Professional Documents
Culture Documents
Method Statement for Electrical PVC Conduits Installation
Method Statement for Electrical PVC Conduits Installation
FOR
ELECTRICAL PVC CONDUITS INSTALLATION
➢ TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1.SCOPE
➢ This procedure to clear the method of the supply, installations of
Electrical PVC Conduits for the project.
➢ This document details Electrical PVC Conduits Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
➢ Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
➢ Material:
➢ Installation:
• During the course of the installation of the conduit system,
procedures for working and dressing the installation as
recommended shall be employed.
• All bends and sets shall be in accordance with IEE regulation 522-
08 formed with the aid of a helical spring fitted internally, with if
necessary, the conduit warmed sufficiently for it to move without
avoidable wall thinning of the out side of the bend.
➢ Commissioning:
• When conduits are run on shuttering, prior to the laying of concrete
insitu, additional security must be provided near to every box and at
intervals of not more than 1.2 meters by binding short lengths of
steel wire, of not less than 2mm diameter twisted around the
conduit and reinforcing steel. The conduits shall be adequately fixed
to prevent excessive movement and damage during the pouring
and setting of concrete and shall be protected from mechanical
damage. Check there is no damage before screed / concrete is
poured. Unless otherwise indicated to cast in conduits shall not be
less than 30mm.cores to plastered over conduits shall not be less
than 5mm.
• Where conduits are left "open ended" prior to wiring they shall be
protected by caps or plugs to prevent the ingress of building
material.
• Ensure conduits are not concealed until works has been inspected
and approved. Ensure that conduit and fittings buried in concrete or
behind plaster are protected against corrosion or electrolytic action
prior to rendering.
➢ Technical Assistance:
• The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
• This instruction shall be scheduled at the convenience of the
staff.
• All such instruction shall be properly recorded.
• WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
➢ PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
➢ SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
➢ FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
2. To ensure that his assistant foreman/ charge hand are aware of
the job requirements and they have enough information to carry
out their duties properly.
➢ SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
➢ STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
➢ Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
➢ Electrical PVC Conduits Components and Accessories
9. EQUIPMENTS REQUIREMENTS
➢ The Equipment that will be engaged for Electrical PVC Conduits
Installation will be as follows:
1. Hack saw
2. Measuring tape
3. Cutting plier
4. Knipex (End cutter)
5. Bending spring
6. Drilling Machine
➢ The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.
13. DISTRIBUTION
➢ Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper