercise.
decision.
The dispute raised complex questions of
construction and application of legislation,
Thus whilst both courts did agree that the
mandatory codes and standard industry
DAB was a condition precedent to arbitration,
practice and would require extensive
in England this meant that the parties had
disclosure. Therefore the “rough and
to submit to the DAB, even though the
ready” process of adjudication was entirely
Judge recognised that there was a real risk
inappropriate to resolve this dispute.
of duplication of costs. This was not a case
However, the Judge noted that this was where either party had invested any time or Jeremy Glover
nothing new: the complexity of a potential money on the preparation for or conduct of Fenwick Elliott
dispute about when the required power an adjudication, and so it can fairly be said that +44(0)207 421 1986
it was better to have one dispute resolution jglover@fenwickelliott.com
Universal view:
International issues around the globe Issue 12, 2014
if completion is or will be delayed, under Service Period of the contract (to reflect the some reasonable precautions and reasonable
Sub-clause 8.4, and fact that the Operation Service Period cannot alternative measures that could be taken to
be extended). It is anticipated that FIDIC will avoid the ISIS threat.
(b) if the event or circumstance is of the
follow the form adopted in the Gold Book
kind described in sub-paragraphs (i) As far as Ebola is concerned, because it is not
when it releases its updated version of the
to (iv) of Sub-clause 19.1 and, in the an airborne disease, again, there are likely to be
1999 Form.
case of subparagraphs (ii) to (iv), occurs various measures that contractors could take
in the Country, payment of any such Establishing force majeure to protect against the risks the disease poses.
Cost….” For example, medical checks could be imposed
Is it a true force majeure event? and employees could be excluded from site
Notice of Force Majeure is given under Sub-
if necessary. Or materials could be sourced
clause 19.2 and the notice is to be delivered in In order to establish Force Majeure, the
from alternative locations and/or suppliers in
accordance with Sub-clause 1.3. Contractor will have to establish that the force
the event that the supply chain was affected
majeure event is included within one of the
Under Sub-clause 19.6, if the execution of (the same would apply to any logistical issues
definitions in Sub-clause 19.1 (or is similar in
substantially all of the works is prevented for a arising out of the ISIS threat).
nature), and that he has been prevented from
continuous period of 84 days (or for multiple performing his contractual obligations in that Is the Contractor being prevented from
periods that total more than 140 days) by performance has become physically or legally performing any of his obligations under the
reason of Force Majeure, then either Party can impossible, as opposed to more difficult or Contract by reason of the Force Majeure?
issue a notice of termination, which will take unprofitable.
effect seven days later. The Engineer will then
Causation issues may arise in circumstances
determine the value of the work that has been Taking this and applying it to the ISIS where a Party is concerned that conditions at
done, and other costs such as demobilisation insurgency, it should be possible to establish or outside the site are too dangerous to allow
costs. that the actions of ISIS in trying to establish its staff or sub-contractors to continue working.
an Islamic State within Iraq constitutes war, The issue here is that if the Contractor’s
The 2008 Gold Book (“the Gold Book”) is also hostilities, terrorism, and invasion and so the
important in the context of force majeure as response was to evacuate the site, a situation
existence of a Force Majeure event ought to be would not be created whereby work would be
it represents a more collaborative, risk sharing able to be satisfied. Epidemics are not explicitly
approach than that which is seen in the 1999 prevented from taking place. The Contractor’s
covered under Sub-clause 19.1, but it must at actions in evacuating the site would stop work,
suite of contracts: indeed, FIDIC is likely to least be arguable that the Ebola outbreak is
follow the Gold Book approach at such time as not the ISIS threat, regardless of how strong
exceptional in its extent and nature, in which that threat is, or is perceived to be.
