Professional Documents
Culture Documents
AC Offshore Substation_For Biginners
AC Offshore Substation_For Biginners
AC Offshore Substation_For Biginners
Karthick P
1
1. Offshore Substation introduction
2. How Offshore wind farm works
3. How Offshore substation is built
4. Sample SLD & Layout
5. How to Select AC or DC Substation
6. Notes to consider for offshore Substation design
7. Notes for offshore Substation Equipment’s
- Transformer
- GIS
- Export / Inter array cable
8. Fire and explosion
9. Protection philosophy
10. Testing and commissioning procedure
2
Offshore Substation introduction:
3
Offshore Substation introduction:
Largest offshore wind farm is Hornsea-1 with 1218MW capacity and commissioned in 2020 (Source:4offshore.com)
Abundance of resources:
Offshore wind can provide high amount of clean and renewable energy to generate more than 420 000TWh per year
worldwide.
Offshore wind technical potential and electricity demand, 2019 (Source: iea.org)
4
Offshore Substation introduction:
Renewable Energy:- Courtesy: IRENA_Renewable_Energy_Statistics_2020
“ By 2030, the Asian offshore market is expected to have installed nearly 100 GW of offshore wind capacity, according
to the Global Offshore Wind Report 2019 published by GWEC (Global Wind energy council)earlier this year.”
5
Offshore Substation introduction:
6
How offshore wind farm works:
WTG Section 7
How offshore wind farm works:
FEED EPCI
Reactive Power
comp. export cable
yes no
Export cable
voltage kV
220
170
110
66
Array grid
voltage kV
110
66
33
Earthing concept
Combined Separate
earthing with aux Tr. earthing
Transformer
shunt reactor
OFWF ODAF /OFAF ONAN cooling type
Transformer type
3-winding 2-winding
Base Solution / Key factor - AC Offshore Substation
Number of power
transformers
2
HV Busbar
scheme
ring double single
Total system
99.9%
99%
95%
availability (%)
Number of export
1+1 Cables per platform
1
Decision sequence
Number of array
Cables to platform
4
1
Platform
floating concept
fix
How We Works:
Number of
platforms
1
Distance to shore
from platform
60km -
-80km
-60km
-20km
20km-
0-
Wind Farm Total
Power
1600
1200
800
400
How We Works:
11
How offshore substation is built:
12
How offshore substation is built:
J- Tube
13
How offshore substation is built:
14
SLD_ 400MW Offshore substation ( With 2 winding transformer_ Typical 1 )
PDF Document
SLD
15
SLD_ 750MW Offshore substation ( With 3 winding transformer_ Typical 2 )
PDF Document
SLD
16
Layout Plan : Topside structure:
17
Types of AC Offshore substation
Customer substations – used for exporting power from a Hub system substations – Two or more HV (or EHV) cable
single wind farm. Customer substations are collector sub- lines exporting power from individual wind farms are
stations which receive MV transmission cables comprising connected to the hub substation radially
the wind farm’s inter-array cable network
18
How to Select of AC or DC Substation
AC DC
19
How to Select of AC or DC Substation
“ Some innovative solutions are being considered such as Gas Insulated Lines or High Temperature
Superconducting Cables, which could provide bulk power transmission over large distances.”
20
Notes to consider for offshore Substation design
21
Notes to consider for offshore Substation design
22
Notes to consider for offshore Substation design
23
Notes to consider for offshore Substation design
* Personal aspects:- To ensure the safety of the personnel who need to operate and maintain the substation
Transport to and from the substation / Transport at each end
Emergency evacuation / Fire & Explosion
Restricted working area due to compact design, etc…
Exposed locations on the substation platform (walkways and staircases)
Electrical hazards when testing or operating
Loss of services such as lighting, heating or communications
* Operational Aspects :- Following operational risks may be encountered
Depletion of protection systems
Fouling of cooling or ventilation system intakes and exhausts
Due to spare parts unavailability
* Commercial Aspects :- Following commercial considerations may have an impact upon design decisions
Loss of production
Insurance costs /claims for accidents
Transport / repair equipment costs
24
Notes to consider for offshore Substation design
Maintenance:-
Any activity to be carried out on an offshore substation platform will typically
cost approximately ten times that of a similar activity carried out onshore.
Equipment Tagging
25
Notes to consider for offshore Substation design
26
Notes to consider for offshore Substation design
System Considerations:-
Some general guidelines to maximize the revenue as below,
No redundancy of expensive and/or reliable components
Optimization of offshore installation and maintenance work
Smart planning of maintenance (prevention rather than repairs)
Maximize availability in terms of energy transmission (not time)
27
Notes to consider for offshore Substation design
Redundancy:-
Redundancy in a system is a cost versus risk decision, risk is
determined by the chance of failure of a certain component and
the impact of failure of a certain component.
* Cost of redundancy is usually higher than for onshore installations.
* Redundancy shall not be available for high cost equipment like
Transformer, cable, etc. , however in some cases the overloading
capacity will be considered in the equipment
* High risk devices like Secondary equipment , Communications,
HVAC and cooling systems shall have redundancy.
* Inter array Cable Considerations
* Export Cable Considerations
* Interconnecting Wind Power Plants
28
Notes to consider for offshore Substation design
Situation 1
Recommended PCC for single wind power plant situation
Situation 2
Recommended PCC for multiple wind power plant situation with Offshore TSO
29
Notes to consider for offshore Substation design
30
Notes to consider for offshore Substation design
Fault Level :-
What is the Limiting Factor on Fault Level?
* Use of three-winding transformers with secondary windings feeding split busbars to effectively split the number of
generators connected in parallel at the offshore AC substation.
* Use of substation transformers with higher impedance to reduce the system fault level contribution at the
generators’ point of connection.
* If a ring design is implemented in the collector strings, the cable impedance can be used to effectively increase
the loop impedance
Three Phase & Single phase faults:-
Currents for this type of fault are the highest met and used in the determination of the ratings of the circuit breakers
in the system.
Infeed from Grid System :-
The fault contribution from the upstream grid can be calculated from the PCC equivalent impedance and the cable and
transformer impedance, up to the fault point.
400 kV, 275 kV and 132 kV the 3 phase rms fault levels may be up to approximately 63 kA, 40 kA and 40 kA respectively.
31
Notes to consider for offshore Substation design
Systems Studies:-
In order to bring together all the relevant aspects in the complex process of designing large offshore wind power
plants, several system studies need to be carried out,
• Load Flow Study
• Short Circuit Study
• Harmonics Study
• Insulation Coordination Study
• Electromagnetic Transient Studies
• HV Export network transient studies
• Flicker and Voltage Fluctuation Study
• Dynamic Stability Study
• Safety Earthing Study
• Neutral Grounding Study
• Protection Coordination Study
• Electro Magnetic Field (EMF) Study
32
Notes for offshore Substation Equipment’s
In General:
Below are the guidance on how to write the technical specifications for the main electrical equipment to be
located on the offshore substation
o Parameters coming from the System Studies
-Short circuit level, full load current, lightning impulse withstand level, transformer impedance etc.
o Important Items to Define to the Platform Supplier associated with regard to the Accommodation for
the Equipment
-Supplier to define to the platform supplier specific requirements for the room in which the equipment is to
be accommodated
33
Notes for offshore Substation Equipment’s
-Power transformer
* Secondary measurements such as temperature measurements, oil analysis and Frequency response assessment
(FRA). Monitoring the condition of key elements of the transformer is necessary particularly the insulating medium, the
cooling plant , DGA, breathers, bellows, barriers and the tap changer. ( Process and analysis software should be kept
onshore) .
* Vacuum switch tap changers are now available, which offer the less maintenance.
*Ambient temperature offshore is lower than onshore. This could bring significant savings not only on the cost of the
cooling equipment but also on the weight and size of the transformers.
* Waves hitting supporting structure continuously and gusts of wind generate
mechanical stress on the structure causing vibrations of various frequency and strength.
* The vibration of the transformer tank is at the fundamental frequency 100 or 120Hz
while operating. To limit this vibration “ Anti vibration isolator between the transformer
and platform” will be provided.
* Aramid ( Hybrid) insulation as per IEC/TS 60076-14 , the weight reduction is upto 25%
* Corrosion factors C5M
* Acceleration force limits for the equipment.
Temporary Bracing on a
Transformer for Sea Transportation
34
Notes for offshore Substation Equipment’s
-Power transformer
Transformers could be located indoors to protect from the environment. Radiators should be located outside .
- Minimum amount of space around the transformers to permit all aspects of planned and unplanned operation,
maintenance and repair works
- Sufficient space must be allowed for handling of any large sized test equipment
- Access should be considered to permit maintenance of the tap-changer and fitting of the extraction tools
- Room dimensions and positioning of the transformer to provide suitable
escape routes and doors
- Ventilation systems to dissipate the heat from the Transformer tank
- Enclosure room needs to be constructed with an oil retaining bund which
would prevent any escape of oil from entering the sea.
- Oil containment tank must be suitably dimensioned to accept as a
minimum the full volume of oil from the largest oil filled device plus the full
volume of water from an automatic fire suppression system plus spare
capacity (suggest 15%)
- Enclosure room should contain a fire detection/alarm system & Fire rated
wall around
- Operation of Buchholz relays may experience problem during large
displacements: generally it should be noted that electromechanical auxiliary
relays can be sensitive to vibration.
35
Notes for offshore Substation Equipment’s
-GIS
• Voltage transformer is equipped at the line side, the cable charge will be discharged through the voltage transformer.
The discharge current causes electro-magnetic force and temperature rise in the windings. The voltage transformer
must be designed so that it ensures mechanical force and thermal capacity of these discharges.
• Current transformer often located on both sides of the circuit breaker to eliminate the blind spot ,However in many
cases Current transformer located in one side to reduce the footprint of GIS
• The equipment will be subject to external forces due to the sea transport
and lifting. Equipment should tolerate such forces. Also to reduce such
forces during sea transport “ sea fastening” must be used.
• Switchgear design needs to allow for these and include any necessary
attachment points for fitting of external sea fastening straps.
36
Notes for offshore Substation Equipment’s
-GIS
37
Notes for offshore Substation Equipment’s
- Power Cable
* IAC ( Inter array Cable) in the range of 20kV or 72kV
* Export cable in the rage of 110 kV, 132 kV, 150 kV or 220 kV. Above 220kV GIS
Line shall be feasible
* Main differences between export and array cables are that the export cables have
a metallic sheath of e.g. lead for water tightness, while the array cables are of the
wet design.
* Both array and export three-phase cables have integrated fiber optic cables (FOC).
* Fiber optic cable for use in the overall control and communications scheme.
38
Notes for offshore Substation Equipment’s
-Power Cable
* IAC & Export cables are to be installed on platforms
with hang-offs for the armouring and J-tubes often
with bend restrictors. For three-core cables, the
hang-off devices include a chamber for trifurcating the
cores located immediate above the J-tube.
39
Fire and Explosion Protection
Fire Protection
Main objectives of the fire and explosion protection system are to
− minimize the risk of fire and explosion
− automatically monitor, detect and give alarm in case of smoke, fires or
explosions
− minimize the propagation and consequences of a fire and/or explosion
Active fire fighting systems are used to control or extinguish a fire (best
practice are listed in DNV-ST145) are foam, deluge, sprinkler, water mist
and inert gas system
40
Fire and Explosion Protection
Explosion protection
− HV switchgear explosion
41
Protection philosophy
Plant Protection
Detect faults and initiate disconnection of faulted equipment across three subsystems:-
The transmission connection to the on-shore substation which may comprise:
- Export cables
- EHV / MV transformers
- EHV shunt reactors
- EHV switchgear and busbars
42
Protection philosophy
The Grid Code or site specific connection conditions may specify the maximum fault clearance times for back-up
protection at the Connection Point which are less than one second.
Tripping Philosophy
If a fault occurs on some upstream (HV) equipment the tripping normally takes out all downstream (LV) plant to avoid
this being left in the closed position when the voltage is restored at the HV end.
EHV cables:
2 independent Biased differential protection and incase of FO communication fails Distance protection will be
enabled as a Main protection. ( In normal operating condition the relay uses fibers in an adjacent cable).
Back up protection will be available at onshore substation.
Inter tripping schemes
EHV switchgear
Low / High impedance busbar Protection (Remote back-up protection for busbars to ensure that, in the event of
busbar protection failure, a remote-end busbar fault will be cleared within the switchgear internal arcing fault withstand
time.)
43
Protection philosophy
Transformer
Biased differential protection, HV / LV REF , Back up protection
MV Switchgear
Busbar protection shall be of Low impedance will be preferred for the MV Switchgear or Reverse Interlocked
Busbar Protection (RIBBP) which is an economical answer making the best use of the logic capabilities of modern
numerical relays.
In general Bus Section CBs are fitted with two directional relays one looking in each direction.
WTG
The main protection for the WTG transformer is provided by overcurrent and earth fault using a definite time
characteristic. The purpose of WTG CB is purely to protect for step up transformer faults.
44
Site Tests and Commissioning
The cost of carrying out any work offshore is approximately ten times the cost of the same activity performed
onshore.
Commissioning sequence:
Document
45
Site Tests and Commissioning
Commissioning sequence:
46
Site Tests and Commissioning
Commissioning sequence:
-Visual inspection to assess any damage, or obvious changes, to equipment conditions and contents
-Any alarms on equipment or the SCADA system and confirmation of the HVAC system operation.
-Extent of the acceleration forces
-Auxiliary generator
-Removal of any transportation bracing or temporary supports,
-Testing of platform and internal lighting,
-Erection of lightning masts and antenna
-Fitting of any ventilation units removed during sea transportation.
-Commissioning the UHF and VHF radios,
-Insulation resistance checks for primary equipment
-Functional and operational checks on the switchgear locally and from the SCADA system
-Tap changer operation and transformer auxiliaries (i.e. cooling fans)
-Fiber optic communication/CCTV/LAN network/Comm between onshore to offshore
-Comm for the protection system/inter-trip between offshore to onshore
47
Site Tests and Commissioning
Commissioning sequence:
- Partial Discharge
48
Site Tests and Commissioning
Commissioning sequence:
Energization of Sub-Circuits
49
Site Tests and Commissioning
Commissioning sequence:
50
Further investigation are required in the below area,
Insulation co –ordination :
IEC standard does not identify switching impulse levels for equipment at voltages below 245 kV
Vibration:
IEC do not include any dedicated provisions for specification or type testing to demonstrate insensitivity to
prospective mechanical impacts to be seen by electrical apparatus on offshore platforms, such as wind gusts or wave
loads
Floating substation
51
Thank You & See You Again
Thank You
52