A

Th e June 2022
Component Manufacturing Don’t Forget!
Adverti$$er
#14275
dverti$
dverti $ er You Saw it in the Page #112

Mass Timber Aerospace Project


Uses Innovative Truss System
A new museum/hanger in British Columbia
mirrors the shapes and curves of a plane

By Johanna Knapschaefer
Reprinted courtesy of Engineering News-Record, copyright BNP Media,
February 7, 2022, all rights reserved.

W
hile having lunch with his executive director at the Four Points hotel in British
Columbia’s Kelowna International Airport, KF Aerospace founder Barry Lapointe
pulled out a red pen, asked the waitress for a piece of paper and began drawing a
building shaped like an aircraft.

This was in May 2017, when he first conceived the concept for the two-story, 60,000-sq-ft KF
Aerospace Center for Excellence museum now nearing completion in Kelowna on the eastern shore
of Okanagan Lake.

The busy entrepreneur was quick to delegate the details, says KF Aerospace executive director
Paula Quinn. “‘It’s got to be mass timber; it’s got to look like an aircraft; and I want it built at the
airport,’ he said, so basically we … had to run with this little drawing,” Quinn recalls. “He wanted
to leave something that would tell the story of aviation in the Okanagan.”

Aerial view of the KF Aerospace museum/hangar before it topped out in mid-November. It is nearing
completion on land between the Kelowna International Airport and Highway 97 in Kelowna, British
Columbia. Photo credit Agency Media, courtesy naturallywood.com.
Continued next page
PHONE: 800-289-5627 Read/Subscribe online at www.componentadvertiser.com FAX: 800-524-4982
A
Th e June 2022
Component Manufacturing Don’t Forget!
Adverti$$er
#14275
dverti$
dverti $ er You Saw it in the Page #113

The clear airplane “design concept of placing people into a hub sandwiched between two hangars
was almost instantaneous,” says Jim Meiklejohn, senior partner at Meiklejohn Architects Inc. in
Kelowna and lead architect for the project.

“The challenge was to develop Lapointe’s diagram into an architecture form that was sophisticated
but remained simple,” Meiklejohn says. “The roof structure was based on our architectural sketches,”
which StructureCraft then modeled using Grasshopper 3D, a plugin that runs inside the Rhino 3D
computer-aided design app that maximizes material efficiency to span the space. “The result was
reminiscent of a complex curved wing shape,” says Meiklejohn, with spars, trusses and cables.

It took StructureCraft three days to install the mass timber hangar roof panels.
Photo credit Agency Media, courtesy naturallywood.com.

Green Construction Wood Program


The $26-million project began on KF Aerospace’s 51st anniversary in March 2021 and is
scheduled to finish on budget and on schedule for its 52nd anniversary next month, Quinn says. It
is the first museum/hangar project of this size with the Green Construction (GC) Wood program,
which supports expanding the use of wood in construction and Canada’s transition to a low-carbon
economy, says Kevin Imthorn, vice president and project manager at Sawchuk Developments Co.,
the British Columbia-based construction manager for the project. Sawchuk is employing a 2010
construction management contract for services, the Canada-wide standard for CM.

Sawchuk completed its first budget for KF Aerospace in May 2020 based on the current site and
produced a Class C budget by December, with a tight timeline to open by March 25.

Continued next page


PHONE: 800-289-5627 Read/Subscribe online at www.componentadvertiser.com FAX: 800-524-4982
A
Th e June 2022
Component Manufacturing Don’t Forget!
Adverti$$er
#14275
dverti$
dverti $ er You Saw it in the Page #114

StructureCraft crews installed 16,856 sq ft of cross-laminated timber (CLT) shear walls, 13,200
sq ft of dowel-laminated timber (DLT) floor panels, 16,000 sq ft of curved DLT roof panels and 9,102
cu ft of glulam beams and columns. Steel used for queen post and reinforcement totals 101,907 kg
(224,667 lb). Grizzly Metal Fab supplied all the steel except the spar trusses, which were supplied
by Western Manufacturing, both of British Columbia.

An average of 12 panels per day are installed with a crew of four people and a crane operator.
Photo credit Agency Media, courtesy naturallywood.com.

Lapointe, KF Aerospace’s sole shareholder, funded the project with support from Natural
Resources Canada (NRCan), which awarded $800,000 to support design and construction in May
2019 when an agreement between NRCan and KF Aerospace was announced, a representative said.
Since then, an additional $100,000 has been awarded to KF Aerospace, one of 30 applicants from
across Canada (10 received awards). KF Aerospace’s Quinn, however, estimated the total received
to date was $700,000 and confirmed that all funds to be disbursed over three years had not been
received as of early February.

“It will be the first of its kind in Canada, using state-of-the-art floor and tall wood-based systems
to accommodate the large spacing between columns—a typical design element for a hangar but not
yet done using this innovative building system,” said NRCan in a statement last year.

Once complete, the structure will include an aviation museum and a conference center. “The
total carbon benefits realized from the use of mass timber for this construction are an estimated
1,753 metric tons (1,932 tons) of carbon dioxide,” NRCan said.

Continued next page


PHONE: 800-289-5627 Read/Subscribe online at www.componentadvertiser.com FAX: 800-524-4982
A
Th e June 2022
Component Manufacturing Don’t Forget!
Adverti$$er
#14275
dverti$
dverti $ er You Saw it in the Page #115

The team developed a concept for spar trusses designed like World War II-era Spitfire fighter planes.
Photo credit Agency Media, courtesy naturallywood.com.