the 1999 suite is revised. case it might be regarded as being a natural
catastrophe. An alternative scenario may arise in relation to
The Gold Book does not contain the usual
1999 suite Clause 19 force majeure provisions. causation whereby the Contractor is unable
Could the Party have reasonably provided
Instead, it drops Clause 19 completely in favour to carry out work that is on the critical path,
against the Force Majeure before entering into
of a new Clause 18 that is headed “exceptional but he can carry out non-critical path work.
the Contract / is the Force Majeure beyond the
risks”, and Clause 17 (which was formerly risk Whilst this may cause substantial problems, it
Party’s control or attributable to the other Party
and responsibility) has been re-named “risk would probably not be prohibitive in terms of
/ could the Party have avoided or overcome
allocation”. The definition of exceptional risks performance of the Contractor’s obligations.
the Force Majeure event once it had arisen?
is very similar to the force majeure definition
Foreseeability (under the civil codes)
at Clause 19, but it is Clause 17 that makes These issues are relatively straightforward and
the Gold Book stand out from the 1999 suite. the ISIS insurgency and Ebola threat provide If foreseeability is an issue under any applicable
Clause 17 sets out the risks that the Employer some good examples. ISIS taking control of civil code (foreseeability does not feature in
and Contractor are to bear in a very detailed Bagdad is arguably an event that could not be the FIDIC form), then the question that has to
manner, having separate regard to the Design- prevented or avoided despite the exercise of be asked is if the force majeure event would
Build Period and the Operation Service Period reasonable diligence by either Party; indeed have been foreseeable to the hypothetical
of the contract. The Contractor is entitled to neither the current Iraqi government or the reasonable party at the time the contract was
an extension of time and its costs if there are international community has been able to entered into. This question is likely to create
any exceptional risks or Employer risks during effectively challenge the advance of ISIS. substantial difficulties.
the Design-Build Period, but to its costs only if However, if parties were affected by what is
those same risks occur during the Operation happening in Bagdad, then there are probably The current security situation in Iraq is seen
Universal view:
International issues around the globe Issue 12, 2014
definition of force majeure at the drafting • If you do have to make a formal Conclusion
stage. They may, for example, narrow the declaration of Force Majeure, once you
definition of force majeure, exclude the have served notice of Force Majeure Force majeure can be a mine field, not least
right that otherwise exists to payment of under Sub-clause 19.2, you need to because the definition of force majeure can
costs, or limit the termination provisions. present your claim for additional time prove to be problematic and difficult issues of
It is always worth checking your contract and/or cost under Sub-clause 20.1 causation and foreseeability can arise.
to see if any bespoke amendments have within 28 days of the date on which you
A possible solution may be found in the
been made which alter the usual force became aware of the Force Majeure event
advance warning procedure that appears in
majeure provisions in order to avoid being or circumstance, or should have been
Sub-clause 8.4 of the FIDIC Gold Book which
caught out. aware of it, and your fully particularised
may assist to better manage difficult events.
• As soon as you become aware of a claim should follow 14 days later. Your
Sub-clause 8.4 provides that each Party shall
potential force majeure event that may claim may be subject to a decision of the
endeavour to advise the other Party in advance
potentially impact the performance of arbitral tribunal in due course so provide
of any known or probable future events or
your contractual obligations or the works, as much documentary evidence as you
circumstances which may adversely affect
serve notice under Sub-clause 19.2. It can.
the work, increase the Contract Price or delay
is better to err on the side of caution • If your claim for relief for Force Majeure the execution of the Works or the Operation
and serve a notice that transpires not looks doubtful under the FIDIC form, Service. The Employer’s Representative may
to be necessary, than to serve a notice consider whether any provisions of require the Contactor to submit an estimate of
too late and lose your entitlement to the relevant civil code might offer you the anticipated effect of the future events or
make a claim. Sub-clause 19.2 is rather assistance. Most civil codes provide relief circumstances, and/or a proposal under Sub-
draconian in that the time bar starts to run for true force majeure events, but a word Clause 13.3 [Variation Procedure].
