Activity ID Activity Name Start Finish Qty Act Qty Qty Act Qty Qty Act Qty Qty Act Qty %
Pre-Fabrication 20%
A18090 Tank No. 8 (9m D) POME B 9-Jan-23 45 45 16 16 43 32 104 93 89.42%
A18080 Tank No. 7 (9m D) POME A 9-Jan-23 45 45 16 16 43 32 104 93 89.42%
A18040 Tank No.3 (20.2m D) ULG 95B 2-Feb-23 129 89 48 30 127 30 304 149 49.01%
A18020 Tank No.1 (20.2m D) ULG97 15-Feb-23 129 89 48 0 127 0 304 89 29.28%
A18050 Tank No.4 (18.8m D) ADO A 10-Feb-23 129 129 48 6 127 46 304 181 59.54%
A18060 Tank No.5 (18.8m D) ADO B 10-Feb-23 129 129 48 6 127 46 304 181 59.54%
A18070 Tank No. 6 (15m D) FW 13-Feb-23 97 73 42 42 99 42 238 157 65.97%
A18030 Tank No.2 (20.2m D) ULG 95A 13-Feb-23 129 129 48 14 127 26 304 169 55.59%
TOTAL WTG (20%) 832 728 314 130 820 254 1966 1112 11.31%
Tank Plate Process Plate Thickness Plate Complete Plate Qty: Work Progress Work Progress Today Activities
(%) (%)
Physical inspection on plates
Check on materials spec, Heat no, plate number, plate size and quantity 596 596 100.0% 100.0% Completed MRIR
Materials Inspection
Mark Plate for traceability with Heat Tracking Code
Segregate plate to each tank Completed
Others Activities
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 03 Aug 2022 A18020
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 27 27 100.0% 100.0% Completed 01/08/2022 A18020
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Welding Completed A18020
Shell plate marking & cutting (course 1) 16mm 6 6 100.0% Completed 17 Aug 2022 A18020
Shell plate marking & cutting (course 2) 14mm 6 6 100.0% Completed 18 Aug 2022 A18020
Shell plate marking & cutting (course 3) 13mm 6 6 100.0% Completed 19 Aug 2022 A18020
ULG 97
Shell plate marking & cutting (course 4) 11mm 6 6 100.0% Completed 23 Aug 2022 A18020
Shell 100.0%
Shell plate marking & cutting (course 5) 9mm 6 6 100.0% Completed 25 Aug 2022 A18020
Shell plate marking & cutting (course 6) 8mm 6 6 100.0% Completed 27 Aug 2022 A18020
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 30 Aug 2022 A18020
Shell plate marking & cutting (course 8) 8mm 6 6 100.0% Completed 07 Sep 2022 A18020
Roof Roof Plate 6mm 1 41 2.4% 2.4% Roof Center Ring Fabrication Ongoing A18020
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 05 Aug 2022 A18030
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 27 27 100.0% 100.0% Completed 03 Aug 2022 A18030
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Welding Completed A18030
Shell plate marking & cutting (course 1) 16mm 6 6 100.0% Completed 07 Dec 2022 A18030
Shell plate marking & cutting (course 2) 14mm 6 6 100.0% Completed 09 Dec 2022 A18030
Shell plate marking & cutting (course 3) 13mm 6 6 100.0% Completed 29 Nov 2022 A18030
ULG 95-A
Shell plate marking & cutting (course 4) 11mm 6 6 100.0% Completed 15 Nov 2022 A18030
Shell 100.0%
Shell plate marking & cutting (course 5) 9mm 6 6 100.0% Completed 16 Dec 2022 A18030
Shell plate marking & cutting (course 6) 8mm 6 6 100.0% Completed 01 Dec 2022 A18030
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 03 Dec 2022 A18030
Shell plate marking & cutting (course 8) 8mm 6 6 100.0% Completed 16 Dec 2022 A18030
Roof Roof Plate 6mm 41 41 100.0% 100.0% Roof Center Ring Fabrication n Welding Ongoing A18030
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 08 Aug 2022 A18040
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 27 27 100.0% 100.0% Completed 04 Aug 2022 A18040
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Welding Completed A18040
Shell plate marking & cutting (course 1) 16mm 6 6 100.0% Completed 17 Dec 2022 A18040
