Plate Cutting Plate Rolling Blasting & Painting

Activity ID Activity Name Start Finish Qty Act Qty Qty Act Qty Qty Act Qty Qty Act Qty %
Pre-Fabrication 20%
A18090 Tank No. 8 (9m D) POME B 9-Jan-23 45 45 16 16 43 32 104 93 89.42%
A18080 Tank No. 7 (9m D) POME A 9-Jan-23 45 45 16 16 43 32 104 93 89.42%
A18040 Tank No.3 (20.2m D) ULG 95B 2-Feb-23 129 89 48 30 127 30 304 149 49.01%
A18020 Tank No.1 (20.2m D) ULG97 15-Feb-23 129 89 48 0 127 0 304 89 29.28%
A18050 Tank No.4 (18.8m D) ADO A 10-Feb-23 129 129 48 6 127 46 304 181 59.54%
A18060 Tank No.5 (18.8m D) ADO B 10-Feb-23 129 129 48 6 127 46 304 181 59.54%
A18070 Tank No. 6 (15m D) FW 13-Feb-23 97 73 42 42 99 42 238 157 65.97%
A18030 Tank No.2 (20.2m D) ULG 95A 13-Feb-23 129 129 48 14 127 26 304 169 55.59%
TOTAL WTG (20%) 832 728 314 130 820 254 1966 1112 11.31%

Erection & Installation Welding NDT


Activity ID Activity Name Start Finish Qty Act Qty Qty Act Qty Qty Act Qty Qty Act Qty %
Installation 70%
A18090 Tank No. 8 (9m D) POME B 9-Jan-23 68 68 78 78 73 73 219 219 99.77%
A18080 Tank No. 7 (9m D) POME A 9-Jan-23 68 68 78 78 73 73 219 219 99.77%
A18040 Tank No.3 (20.2m D) ULG 95B 2-Feb-23 182 72 223 92 176 99 581 263 45.27%
A18020 Tank No.1 (20.2m D) ULG97 15-Feb-23 182 1 223 1 176 4 581 6 1.03%
A18050 Tank No.4 (18.8m D) ADO A 10-Feb-23 181 97 222 97 166 64 569 258 45.34%
A18060 Tank No.5 (18.8m D) ADO B 10-Feb-23 181 47 222 50 166 44 569 141 24.78%
A18070 Tank No. 6 (15m D) FW 13-Feb-23 131 61 166 69 109 60 406 190 46.80%
A18030 Tank No.2 (20.2m D) ULG 95A 13-Feb-23 182 40 223 40 176 10 581 90 15.49%
TOTAL WTG (70%) 1175 453 1435 505 1115 427 3725 1385 26.03%
Date: 09-01-2024 Tank Fabrication: Weekly Plate Cutting Work Progress KJS YARD Manpower : 3 Fitter
(0800-1700)

Tank Plate Process Plate Thickness Plate Complete Plate Qty: Work Progress Work Progress Today Activities
(%) (%)
Physical inspection on plates
Check on materials spec, Heat no, plate number, plate size and quantity 596 596 100.0% 100.0% Completed MRIR
Materials Inspection
Mark Plate for traceability with Heat Tracking Code
Segregate plate to each tank Completed

Others Activities
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 03 Aug 2022 A18020
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 27 27 100.0% 100.0% Completed 01/08/2022 A18020
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Welding Completed A18020
Shell plate marking & cutting (course 1) 16mm 6 6 100.0% Completed 17 Aug 2022 A18020
Shell plate marking & cutting (course 2) 14mm 6 6 100.0% Completed 18 Aug 2022 A18020
Shell plate marking & cutting (course 3) 13mm 6 6 100.0% Completed 19 Aug 2022 A18020
ULG 97
Shell plate marking & cutting (course 4) 11mm 6 6 100.0% Completed 23 Aug 2022 A18020
Shell 100.0%
Shell plate marking & cutting (course 5) 9mm 6 6 100.0% Completed 25 Aug 2022 A18020
Shell plate marking & cutting (course 6) 8mm 6 6 100.0% Completed 27 Aug 2022 A18020
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 30 Aug 2022 A18020
Shell plate marking & cutting (course 8) 8mm 6 6 100.0% Completed 07 Sep 2022 A18020
Roof Roof Plate 6mm 1 41 2.4% 2.4% Roof Center Ring Fabrication Ongoing A18020
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 05 Aug 2022 A18030
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 27 27 100.0% 100.0% Completed 03 Aug 2022 A18030
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Welding Completed A18030
Shell plate marking & cutting (course 1) 16mm 6 6 100.0% Completed 07 Dec 2022 A18030
Shell plate marking & cutting (course 2) 14mm 6 6 100.0% Completed 09 Dec 2022 A18030
Shell plate marking & cutting (course 3) 13mm 6 6 100.0% Completed 29 Nov 2022 A18030
ULG 95-A
Shell plate marking & cutting (course 4) 11mm 6 6 100.0% Completed 15 Nov 2022 A18030
Shell 100.0%
Shell plate marking & cutting (course 5) 9mm 6 6 100.0% Completed 16 Dec 2022 A18030
Shell plate marking & cutting (course 6) 8mm 6 6 100.0% Completed 01 Dec 2022 A18030
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 03 Dec 2022 A18030
Shell plate marking & cutting (course 8) 8mm 6 6 100.0% Completed 16 Dec 2022 A18030
Roof Roof Plate 6mm 41 41 100.0% 100.0% Roof Center Ring Fabrication n Welding Ongoing A18030
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 08 Aug 2022 A18040
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 27 27 100.0% 100.0% Completed 04 Aug 2022 A18040
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Welding Completed A18040
Shell plate marking & cutting (course 1) 16mm 6 6 100.0% Completed 17 Dec 2022 A18040
Shell plate marking & cutting (course 2) 14mm 6 6 100.0% Completed 14 Dec 2022 A18040
Shell plate marking & cutting (course 3) 13mm 6 6 100.0% Completed 15 Dec 2022 A18040
ULG 95-B
Shell plate marking & cutting (course 4) 11mm 6 6 100.0% Completed 13 Dec 2022 A18040
Shell 100.0%
Shell plate marking & cutting (course 5) 9mm 6 6 100.0% Completed 16 Dec 2022 A18040
Shell plate marking & cutting (course 6) 8mm 6 6 100.0% Completed 10 Dec 2022 A18040
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 20 Dec 2022 A18040
Shell plate marking & cutting (course 8) 8mm 6 6 100.0% Completed 22 Dec 2022 A18040
Roof Roof Plate 6mm 1 41 2.4% 2.4% Roof Center Ring Fabrication Ongoing A18040
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 11 11 100.0% Completed 26 Jul 2022 A18080
100.0%
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Completed A18080
Shell plate marking & cutting (course 1) 8mm 4 4 100.0% Completed 03 Sep 2022 A18080
POME-A Shell plate marking & cutting (course 2) 8mm 4 4 100.0% Completed 06 Sep 2022 A18080
Shell 100.0%
Shell plate marking & cutting (course 3) 8mm 4 4 100.0% Completed 06 Sep 2022 A18080
Shell plate marking & cutting (course 4) 8mm 4 4 100.0% Completed 10 Sep 2022 A18080
Roof Roof Plate 6mm 17 17 100.0% 100.0% Completed 22 May 2023 A18080
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 11 11 100.0% Completed 28 Jul 2022 A18090
100.0%
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Completed A18090
Shell plate marking & cutting (course 1) 8mm 4 4 100.0% Completed 09 Sep 2022 A18090
POME-B Shell plate marking & cutting (course 2) 8mm 4 4 100.0% Completed 10 Sep 2022 A18090
Shell 100.0%
Shell plate marking & cutting (course 3) 8mm 4 4 100.0% Completed 11 Sep 2022 A18090
Shell plate marking & cutting (course 4) 8mm 4 4 100.0% Completed 15 Sep 2022 A18090
Roof Roof Plate 6mm 17 17 100.0% 100.0% Completed 25 May 2023 A18090
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 11 Aug 2022 A18050
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 27 27 100.0% 100.0% Completed 11 Aug 2022 A18050
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Completed 26 Oct 2022 A18050
Shell plate marking & cutting (course 1) 16mm 6 6 100.0% Completed 01 Nov 2022 A18050
Shell plate marking & cutting (course 2) 14mm 6 6 100.0% Completed 29 Oct 2022 A18050
Shell plate marking & cutting (course 3) 13mm 6 6 100.0% Completed 29 Oct 2022 A18050
ADO-A
Shell plate marking & cutting (course 4) 11mm 6 6 100.0% Completed 02 Nov 2022 A18050
Shell 100.0%
Shell plate marking & cutting (course 5) 9mm 6 6 100.0% Completed 28 Oct 2022 A18050
Shell plate marking & cutting (course 6) 9mm 6 6 100.0% Completed 22 Oct 2022 A18050
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 27 Oct 2022 A18050
Shell plate marking & cutting (course 8) 8mm 6 6 100.0% Completed 22 Dec 2022 A18050
Roof Roof Plate 6mm 41 41 100.0% 100.0% Cutting Completed A18050
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 13 Aug 2022 A18060
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 27 27 100.0% 100.0% Completed 02 Sep 2022 A18060
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Completed 26 Oct 2022 A18060
Shell plate marking & cutting (course 1) 16mm 6 6 100.0% Completed 29 Nov 2022 A18060
Shell plate marking & cutting (course 2) 14mm 6 6 100.0% Completed 29 Nov 2022 A18060
Shell plate marking & cutting (course 3) 13mm 6 6 100.0% Completed 15 Nov 2022 A18060
ADO-B
Shell plate marking & cutting (course 4) 11mm 6 6 100.0% Completed 07 Nov 2022 A18060
Shell 100.0%
Shell plate marking & cutting (course 5) 9mm 6 6 100.0% Completed 04 Dec 2022 A18060
Shell plate marking & cutting (course 6) 9mm 6 6 100.0% Completed 16 Jan 2023 A18060
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 22 Dec 2022 A18060
Shell plate marking & cutting (course 8) 8mm 6 6 100.0% Completed 22 Nov 2022 A18060
Roof Roof Plate 6mm 41 41 100.0% 100.0% Cutting Completed A18060
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 09 Sep 2022 A18070
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 17 17 100.0% 100.0% Completed 18 Sep 2022 A18070
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Completed 10 Mar 2023 A18070
Shell plate marking & cutting (course 1) 12mm 6 6 100.0% Completed 12 Jan 2023 A18070
Shell plate marking & cutting (course 2) 11mm 6 6 100.0% Completed 12 Jan 2023 A18070
Fire Water Shell plate marking & cutting (course 3) 10mm 6 6 100.0% Completed 12 Jan 2023 A18070
Shell Shell plate marking & cutting (course 4) 9mm 6 6 100.0% 100.0% Completed 14 Jan 2023 A18070
Shell plate marking & cutting (course 5) 8mm 6 6 100.0% Completed 13 Jan 2023 A18070
Shell plate marking & cutting (course 6) 8mm 6 6 100.0% Completed 08 Jan 2023 A18070
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 30 Dec 2022 A18070
Roof Roof Plate 6mm 1 25 4.0% 4.0% Roof Center Ring Fabrication n Welding Ongoing A18070
Total 728 832 68.9%
Date: 09-01-2024 (0800-
1700) Tank Fabrication: Plate Rolling Work Progress Manpower : 3 Rolling Crew

