Professional Documents
Culture Documents
DDMRP Study Material
DDMRP Study Material
DDMRP Study Material
All these parts’ buffer levels are determined by summing the zones that comprise them
GREEN
The green zone is the heart of the supply order generation process embedded in the buffer. It
determines average order frequency and typical order size. The green zone is determined by
one of three factors. Whichever factor yields the greatest number determines the size of the
green zone. In this way it represents a conservative view with regard to recommended and
average order frequency.
YELLOW
The yellow zone is the heart of the inventory coverage in the buffer. The yellow zone is always
calculated as 100 percent average daily usage (ADU) × decoupled lead time (DLT)
RED
The red zone is the embedded safety in the buffer. The higher the variability associated with
the part or SKU, the larger the red zone will be. Calculating the red zone is accomplished with
three sequential equations. Buffer profiles.
3 Factors:
a. Type: manufactured (M), purchased (P), or distributed (D).
b. LT: This spread could be anywhere from almost zero lead time for on-site
supplier-managed inventory to lead times measured in months or years. There
are differing circumstances that dictate what the parameters defining short,
medium, and long within any particular environment will be. The lead time
category will then be used to supply a “lead time factor” to parts within a
profile.
1. Notice that the longer the lead time of the part, the smaller the lead time
factor should be. BIG CONCEPTUAL DIFERENCE. DDMRP is about creating
and protecting the flow of information and materials. For long lead time
parts, DDMRP is attempting to create a frequent demand signal relating to
actual need and a corresponding supplying “pipeline” delivering a steady
stream of supply orders. Difference embedded, decipting between large
infrequent orders and a steadier stream of smaller more frequent orders.
2. A smaller lead time factor produces a smaller green zone calculation. Since
the green zone determines average order size and frequency, a smaller
lead time factor will lead to smaller and more frequent orders.
Combination Matrix
Atributos Individuais
LT = 0,5
Var = 0,33
Green ( e heart of the supply order generation , will determine the average order
frequency and typical order size for the part, determined 1 of below 3 options )
Yellow (yellow zone is the heart of the inventory coverage in the buffer). most
straightforward zone to calculate in a buffer. The yellow zone is always calculated as
ADU multiplied by the decoupled lead time. [ADU (10 per day) × DLT (12 days)].
Red : The red zone is the embedded safety in the buffer : The higher the variability
associated with the part or SKU, the larger the red zone will be.
o 1 Base : [ADU (10 per day) × DLT (12 days) × lead time factor (0.5)] = value is 60
This lead time factor corresponds to the same ranges used for the
green zone calculation but can have a different numerical value.
o +
o 2 Safety : ” The red safety is calculated as a percentage of the red base. S
determined by the variability factor. [red base of 60 × 0.33 (variability factor)].
o Totaç [red base (60) + red safety (20)]
Once all zones are calculated, we can add them together to get a total buffer. In this case it is
270 [red (80) + yellow (120) + green (70)]
Remarks
So, in summary: