RPT-7006-GG-01-61-00-007-0
RPT-7006-GG-01-61-00-007-0
RPT-7006-GG-01-61-00-007-0
PLANT: COMMON
HOLD LIST
REVISION HISTORY
Rev
Section or Page
. Date Description of Change
Revised
No.
TABLE OF CONTENTS
1. PROJECT DESCRIPTION.......................................................................................................
1.1 Introduction....................................................................................................................
1.2 Project Objective and Scope.........................................................................................
1.3 Purpose of this Document.............................................................................................
2. DEFINITIONS & ABBREVIATIONS.....................................................................................
2.1 Definitions......................................................................................................................
2.2 Abbreviations.................................................................................................................
3. REFERENCE DOCUMENTS...................................................................................................
3.1 Order of Precedence.....................................................................................................
3.2 References....................................................................................................................
4. CONSTRUCTABILITY REVIEW STUDY............................................................................
4.1 Introduction....................................................................................................................
4.2 Basis..............................................................................................................................
4.3 Process.........................................................................................................................
4.4 Guidewords.................................................................................................................
4.5 Major Challenges / Difficulties, Issues & Concerns.....................................................
5. CONSTRUCTABILITY WORKSHOP TEAM, CHECKLIST & RECORDING............
5.1 Workshop Team..........................................................................................................
5.2 Constructability Workshop Recording.........................................................................
6. CONSTRUCTABILITY REVIEW RESULTS.....................................................................
7. CHAIRMAN’S REMARKS....................................................................................................
APPENDIX I – VIP TOR.....................................................................................................................
APPENDIX II – CONSTRUCTABILITY REVIEW WORKSHOP ATTENDEES......................
APPENDIX III – CONSTRUCTABILITY REVIEW WORKSHEET...........................................
1. PROJECT DESCRIPTION
1.1 Introduction
The Habshan & Bab Gas Complex is a set of gas processing facilities operated by ADNOC
Gas Processing (AGP) and located approximately 140km southwest of the city of Abu Dhabi.
The first plant in the complex was commissioned almost four decades ago. Since then, several
other plants were added to the complex making it one of the largest gas processing facilities in
the world.
In order to ensure the continued viability of Habshan and Bab Gas Complex, ADNOC Gas
Processing regularly reviews the installed equipment and systems, and carries out necessary
refurbishments, upgrades, replacements and additions to ensure that the facilities can be
operated in a safe, sustainable and efficient manner. This Project is a continuation of these
efforts.
ADNOC Gas Processing (hereinafter referred to as COMPANY) has assigned M/s Bilfinger
Tebodin Middle East Ltd. (hereafter referred to as CONSULTANT) to carry out Front End
Engineering & Design (FEED) and Detail Engineering for the Project to enable COMPANY to
engage a Procurement & Construction (PC) CONTRACTOR to execute the Project.
CONSULTANT shall perform Engineering for the PROJECT as per Scope of Services under
the framework Agreement No. TE.18.048 (J) / 2018-21 /SRC/021. CONSULTANT shall carry
out Engineering for the project to enable COMPANY to engage a Procurement & Construction
(PC) CONTRACTOR to execute the Project without further detailed engineering.
1.2 Project Objective and Scope
The objective of the Project is to ensure safety and security of personnel and buildings by
providing adequate public address system annunciation, safety monitoring and incident review
capability, and controlled access to critical buildings by implementing/enhancing the Public
Address, CCTV and Access Control Systems in accordance with International Codes,
Standards, HSE and Electronic Security requirements.
The scope includes the following main items, in addition to all associated multi-disciplinary
works:
New CCTV and Access Control Systems in Habshan & Bab Process Buildings
New Public Address System in Bab Plant Area & Residential Complex
Integration of the above system including Security LAN and Video Analytics
The purpose of this document is to present the Constructability Review Workshop outcome for
the Project Scope.