Plate Plate Work Progress


Tank Plate Course Process Thickness Complete Plate Qty: (%) Today Activities

Others Activities
Course 1 Plate Rolling 16mm 6 0.0% A18020
Course 2 Plate Rolling 14mm 6 0.0% A18020
Course 3 Plate Rolling 13mm 6 0.0% A18020
Course 4 Plate Rolling 11mm 6 0.0% A18020
Shell
ULG 97 Course 5 Plate Rolling 9mm 6 0.0% A18020
Course 6 Plate Rolling 8mm 6 0.0% A18020
Course 7 Plate Rolling 8mm 6 0.0% A18020
Course 8 Plate Rolling 8mm 6 0.0% A18020
Roof Top Ring Angle 150x150x6m 0 11 0.0%
Course 1 Plate Rolling 16mm 6 6 100.0% Completed 01/03/2023 A18030
Course 2 Plate Rolling 14mm 2 6 33.3% Completed 01/03/2023 A18030
Course 3 Plate Rolling 13mm 6 0.0% A18030
Course 4 Plate Rolling 11mm 6 0.0% A18030
Shell
ULG 95-A Course 5 Plate Rolling 9mm 6 0.0% A18030
Course 6 Plate Rolling 8mm 6 0.0% A18030
Course 7 Plate Rolling 8mm 6 0.0% A18030
Course 8 Plate Rolling 8mm 6 6 100.0% Completed A18030
Roof Top Ring Angle 150x150x6m 11 11 100.0% Completed
Course 1 Plate Rolling 16mm 6 6 100.0% Completed 20/02/2023 A18040
Course 2 Plate Rolling 14mm 6 6 100.0% Completed 01/03/2023 A18040
Course 3 Plate Rolling 13mm 6 6 100.0% Completed 18/07/2023 A18040
Course 4 Plate Rolling 11mm 6 6 100.0% Completed 21/08/2023 A18040
Shell
ULG 95-B Course 5 Plate Rolling 9mm 6 6 100.0% Completed 25/09/2023 A18040
Course 6 Plate Rolling 8mm 6 0.0% A18040
Course 7 Plate Rolling 8mm 6 0.0% A18040
Course 8 Plate Rolling 8mm 6 0.0% A18040
Roof Top Ring Angle 150x150x6m 0 11 0.0%
Course 1 Plate Rolling 8mm 4 4 100.0% Completed A18080
Course 2 Plate Rolling 8mm 4 4 100.0% Completed A18080
POME-A Shell
Course 3 Plate Rolling 8mm 4 4 100.0% Completed A18080
Course 4 Plate Rolling 8mm 4 4 100.0% Completed A18080
Course 1 Plate Rolling 8mm 4 4 100.0% Completed A18090
Course 2 Plate Rolling 8mm 4 4 100.0% Completed A18090
POME-B Shell
Course 3 Plate Rolling 8mm 4 4 100.0% Completed A18090
Course 4 Plate Rolling 8mm 4 4 100.0% Completed A18090
Course 1 Plate Rolling 16mm 6 0.0% A18050
Course 2 Plate Rolling 14mm 6 0.0% A18050
Course 3 Plate Rolling 13mm 6 0.0% A18050
Course 4 Plate Rolling 11mm 6 0.0% A18050
Shell
ADO-A Course 5 Plate Rolling 9mm 6 0.0% A18050
Course 6 Plate Rolling 9mm 6 0.0% A18050
Course 7 Plate Rolling 8mm 6 0.0% A18050
Course 8 Plate Rolling 8mm 6 6 100.0% Completed A18050
Roof Top Ring Angle 150x150x6m 10 10 100.0% Completed
Course 1 Plate Rolling 16mm 6 0.0% A18060
Course 2 Plate Rolling 14mm 6 0.0% A18060
Course 3 Plate Rolling 13mm 6 0.0% A18060
Course 4 Plate Rolling 11mm 6 0.0% A18060
Shell
ADO-B Course 5 Plate Rolling 9mm 6 0.0% A18060
Course 6 Plate Rolling 9mm 6 0.0% A18060
Course 7 Plate Rolling 8mm 6 0.0% A18060
Course 8 Plate Rolling 8mm 6 6 100.0% Completed A18060
Roof Top Ring Angle 150x150x6m 10 10 100.0% Completed
Course 1 Plate Rolling 12mm 6 6 100.0% Completed 19/08/2023 A18070
Course 2 Plate Rolling 11mm 6 6 100.0% Completed 02/09/2023 A18070
Course 3 Plate Rolling 10mm 6 6 100.0% Completed 03/09/2023 A18070
Shell Course 4 Plate Rolling 9mm 6 6 100.0% Completed 23/09/2023 A18070
Fire Water
Course 5 Plate Rolling 8mm 6 6 100.0% Completed 05/12/2023 A18070
Course 6 Plate Rolling 8mm 6 6 100.0% Completed 09/12/2023 A18070
Course 7 Plate Rolling 8mm 6 6 100.0% Completed 09/12/2023 A18070
Roof Top Ring Angle 150x150x6m 2 8 25.0% Ongoing
Total 161 367 43.9%
Date: 09-01-2024 KJS YARD Manpower : 4 pax Blasting &
Tank Fabrication: Plate Blasting & Painting Work Progress
(0800-1700) Painting Crew (13th, 14th, 19th Raining)

Work
Plate Plate
Tank Plate Course Process Plate Qty: Progress Today Activities
Thickness Complete
(%)

Others Activities

Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18020
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 27 0.0% A18020
Course 1 Blasting and 1st Coat Primer 16mm 0 6 0.0% A18020
Course 2 Blasting and 1st Coat Primer 14mm 0 6 0.0% A18020
Course 3 Blasting and 1st Coat Primer 13mm 0 6 0.0% A18020
Course 4 Blasting and 1st Coat Primer 11mm 0 6 0.0% A18020
ULG 97 Shell
Course 5 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18020
Course 6 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18020
Course 7 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18020
Course 8 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18020
Top Ring Blasting and 1st Coat Primer 0 11 0.0%
Roof
Roof Plate Blasting and 1st Coat Primer 6mm 0 40 0.0% A18020
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18030
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 27 0.0% A18030
Course 1 Blasting and 1st Coat Primer 16mm 0 6 0.0% A18030
Course 2 Blasting and 1st Coat Primer 14mm 0 6 0.0% A18030
Course 3 Blasting and 1st Coat Primer 13mm 0 6 0.0% A18030
Course 4 Blasting and 1st Coat Primer 11mm 0 6 0.0% A18030
ULG 95-A Shell
Course 5 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18030
Course 6 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18030
Course 7 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18030
Course 8 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed A18030
Top Ring Blasting and 1st Coat Primer 11 11 100.0% Completed 19/12/2023
Roof
Roof Plate Blasting and 1st Coat Primer 6mm 20 40 50.0% Ongoing A18030
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18040
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 27 0.0% A18040
Course 1 Blasting and 1st Coat Primer 16mm 6 6 100.0% Completed 04 Mar 2023 A18040
Course 2 Blasting and 1st Coat Primer 14mm 6 6 100.0% Completed A18040
Course 3 Blasting and 1st Coat Primer 13mm 6 6 100.0% Completed 21 Jul 2023 A18040
Course 4 Blasting and 1st Coat Primer 11mm 6 6 100.0% Completed 28 Aug 2023 A18040
ULG 95-B Shell
Course 5 Blasting and 1st Coat Primer 9mm 6 6 100.0% Completed 12 Oct 2023 A18040
Course 6 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18040
Course 7 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18040
Course 8 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18040
Top Ring Blasting and 1st Coat Primer 0 11 0.0%
Roof
Roof Plate Blasting and 1st Coat Primer 6mm 0 40 0.0% A18040
Bottom Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 11 0.0% A18080
Course 1 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 07 Jan 2023 A18080
Course 2 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 09 Jan 2023 A18080
POME-A Shell
Course 3 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 11 Jan 2023 A18080
Course 4 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 13 Jan 2023 A18080
Roof Plate Blasting and 1st Coat Primer 6mm 16 16 100.0% Completed 23/09/2023 A18080
Bottom Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 11 0.0% A18090
Course 1 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 08 Jan 2023 A18090
Course 2 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 10 Jan 2023 A18090
POME-B Shell
Course 3 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 12 Jan 2023 A18090
Course 4 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 14Jan 2023 A18090
Roof Plate Blasting and 1st Coat Primer 6mm 16 16 100.0% Completed 23/09/2023 A18090
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18050
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 27 0.0% A18050
Course 1 Blasting and 1st Coat Primer 16mm 0 6 0.0% A18050
Course 2 Blasting and 1st Coat Primer 14mm 0 6 0.0% A18050
Course 3 Blasting and 1st Coat Primer 13mm 0 6 0.0% A18050
Course 4 Blasting and 1st Coat Primer 11mm 0 6 0.0% A18050
ADO-A Shell
Course 5 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18050
Course 6 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18050
Course 7 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18050
Course 8 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed 08/11/2023 A18050
Top Ring Blasting and 1st Coat Primer 10 10 100.0% Completed 18/12/2023
Roof
Roof Plate Blasting and 1st Coat Primer 6mm 40 40 100.0% Completed 21/11/2023 A18050
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18060
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 27 0.0% A18060
Course 1 Blasting and 1st Coat Primer 16mm 0 6 0.0% A18060
Course 2 Blasting and 1st Coat Primer 14mm 0 6 0.0% A18060
Course 3 Blasting and 1st Coat Primer 13mm 0 6 0.0% A18060
Course 4 Blasting and 1st Coat Primer 11mm 0 6 0.0% A18060
ADO-B Shell
Course 5 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18060
Course 6 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18060
Course 7 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18060
Course 8 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed 10/11/2023 A18060
Top Ring Blasting and 1st Coat Primer 10 10 100.0% Completed 8/12/2023
Roof
Roof Plate Blasting and 1st Coat Primer 6mm 40 40 100.0% Completed 12/12/2023 A18060
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18070
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 21 0.0% A18070
Course 1 Blasting and 1st Coat Primer 12mm 6 6 100.0% Completed 21 Aug 2023 A18070
Course 2 Blasting and 1st Coat Primer 11mm 6 6 100.0% Completed 12 Sep 2023 A18070
Course 3 Blasting and 1st Coat Primer 10mm 6 6 100.0% Completed 13 Sep 2023 A18070
FW Shell Course 4 Blasting and 1st Coat Primer 9mm 6 6 100.0% Completed 17 Oct 2023 A18070
Course 5 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed A18070
Course 6 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed A18070
Course 7 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed A18070
FW

Top Ring Blasting and 1st Coat Primer 8


Roof
Roof Plate Blasting and 1st Coat Primer 6mm 0 24 0.0% A18070

Total 285 881 32.3%


Date: 09-01-2024
(0800-1700) Tank Erection: Fit-up Work Progress SITE Manpower : 10 pax Tank Crew (13th, 14th, 19th Raining)

Plate Plate Work Work


Tank Plate Process Thickness Complete Plate Qty: Progress Progress Today Activities
(%) (%)

Others Activities

Annular Annular Plate Cutting 12mm 0 12 0.0% 0.0% A18020


Bottom Bottom Plate 10mm 0 27 0.0% 0.0% A18020
Sump Sump Pit Fit-up 10mm 1 1 100.0% 100.0% Fit-up Completed 20 Nov 2022 A18020
Fillet Joint Shell Plate to Bottom Plate 16mm 0 1 0.0% 0.0%
63.46m
Shell plate Course 1 16mm 0 6 0.0% A18020
Shell Course 1 Manholes 16mm 0 1 0.0% A18020
Shell plate Course 2 14mm 0 6 0.0% A18020
Shell plate Course 3 13mm 0 6 0.0% A18020
Shell
ULG 97 Shell plate Course 4 11mm 0 6 0.0% 0.0% A18020
Shell plate Course 5 9mm 0 6 0.0% A18020
Shell plate Course 6 8mm 0 6 0.0% A18020
Shell plate Course 7 8mm 0 6 0.0% A18020
Shell plate Course 8 8mm 0 6 0.0% A18020
Top Ring Angle 150×150×15 63.485m 0 11 0.0% 0.0% A18020
Rafter UPN220 x 80 x 12.5mm thickness 8.72m 0 41 0.0% A18020
Roof 0.0%
Roof Plate 6mm 0 40 0.0% A18020
1 182
Annular Annular Plate Cutting 12mm 12 12 100.0% 100.0% Annular Laying Completed, Fit- up Completed, Inspection Completed A18030
Bottom Bottom Plate 10mm 27 27 100.0% 100.0% Laying Completed, Cutting & Fit-up All Completed A18030
Sump Sump Pit Fit-up 10mm 1 1 100.0% 100.0% Fit-up Completed 20 Nov 2022, Sump Pit Plate Installation Completed A18030
Fillet Joint Shell Plate to Bottom Plate 16mm 0 1 0.0% 0.0%
63.46m
Shell plate Course 1 16mm 0 6 0.0% A18030
Shell Course 1 Manholes 16mm 0 1 0.0% A18030
Shell plate Course 2 14mm 0 6 0.0% A18030
Shell plate Course 3 13mm 0 6 0.0% A18030
Shell
ULG 95-A Shell plate Course 4 11mm 0 6 0.0% 0.0% A18030
Shell plate Course 5 9mm 0 6 0.0% A18030
Shell plate Course 6 8mm 0 6 0.0% A18030
Shell plate Course 7 8mm 0 6 0.0% A18030
Shell plate Course 8 8mm 0 6 0.0% Shell Plate location marking completed, Setup shell plate bottom support Completed A18030
Top Ring Angle 150×150×15 63.485m 0 11 0.0% 0.0% A18030
Rafter UPN220 x 80 x 12.5mm thickness 8.72m 0 41 0.0% A18030
Roof 0.0%
Roof Plate 6mm 0 40 0.0% A18030
40 182
Annular Annular Plate Cutting 12mm 12 12 100.0% 100.0% Annular Laying Completed, Fit- up Completed, Inspection Completed A18040
Bottom Bottom Plate 10mm 27 27 100.0% 100.0% Laying Completed, Cutting & Fit-up All Completed A18040
Sump Sump Pit Fit-up 10mm 1 1 100.0% 100.0% Fit-up Completed 20 Nov 2022, Sump Pit Plate Installation Completed A18040
Fillet Joint Shell Plate to Bottom Plate 16mm 1 1 100.0% 100.0% Fit up Completed, QAQC Inspection Completed
63.46m
Shell plate Course 1 16mm 6 6 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18040
Shell Course 1 Manholes 16mm 1 1 100.0% Opening Completed A18040
Shell plate Course 2 14mm 6 6 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18040
Shell plate Course 3 13mm 6 6 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18040
Shell
ULG 95-B Shell plate Course 4 11mm 6 6 100.0% 63.3% Erection Completed , Gouging, Grinding and fit up completed for welding A18040
Shell plate Course 5 9mm 6 6 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18040
Shell plate Course 6 8mm 0 6 0.0% A18040
Shell plate Course 7 8mm 0 6 0.0% A18040
Shell plate Course 8 8mm 0 6 0.0% A18040
Top Ring Angle 150×150×15 63.485m 0 11 0.0% 0.0% A18040
Rafter UPN220 x 80 x 12.5mm thickness 8.72m 0 41 0.0% A18040
Roof 0.0%
Roof Plate 6mm 0 40 0.0% A18040
72 182
Bottom Bottom Plate 10mm 11 11 100.0% 100.0% Shell Course 1 to Bottom Plate Fit up Completed A18080
Sump Sump Pit Fit-up 10mm 1 1 100.0% 100.0% Fit-up Completed 20 Nov 2022, Sump Pit Plate Installation Completed A18080
Fillet Joint Shell Plate to Bottom Plate 8mm 1 1 100.0% Fit up Completed, Inspection Completed, Diesel Check Completed
22.275m
Shell plate Course 1 8mm 4 4 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18080
Shell Course 1 Manholes 8mm 1 1 100.0% Manholes Opening Completed A18080
Shell Nozzles 8mm 0.5 1 50.0% 97.4% Mark-out All Nozzles Position, QAQC Inspection Completed A18080
POME-A Shell plate Course 2 8mm 4 4 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18080
Shell plate Course 3 8mm 4 4 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18080
Shell plate Course 4 8mm 4 4 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18080
Top Ring Top Annular Plate 28.74m 4 4 100.0% 100.0% Install & Fit up Completed A18040
Rafter 3.21m 17 17 100.0% Center Ring & Rafter Fit-up Completed (On Ground & Top), Grinding & Power Brush for MPI Completed A18080
Roof 100.0%
Roof Plate 6mm 16 16 100.0% Roof Plate Fit up Completed (On ground & On Top), Grinding & Power Brush for MPI A18080
68 68
Bottom Bottom Plate 10mm 11 11 100.0% 100.0% Shell Course 1 to Bottom Plate Fit up Completed A18090
Sump Sump Pit Fit-up 10mm 1 1 100.0% 100.0% Fit-up Completed 20 Nov 2022, Sump Pit Plate Installation Completed A18090
Fillet Joint Shell Plate to Bottom Plate 8mm 1 1 100.0% Fit up Completed, Inspection Completed
22.275m
Shell plate Course 1 8mm 4 4 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18090
Shell Course 1 Manholes 8mm 1 1 100.0% Manholes Opening Completed A18090
Shell Nozzles 8mm 0.5 1 50.0% 97.4% Mark-out All Nozzles Position, QAQC Inspection Completed A18090
POME-B Shell plate Course 2 8mm 4 4 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18090
Shell plate Course 3 8mm 4 4 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18090
Shell plate Course 4 8mm 4 4 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18090
Top Ring Top Annular Plate 28.74m 4 4 100.0% 100.0% Install & Fit up Completed A18040
Rafter 3.21m 17 17 100.0% Center Ring & Rafter Fit-up Completed (On Ground & Top), Grinding & Power Brush for MPI Completed A18090
Roof 100.0%
Roof Plate 6mm 16 16 100.0% Roof Plate Fit up Completed (On ground & On Top), Grinding & Power Brush for MPI A18090
68 68
Annular Annular Plate Cutting 12mm 12 12 100.0% 100.0% Annular Laying Completed, Fit- up Completed, Inspection Completed A18050
Bottom Bottom Plate 10mm 27 27 100.0% 100.0% Bottom Plate Laying, Cutting n Fit-up Completed, Short seam fit-up Completed, Long Seam fit-up Completed A18050
Sump Sump Pit Fit-up 10mm 1 1 100.0% 100.0% Fit-up Completed 20 Nov 2022 A18050
Fillet Joint Shell Plate to Bottom Plate 16mm 0 1 0.0% 0.0%
59.06m
Shell plate Course 1 16mm 0 6 0.0% A18050
Shell Course 1 Manholes 16mm 0 1 0.0% A18050
Shell plate Course 2 14mm 0 6 0.0% A18050
Shell plate Course 3 13mm 0 6 0.0% A18050
Shell
Shell plate Course 4 11mm 0 6 0.0% 12.2% A18050
ADO-A Shell plate Course 5 9mm 0 6 0.0% A18050
Shell plate Course 6 9mm 0 6 0.0% A18050
Shell plate Course 7 8mm 0 6 0.0% A18050
Shell plate Course 8 8mm 6 6 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18050
Top Ring Angle 150×150×15 59.087m 10 10 100.0% 100.0% Install Completed, Fit up Ongoing 70% A18050
Center ring Fit up Completed, Rafter Install Completed, , Connection Plate Fit up Completed, Shell Support Chair for
Rafter UPN220 x 80 x 12.5mm thickness 8.1m 41 41 100.0% Rafter Fit up Completed. Girders Angle fit up ongoing 25/160nos A18050
Roof 100.0%
Roof Plate 6mm 0 40 0.0% Setting up Chain Hoist Lifting A18050
97 181
Annular Annular Plate Cutting 12mm 12 12 100.0% 100.0% Annular Laying Completed, Fit- up Completed, Inspection Completed A18060
Bottom Bottom Plate 10mm 27 27 100.0% 100.0% Bottom Plate Laying, Cutting n Fit-up Completed, Short seam fit-up Completed, Long Seam fit-up Completed A18060
Sump Sump Pit Fit-up 10mm 1 1 100.0% 100.0% Fit-up Completed 20 Nov 2022 A18060
Fillet Joint Shell Plate to Bottom Plate 16mm 0 1 0.0% 0.0%
59.06m
Shell plate Course 1 16mm 0 6 0.0% A18060
Shell Course 1 Manholes 16mm 0 1 0.0% A18060
Shell plate Course 2 14mm 0 6 0.0% A18060
Shell plate Course 3 13mm 0 6 0.0% A18060
Shell
Shell plate Course 4 11mm 0 6 0.0% 12.2% A18060
ADO-B
Shell plate Course 5 9mm 0 6 0.0% A18060
Shell plate Course 6 9mm 0 6 0.0% A18060
Shell plate Course 7 8mm 0 6 0.0% A18060
Shell plate Course 8 8mm 6 6 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18060
Top Ring Angle 150×150×15 59.087m 0 10 0.0% 0.0% Installation Ongoing A18060
Rafter Cutting Completed, Rafter Connection Plate Fit up Completed, Shell Support Chair for Rafter fit-up ongoing
Rafter UPN220 x 80 x 12.5mm thickness 8.1m 1 41 2.4% 30/40 A18060
Roof 2.4%
Roof Plate 6mm 0 40 0.0% Setting up Chain Hoist Lifting A18060
47 181
Annular Annular Plate Cutting 12mm 12 12 100.0% 100.0% Annular Laying Completed, Fit- up Completed, Inspection Completed A18070
Bottom Bottom Plate 10mm 17 17 100.0% 100.0% Bottom Plate Laying, Cutting n Fit-up Completed, Short seam fit-up Completed, Long Seam fit-up Completed A18070
Sump Sump Pit installation 10mm 1 1 100.0% 100.0% Fit up Sump pit upper n lower plate Completed A18070
Fillet Joint Shell Plate to Bottom Plate 12mm 0 1 0.0% 0.0%
47.13m
Shell plate Course 1 12mm 6 6 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18070
Shell Course 1 Manholes 12mm 1 1 100.0% Manholes Opening Completed A18070
Shell plate Course 2 11mm 6 6 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18070
Shell Shell plate Course 3 10mm 6 6 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18070
Fire Water 72.1%
Shell plate Course 4 9mm 6 6 100.0% Erection Completed , Gouging, Grinding and fit up completed for welding A18070
Shell plate Course 5 8mm 6 6 100.0% Erection Completed, Vertical fit up completed for welding A18070
Shell plate Course 6 8mm 0 6 0.0% A18070
Shell plate Course 7 8mm 0 6 0.0% A18070
Top Ring Angle 150×150×12 47.149 0 8 0.0% 0.0% A18070
Rafter UPN140 5.76m 0 25 0.0% A18070
Roof 0.0%
Roof Plate 6mm 0 24 0.0% A18070
Fire Water

61 131

Total 453 1175 38.6%


Date: 09-01-2024
Tank Erection: Scaffolding Erection Progress SITE Manpower : 6 Scaffolding Crew (13th, 14th, 19th Raining)
(0800-1700)

Internal
External By Shell
Hanging
BS1139 Course Work Work
Platform
Tank Plate Process Scaffoldin (internal Progress Progress Today Activities
or
g & (%) (%)
scaffoldin
Pipes External)
g

Others Activities ADO-A & ADO-B Rafter Center Ring Scaffolding Erection Completed
Shell plate Course 2 1.0 1.0 2 100.0% Erection Completed 04 Mar
Shell plate Course 3 1.0 1.0 2 100.0% Internal Completed, External Completed
POME-A Shell 100.0%
Shell plate Course 4 1.0 1.0 2 100.0% Internal Completed, External Completed
Roof Level 1.0 1.0 2 100.0% Internal Completed, External Completed
Shell plate Course 2 1.0 1.0 2 100.0% Erection Completed 14 Mar
Shell plate Course 3 1.0 1.0 2 100.0% Internal Completed, External Completed
POME-B Shell 100.0%
Shell plate Course 4 1.0 1.0 2 100.0% Internal Completed, External Completed
Roof Level 1.0 1.0 2 100.0% Internal Completed, External Completed
Shell plate Course 2 0.0 0.0 2 0.0%
Shell plate Course 3 0.0 0.0 2 0.0%
Shell plate Course 4 0.0 0.0 2 0.0%
Shell plate Course 5 0.0 0.0 2 0.0%
ULG95-A Shell 0.0%
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Shell plate Course 8 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Shell plate Course 2 1.0 1.0 2 100.0% External Completed 01 Apr, internal completed 04 Apr
Shell plate Course 3 1.0 1.0 2 100.0% Internal Completed, External Completed
Shell plate Course 4 1.0 1.0 2 100.0% Internal Completed, External Completed
Shell plate Course 5 1.0 1.0 2 100.0% Internal Completed, External Completed
ULG95-B Shell 50.0%
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Shell plate Course 8 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Shell plate Course 2 0.0 0.0 2 0.0%
Shell plate Course 3 0.0 0.0 2 0.0%
Shell plate Course 4 0.0 0.0 2 0.0%
Shell plate Course 5 0.0 0.0 2 0.0%
ULG97 Shell 0.0%
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Shell plate Course 8 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Shell plate Course 2 1.0 1.0 2 100.0% External Completed
Shell plate Course 3 0.0 0.0 2 0.0%
Shell plate Course 4 0.0 0.0 2 0.0%
Shell plate Course 5 0.0 0.0 2 0.0%
ADO-A Shell 100.0%
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Shell plate Course 8 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Shell plate Course 2 1.0 1.0 2 100.0% External Completed
Shell plate Course 3 0.0 0.0 2 0.0%
Shell plate Course 4 0.0 0.0 2 0.0%
Shell plate Course 5 0.0 0.0 2 0.0%
ADO-B Shell 100.0%
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Shell plate Course 8 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Shell plate Course 2 1.0 1.0 2 100.0% External Completed, Internal Completed
Shell plate Course 3 1.0 1.0 2 100.0% External Completed, Internal Completed
Shell plate Course 4 1.0 1.0 2 100.0% External Completed, Internal Completed
FIRE WATER Shell Shell plate Course 5 1.0 1.0 2 100.0% 57.1% External Ongoing 90%, Internal Completed
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Total 18.0 18.0 110.0 32.7%
Date: 09-01-2024 (0800- SITE Manpower : 9 Welders (13th, 14th, 19th Raining)
Tank Erection: Welding Work Progress
1700)

Plate
Plate Work Work Today Activities
Tank Plate Welding Area Thickness or Plate Qty:
Complete Progress (%) Progress (%)
Length