Spitfire-Inspired Spar Truss Wings


Lucas Epp, vice president and head of engineering at British-Columbia-based structural
engineering and timber construction firm StructureCraft, says the team developed a concept for spar
trusses designed like World War II-era Spitfire fighter planes. “This spar truss goes along the wing
while the rib trusses run perpendicular to the spar trusses and create the shaping of the wing,” he
says. This Spitfire-spar-truss concept “turned our roof structure into a giant steel spar truss, spanning
across 115-ft-wide operable glass doors, with timber rib trusses that create the shaping,” Epp says.
The structural design team matched some of Lapointe’s favorite math equations for how to describe
the exact shape of a wing profile to allow them to play with that shape.

In the first meeting with Lapointe, while discussing development of airfoil wing shapes from
the Wright brothers to the supersonic stealth fighters, the team chose the classic NACA (National
Advisory Committee for Aeronautics) airfoil equation, Epp recalls. Using that equation, the team
took a computational engineering approach to develop “parametric models which used genetic
algorithms to optimize and iterate on the different geometrical shapes for the wings using real-time
structural analysis to assist in creating the most structurally efficient truss structure,” he says.

Continued next page


PHONE: 800-289-5627 Read/Subscribe online at www.componentadvertiser.com FAX: 800-524-4982
A
Th e June 2022
Component Manufacturing Don’t Forget!
Adverti$$er
#14275
dverti$
dverti $ er You Saw it in the Page #116

The central “fuselage” hub constructed mainly of DLT and glulam, flanked by two hangar “wings.” The
cantilevered DLT roof consist of flat panels lined up on edge along the curved glulam beams. Photo credit
Shawn Talbot, courtesy naturallywood.com.

Design Hurdles
During design development, one challenge involved building the center high enough so that
travelers could observe aircraft on the runway from the second floor without obstruction by private
single-story-high AST hangars that the site overlooks. “We used a drone to help set and confirm
our elevation for the second floor,” Imthorn says.

“This resulted in a second floor that was to be 23 feet above the main floor,” posing the challenge
of how to connect these two spaces, says Meiklejohn. The solution was a spiral, freestanding doubly
curved CLT timber-concrete composite staircase, Epp says. The design includes timber on the bottom
with concrete on the top to add strength and some mass, he notes. StructureCraft is using inhouse
radial jigs to build the 24-ft-high by 80-ft-long staircase in halves at its manufacturing facility in
Abbotsford, British Columbia. Nothing like it was commercially available in North America or
worldwide.

Continued next page


PHONE: 800-289-5627 Read/Subscribe online at www.componentadvertiser.com FAX: 800-524-4982
A
Th e June 2022
Component Manufacturing Don’t Forget!
Adverti$$er
#14275
dverti$
dverti $ er You Saw it in the Page #117

Fabrication of doubly-curved CLT forms a structurally freestanding CLT staircase. Each CLT lamination
had to be form-fitted and glued into place on a custom jig. Photo courtesy StructureCraft.

Code Considerations
During a 2019 design charrette, the owner, Sawchuk and Vancouver-based code consultant GHL
joined to consider a hybrid building with two-hour fire separations between the hangars and the
building hub, which includes the museum and gallery area, but “settled on a mass timber project”
with two-hour separations between the hangars and the hub, Imthorn says. Lapointe was determined
to have a mass-timber project that sourced as much timber as possible locally within the province.

To achieve Lapoint’s vision of building a locally sourced project, Sawchuk was successful in
sourcing its wood from British Columbia, Imthorn says. In designing its four steel hangar doors,
two of which are 40 ft wide by 31 ft tall and two are 114 ft wide by 31 ft tall—a scale that Imthorn
claims has never been manufactured before—it chose Powerlift of Minneapolis.

Continued next page


PHONE: 800-289-5627 Read/Subscribe online at www.componentadvertiser.com FAX: 800-524-4982
A
Th e June 2022
Component Manufacturing Don’t Forget!
Adverti$$er
#14275
dverti$
dverti $ er You Saw it in the Page #118

Rendering of the 60,000-sq-ft KFA Center for Excellence, which expands its “wings” from a central fuselage-
shaped hub with conference rooms and offices. Photo courtesy StructureCraft.

Permitting and Approvals


Once building permits are in hand, it can take three months or more to receive approvals from
YLW, Navigation Canada and Transport Canada to allow for equipment mobilization, he says.
“Everything takes three times as long as the traditional project,” a result of an inherently challenging
regulatory environment aggravated by COVID-19, Imthorn says.

Setting up a crane can be an ordeal, he says. There is “an invisible surface around the airport
called the obstacle limitation surface (OLS),” he says. “You can’t have anything from the ground
penetrating that OLS: the air space around the airport that needs to be maintained free of obstacles,”
he says.

“We had to make sure our building sat underneath this OLS, and any time we had a crane set up,
we had to have prior approvals from NavCanada and Transport Canada since that would penetrate
the OLS,” he says. That required extensive planning since the pandemic made it more difficult to
reach officials. Permitting is currently finalized, with closing documentation required to “rubber
stamp” the close of construction for NavCan and Transport Canada, Imthorn says. “They need to
know the buildings are in now in the vicinity of their airspace … and we have to put a strobe light
on top of the building,” he says.

PHONE: 800-289-5627 Read/Subscribe online at www.componentadvertiser.com FAX: 800-524-4982