2.1 Definitions
SUBCONTRACTOR The party(s) to whom any part of Project has been subcontracted
by CONSULTANT.
PROJECT Habshan and Bab Telecom Systems Upgrade Project No. 7006.
CONTRACTOR The party which carries out all or part of the procurement,
construction, commissioning or management of the Project.
2.2 Abbreviations
JB Junction Box
PC Procurement Construction
UG Underground
3. REFERENCE DOCUMENTS
Project Documents;
COMPANY DGS;
3.2 References
Project Documents
ADNOC Standards
4.1 Introduction
The Constructability Review includes and tries to address anything that can make Project
easier, faster, safer and / or more cost effective to build, while maintaining quality, safety and
access for employees, tools and equipment during construction, production and / or
maintenance.
The main objectives of the Constructability Review were to the extent possible:
Constructability Review efforts can support all Project objectives such as: reducing cost,
shortening schedules, improve quality, security & safety, and enhance management of risk.
4.2 Basis
The Constructability Review was conducted in accordance with, Doc No. AGPM-VIP-401K
ADNOC VALUE IMPROVING PRACTICE (VIP): CONSTRUCTABILITY Guideline and in
accordance with the VIP Terms of Reference for the Study provided in APPENDIX-I.
4.3 Process
The following categories were subject to Review and Analysis:
Completing Project within Budget & Schedule;
Maintaining Quality;
Fulfilling Scope;
Site conditions;
Layout;
Site access;
Logistics;
Construction Schedule;
Tie-in aspects;
Transportation of materials;
Lifting requirements;
HSE requirements;
Guide Words
Risks across Dust fume, contamination spills, ignition source, heat, noise,
construction / vibration, electromagnetic radiation
operations boundary
Transiting services / Pipes, cables, Ducts etc. in affected area, both above / below
Utilities ground (buried services), headroom (structures etc.), on
boundary, Availability of permanent / temporary power, lighting,
drainage, water, telecom
Major Risks Falls, Collapse, Struck by, Manual handling, electricity Fire,
Substance, Noise
Access / Sequence Routes identified for on/off site and structures, vehicular,
bridges, pedestrian, emergency services, large plant, cranes,
access for lifting, scaffolding, need for, (control of modifications /
approval for use), platforms, cradles, sufficient safety harness
anchors provided, area release programmes, sequential /
CONSULTANT Doc. No. Document No. Doc. Class Page
3415079 RPT-7006-GG-01-61-00-007 2 10 of 20
ADNOC GAS PROCESSING
Guide Words
Guide Words
Following discussion and agreement by the Review Team, any Recommendations / Actions
identified based on each criteria subject to analysis were recorded in the Constructability
Worksheet including Action parties responsible for action closure.
The output of the Workshop was captured in a specially prepared Constructability Worksheet in
excel format which is provided in APPENDIX-III of this Report.
In total, 68 Construction Review Criteria were subject to analysis by the Review Team which
resulted in 26 Recommendations / Actions as shown in Table 6-1 of this Report.
Sl. Table 6-1: Constructability Review Recommendations
Recommendation / Action Responsibility
No.
Detailed Method Statements to be developed for the
Installation of CCTV, ACS, PAGA and ancillary Systems, UPS,
1. Cable Installation, JB's etc. and included in PC SoW. In Consultant (BTME)
addition, the list of challenges associated with Installation shall
also be included.
Sl.
Recommendation / Action Responsibility
No.
Sl.
Recommendation / Action Responsibility
No.
Sl.
Recommendation / Action Responsibility
No.
7. CHAIRMAN’S REMARKS
The Team worked efficiently and all inputs were welcomed both by COMPANY and
CONSULTANT.
It is strongly advised that Recommendations resulting from this Study be implemented by the
nominated Action Party in order to effectively manage the Constructability issues associated
with the PROJECT which can contribute to the PROJECT realizing its objectives.
Project: HABSHAN & BAB TELECOM SYSTEMS UPGRADE PROJECT No. 7006