Bill of Quantities

Construction of Project Nexus


ITEM SCOPE OF WORKS QTY. UNI UNIT TOTAL COST
NO. T COST
A. OTHER GENERAL REQUIREMENTS
SPL-1 Project Billboard/Signboard 1.00 each 25 500
SPL-2 Construction Safety and Health 1.00 L.S. 250,000 250,000
Provision of Temporary Facilities for 5,000 30,000
SPL-3 180.00 days
Engineer (Rental Basis)
SPL-4 Mobilization/Demobilization 1.00 L.S. 20,000 20,000
SPL-5 Layout 250.00 sq.m 6,250 1,562,500
B. EARTHWORKS
800(1) Clearing & Grubbing 270.00 sq.m 11 3,000
803(1)a Structural Excavation (Common Soil) 166.81 cu.m 300 50,000
C. STRUCTURAL CONCRETE
900(1)c2 Structural Concrete 360.16 cu.m 2,500 900,000
902(1) Reinforcing Steel Bar 33,401.94 kg 40 1,336,077
D. FINISHING WORKS & OTHER CIVIL
WORKS
1002(5) Plumbing Works 1.00 L.S. 500,000 500,000
1101 Electrical Works 1.00 L.S. 500,000 500,000
1003(1) Fiber Cement Board on Metal Frame 593.89 Sq.m
Ceiling
Finishing Works (Fix glass, Door lockset, 5,000 5,000
1004 Cladding, WPC Panels, Air Conditioning, & 1.00 L.S.
1012(1) Tempered Glass Door & Windows 64.40 sq.m 500 32,000
1010(2) Wooden Panel Door 2 each 2,500 5,000
1032 Painting Works (Masonry & Metal) 512.76 Sq.m 20,000
E. MASONRY WORKS
1046 Masonry Works (100mm/150mm CHB) 1,357.58 Sq.m 30 105,000
1018 Glazed Tiles / Unglazed Tiles 250.00 Sq.m 1,000 250,000
1027(1) Cement Plaster Finish 400.00 Sq.m 300 120,000
1300 Decorative Floor Bricks 90.30 sq.m 500 45,000
F. STEEL WORKS AND ROOFING
WORKS
1013(2) Fabricated Metal Roofing Accessory 1.00 L.S. 10,000 10,000
1014 Prepainted Metal Sheet (Rib Type) 230.00 Sq.m 1,000 230,000
1,000 250,000
1047 Structural Steel Works (Framing, Truss, 4,211.33 kg
Purlins)
G. DRAINAGE & SEPTIC VAULT
SPL-6 Storm Drainage & Downspout 1.00 L.s. 500 500
SPL-7 Septic Vault 1.00 L.s. 25,000 25,000
TOTAL BID PRICE 6,249,577