from 14 days from when the Contractor of warning. Not all provide a clear right
should have become aware of the Force to compensation2, and some require the If parties incorporate the provisions of Sub-
Majeure event, and common and civil law force majeure event to be unforeseeable clause 8.4 of the Gold Book into their contracts,
jurisdictions will generally uphold time at the time the contract was entered into, then it is to be hoped that the parties would
bar provisions. which can create considerable difficulties be able to better manage force majeure type
• If you find yourself in a potential force in countries such as Iraq that are mired events, and that the formal declaration of force
majeure situation, you need to reduce by security and political conflict, as noted majeure would be the very last resort.
the risk surrounding whether an event is above.
a true force majeure event by entering • If you do need to demobilise and/or
into without prejudice discussions with evacuate, prepare an inventory of all
the other party. Try and agree what will equipment and materials on site and Footnotes
constitute a force majeure event before secure photographic, video and/or 1. See, for example, Article 1148 of the
the event actually arises, and / or agree documentary evidence of the physical French Civil Code which provides
legitimate steps you can take to mitigate condition of the site and works, as well as that a force majeure event must be
the risk in a given set of circumstances. the progress of the works. Be sure to copy unforeseeable, and render performance
If all else fails, speak to the other party to any paperwork in relation to progress both impossible and outside the
see if you can suspend or terminate the payments, variations, or any pending control of the party who seeks to invoke
works rather than declaring force majeure claims before you leave. If you are suspension of the relevant contractual
to avoid any liability that might otherwise unable to take soft copies, endeavour to obligation.
arise from a false declaration of force transport hard copies to a safe and secure 2. See, for example, Articles 168 and 425
majeure. location. This documentation will be of the Iraqi civil code which make no
• Before making any firm decisions about invaluable in substantiating future claims mention of compensation
whether to cease work, obtain as much or defences that you might bring in due
information as you can about the force course relating to the Force Majeure, or
majeure event. In the case of ISIS, try and in circumstances where theft or damage
get reports from security advisers and occurs due to the actions of a third party. Lisa Kingston
any information that might be published Most claims and defences fail due to a Fenwick Elliott
by government agencies to support the lack of supporting evidence.
+44(0)207 421 1986
existence of your force majeure event.
lkingston@fenwickelliott.com
Universal view:
International issues around the globe Issue 12, 2014
Clause 1.1 of the contract provided: The subcontract also provided that the where there was a discretionary right (for
parties “shall uphold the highest standards example awarding a discretionary bonus to an
“The Partnering Team members shall work of business ethics in the performance of the employee). In those circumstances a decision-
together and individually in the spirit of trust, contract. Honesty, fairness and integrity shall be maker’s discretion will be limited, as a matter of
fairness and mutual cooperation for the paramount principles in the dealings between the necessary implication, by concepts of honest
benefit of the Term Programme . . . and in all parties.” good faith and genuineness and the need for
matters governed by the Partnering Contract the absence of arbitrariness, capriciousness,
they shall act reasonably and without delay.” Ramsey J referred to the Court of Appeal perverseness and irrationality.
decision in Socimer International Bank Ltd
The contract contained an “unqualified and (in liquidation) v Standard Bank London Ltd,9 Good faith in UAE contracts
unconditional right to terminate” at any time (i.e. which related to the standard to be applied
termination for convenience). in circumstances where the valuation of In stark contrast, a duty to act in good faith is
assets was left entirely in one party’s hands. In implied into all contracts that are subject to
SAH terminated the contract and TSG argued that case it was held that a decision-maker’s UAE law. This is underscored by principles of
that the termination was wrongful and in discretion will be limited, as a matter of fairness developed under Sharia law.
breach of clause 1.1. The issue the court had necessary implication, by concepts of honest
to decide was whether the good faith clause good faith and genuineness and the need for Article 246 of the UAE Civil Code provides that:
was pervasive such that it applied to the whole the absence of arbitrariness, capriciousness,
contract and therefore to the termination “a contract must be performed in accordance
perverseness and irrationality. However, the
provisions. with its contents, and in a manner consistent
decision remained with the decision-maker
with the requirements of good faith”.
and was therefore subjective.
