Professional Documents
Culture Documents
Revised WTP comm. plan
Revised WTP comm. plan
1.1.3 commissioning of The single equipment of the electric valves and water pumps
1.1.7 The single equipment commissioning of the softened water system has been completed and is now in standby mode
The dosing system has been configured, such as bactericidal and algal agents, flocculants, scale inhibitors, reducing
1.1.8
agents, etc
Turn on the inlet valve of the clarifier's raw water and adjust the flow rate to 60 t/h (flow rate without water in the
1.2.1
clarifier)
Turn on the flocculant metering pump, adjust the dosage of flocculant according to the table below, and increase the
1.2.2
dosage for the first inlet water
After the clarification tank is filled with water, the bottom discharge is carried out. After the clean water flows out, then
1.2.4
close the bottom discharge of the clarification tank
1.2.5 Turn on the raw water inlet valve and adjust it to the rated flow rate, then put it into the raw water pretreatment system
Turn on the 7 # exhaust valve and 6 # flushing exhaust valve. When the water level in the filter drops to 20-30mm above
1.3.1.1
the filter material layer, turn off the 6 # flushing exhaust valve and keep the 7 # exhaust valve open
Manually turn on the 4 # back flushing drainage valve and the 2 # back flushing inlet valve, execute the back flushing
1.3.1.2
program, and the back flushing flow rate shall be 21.6-36m ³/ H (Water flushing intensity 3-5 L/s. m2.)
Manually turn on the 3 # air compressor intake valve and stir the multi-medium filter. The intake pressure should be
1.3.1.3 controlled between 0.06-0.1Mpa, and the intake volume should be 1.2-2.4 m3/min (with a flushing intensity of 10-20 L/s.
m2). After the water quality is clear, close the 3 # compressed air intake valve.
Stop flushing after the effluent water quality test is qualified. Turn off the 2 # backflushing inlet valve, 3 # air compressor
1.3.1.4
inlet valve, 4 # back flushing drainage valve, and 7 # exhaust valve
Simulate the pressure difference before and after the filter to the rated value (short circuit the differential pressure
1.3.1.5
switch), and observe whether the automatic backflushinging is normal
1.3.2.3 After the exhaust valve releases water, turn on the 6 # flushing drainage valve and turn off the 7 # exhaust valve
1.3.2.4 Stop flushing after the water quality is clear and put it into automatic operation
1.4 Commissioning
1.4.1.1 The water level of the clean water tank (RCC) reaches 2/3 or above
1.4.1.2 Turn on the exhaust valve and the inlet valve of the exchanger
1.4.1.3 Turn on the softened water feed pump and close it after the exhaust valve overflows
Manually open the flushing drainage valve, control the flushing for 5-10 minutes, then close the flushing drainage valve
1.4.1.4
and put it into automatic operation
Turn on the 7 # exhaust valve and 6 # flushing exhaust valve. When the water level in the filter drops to 20-30mm above
1.4.2.1
the filter material layer, turn off the 6 # flushing exhaust valve and keep the 7 # exhaust valve open
Manually turn on the 4 # back flushing drainage valve and the 2 # back flushing inlet valve, and execute the back flushing
1.4.2.2
program
The standard for controlling the back flushing flow rate is to control the resin layer to expand beyond the center of the
1.4.2.3
upper mirror during back flushing, and the entire resin layer to be loose
1.4.3 The regeneration of sodium ion exchanger
1.4.3.1 Manually turn on the middle discharge valve and exhaust valve until the water flows out of the middle discharge pipe
1.4.3.2 Turn on the salt inlet valve and start the dissolved salt regeneration water pump
Control the dissolved salt flow rate to 5t/h, fill the saturated salt solution in one shoot, and soak
1.4.3.3
the sodium ion resin for 1 hour
1.4.3.4 Repeat the back flushing and flushing steps after 1 hour
1.4.3.5 After the effluent quality meets the standards, put it into operation.
Please refer to the softened water system which is the same way.