Others Activities

Annular Annular Plate 12mm 0 12 0.0% 0.0% A18020


Bottom Bottom Plate 10mm 0 27 0.0% 0.0% A18020
Sump Sump Pit 10mm 1 1 100.0% 100.0% Welding Completed A18020
Fillet Joint Shell Plate to Bottom Plate 63.46m 16mm 0 1 0.0% 0.0%
Shell plate Course 1 Vertical 2.48m 16mm 0 6 0.0% A18020
Shell plate Course 2 Vertical 2.48m 14mm 0 6 0.0% A18020
Shell plate Course 3 Vertical 2.48m 13mm 0 6 0.0% A18020
Shell plate Course 4 Vertical 2.48m 11mm 0 6 0.0% A18020
Shell plate Course 5 Vertical 2.48m 9mm 0 6 0.0% A18020
Shell plate Course 6 Vertical 2.48m 8mm 0 6 0.0% A18020
Shell plate Course 7 Vertical 2.48m 8mm 0 6 0.0% A18020
Shell
ULG 97 Shell plate Course 8 Vertical 2.14m 8mm 0 6 0.0% 0.0% A18020
Shell plate Course 1 & 2 Horizontal 63.485m 16-14mm 0 6 0.0% A18020
Shell plate Course 2 & 3 Horizontal 63.485m 14-13mm 0 6 0.0% A18020
Shell plate Course 3 & 4 Horizontal 63.485m 13-11mm 0 6 0.0% A18020
Shell plate Course 4 & 5 Horizontal 63.485m 11-9mm 0 6 0.0% A18020
Shell plate Course 5 & 6 Horizontal 63.485m 9-8mm 0 6 0.0% A18020
Shell plate Course 6 & 7 Horizontal 63.485m 8-8mm 0 6 0.0% A18020
Shell plate Course 7 & 8 Horizontal 63.485m 8-8mm 0 6 0.0% A18020
Top Ring Angle 150×150×15 63.485m 0 11 0.0% 0.0% A18020
Rafter UPN220 x 80 x 12.5mm thickness 8.72m 0 41 0.0% 0.0% A18020
Roof
Roof Plate 6mm 0 40 0.0% 0.0% A18020
1 223
Annular Annular Plate 12mm 12 12 100.0% 100.0% Welding Completed A18030
Bottom Bottom Plate 10mm 27 27 100.0% 100.0% Short Seam Welding 100%, Long Seam Ongoing 100% A18030
Sump Sump Pit 10mm 1 1 100.0% 100.0% Welding Completed A18030
Fillet Joint Shell Plate to Bottom Plate 63.46m 16mm 0 1 0.0% 0.0%
Shell plate Course 1 Vertical 2.48m 16mm 0 6 0.0% A18030
Shell plate Course 2 Vertical 2.48m 14mm 0 6 0.0% A18030
Shell plate Course 3 Vertical 2.48m 13mm 0 6 0.0% A18030
Shell plate Course 4 Vertical 2.48m 11mm 0 6 0.0% A18030
Shell plate Course 5 Vertical 2.48m 9mm 0 6 0.0% A18030
Shell plate Course 6 Vertical 2.48m 8mm 0 6 0.0% A18030
Shell plate Course 7 Vertical 2.48m 8mm 0 6 0.0% A18030
Shell
ULG 95-A Shell plate Course 8 Vertical 2.14m 8mm 0 6 0.0% 0.0% A18030
Shell plate Course 1 & 2 Horizontal 63.485m 16-14mm 0 6 0.0% A18030
Shell plate Course 2 & 3 Horizontal 63.485m 14-13mm 0 6 0.0% A18030
Shell plate Course 3 & 4 Horizontal 63.485m 13-11mm 0 6 0.0% A18030
Shell plate Course 4 & 5 Horizontal 63.485m 11-9mm 0 6 0.0% A18030
Shell plate Course 5 & 6 Horizontal 63.485m 9-8mm 0 6 0.0% A18030
Shell plate Course 6 & 7 Horizontal 63.485m 8-8mm 0 6 0.0% A18030
Shell plate Course 7 & 8 Horizontal 63.485m 8-8mm 0 6 0.0% A18030
Top Ring Angle 150×150×15 63.485m 0 11 0.0% 0.0% A18030
Rafter UPN220 x 80 x 12.5mm thickness 8.72m 0 41 0.0% 0.0% Center Ring Welding Ongoing A18030
Roof
Roof Plate 6mm 0 40 0.0% 0.0% A18030
40 223
Annular Annular Plate 12mm 12 12 100.0% 100.0% Welding Completed A18040
Bottom Bottom Plate 10mm 27 27 100.0% 100.0% Short Seam Welding 100%, Long Seam Welding 100% A18040
Sump Sump Pit 10mm 1 1 100.0% 100.0% Welding Completed A18040
Fillet Joint Shell Plate to Bottom Plate 63.46m 16mm 1.0 1 100.0% 100.0% Welding Ongoing 100%
Shell plate Course 1 Vertical 2.48m 16mm 4 6 66.7% 4 nos Vertical Welding Completed A18040
Shell plate Course 2 Vertical 2.48m 14mm 6 6 100.0% External Welding Completed, Internal Welding Completed A18040
Shell plate Course 3 Vertical 2.48m 13mm 6 6 100.0% External Welding Completed, Internal Welding Completed A18040
Shell plate Course 4 Vertical 2.48m 11mm 6 6 100.0% External Welding Completed, Internal Welding Completed A18040
Shell plate Course 5 Vertical 2.48m 9mm 6 6 100.0% External Welding Completed, Internal Welding Completed A18040
Shell plate Course 6 Vertical 2.48m 8mm 0 6 0.0% A18040
Shell plate Course 7 Vertical 2.48m 8mm 0 6 0.0% A18040
Shell
ULG 95-B Shell plate Course 8 Vertical 2.14m 8mm 0 6 0.0% 56.7% A18040
Shell plate Course 1 & 2 Horizontal 63.485m 16-14mm 5 6 83.3% External Welding Completed, Internal Welding Completed A18040
Shell plate Course 2 & 3 Horizontal 63.485m 14-13mm 6 6 100.0% External Welding Completed, Internal Welding Completed A18040
Shell plate Course 3 & 4 Horizontal 63.485m 13-11mm 6 6 100.0% External Welding Completed, Internal Welding Completed A18040
Shell plate Course 4 & 5 Horizontal 63.485m 11-9mm 6 6 100.0% External Welding Completed, Internal Welding Completed A18040
Shell plate Course 5 & 6 Horizontal 63.485m 9-8mm 0 6 0.0% A18040
Shell plate Course 6 & 7 Horizontal 63.485m 8-8mm 0 6 0.0% A18040
Shell plate Course 7 & 8 Horizontal 63.485m 8-8mm 0 6 0.0% A18040
Top Ring Angle 150×150×15 63.485m 0 11 0.0% 0.0% A18040
Rafter UPN220 x 80 x 12.5mm thickness 8.72m 0 41 0.0% 0.0% A18040
Roof
Roof Plate 6mm 0 40 0.0% 0.0% A18040
92 223
Bottom Bottom Plate 10mm 11 11 100.0% 100.0% Short Seam Welding 100%, Long Seam Welding 100% A18080
Sump Sump Pit 10mm 1 1 100.0% 100.0% Welding Completed A18080
Fillet Joint Shell Plate to Bottom Plate 22.275m 8mm 1.0 1 100.0% 100.0% External Welding Completed, Internal Welding Completed,
Shell plate Course 1 Vertical 2.28m 8mm 4 4 100.0% External Welding Completed, Internal Welding Completed, A18080
Shell plate Course 2 Vertical 2.28m 8mm 4 4 100.0% External Welding Completed, Internal Welding Completed, A18080
Shell plate Course 3 Vertical 2.28m 8mm 4 4 100.0% External Welding Completed, Internal welding Completed A18080
Shell
Shell plate Course 4 Vertical 1.96m 8mm 4 4 100.0% 100.0% External Welding Completed, Internal welding Completed A18080
POME-A Shell plate Course 1 & 2 Horizontal 28.74m 8-8mm 4 4 100.0% External Welding Completed, Internal welding Completed A18080
Shell plate Course 2 & 3 Horizontal 28.74m 8-8mm 4 4 100.0% External Welding Completed, Internal welding Completed A18080
Shell plate Course 3 & 4 Horizontal 28.74m 8-8mm 4 4 100.0% External Welding Completed, Internal Welding Completed A18080
Top Ring Top Annular Plate 28.74m 4 4 100.0% 100.0% Welding Completed A18040
Rafter 3.21m 17 17 100.0% Center Ring Plate Welding Completed, Rafter to Center Ring A18080
Roof 100.0% Completed
Roof Plate 6mm 16 16 100.0% Welding Completed 16/16 (On Ground & On Top) A18080
78 78