The court accepted that, in principle, an
express obligation to act in good faith could be This in effect is a requirement not to use
Ramsey J decided that the same standard
pervasive and, depending on the nature and the terms of a contract to abuse the rights
applied in these circumstances and was not
drafting of the clause, it may be possible for it of the other contracting party, not to cause
impacted by the express clause in the contract
to affect all aspects of the contract. unjustified damage to the other party and to
although that clause was consistent with
act reasonably and moderately.
it. He went on to find that termination had
However, the court held that this was not
been justified on four of the five main grounds Decisions of the Dubai Court of Cassation
the case here. The contract contained an
alleged in the contractor’s notice of default.10 have ruled that an act of bad faith by one
unqualified right to terminate for convenience,
to which the obligation to act in good faith contracting party may provide a cause of
Summary
could not possibly extend. The entitlement action for the other and the duty of good faith
to terminate the contract was absolute. Each It seems then that the English courts are not is therefore overarching, unlike at English law.
party was entitled to terminate at any time. ready to imply a general doctrine of good In deciding whether an act constitutes bad
Further, clause 1.1 primarily related to the faith. The judgment of the High Court in Yam faith the court may also look at Article 106 of
assumption, deployment and performance of Seng appears to have been sidelined (if not the UAE Civil Code which provides that a party
roles, expertise and responsibilities set out in directly overruled) by the Court of Appeal and is prohibited from exercising its rights if:
the Partnering Documents. subsequent cases.
• it is intended to infringe the rights of
In the later 2014 case of Bluewater Energy If the parties want to have an express duty of another party;
Services BV v (1) Mercon Steel Structures BV and good faith they need to create one and they
others,8 Ramsey J examined again the impact • the outcome is contrary to the rules of
should think very carefully about its scope. The
of a good faith provision in the context of Islamic Sharia, the law, public order, or
English courts will not allow good faith-type
termination. morals;
wording to overrule an absolute contractual
right such as the right to terminate for • the desired gain is disproportionate to the
That contract provided for a notice of default convenience. The parties will need to expressly harm that will be suffered by the other
to be issued to the subcontractor requiring provide that a good faith obligation operates in party; or
them to “immediately commence and thereafter relation to such a provision.
continuously proceed with action satisfactory to • it exceeds the bounds of custom or
Bluewater to remedy such default”. If they did The situation might, however, be different if practice.
not do so, a notice of termination could then there was evidence to suggest a breach of an
be issued. express good faith obligation in circumstances
Commentary:
International dispute resolution & adjudication Issue 12, 2014
There are some potentially wide-ranging of good faith is not applicable to the Footnotes
ramifications of this including: obligation itself but to the performance
of the obligation. Accordingly the parties’ 1. With thanks to Lisa Kingston of Fenwick
• Good faith is most likely to be applied to agreement that the employer may Elliott for her great assistance in preparing
evidence for, or to support, an allegation terminate the contract for convenience this paper and Ahmed Ibrahim of Ahmed
of breach. Where, for example, building is a valid agreement and the UAE courts Ibrahim Advocates and Legal Consultants
materials are found to be defective a will normally uphold this. Although this for his assistance in relation to the position
breach will be easier to establish if there employer’s right might be looked at as under UAE Law.
has been some attempt to conceal this or contradicting the good faith principle, it 2. [2013] EWHC 111 (QB) (February 2013)
cover up the materials once incorporated would be an enforceable contract term as 3. [2013] EWCA Civ 200 (March 2013).
into the works. it was freely entered into. However, if the 4. Clause 3.5 of the contract.