Manually turn on the 6 # exhaust valve and 5 # positive discharge valve. When the water level in
2.2.1.1 the filter drops to 20-30mm above the filter material layer, turn off the 6 # positive discharge
valve
Stop flushing after the effluent water quality test is qualified. Turn off the 2 # back flushing inlet valve, 3 # back flushing drainage
2.2.1.4
valve, and 6 # exhaust valve
Simulate the pressure difference before and after the filter to the rated value (short circuit the differential pressure switch), and
2.2.1.5
observe whether the automatic back flushing is normal
Turn on the exhaust valve # 6 and inlet valve # 1 of the activated carbon filter, and exhaust is completed after the exhaust pipeline #
2.2.2.1
6 continues to discharge water
Turn on the 5 # washing discharge valve, and at the same time, turn off the exhaust valve at 6 #.
2.2.2.3
Adjust the opening of the manual inlet valve to control the flow rate of 18m ³/ H
At this moment, the filter becomes the flushing state, and the effluent becomes clear. The
2.2.2.4
flushing process is complete
2.3.1 Fully turn on the drain valve of the ultrafiltration inlet main pipe
2.3.2 Start the pre-treatment system and flush the ultrafiltration inlet main pipe until it is clean
Slowly turn on the drain valve of the ultrafiltration outlet main pipe, turn off the drain valve of
2.3.3
the inlet main pipe, and flush the outlet main pipe
After flushing the system, turn on the drain to discharge the remaining water, and install the
2.3.4
ultrafiltration filter element
Turn off the drain valve, slowly turn on the inlet valve to exhaust the air inside the ultrafiltration,
2.3.5
and put the ultrafiltration into operation to filter the water
When the water level in the buffer water tank is greater than 2/3, apply ultrafiltration for
2.3.6
automatic back flushing
Observe whether the automatic flushing, back flushing, and gas flushing processes of
2.3.7
ultrafiltration are reliable
2.4.2.1 Adjust the pressure control and monitoring system of the reverse osmosis feedwater pump
Check whether the connections between all pipelines of the device are complete, whether the
2.4.2.2
pressure gauge is complete, and whether the pipeline connections are tight
2.4.2.3 Turn on the inlet valve of the security filter element and start the pre-treatment equipment
2.4.2.4 Turn on the exhaust valve of the security filter to exhaust the air
Start the reducing agent dosing device (control the ratio concentration of reducing agent sodium
2.4.2.5
bisulfite at 5%)
2.4.2.6 Start the scale inhibitor dosing device (control the scale inhibitor raw liquid ratio at 10%, Note
After the components are filled with water, fully turn on the pressure gauge switches,
2.4.2.7
concentration discharge valves, effluent discharge valves, and inlet valves of the RO system
Adjust the inlet pressure of the high-pressure pump to be greater than 0.2MPa, start the
2.4.2.8
high-pressure pump, and perform system flushing (flushing until clear water flows out)
Use the device inlet valve and adjust the concentration drain valve, the total pressure
difference of the control device is less than 0.3MPa, and adjust the production water
2.4.2.9
discharge valve to the working pressure 15 minutes after the production water is discharged,
and check whether the high and low pressure pipelines and instruments are normal
Adjust the inlet valve and concentrated water outlet valve to produce water to the rated level,
2.4.2.10
with a concentrated water ratio of 3:1, and a system design recovery rate of 75%
Detect the conductivity of the product water. If it meets the requirements, first turn on the
2.4.2.11
reverse osmosis outlet valve, and then turn off the produced water discharge valve
The system runs stably for 1 hour under standard conditions, measuring the production
2.4.2.12
water flow rate and desalination rate
Simultaneously turn on the decarbonization fan and RO production water tank drain valve for
2.4.2.13
water tank flushing, and turn off the drain valve after flushing
When the RO water tank is greater than 2/3, turn on the lower inlet valve and upper
2.4.2.14
drainage valve of the mixed bed
Start the intermediate pump, control the outlet valve of the intermediate pump to maintain
2.4.2.15
the balance of inlet and outlet water, and flush the mixed bed
After the back flushing is completed, perform a back flushing (open the inlet and outlet
2.4.2.16 valves to ensure that the drainage meets the effluent water quality standards as the
endpoint, with a back flushing flow rate of 15-30 meters/hour)
After flushing is completed, the equipment is put into automatic operation. Check if the logic
2.4.2.17 is correct, whether the start and stop are normal, and whether the dosing device
automatically starts and stops
Concentrated water: flow rate, pressure, and the inlet pressure of each section