Bottom Bottom Plate 10mm 11 11 100.0% 100.0% Short Seam Welding 100%, Long Seam Welding 100% A18090
Sump Sump Pit 10mm 1 1 100.0% 100.0% Welding Completed A18090
Fillet Joint Shell Plate to Bottom Plate 22.275m 8mm 1 1 100.0% 100.0% External Welding Completed, Internal Welding Completed,
Shell plate Course 1 Vertical 2.28m 8mm 4 4 100.0% External Welding Completed, Internal Welding Completed, A18090
Shell plate Course 2 Vertical 2.28m 8mm 4 4 100.0% External Welding Completed, Internal Welding Completed, A18090
Shell plate Course 3 Vertical 2.28m 8mm 4 4 100.0% External Welding Completed, Internal Welding Completed, A18090
Shell
Shell plate Course 4 Vertical 1.96m 8mm 4 4 100.0% 100.0% External Welding Completed, Internal Welding Completed A18090
POME-B Shell plate Course 1 & 2 Horizontal 28.74m 8-8mm 4 4 100.0% External Welding Completed, Internal Welding Completed, A18090
Shell plate Course 2 & 3 Horizontal 28.74m 8-8mm 4 4 100.0% External Welding Completed, Internal Welding Completed, A18090
Shell plate Course 3 & 4 Horizontal 28.74m 8-8mm 4 4 100.0% External Welding Completed, Internal Welding Completed, A18090
Top Ring Top Annular Plate 28.74m 4 4 100.0% 100.0% Welding Completed A18040
Rafter 3.21m 17 17 100.0% Center Ring Plate Welding Completed, Rafter to Center Ring A18090
Roof 100.0% Completed
Roof Plate 6mm 16 16 100.0% Welding Completed 16/16 (On Ground & On Top) A18090
78 78
Annular Annular Plate 12mm 12 12 100.0% 100.0% Welding Completed A18050
Bottom Bottom Plate 10mm 27 27 100.0% 100.0% Short Seam Welding 100%, Long Seam Welding 100% A18050
Sump Sump Pit 10mm 1 1 100.0% 100.0% Welding Completed A18050
Fillet Joint Shell Plate to Bottom Plate 59.06m 16mm 0 1 0.0% 0.0%
Shell plate Course 1 Vertical 2.48m 16mm 0 6 0.0% A18050
Shell plate Course 2 Vertical 2.48m 14mm 0 6 0.0% A18050
Shell plate Course 3 Vertical 2.48m 13mm 0 6 0.0% A18050
Shell plate Course 4 Vertical 2.48m 11mm 0 6 0.0% A18050
Shell plate Course 5 Vertical 2.48m 9mm 0 6 0.0% A18050
Shell plate Course 6 Vertical 2.48m 9mm 0 6 0.0% A18050
Shell plate Course 7 Vertical 2.48m 8mm 0 6 0.0% A18050
Shell
Shell plate Course 8 Vertical 2.14m 8mm 6 6 100.0% 6.7% External Completed, Internal Completed A18050
ADO-A Shell plate Course 1 & 2 Horizontal 59.087m 16-14mm 0 6 0.0% A18050
Shell plate Course 2 & 3 Horizontal 59.087m 14-13mm 0 6 0.0% A18050
Shell plate Course 3 & 4 Horizontal 59.087m 13-11mm 0 6 0.0% A18050
Shell plate Course 4 & 5 Horizontal 59.087m 11-9mm 0 6 0.0% A18050
Shell plate Course 5 & 6 Horizontal 59.087m 9-9mm 0 6 0.0% A18050
Shell plate Course 6 & 7 Horizontal 59.087m 9-8mm 0 6 0.0% A18050
Shell plate Course 7 & 8 Horizontal 59.087m 8-8mm 0 6 0.0% A18050
Top Ring Angle 150×150×15 59.087m 10 10 100.0% 100.0% Top Ring Angle Welding Completed A18050
Center Ring & Rafter Connection Plate Welding 100%, Channel to
Rafter UPN220 x 80 x 12.5mm thickness 8.1m 41 41 100.0% 100.0% connection Plate 90%, Girders Welding Ongoing, Rafter Support Chairs A18050
Roof Welding Completed
Roof Plate 6mm 0 40 0.0% 0.0% A18050
97 222
Annular Annular Plate 12mm 12 12 100.0% 100.0% Welding Completed A18060
Bottom Bottom Plate 10mm 27 27 100.0% 100.0% Short Seam Welding 100%, Long Seam Welding 100% A18060
Sump Sump Pit 10mm 1 1 100.0% 100.0% Welding Completed A18060
Fillet Joint Shell Plate to Bottom Plate 59.06m 16mm 0 1 0.0% 0.0%
Shell plate Course 1 Vertical 2.48m 16mm 0 6 0.0% A18060
Shell plate Course 2 Vertical 2.48m 14mm 0 6 0.0% A18060
Shell plate Course 3 Vertical 2.48m 13mm 0 6 0.0% A18060
Shell plate Course 4 Vertical 2.48m 11mm 0 6 0.0% A18060
Shell plate Course 5 Vertical 2.48m 9mm 0 6 0.0% A18060
Shell plate Course 6 Vertical 2.48m 9mm 0 6 0.0% A18060
Shell plate Course 7 Vertical 2.48m 8mm 0 6 0.0% A18060
Shell
ADO-B Shell plate Course 8 Vertical 2.14m 8mm 6 6 100.0% 6.7% External Completed, Internal Completed A18060
Shell plate Course 1 & 2 Horizontal 59.087m 16-14mm 0 6 0.0% A18060
Shell plate Course 2 & 3 Horizontal 59.087m 14-13mm 0 6 0.0% A18060
Shell plate Course 3 & 4 Horizontal 59.087m 13-11mm 0 6 0.0% A18060
Shell plate Course 4 & 5 Horizontal 59.087m 11-9mm 0 6 0.0% A18060
Shell plate Course 5 & 6 Horizontal 59.087m 9-9mm 0 6 0.0% A18060
Shell plate Course 6 & 7 Horizontal 59.087m 9-8mm 0 6 0.0% A18060
Shell plate Course 7 & 8 Horizontal 59.087m 8-8mm 0 6 0.0% A18060
Top Ring Angle 150×150×15 59.087m 3 10 30.0% 30.0% Tor Ring Angle Welding Ongoing 30% A18060
Rafter UPN220 x 80 x 12.5mm thickness 8.1m 1 41 2.4% 2.4% Center Ring & Rafter Connection Plate Welding Completed A18060
Roof
Roof Plate 6mm 0 40 0.0% 0.0% A18060
50 222
Annular Annular Plate 12mm 12 12 100.0% 100.0% Welding Completed A18070
Bottom Bottom Plate 10mm 17 17 100.0% 100.0% Short Seam 100%, Long Seam 100% A18070
Sump Sump Pit 10mm 1 1 100.0% 100.0% Welding of sump pit upper n lower plate Completed A18070
Fillet Joint Shell Plate to Bottom Plate 47.13m 12mm 0 1 0.0% 0.0%
Shell plate Course 1 Vertical 2.48m 12mm 6 6 100.0% External Completed, Internal Completed A18070
Shell plate Course 2 Vertical 2.48m 11mm 6 6 100.0% External Completed, Internal Completed A18070
Shell plate Course 3 Vertical 2.48m 10mm 6 6 100.0% External Completed, Internal Completed A18070
Shell plate Course 4 Vertical 2.48m 9mm 3 6 50.0% External Completed, Internal Completed A18070
Shell plate Course 5 Vertical 2.48m 8mm 0 6 0.0% Preparation to Weld A18070
Shell plate Course 6 Vertical 2.48m 8mm 0 6 0.0% A18070
Shell
Fire Water Shell plate Course 7 Vertical 2.12m 8mm 0 6 0.0% 50.0% A18070
Shell plate Course 1 & 2 Horizontal 47.149m 12-11mm 6 6 100.0% External Completed, Internal Completed A18070
Shell plate Course 2 & 3 Horizontal 47.149m 11-10mm 6 6 100.0% External Completed, Internal Completed A18070
Shell plate Course 3 & 4 Horizontal 47.149m 10-9mm 6 6 100.0% External Completed, Internal Completed A18070
Shell plate Course 4 & 5 Horizontal 47.149m 9-8mm 0 6 0.0% A18070
Shell plate Course 5 & 6 Horizontal 47.149m 8-8mm 0 6 0.0% A18070
Shell plate Course 6 & 7 Horizontal 47.149m 8-8mm 0 6 0.0% A18070
Top Ring Angle 150×150×12 47.149m 0 8 0.0% 0.0% A18070
Rafter UPN140 5.76m 0 25 0.0% A18070
Roof 0.0%
Roof Plate 6mm 0 24 0.0% A18070
Fire Water