employer relies on this contract provision 5. At first instance the High Court ruled
• Reliance on a time bar notice (e.g. FIDIC’s to terminate the contract in circumstances that the Trust had abused its contractual
clause 20.1) is likely to be restricted where that give rise to performing the contract powers in relation to the service credits
a party seeking to rely on it knew about in a manner that is inconsistent with and breached the express provision of
that breach previously (for example, good faith, then the court might have a Clause 3.5. It further held that the Trust
if notification of the claim was made different view. For example, if the contract had acted capriciously and irrationally
informally and is recorded in meeting provides for termination for convenience in the way in which it deducted out the
minutes or similar but was never formally and limits the liability of the employer credits (e.g. deducting £84,540 for one day
made). In other words, denying a claim to compensate the contractor for the out of date chocolate mousse).
due to the time bar when it had already work done until the date of termination, 6. [2013] EWHC 1151 (TCC).
been communicated, albeit informally, but excluding mobilisation cost, the 7. TPC 2005 as amended in 2008.
would be an act of bad faith. employer who terminates the contract 8. (2) Mercon Holding BV; (3) Mercon Groep
for convenience immediately after BV [2014] EWHC 2132 (TCC).
• Avoiding liability for a very substantial 9. [2008] EWCA Civ 116
mobilisation and before the contractor
claim due to a time bar may also be 10. In the Compass case, Jackson LJ had
has done any work is performing the
unlawful where the losses were serious rejected such an implied term on the
contract in bad faith. In this case, the
and unequal with the employer’s grounds that the term in question was an
contractor might rely on Articles 246
contractual claim to be notified in a absolute contractual right and not one
(good faith), 106 (abuse of right) and
required time period (for example 28 days which could be exercised with discretion
390(2) (claiming actual loss) of the UAE
under clause 20.1 of FIDIC). Article 106
Civil Code to recoup its losses.
(1) of the UAE Civil Code provides that “a
person shall be held liable for an unlawful
exercise of his rights” and this, together Overview
with the good faith obligation, may be
used to challenge the effectiveness of a The stark contrast between the position
time bar in such circumstances. regarding good faith under English law and
that under the UAE Civil Code remains in place.
• Whilst the UAE Civil Code does provide This may make a real difference with regard to
that parties may fix a pre-agreed how some standard provisions in construction
compensation mechanism or amount in contracts are interpreted. As outlined above,
their contract, the court may also vary the the same time bar and termination for
pre-agreed amount of compensation or convenience provisions may result in very
damages to equal the actual loss in any different outcomes on similar facts, depending
event, regardless of whether there was on how the governing law approaches the
any “act of prevention” on the part of the issue of good faith.
employer.11
enforcement issues. Courts of the UAE trend by the UAE courts away from overturning
arbitration awards on purely technical reasons.
The Enforcement Judge is required to A similar situation can be seen in the courts of
follow shariah principles, unless the law the UAE, as there are a number of technicalities Although there are still exceptions to this trend,
stipulates otherwise, and Article 9 of the new which are peculiar to UAE law. Such there seems to be a more arbitration-friendly
Enforcement Law provides for compulsory technicalities include requirements that: climate in the UAE and the developments are
enforcement upon the presentation of an positive.
executive deed, including a final arbitral award. • a UAE award must be physically signed
within the UAE;
Conclusion
Also, notably, appeals of the Enforcement
Judge’s decisions suspend enforcement. This • the legal representative of each party
The new Enforcement Law in Saudi Arabia is
goes against domestic law trends seen in other possesses a valid power of attorney to act
a positive step in the right direction. It should
parts of the world such as France. in the proceedings; and
guarantee that the merit of the dispute is
• witnesses should not be present in the no longer revisited; however, it is yet to be
The Enforcement Judge may enforce foreign
evidentiary hearing except when they determined what effect the provisions will
arbitral awards only on the basis of the
are giving evidence (however, it is worth have in practice. The new Enforcement Law
principles of reciprocity, refusing to enforce
noting that this is often relaxed by the does not protect parties or foreign awards
arbitral awards from jurisdictions that would
agreement of the parties). that are unfamiliar to Saudi law or shariah law
not enforce Saudi judgments or awards, and if
concepts.
the party seeking enforcement can ensure that:
In the past, awards have been overturned by
the courts for apparently insignificant errors Similarly, the positive advances in the UAE are
• Saudi courts do not have jurisdiction with
such as the tribunal’s failure to sign each page encouraging, but while fewer technicalities are
regard to the dispute;
of the award in full, instead simply initialling being flagged by the courts, it is still important
• the award was rendered in compliance each page. The Bechtel case is an example to know the pitfalls that can arise.
with due process requirements; of this, where the Dubai Court of Cassation
overturned an arbitration award because
• the award is in final form in the law of the the oath used to swear in witnesses during
seat of the arbitration; the arbitration did not follow the formula
prescribed for UAE court hearings.
• the award does not contradict a judgment
or order issued on the same subject by a Notably, the Paris Court of Appeal upheld the
judicial authority in the Kingdom of Saudi award in favour of Bechtel, setting aside the
Arabia; and Dubai Court of Cassation’s decision. The Paris
Court of Appeal ruled that the arbitral award
• the award does not contain anything
satisfied the requirement.
contradictory to Saudi public policy.
Positive trends in UAE courts
• The new Enforcement Judge will be
specialised in the enforcement of However, despite the history of technicalities, Nicholas Gould
awards, and judgments should be more there are also positive developments in the Fenwick Elliott
expedient. UAE courts. There appears to be a general ngould@fenwickelliott.com
News and events
Trends, topics and news from Fenwick Elliott Issue 12, 2014
This edition sponsor of this event we are able to offer a 30% always interested to hear your feedback and
discount using the VIP code FKW82533FEE. would welcome suggestions regarding any
Seminars and conferences Guests can register online, via email to aspects of contruction, energy or engineering
Fenwick Elliott once again supported the FIDIC professionalcustserv@informa.com or by sector that you would like us to cover. Please
International Contract Users’ Conference 2014 calling +44 (0) 20 7017 5503. contact Jeremy Glover with any suggestions
which took place on 2-3 December 2014 in jglover@fenwickelliott.com.
2014
London.
2014 has been a busy year for the firm and
Nicholas Gould, Partner, Jeremy Glover, Partner one in which the team has grown. During the
and Vincent LeLoup, EC Harris discussed past twelve months we have had two new International Quarterly is produced
“Time Bar Application under a Civil Law and a partners in the firm, David Bebb and Thomas
quartely by Fenwick Elliott LLP, the
Common Law Perspective” in the morning of leading specialist construction law
Young were promoted internally from senior firm in the UK, working with clients in
the second day. associates to partners and we have also had the building, engineering and energy
Fenwick Elliott are also supporting the FIDIC one new senior associate (Marc Wilkins) and sectors throughout the world.
Middle East Contract Users 2015 Conference three new associates (Martin Ewen, Robbie
McCrea and Suryen Nullatamby) join the
International Quarterly is a newsletter
in March next year. Both Nicholas and Jeremy and does not provide legal advice.
will be speaking on the first day providing firm. This further strengthens our team of
practical insights as to the reasons behind construction law specialists. Edited by Jeremy Glover, Partner, Fenwick Elliott LLP
jglover@fenwickelliott.com Tel: + 44 (0) 207 421 1986
the application of time bars, their operation This publication Fenwick Elliott LLP
under different Governing Laws (civil law vs. Aldwych House, 71-91 Aldwych
common law jurisdictions), ways around it We aim to provide you with articles that are London , WC2B 4HN
and recent jurisprudence on this matter. As a informative and useful to your daily role. We are www.fenwickelliott.com
Follow us on and for the latest construction and energy legal updates