Shell plate marking & cutting (course 2) 14mm 6 6 100.0% Completed 14 Dec 2022 A18040
Shell plate marking & cutting (course 3) 13mm 6 6 100.0% Completed 15 Dec 2022 A18040
ULG 95-B
Shell plate marking & cutting (course 4) 11mm 6 6 100.0% Completed 13 Dec 2022 A18040
Shell 100.0%
Shell plate marking & cutting (course 5) 9mm 6 6 100.0% Completed 16 Dec 2022 A18040
Shell plate marking & cutting (course 6) 8mm 6 6 100.0% Completed 10 Dec 2022 A18040
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 20 Dec 2022 A18040
Shell plate marking & cutting (course 8) 8mm 6 6 100.0% Completed 22 Dec 2022 A18040
Roof Roof Plate 6mm 1 41 2.4% 2.4% Roof Center Ring Fabrication Ongoing A18040
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 11 11 100.0% Completed 26 Jul 2022 A18080
100.0%
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Completed A18080
Shell plate marking & cutting (course 1) 8mm 4 4 100.0% Completed 03 Sep 2022 A18080
POME-A Shell plate marking & cutting (course 2) 8mm 4 4 100.0% Completed 06 Sep 2022 A18080
Shell 100.0%
Shell plate marking & cutting (course 3) 8mm 4 4 100.0% Completed 06 Sep 2022 A18080
Shell plate marking & cutting (course 4) 8mm 4 4 100.0% Completed 10 Sep 2022 A18080
Roof Roof Plate 6mm 17 17 100.0% 100.0% Completed 22 May 2023 A18080
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 11 11 100.0% Completed 28 Jul 2022 A18090
100.0%
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Completed A18090
Shell plate marking & cutting (course 1) 8mm 4 4 100.0% Completed 09 Sep 2022 A18090
POME-B Shell plate marking & cutting (course 2) 8mm 4 4 100.0% Completed 10 Sep 2022 A18090
Shell 100.0%
Shell plate marking & cutting (course 3) 8mm 4 4 100.0% Completed 11 Sep 2022 A18090
Shell plate marking & cutting (course 4) 8mm 4 4 100.0% Completed 15 Sep 2022 A18090
Roof Roof Plate 6mm 17 17 100.0% 100.0% Completed 25 May 2023 A18090
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 11 Aug 2022 A18050
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 27 27 100.0% 100.0% Completed 11 Aug 2022 A18050
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Completed 26 Oct 2022 A18050
Shell plate marking & cutting (course 1) 16mm 6 6 100.0% Completed 01 Nov 2022 A18050
Shell plate marking & cutting (course 2) 14mm 6 6 100.0% Completed 29 Oct 2022 A18050
Shell plate marking & cutting (course 3) 13mm 6 6 100.0% Completed 29 Oct 2022 A18050
ADO-A
Shell plate marking & cutting (course 4) 11mm 6 6 100.0% Completed 02 Nov 2022 A18050
Shell 100.0%
Shell plate marking & cutting (course 5) 9mm 6 6 100.0% Completed 28 Oct 2022 A18050
Shell plate marking & cutting (course 6) 9mm 6 6 100.0% Completed 22 Oct 2022 A18050
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 27 Oct 2022 A18050
Shell plate marking & cutting (course 8) 8mm 6 6 100.0% Completed 22 Dec 2022 A18050
Roof Roof Plate 6mm 41 41 100.0% 100.0% Cutting Completed A18050
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 13 Aug 2022 A18060
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 27 27 100.0% 100.0% Completed 02 Sep 2022 A18060
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Completed 26 Oct 2022 A18060
Shell plate marking & cutting (course 1) 16mm 6 6 100.0% Completed 29 Nov 2022 A18060
Shell plate marking & cutting (course 2) 14mm 6 6 100.0% Completed 29 Nov 2022 A18060
Shell plate marking & cutting (course 3) 13mm 6 6 100.0% Completed 15 Nov 2022 A18060
ADO-B
Shell plate marking & cutting (course 4) 11mm 6 6 100.0% Completed 07 Nov 2022 A18060