69 166

Total 505 1435 35.2%


Date: 09-01-2024 Tank Erection: NDT Progress RT Manpower : 3 RT Crews (4th Raining)
(0800-1700)
Quantity Estimate Estimate
Plate Thickness Complete Work
Tank Plate Welding Area or Length Qty of RT Film Progress Activities & API 650 Requirement
d MPI (%)

Others Activities

Annular Annular Plate 12mm 0 6 0.0%


Bottom Bottom Plate 10mm 0 1 0.0%
Sump Sump Pit 10mm 4 2 2 100.0% RT Completed, MPI Completed 18 Jan 2023
Shell plate Course 1 Vertical 2.48m 16mm 0 12 0.0% Each Thickness 1st 3m, next 30m, >10mm ALL T-joints RT, Each Welder x 1 film
Shell plate Course 2 Vertical 2.48m 14mm 0 24 0.0% Each Thickness 1st 3m, next 30m, >10mm ALL T-joints RT, Each Welder x 1 film
Shell plate Course 3 Vertical 2.48m 13mm 0 24 0.0% Each Thickness 1st 3m, next 30m, >10mm ALL T-joints RT, Each Welder x 1 film
Shell plate Course 4 Vertical 2.48m 11mm 0 24 0.0% Each Thickness 1st 3m, next 30m, >10mm ALL T-joints RT, Each Welder x 1 film
Shell plate Course 5 Vertical 2.48m 9mm 0 7 0.0% Each Thickness 1st 3m, next 30m, Each Welder x 1 film
Shell plate Course 6 Vertical 2.48m 8mm 0 7 0.0% Each Thickness 1st 3m, next 30m, Each Welder x 1 film
Shell plate Course 7 Vertical 2.48m 8mm 0 1 0.0% Each Thickness 1st 3m, next 30m
Shell Shell plate Course 8 Vertical 2.14m 8mm 0 1 0.0% Each Thickness 1st 3m, next 30m
ULG 97 Shell plate Course 1 & 2 Horizontal 63.485m 16-14mm 0 2 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 2 & 3 Horizontal 63.485m 14-13mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 3 & 4 Horizontal 63.485m 13-11mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 4 & 5 Horizontal 63.485m 11-9mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 5 & 6 Horizontal 63.485m 9-8mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 6 & 7 Horizontal 63.485m 8-8mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 7 & 8 Horizontal 63.485m 8-8mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Top Ring Angle 150×150×15 63.485m 0 12 0.0%
Roof Rafter UPN220 x 80 x 12.5mm thickness 8.72m 0 41 0.0%
Roof Plate 6mm 0 4 0.0%
4 176
Annular Annular Plate 12mm 6 6 100.0% RT Completed 25 Oct
Bottom Bottom Plate 10mm 0 1 0.0%
Sump Sump Pit 10mm 4 2 2 100.0% RT Completed, MPI Completed 18 Jan 2023
Shell plate Course 1 Vertical 2.48m 16mm 0 12 0.0% Each Thickness 1st 3m, next 30m, >10mm ALL T-joints RT, Each Welder x 1 film
Shell plate Course 2 Vertical 2.48m 14mm 0 24 0.0% Each Thickness 1st 3m, next 30m, >10mm ALL T-joints RT, Each Welder x 1 film
Shell plate Course 3 Vertical 2.48m 13mm 0 24 0.0% Each Thickness 1st 3m, next 30m, >10mm ALL T-joints RT, Each Welder x 1 film
Shell plate Course 4 Vertical 2.48m 11mm 0 24 0.0% Each Thickness 1st 3m, next 30m, >10mm ALL T-joints RT, Each Welder x 1 film
Shell plate Course 5 Vertical 2.48m 9mm 0 7 0.0% Each Thickness 1st 3m, next 30m, Each Welder x 1 film
Shell plate Course 6 Vertical 2.48m 8mm 0 7 0.0% Each Thickness 1st 3m, next 30m, Each Welder x 1 film
Shell plate Course 7 Vertical 2.48m 8mm 0 1 0.0% Each Thickness 1st 3m, next 30m
Shell Shell plate Course 8 Vertical 2.14m 8mm 0 1 0.0% Each Thickness 1st 3m, next 30m
ULG 95-A Shell plate Course 1 & 2 Horizontal 63.485m 16-14mm 0 2 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 2 & 3 Horizontal 63.485m 14-13mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 3 & 4 Horizontal 63.485m 13-11mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 4 & 5 Horizontal 63.485m 11-9mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 5 & 6 Horizontal 63.485m 9-8mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 6 & 7 Horizontal 63.485m 8-8mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Shell plate Course 7 & 8 Horizontal 63.485m 8-8mm 0 1 0.0% Each Thickness 1st 3m, next 60m
Top Ring Angle 150×150×15 63.485m 0 12 0.0%
Roof Rafter UPN220 x 80 x 12.5mm thickness 8.72m 0 41 0.0%
Roof Plate 6mm 0 4 0.0%
10 176
Annular Annular Plate 12mm 6 6 100.0% RT Completed 11/02/2023, All RT Pass
Bottom Bottom Plate 10mm 0 1 0.0%
Sump Sump Pit 10mm 4 2 2 100.0% RT Completed, MPI Completed 18 Jan 2023
Shell plate Course 1 Vertical 2.48m 16mm 8 12 66.7% RT Completed 19 & 20 Apr (Pending 4 Joints RT for Plate Opening), MPI Completed
Shell plate Course 2 Vertical 2.48m 14mm 21 24 87.5% RT Completed 13 Aug (Pending 3 Tee Joints RT for Plate Opening), MPI Completed
Shell plate Course 3 Vertical 2.48m 13mm 24 24 100.0% RT Completed 26 Aug, MPI Completed
Shell plate Course 4 Vertical 2.48m 11mm 24 24 100.0% RT Completed 01/11/2023
Shell plate Course 5 Vertical 2.48m 9mm 7 7 100.0% RT Completed
Shell plate Course 6 Vertical 2.48m 8mm 0 7 0.0%
Shell plate Course 7 Vertical 2.48m 8mm 0 1 0.0%
Shell Shell plate Course 8 Vertical 2.14m 8mm 0 1 0.0%
ULG 95-B Shell plate Course 1 & 2 Horizontal 63.485m 16-14mm 2 2 100.0% RT Completed 13 Aug
Shell plate Course 2 & 3 Horizontal 63.485m 14-13mm 1 1 100.0% RT Completed 26 Aug
Shell plate Course 3 & 4 Horizontal 63.485m 13-11mm 1 1 100.0% RT Completed 01/11/2023
Shell plate Course 4 & 5 Horizontal 63.485m 11-9mm 1 1 100.0% RT Completed
Shell plate Course 5 & 6 Horizontal 63.485m 9-8mm 0 1 0.0%
Shell plate Course 6 & 7 Horizontal 63.485m 8-8mm 0 1 0.0%
Shell plate Course 7 & 8 Horizontal 63.485m 8-8mm 0 1 0.0%
Top Ring Angle 150×150×15 63.485m 0 12 0.0%
Roof Rafter UPN220 x 80 x 12.5mm thickness 8.72m 0 41 0.0%
Roof Plate 6mm 0 4 0.0%
99 176
Bottom Bottom Plate 10mm 13 1 12 100.0% RT Completed
Sump Sump Pit 10mm 3 2 1 100.0% RT Completed, MPI Completed
Shell plate Course 1 Vertical 2.28m 8mm 4 4 100.0% RT Completed 19 & 20 Apr, MPI Completed
Shell plate Course 2 Vertical 2.28m 8mm 4 4 100.0% RT Completed 19 & 20 Apr, MPI Completed
Shell plate Course 3 Vertical 2.28m 8mm 4 4 100.0% RT Completed 15 Apr, MPI Completed
Shell Shell plate Course 4 Vertical 1.96m 8mm 4 4 100.0% RT Completed 20 Aug 2023, MPI Completed
POME-A Shell plate Course 1 & 2 Horizontal 28.74m 8-8mm 2 2 100.0% RT Completed 19 & 20 Apr, MPI Completed
Shell plate Course 2 & 3 Horizontal 28.74m 8-8mm 2 2 100.0% RT Completed 15 Apr, MPI Completed
Shell plate Course 3 & 4 Horizontal 28.74m 8-8mm 2 2 100.0% RT Completed 20 Aug 2023, MPI Completed
Rafter (10% MPI) 3.21m 33 33 100.0% MPI On Ground Completed, On Top Completed 17 Nov
Roof
Roof Plate (10% MPI) 6mm 2 2 100.0% MPI Completed 27 Nov
73 73
Bottom Bottom Plate 10mm 13 1 12 100.0% RT Completed
Sump Sump Pit 10mm 3 2 1 100.0% RT Completed, MPI Completed
Shell plate Course 1 Vertical 2.28m 8mm 4 4 100.0% RT Completed 19 & 20 Apr, MPI Completed
Shell plate Course 2 Vertical 2.28m 8mm 4 4 100.0% RT Completed 19 & 20 Apr, MPI Completed
Shell plate Course 3 Vertical 2.28m 8mm 4 4 100.0% RT Completed 20 Aug 2023, MPI Completed
Shell Shell plate Course 4 Vertical 1.96m 8mm 4 4 100.0% RT Completed 20 Aug 2023, MPI Completed
POME-B Shell plate Course 1 & 2 Horizontal 28.74m 8-8mm 2 2 100.0% RT Completed 20 Aug 2023, MPI Completed
Shell plate Course 2 & 3 Horizontal 28.74m 8-8mm 2 2 100.0% RT Completed 20 Aug 2023, MPI Completed
Shell plate Course 3 & 4 Horizontal 28.74m 8-8mm 2 2 100.0% RT Completed 20 Aug 2023, MPI Completed
Rafter (10% MPI) 3.21m 33 33 100.0% MPI On Ground Completed, On Top Completed 17 Nov
Roof
Roof Plate (10% MPI) 6mm 2 2 100.0% MPI Completed 27 Nov
73 73
Annular Annular Plate 12mm 6 6 100.0% 6 Joints RT on 17 Jun 2023, Results All Pass
Bottom Bottom Plate 10mm 0 1 0.0%
Sump Sump Pit 10mm 4 2 2 100.0% RT Completed, MPI Completed 18 Jan 2023
Shell plate Course 1 Vertical 2.48m 16mm 0 18 0.0%
Shell plate Course 2 Vertical 2.48m 14mm 0 18 0.0%
Shell plate Course 3 Vertical 2.48m 13mm 0 18 0.0%
Shell plate Course 4 Vertical 2.48m 11mm 0 18 0.0%
Shell plate Course 5 Vertical 2.48m 9mm 0 7 0.0%
Shell plate Course 6 Vertical 2.48m 8mm 0 7 0.0%
Shell plate Course 7 Vertical 2.48m 8mm 0 3 0.0%
Shell Shell plate Course 8 Vertical 2.14m 8mm 3 3 100.0% RT Completed
ADO-A Shell plate Course 1 & 2 Horizontal 63.485m 16-14mm 0 2 0.0%
Shell plate Course 2 & 3 Horizontal 63.485m 14-13mm 0 1 0.0%
Shell plate Course 3 & 4 Horizontal 63.485m 13-11mm 0 1 0.0%
Shell plate Course 4 & 5 Horizontal 63.485m 11-9mm 0 1 0.0%
Shell plate Course 5 & 6 Horizontal 63.485m 9-9mm 0 1 0.0%
Shell plate Course 6 & 7 Horizontal 63.485m 9-8mm 0 1 0.0%
Shell plate Course 7 & 8 Horizontal 63.485m 8-8mm 0 1 0.0%
Top Ring Angle 150×150×15 59.06m 10 10 100.0% MPI Completed
Rafter UPN220 x 80 x 12.5mm thickness 8.72m 41 41 100.0% Roof Center Ring MPI Completed, Rafter chairs n connection plate MPI Completed
Roof
Roof Plate 6mm 0 4 0.0%
64 166
Annular Annular Plate 12mm 6 6 100.0% 6 Joints RT on 17 Jun 2023, Results All Pass
Bottom Bottom Plate 10mm 0 1 0.0%
Sump Sump Pit 10mm 4 2 2 100.0% RT Completed, MPI Completed 18 Jan 2023
Shell plate Course 1 Vertical 2.48m 16mm 0 18 0.0%
Shell plate Course 2 Vertical 2.48m 14mm 0 18 0.0%
Shell plate Course 3 Vertical 2.48m 13mm 0 18 0.0%
Shell plate Course 4 Vertical 2.48m 11mm 0 18 0.0%
Shell plate Course 5 Vertical 2.48m 9mm 0 7 0.0%
Shell plate Course 6 Vertical 2.48m 8mm 0 7 0.0%
Shell plate Course 7 Vertical 2.48m 8mm 0 3 0.0%
Shell Shell plate Course 8 Vertical 2.14m 8mm 3 3 100.0% RT Completed
ADO-B Shell plate Course 1 & 2 Horizontal 63.485m 16-14mm 0 2 0.0%
Shell plate Course 2 & 3 Horizontal 63.485m 14-13mm 0 1 0.0%
Shell plate Course 3 & 4 Horizontal 63.485m 13-11mm 0 1 0.0%
Shell plate Course 4 & 5 Horizontal 63.485m 11-9mm 0 1 0.0%
Shell plate Course 5 & 6 Horizontal 63.485m 9-9mm 0 1 0.0%
Shell plate Course 6 & 7 Horizontal 63.485m 9-8mm 0 1 0.0%
Shell plate Course 7 & 8 Horizontal 63.485m 8-8mm 0 1 0.0%
Top Ring Angle 150×150×15 59.06m 10 10 100.0% MPI Completed
Roof Rafter UPN220 x 80 x 12.5mm thickness 8.72m 21 41 51.2% Roof Center Ring MPI Completed, Rafter connection plate MPI Completed
Roof Plate 6mm 0.0 4 0.0%
44 166
Annular Annular Plate 12mm 6 6 100.0% RT Completed 13 Aug
Bottom Bottom Plate 10mm 0 1 0.0%
Sump Sump Pit 10mm 4 2 2 100.0% RT Completed 19 & 20 Apr, MPI Completed
Shell plate Course 1 Vertical 2.48m 12mm 18 18 100.0% RT Completed 21 Oct
Shell plate Course 2 Vertical 2.48m 11mm 18 18 100.0% RT Completed 21 Oct
Shell plate Course 3 Vertical 2.48m 10mm 7 7 100.0% RT Completed
Shell plate Course 4 Vertical 2.48m 9mm 3 3 100.0% RT Completed
Shell plate Course 5 Vertical 2.48m 8mm 0 3 0.0%
Shell plate Course 6 Vertical 2.48m 8mm 0 3 0.0%
Shell Shell plate Course 7 Vertical 2.12m 8mm 0 3 0.0%
Fire Water Shell plate Course 1 & 2 Horizontal 47.149m 12-11mm 2 2 100.0% RT Completed 21 Oct
Shell plate Course 2 & 3 Horizontal 47.149m 11-10mm 1 1 100.0% RT Completed
Shell plate Course 3 & 4 Horizontal 47.149m 10-9mm 1 1 100.0% RT Completed
Shell plate Course 4 & 5 Horizontal 47.149m 9-8mm 0 1 0.0%
Shell plate Course 5 & 6 Horizontal 47.149m 8-8mm 0 1 0.0%
Shell plate Course 6 & 7 Horizontal 47.149m 8-8mm 0 1 0.0%
Top Ring Angle 150×150×12 47.149m 0 8 0.0%
Roof Rafter UPN140 5.76m 0 25 0.0%
Roof Plate 6mm 0 3 0.0%
Fire Water

60 109
Total 794 1417 704 37.4%