PART A : BOQ for Development of New Ash Pond

ASR
Actual
Sl No Item Unit L B H Qty Remarks Actual Qty. Rate Amount
Amount
1 Area Cleaning,Removing of vegetatations Sqm 450 280 126000 126000 5 630000 630000

2 Tree Cutting & Removing from Site Nos 100 0 0 0

A Major Construction Activities 0 0

Earth Work in Excavation in ordinary and hard soil


upto and including 7.0 mtr lift including pumping
Top Width - 6.0 Mtr
out any water accumulating inside the excavation
Base Width - 31 Mtr
2 and transporting the excavated soil upto any lead Cum 120699 103165.831 60 7241945.13 6189949.86
Height - 5.0 Mtr
inside ash disposal area and stacking selectively as Slope : 1: 2.5
directed by the Engineer,all complete as per
drawing, specification & direction of the Engineer.
Earth Work in Filling for embankment in layers not
exceeding 250 mm measured loose in proper
profile to various heights above existing ground
level to various heights of ash pond after stripping Dyke Embankment
0.5 X 37 X 980 X5
3 of 75 mm top soil as per spec,watering of each Cum 95039 & Access Road to 97961.568 40 3801546 3918462.732
0.5 X 4X100X14
layer in stipulated manner to achieve the 95 % of Decanting Pond
maximum dry density at optimum moisture
content & back filling in and around the
structure.,complete as per spec and direction of
980 15.5 0.5 7595 Dyke Bed 4843.964 0 0
Supplying ,laying,watering of coarse Sand in dyke
4 Cum
& bed as per drawing ,specification. 980 0.5 4 1960 Vertical Chimeney 2374.340 0 0
105196 0.075 7889.7 At Deposition Area 54 0 0
17444.7 7272.3036 650 11339055 4726997.34
Supply ,Laying & jointing of 500 micron HDPE Film
5 Sqm 105196 105196 At Deposition Area 0 0
at bed & Slopes
Slopes Sqm 980 13.47 13200.6 0 0
Anchoring Sqm 1960 0 0
Wastage & Lap Sqm 4651 0 0
125007.6 0 0 0
Fly ash brick Pitching for protection of HDPE in
6 Sqm 980 15 14700 18408.2 350 5145000 6442870
slopes & toe wall at upstream side.
7 WMM of 100 MM thickness Cum 1450 5.5 0.1 797.5 1500 1196250 0
8 Ash Evacuation & Filling Cum 100000 0.1 10000 4500 100 1000000 450000
0 0
0 0
B Decanting Arrangement 0 0
Earth Work in Excavation in ordinary and hard soil
upto and including 7.0 mtr lift including pumping
out any water accumulating inside the excavation
1 and transporting the excavated soil upto any lead Cum 95 50 4 19000 17916.165 60 1140000 1074969.9
inside ash disposal area and stacking selectively as
directed by the Engineer,all complete as per
drawing, specification & direction of the Engineer.
Well Cum 5 5 5 125 192 60 7500 11520
Hume Pipe Laying Cum 200 1.5 1.5 450 0 60 27000 0
19575 18108.165 0 0
Supply ,Laying & jointing of 500 micron HDPE Film
2 Sqm 95 50 4750 0 0
at bed
At Slopes Sqm 290 12 3480 0 0
Lap & Wastage Sqm 840 0 0
9070 0 0 0
Fly ash brick Pitching for protection of HDPE in
3 Sqm 3480 0 350 1218000 0
slopes & bed.
Supplying & laying in position design mix cement
concrete of M 25 Grade for reinforced concrete
work using crushed stone as coarse aggregate
4 including mixing,conveying,laying,compacting & Cum 0 0
curing etc for decanting well & encasing of
decanting pipe line etc complete as direction of
the Engineer.
Raft Cum 4.5 4.5 0.6 12.15 0 0
Wall Cum 9 0.6 5 27 0 0
Drain Bottom Cum 190 1 0.25 47.5 0 0
Top Cum 190 1 0.25 47.5 0 0
Wall Cum 380 0.25 1 95 0 0
229.15 167.556 4400 1008260 737246.4
Supplying & laying in position plain cement
concrete of 1:3:6 Grade using crushed stone as
coarse aggregate including
5 Cum 200 1.7 0.15 51 0 0
mixing,conveying,laying,compacting & curing
etc.or decanting well & encasing of decanting pipe
line complete as direction of the Engineer.
Cum 5.5 5.5 0.15 4.5375 0 0
55.5375 19.201 3500 194381.25 67203.5
Supplying & laying in position plum concrete for
decanting well M10 Grade with mixing of 150 mm
6 Cum 2 2 1.8 7.2 9.11 3500 25200 31885
stone at site etc. complete as direction of the
Engineer.
Supplying,Cutting,bending & binding with 20
gauge annealed soft iron wire and placing in
7 position HYSD (Fe 415) reinforcement of all Kg 35000 35000 7541 75 2625000 565575
diameters to RCC members as per direction of the
Engineer.
Supplying,installing dismantling & removing ply
wood form works including necessary rendering of
8 concrete surfaces after exposure as per Sqm 2100 2100 437.403 450 945000 196831.35
drawings,specifications and direction of the
Engineer.
Supplying,laying and jointing RCC hume pipes 500
mm dia of class NP4 as per IS 458 (1st class
bedding) with collars and all necessary fixtures
9 Rm 200 200 130 3000 600000 390000
including grouting with joints with 1:2 cement
sand mortar, curing etc. all complete as per
drawing , spec & direction of the Engineer.
Supplying & laying of gravel of 40 MM down size
10 for filter media in decanting well with proper Cum 14 6 1.5 126 0 1500 189000 0
stacking as per drawing.
Shifting & laying Carbon Steel Piping of 200 mm
11 dia for dishcarge of decanted water / garlanding mtr 600 600 800 480000 0
over dyke for ash slurry disposal.
0 0
C Drainage Arrangemnt 0 0
1 Earth work in excavation Cum 980 1.3 0.6 764.4 500 60 45864 30000
Earth work in filling including cutting from borrow
2 pit, transportation upto 1.0 km etc. complete as Cum 980 3 0.5 1470 0 40 58800 0
directed by EIC
3 Dressing of area sqm 980 3 2940 0 0 0
4 Providing & laying sand Cum 568 Well & Hume pipe 40.279 650 369200 26181.35
5 PCC 1:3:6 Cum 980 1.4 0.1 137.2 127.67 3500 480200 446845
6 RCC in M-25 grade in sub structure Cum 10 0 4500 45000 0
Supplying,Cutting,bending & binding with 20
gauge annealed soft iron wire and placing in
7 position HYSD (Fe 415) reinforcement of all Kg 700 0 75 52500 0
diameters to RCC members as per direction of the
Engineer.
8 Shuttering & deshuttering in Sub structure sqm 90 0 450 40500 0
230 mm thick RR masonry with 1:6 Cement
9 Cum 1960 0.3 0.7 411.6 250 2000 823200 500000
Mortar
10 230 mm thick RR Packing Cum 980 1.9 0.6 1117.2 889.296 2000 2234400 1778592
Providing , laying and maintaining upto required
11 growth grass turfing etc. complete as directed by Sqm 980 15 14700 10542.2885 40 588000 421691.54
EIC
E MCC Room & Pump House 0 0