Shell 100.0%
Shell plate marking & cutting (course 5) 9mm 6 6 100.0% Completed 04 Dec 2022 A18060
Shell plate marking & cutting (course 6) 9mm 6 6 100.0% Completed 16 Jan 2023 A18060
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 22 Dec 2022 A18060
Shell plate marking & cutting (course 8) 8mm 6 6 100.0% Completed 22 Nov 2022 A18060
Roof Roof Plate 6mm 41 41 100.0% 100.0% Cutting Completed A18060
Annular Mark out annular plate & Annular Plate Cutting 12mm 12 12 100.0% Completed 09 Sep 2022 A18070
Bottom Mark out bottom plate & Bottom Plate Cutting 10mm 17 17 100.0% 100.0% Completed 18 Sep 2022 A18070
Sump Fabrication for Sump Plate 10mm 1 1 100.0% Completed 10 Mar 2023 A18070
Shell plate marking & cutting (course 1) 12mm 6 6 100.0% Completed 12 Jan 2023 A18070
Shell plate marking & cutting (course 2) 11mm 6 6 100.0% Completed 12 Jan 2023 A18070
Fire Water Shell plate marking & cutting (course 3) 10mm 6 6 100.0% Completed 12 Jan 2023 A18070
Shell Shell plate marking & cutting (course 4) 9mm 6 6 100.0% 100.0% Completed 14 Jan 2023 A18070
Shell plate marking & cutting (course 5) 8mm 6 6 100.0% Completed 13 Jan 2023 A18070
Shell plate marking & cutting (course 6) 8mm 6 6 100.0% Completed 08 Jan 2023 A18070
Shell plate marking & cutting (course 7) 8mm 6 6 100.0% Completed 30 Dec 2022 A18070
Roof Roof Plate 6mm 1 25 4.0% 4.0% Roof Center Ring Fabrication n Welding Ongoing A18070
Total 728 832 68.9%
Date: 09-01-2024 (0800-
1700) Tank Fabrication: Plate Rolling Work Progress Manpower : 3 Rolling Crew
Others Activities
Course 1 Plate Rolling 16mm 6 0.0% A18020
Course 2 Plate Rolling 14mm 6 0.0% A18020
Course 3 Plate Rolling 13mm 6 0.0% A18020
Course 4 Plate Rolling 11mm 6 0.0% A18020
Shell
ULG 97 Course 5 Plate Rolling 9mm 6 0.0% A18020
Course 6 Plate Rolling 8mm 6 0.0% A18020
Course 7 Plate Rolling 8mm 6 0.0% A18020
Course 8 Plate Rolling 8mm 6 0.0% A18020
Roof Top Ring Angle 150x150x6m 0 11 0.0%
Course 1 Plate Rolling 16mm 6 6 100.0% Completed 01/03/2023 A18030
Course 2 Plate Rolling 14mm 2 6 33.3% Completed 01/03/2023 A18030
Course 3 Plate Rolling 13mm 6 0.0% A18030
Course 4 Plate Rolling 11mm 6 0.0% A18030
Shell
ULG 95-A Course 5 Plate Rolling 9mm 6 0.0% A18030
Course 6 Plate Rolling 8mm 6 0.0% A18030
Course 7 Plate Rolling 8mm 6 0.0% A18030
Course 8 Plate Rolling 8mm 6 6 100.0% Completed A18030
Roof Top Ring Angle 150x150x6m 11 11 100.0% Completed
Course 1 Plate Rolling 16mm 6 6 100.0% Completed 20/02/2023 A18040
Course 2 Plate Rolling 14mm 6 6 100.0% Completed 01/03/2023 A18040
Course 3 Plate Rolling 13mm 6 6 100.0% Completed 18/07/2023 A18040
Course 4 Plate Rolling 11mm 6 6 100.0% Completed 21/08/2023 A18040
Shell
ULG 95-B Course 5 Plate Rolling 9mm 6 6 100.0% Completed 25/09/2023 A18040
Course 6 Plate Rolling 8mm 6 0.0% A18040
Course 7 Plate Rolling 8mm 6 0.0% A18040
Course 8 Plate Rolling 8mm 6 0.0% A18040
Roof Top Ring Angle 150x150x6m 0 11 0.0%
Course 1 Plate Rolling 8mm 4 4 100.0% Completed A18080
Course 2 Plate Rolling 8mm 4 4 100.0% Completed A18080
POME-A Shell
Course 3 Plate Rolling 8mm 4 4 100.0% Completed A18080
Course 4 Plate Rolling 8mm 4 4 100.0% Completed A18080
Course 1 Plate Rolling 8mm 4 4 100.0% Completed A18090
Course 2 Plate Rolling 8mm 4 4 100.0% Completed A18090
POME-B Shell
Course 3 Plate Rolling 8mm 4 4 100.0% Completed A18090
Course 4 Plate Rolling 8mm 4 4 100.0% Completed A18090
Course 1 Plate Rolling 16mm 6 0.0% A18050
Course 2 Plate Rolling 14mm 6 0.0% A18050
Course 3 Plate Rolling 13mm 6 0.0% A18050
Course 4 Plate Rolling 11mm 6 0.0% A18050
Shell
