Professional Documents
Culture Documents
Method statement for Hydrostatic test
Method statement for Hydrostatic test
Method statement for Hydrostatic test
REVISION HISTORY
Plant Hassera
Project Natural Of Resource kurdistan 165mW GAS
Document Title Method statement for Hydrostatic test
Client/ Company
AGGREKO
CONTRACTOR
VOLTEC LTD
2. DEFINITIONS
PROJECT
Natural Of Resource kurdistan 165mW GAS
COMPANY AGGREKO
3. REFERENCE DOCUMENTS
4. RESOURCES
4.1. PERSONNEL
Work will be carried out by qualified personnel as below:
• Mechanical Engineers
• Mechanical Technician
• QC Engineers
• HSE Supervisor
• Labour’s
4.2. EQUIPMENT
In accordance to work requirements, the following machineries and equipment will be used
in general:
• Standard accessories (e.g. pressure gage, relief valve, hand valve, flange blind).
• Hand tools
• Compressed air.
• Water pump.
5. STATUS OF THE WORK
Piping Hydrostatic Test will be performed after:
- Completion and Release by QC of the piping section to be pressure tested.
- Review and Acceptance by Contractor of the test pack documentation for the piping section.
6. APPLICATIONS
The document is applicable for the new piping lines and not applicable for:
• Any package equipment previously tested by Manufacturer / Vendor.
• Piping open to the atmosphere, unless specified in the piping list.
• Instrument impulse lines between the block valve at the process or utility line and the connected
instrument.
• Equipment.
• Instrument components which shall be blinded-off or removed. (Analyzer, flow instruments, flow
meters, level gauges, level instruments, pressure gauges, pressure instruments, pressure
regulators, and pressure switches, relief valves, orifice plate, pressure relief valves, etc.)
• Temporary spades and blinds installed for testing purposes shall be of specified rating as
mentioned in the isometric drawing.
• Temporary piping, jumpers, vent valves, drain valves, spacers, test spades and blinds shall
be readily identifiable by painting colour. All temporary items shall be numbered on the
test diagrams and mentioned in the post test punch list for clearance after test
completion.
• Pressure tests shall not be conducted through control valves. All control valves and relief
valves may be removed or blinded off during pressure testing.
• Piping shall be tested prior to installation of in-line items such as rupture discs, displacement
and turbine meters, orifice plates, flow nozzles, level gauges, rota meter, strainers and
similar components. Instruments shall not be connected during piping pressure tests. If it
is not practicable to perform testing prior to installation of in line items, it shall be the
Contractor responsibility to remove or disconnect these items so that tests can be
performed, and to re-install such items after testing. Sealing and plugging of systems
after removal of inline items shall be performed for test and reinstated after testing.
• Check valves shall be removed unless otherwise agreed by Company.
• Expansion bellows and/or spring supports shall be restrained or removed during testing.
Each case shall be referred to Engineering.
• Care shall be taken to avoid overloading any part of the pipe support system or support
structures. Piping which is counterweight supported shall be temporarily blocked to
sustain the weight of the test medium. Spring hangers which have been provided with
stops for carrying the test load normally do not require additional temporary supports. If
this is not the case, temporary support shall be provided before filling the system. Holding
pins and spring stops shall not be removed from spring supports or hangers until testing
is completed and permission to remove the stops shall be obtained from Company.
• If piping designed for vapor or gas in service is proposed for hydro test then it shall be
provided with additional temporary supports to support the weight of the test liquid. The
requirement of temporary supports shall be specified in the isometric drawing attached to
the test pack.
• Large adjacent lines shall not be tested simultaneously if the weight of the combined tests
may overload the structure or supports.
• Equipment shall be isolated from pressure test. Test blinds shall be installed at the flanges
of equipment to provide positive isolation prior to filling the test circuit.
10. HSE
10.1. Safety
• The Test Supervisor shall co-ordinate with safety manager all test activities, and obtains his
agreement on all safety aspects.
• The Safety Manager or his designee shall at all times ensure that only essential personnel
are allowed into the designated Exclusion Zone. Personnel to be inducted shall be
identified prior to each test and their specific responsibility to areas shall be assigned.
These areas to be walked prior to test commencing to familiarise personnel involved in
the test.
• Personnel to have helmet identification issued during the pre-test tool box talk to ensure
only essential personnel are within test areas. Contractor shall ensure that the
Company’s and all Subcontractors whose operations border the Test Systems barriers
are fully aware of safety requirements.
• The Safety manager shall assign one-person full time to each road barrier. The person
assigned shall be in radio contact with Safety Manager and Test supervisor.
• The Safety manager shall ensure that adequate communication means is available so that
he can immediately be made aware of any dangerous situation at the Terminal or along
the test pipe system. The Test supervisor and safety Manager shall be in contact at all
times during testing.
• Leak detection shall not be carried out during periods of rain.
• The exclusion zone shall be positively identified by placing of clear warning sign at all
vehicular and pedestrian accesses. Provision for lighting shall be made to ensure the
exclusion zone is positively identified during the hours of darkness, if required. It shall be
ensured that non-essential personnel are clear of exclusion zones.
• The Regulator (Globe) Valve shall be able to control the flow into Test System within the
required pressurisation rates.
• Pressure Gauge Manifolds shall be hydrostatically tested after assembly to a test pressure
above the expected pressure test.
• Prior to commencement of any test the Contractor shall confirm that relief valves are
correctly set and operating properly and that pressure gauges and pressure recorders
have been correctly set, calibrated and are operating properly. The records shall be made
available to Company for verification.
10.3. General
1. Work is to be carried out in a safe manner and in accordance with the HSE Plan). Site
operatives shall be well inducted for the safe operation of the machineries, equipment &
tools to be used.
2. Personnel Protective Equipment’s will be used by all staff & labours. The minimum
personal protective equipment is as follows: a. Safety helmet
b. Safety footwear
c. Eye protection
d. Gloves
e. Overalls
f. Safety Harness
g. Any other equipment required by the site operator or deemed necessary by the task.
3. Before carrying out the field works, work permit will be obtained from authority, daily or as
per the regulation implemented. Internal Permits for all Hot works, old work, Electrical
works, Lifting activities. Confined Space work. Radiography, Night shift works will be
issued.
4. All regulation implemented by authority at site will be respected.
5. Proper barricades and traffic signs shall be placed around the work site location whenever
required.
6. Trained flagman to regulate the traffic passages of vehicles and machineries.
7. "Tool Box" talk or "Safety Talk" shall be conducted prior to the commencement of each
activity.
8. If weather will be dusty in some times during the work periods, then water will be sprayed
whenever required on dusty areas to prevent blowing and spread of dust.
.