Earth Work in Excavation in ordinary and hard soil


upto and including 7.0 mtr lift including pumping
out any water accumulating inside the excavation
1 and transporting the excavated soil upto any lead Cum 20 10 3 600 15 60 36000 900
inside ash disposal area and stacking selectively as
directed by the Engineer,all complete as per
drawing, specification & direction of the Engineer.
Earth work in filling including cutting from borrow
2 pit, transportation upto 1.0 km etc. complete as Cum 300 0 40 12000 0
directed by EIC
Supplying and laying in position of second nd class
3 brick with 1:6 Cement Mortar for raking joints , Cum 60 0.23 3.5 48.3 73.856 4000 193200 295423.5
curing etc.
4 Providing & laying sand Cum 20 10 0.3 60 0 650 39000 0
Supplying & laying in position plain cement
concrete of 1:3:6 Grade using crushed stone as
5 coarse aggregate including Cum 20 10 0.1 20 7.543 3500 70000 26400.5
mixing,conveying,laying,compacting & curing etc.
complete as direction of the Engineer.
Supplying & laying in position design mix cement
concrete of M 25 Grade for reinforced concrete
6 work using crushed stone as coarse aggregate Cum 80 60.751 4500 360000 273379.5
including mixing,conveying,laying,compacting &
curing etc. complete as direction of the Engineer.
Supplying,Cutting,bending & binding with 20
gauge annealed soft iron wire and placing in
7 position HYSD (Fe 415) reinforcement of all Kg 16500 6594 75 1237500 494550
diameters to RCC members as per direction of the
Engineer.
8 Shuttering & deshuttering in Sub structure Sqm 70 10 700 278.776 450 315000 125449.2
52 mm thick cement concrete flooring with
concrete hardener topping, under layer 40 mm
thick cement concrete 1:2:4 (1 cement : 2 coarse
9 sand : 4 graded stone aggregate 20 mm nominal Sqm 20 10 200 41.54 400 80000 16616
size) and top layer 12mm thick cement hardener
consisting of mix 1:2 (1 cement hardener mix : 2
graded stone aggregate 6 mm nominal size) by
10 Plastering of 12 mm thickness Sqm 51 10 510 412.827 300 153000 123848.1
11 Painting ( Inside & Outside ) Sqm 51 10 510 166.7 180 91800 30006
Electrical accessories like cables, transformer
12 shifting & placing,Monorail arrangment,fencing LS 1 1 0 0 0
etc.
Grand Total 46138301.38 30023394