SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Hot Tap & Stopple Connection Installations (Latest* SAEP-311, 13 SEPT 2009)
SATIP-L-052-01 14-May-18 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SPECIAL PROCESS (HOT TAPS) REQUIRE THE BEST QUALITY PRACTICE, CPI & EFFICIENT METHODS IN PROCEDURES. ENSURE INSPECTORS & PACKAGES
1.0 DOCUMENT REVIEW
HAVE ALL THE CHECKLISTS APPLICABLE TO THESE INSTALLATIONS, INCLUDING THOSE FOR NDE, COATINGS, ETC. SEE "NOTICE" IN GENERAL NOTES.
Hot Tap/Stopple & Reinforcement Perform in accordance with Step 3.1 and obtain the
1.2 SAIC-L-2091 SAIC-L-2091 RH RH
Calculation Request-Form 7627 information necessary to assure
SAIC-W-2001 SAIC-W-2001
1.3 WPS/WPQR (Plant Piping) RH RH Use SAIC-L-2090 & Note WPS Reqmts for Hot Taps
1.4 WPS/WPQR (Pipelines) SAIC-W-2038 SAIC-W-2038 RH RH Use SAIC-L-2090 & Note WPS Reqmts for Hot Taps
1.5 WPS/WPQR (Pressure Vessels) SAIC-W-2058 SAIC-W-2058 RH RH Use SAIC-L-2090 & Note WPS Reqmts for Hot Taps
1.6 WPS/WPQR (Pressure Vessels) SAIC-W-2075 SAIC-W-2075 RH RH Use SAIC-L-2090 & Note WPS Reqmts for Hot Taps
SAIC-W-2035
SAIC-W-2035 Vessels & Tanks utilize same as Plant Piping Systems
1.7 Welder Qualification Record (Plants) RH R
(SAIC-W-2035), Pipelines utilize (SAIC-W-2039)
1.8 Welder Qualification Record (Pipelines) SAIC-W-2039 SAIC-W-2039 RH R Pipelines utilize (SAIC-W-2039)
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Hot Tap & Stopple Connection Installations (Latest* SAEP-311, 13 SEPT 2009)
SATIP-L-052-01 14-May-18 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Hot Tap Valves and/or Sandwich Valves Refer to SATIP-L--108-01 (Field Testing Required) Use
2.2 See Remarks See Remarks
(Receipt Insp & Field Testing) SATR-A-2001-V (Valve Test & Insp Form)
2.3 Material Storage and Preservation SAIC-L-2093 SAIC-L-2093 W W Organized & segregated per Hot Tap (Unique ID #)
3.0 INSTALLATION NOTICE: See "Notice" in General Notes Relative to Insp Requests for Hot Tap & associated NDE activities. Use SAIC-L-2090 in all activities below.
SAIC-L-2094 SAIC-L-2094
3.2 Pre-Welding Insp. (Set-Up of sticker) H H
SAIC-W-2007
3.3 Visual Insp of Welds (PLANT PIPING) SAIC-W-2007 H W Use applicable In-Process welding checklists also
3.4 Visual Insp of Welds (PIPELINES) SAIC-W-2050 SAIC-W-2050 H W Use applicable In-Process welding checklists also
3.5 Visual Insp of Welds (VESSELS) SAIC-W-2070 SAIC-W-2070 H W Use applicable In-Process welding checklists also
3.6 Visual Insp of Welds (API TANKS) SAIC-W-2087 SAIC-W-2087 H W Use applicable In-Process welding checklists also
NDE (PT or MPT of Sticker weld prior to Refer to SATR-NDE-PT-2002 (Penetrant Testing) or
3.7 See Remarks See Remarks
reinforcing pad installation) SATR-NDE-MPT-2003 (Magnetic Particle Testing)
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Hot Tap & Stopple Connection Installations (Latest* SAEP-311, 13 SEPT 2009)
SATIP-L-052-01 14-May-18 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Flange joint inspection (gasket verification USE SATR-L-2001 - * Each Package contains proposed
3.10 SAIC-L-2014 SAIC-L-2014 H W
& bolt tightening) documentation for Inspection & Testing
Inspect Cut Coupon (Fitness for Service See also SAIC-L-2090, Service Consideration
3.11 SAIC-L-2096 SAIC-L-2096 W W
Evaluation Checklist for Inspection Assessment Guide
3.13 Coating Application See Remarks See Remarks Refer to the applicable H-Series SATIP (Coating)
3.14 Stopper/Plug Installation See Remarks See Remarks S S Activity Performed by SA Hot Tap & Stoppling Unit
Final Inspection (Walkthrough) for Hot Package, Package, Package Review & Signoff (QA Certified Completion)
3.15 H H
Tap & Stopple Installations Drawings Drawings Each Package is its own PMCC - Close all items
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Hot Tap & Stopple Connection Installations (Latest* SAEP-311, 13 SEPT 2009)
SATIP-L-052-01 14-May-18 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1
of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.