ADO-A Course 5 Plate Rolling 9mm 6 0.0% A18050
Course 6 Plate Rolling 9mm 6 0.0% A18050
Course 7 Plate Rolling 8mm 6 0.0% A18050
Course 8 Plate Rolling 8mm 6 6 100.0% Completed A18050
Roof Top Ring Angle 150x150x6m 10 10 100.0% Completed
Course 1 Plate Rolling 16mm 6 0.0% A18060
Course 2 Plate Rolling 14mm 6 0.0% A18060
Course 3 Plate Rolling 13mm 6 0.0% A18060
Course 4 Plate Rolling 11mm 6 0.0% A18060
Shell
ADO-B Course 5 Plate Rolling 9mm 6 0.0% A18060
Course 6 Plate Rolling 9mm 6 0.0% A18060
Course 7 Plate Rolling 8mm 6 0.0% A18060
Course 8 Plate Rolling 8mm 6 6 100.0% Completed A18060
Roof Top Ring Angle 150x150x6m 10 10 100.0% Completed
Course 1 Plate Rolling 12mm 6 6 100.0% Completed 19/08/2023 A18070
Course 2 Plate Rolling 11mm 6 6 100.0% Completed 02/09/2023 A18070
Course 3 Plate Rolling 10mm 6 6 100.0% Completed 03/09/2023 A18070
Shell Course 4 Plate Rolling 9mm 6 6 100.0% Completed 23/09/2023 A18070
Fire Water
Course 5 Plate Rolling 8mm 6 6 100.0% Completed 05/12/2023 A18070
Course 6 Plate Rolling 8mm 6 6 100.0% Completed 09/12/2023 A18070
Course 7 Plate Rolling 8mm 6 6 100.0% Completed 09/12/2023 A18070
Roof Top Ring Angle 150x150x6m 2 8 25.0% Ongoing
Total 161 367 43.9%
Date: 09-01-2024 KJS YARD Manpower : 4 pax Blasting &
Tank Fabrication: Plate Blasting & Painting Work Progress
(0800-1700) Painting Crew (13th, 14th, 19th Raining)
Work
Plate Plate
Tank Plate Course Process Plate Qty: Progress Today Activities
Thickness Complete
(%)
Others Activities
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18020
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 27 0.0% A18020
Course 1 Blasting and 1st Coat Primer 16mm 0 6 0.0% A18020
Course 2 Blasting and 1st Coat Primer 14mm 0 6 0.0% A18020
Course 3 Blasting and 1st Coat Primer 13mm 0 6 0.0% A18020
Course 4 Blasting and 1st Coat Primer 11mm 0 6 0.0% A18020
ULG 97 Shell
Course 5 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18020
Course 6 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18020
Course 7 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18020
Course 8 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18020
Top Ring Blasting and 1st Coat Primer 0 11 0.0%
Roof
Roof Plate Blasting and 1st Coat Primer 6mm 0 40 0.0% A18020
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18030
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 27 0.0% A18030
Course 1 Blasting and 1st Coat Primer 16mm 0 6 0.0% A18030
Course 2 Blasting and 1st Coat Primer 14mm 0 6 0.0% A18030
Course 3 Blasting and 1st Coat Primer 13mm 0 6 0.0% A18030
Course 4 Blasting and 1st Coat Primer 11mm 0 6 0.0% A18030
ULG 95-A Shell
Course 5 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18030
Course 6 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18030
Course 7 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18030
Course 8 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed A18030
Top Ring Blasting and 1st Coat Primer 11 11 100.0% Completed 19/12/2023
Roof
Roof Plate Blasting and 1st Coat Primer 6mm 20 40 50.0% Ongoing A18030
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18040
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 27 0.0% A18040
Course 1 Blasting and 1st Coat Primer 16mm 6 6 100.0% Completed 04 Mar 2023 A18040
Course 2 Blasting and 1st Coat Primer 14mm 6 6 100.0% Completed A18040
Course 3 Blasting and 1st Coat Primer 13mm 6 6 100.0% Completed 21 Jul 2023 A18040
Course 4 Blasting and 1st Coat Primer 11mm 6 6 100.0% Completed 28 Aug 2023 A18040
ULG 95-B Shell
Course 5 Blasting and 1st Coat Primer 9mm 6 6 100.0% Completed 12 Oct 2023 A18040
Course 6 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18040
Course 7 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18040
Course 8 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18040
Top Ring Blasting and 1st Coat Primer 0 11 0.0%
Roof
Roof Plate Blasting and 1st Coat Primer 6mm 0 40 0.0% A18040
Bottom Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 11 0.0% A18080
Course 1 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 07 Jan 2023 A18080
Course 2 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 09 Jan 2023 A18080
POME-A Shell
Course 3 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 11 Jan 2023 A18080
Course 4 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 13 Jan 2023 A18080
Roof Plate Blasting and 1st Coat Primer 6mm 16 16 100.0% Completed 23/09/2023 A18080
Bottom Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 11 0.0% A18090
Course 1 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 08 Jan 2023 A18090
Course 2 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 10 Jan 2023 A18090
POME-B Shell
Course 3 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 12 Jan 2023 A18090
Course 4 Blasting and 1st Coat Primer 8mm 4 4 100.0% Completed 14Jan 2023 A18090
Roof Plate Blasting and 1st Coat Primer 6mm 16 16 100.0% Completed 23/09/2023 A18090
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18050
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 27 0.0% A18050
Course 1 Blasting and 1st Coat Primer 16mm 0 6 0.0% A18050
Course 2 Blasting and 1st Coat Primer 14mm 0 6 0.0% A18050
Course 3 Blasting and 1st Coat Primer 13mm 0 6 0.0% A18050
Course 4 Blasting and 1st Coat Primer 11mm 0 6 0.0% A18050
ADO-A Shell
Course 5 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18050
Course 6 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18050
Course 7 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18050
Course 8 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed 08/11/2023 A18050
Top Ring Blasting and 1st Coat Primer 10 10 100.0% Completed 18/12/2023
Roof
Roof Plate Blasting and 1st Coat Primer 6mm 40 40 100.0% Completed 21/11/2023 A18050
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18060
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 27 0.0% A18060
Course 1 Blasting and 1st Coat Primer 16mm 0 6 0.0% A18060
Course 2 Blasting and 1st Coat Primer 14mm 0 6 0.0% A18060
Course 3 Blasting and 1st Coat Primer 13mm 0 6 0.0% A18060
Course 4 Blasting and 1st Coat Primer 11mm 0 6 0.0% A18060
ADO-B Shell
Course 5 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18060
Course 6 Blasting and 1st Coat Primer 9mm 0 6 0.0% A18060
Course 7 Blasting and 1st Coat Primer 8mm 0 6 0.0% A18060
Course 8 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed 10/11/2023 A18060
Top Ring Blasting and 1st Coat Primer 10 10 100.0% Completed 8/12/2023
Roof
Roof Plate Blasting and 1st Coat Primer 6mm 40 40 100.0% Completed 12/12/2023 A18060
Annular Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 12mm 0 12 0.0% A18070
Bottom Plate Blasting and 1st Coat Primer, 2nd Coat, 3rd Coat 10mm 0 21 0.0% A18070
Course 1 Blasting and 1st Coat Primer 12mm 6 6 100.0% Completed 21 Aug 2023 A18070
Course 2 Blasting and 1st Coat Primer 11mm 6 6 100.0% Completed 12 Sep 2023 A18070
Course 3 Blasting and 1st Coat Primer 10mm 6 6 100.0% Completed 13 Sep 2023 A18070
FW Shell Course 4 Blasting and 1st Coat Primer 9mm 6 6 100.0% Completed 17 Oct 2023 A18070
Course 5 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed A18070
Course 6 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed A18070
Course 7 Blasting and 1st Coat Primer 8mm 6 6 100.0% Completed A18070
FW
Others Activities
61 131
Internal
External By Shell
Hanging
BS1139 Course Work Work
Platform
Tank Plate Process Scaffoldin (internal Progress Progress Today Activities
or
g & (%) (%)
scaffoldin
Pipes External)
g
Others Activities ADO-A & ADO-B Rafter Center Ring Scaffolding Erection Completed
Shell plate Course 2 1.0 1.0 2 100.0% Erection Completed 04 Mar
Shell plate Course 3 1.0 1.0 2 100.0% Internal Completed, External Completed
POME-A Shell 100.0%
Shell plate Course 4 1.0 1.0 2 100.0% Internal Completed, External Completed
Roof Level 1.0 1.0 2 100.0% Internal Completed, External Completed
Shell plate Course 2 1.0 1.0 2 100.0% Erection Completed 14 Mar
Shell plate Course 3 1.0 1.0 2 100.0% Internal Completed, External Completed
POME-B Shell 100.0%
Shell plate Course 4 1.0 1.0 2 100.0% Internal Completed, External Completed
Roof Level 1.0 1.0 2 100.0% Internal Completed, External Completed
Shell plate Course 2 0.0 0.0 2 0.0%
Shell plate Course 3 0.0 0.0 2 0.0%
Shell plate Course 4 0.0 0.0 2 0.0%
Shell plate Course 5 0.0 0.0 2 0.0%
ULG95-A Shell 0.0%
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Shell plate Course 8 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Shell plate Course 2 1.0 1.0 2 100.0% External Completed 01 Apr, internal completed 04 Apr
Shell plate Course 3 1.0 1.0 2 100.0% Internal Completed, External Completed
Shell plate Course 4 1.0 1.0 2 100.0% Internal Completed, External Completed
Shell plate Course 5 1.0 1.0 2 100.0% Internal Completed, External Completed
ULG95-B Shell 50.0%
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Shell plate Course 8 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Shell plate Course 2 0.0 0.0 2 0.0%
Shell plate Course 3 0.0 0.0 2 0.0%
Shell plate Course 4 0.0 0.0 2 0.0%
Shell plate Course 5 0.0 0.0 2 0.0%
ULG97 Shell 0.0%
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Shell plate Course 8 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Shell plate Course 2 1.0 1.0 2 100.0% External Completed
Shell plate Course 3 0.0 0.0 2 0.0%
Shell plate Course 4 0.0 0.0 2 0.0%
Shell plate Course 5 0.0 0.0 2 0.0%
ADO-A Shell 100.0%
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Shell plate Course 8 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Shell plate Course 2 1.0 1.0 2 100.0% External Completed
Shell plate Course 3 0.0 0.0 2 0.0%
Shell plate Course 4 0.0 0.0 2 0.0%
Shell plate Course 5 0.0 0.0 2 0.0%
ADO-B Shell 100.0%
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Shell plate Course 8 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Shell plate Course 2 1.0 1.0 2 100.0% External Completed, Internal Completed
Shell plate Course 3 1.0 1.0 2 100.0% External Completed, Internal Completed
Shell plate Course 4 1.0 1.0 2 100.0% External Completed, Internal Completed
FIRE WATER Shell Shell plate Course 5 1.0 1.0 2 100.0% 57.1% External Ongoing 90%, Internal Completed
Shell plate Course 6 0.0 0.0 2 0.0%
Shell plate Course 7 0.0 0.0 2 0.0%
Roof Level 0.0 0.0 2 0.0%
Total 18.0 18.0 110.0 32.7%
Date: 09-01-2024 (0800- SITE Manpower : 9 Welders (13th, 14th, 19th Raining)
Tank Erection: Welding Work Progress
1700)
Plate
Plate Work Work Today Activities
Tank Plate Welding Area Thickness or Plate Qty:
Complete Progress (%) Progress (%)
Length
Others Activities
69 166
Others Activities
60 109
Total 794 1417 704 37.4%