METHOD STATEMENT FOR SHUTTERING
METHOD STATEMENT FOR SHUTTERING
METHOD STATEMENT FOR SHUTTERING
PMS : _____________________
1|Page
REDEVELOPMENT OF VARKALA SIVAGIRI RAILWAY STATION
KRDCL/RVNL(JV)
Method Rev.No. 00
Statement
CONTENTS
1. PURPOSE.
2. SCOPE.
3. RESPONSIBILITY.
4. METHODOLOGY OF WORKING PROCEDURE.
5. SAFE OPERATING PROCEDURE.
PURPOSE
The purpose of this Work Procedure is to provide a controlled system of operation within project
specifications and applicable codes/standards.
SCOPE
This Work Procedure shall cover the Execution of Shuttering works and identify the sequence of
operations and HSE Guidelines.
2|Page
METHODOLOGY FOR EXECUTING SHUTTERING WORKS:
SAFETY ASPECTS:
All the labor involved in the work will have all PPE (Personal protective equipment).
Safety Supervisors will supervise during the execution of work.
In case of night work proper lighting shall be provided.
Walk-way, working platform with handrails, staging towers / Ladders shall be provided as required.
3|Page