Professional Documents
Culture Documents
6,05,000
6,05,000
92 MLD
NAME OF WORK :- Providing LWSS Jubble Kharian,Singwin,Nara & Darkoti etc. in Tehsil Barsar
Distt. Hamirpur (HP)
(S/H :- C/O WTP OF 1.92 MLD)
Design data :- The below mentioned design data has been considered for working out the
tentative sizes of different unit.
Material of construction :- = "M 20"
Design discharge :- = 1.920 MLD
Add 5%for wastage = 0.096 MLD
Total = 2.016 MLD
or = 2016.00 m3/day
or = 0.0233333 m3/sec.
or = 23.3333 LPS
Detention period of inlet chamber :- = 60.00 Seconds.
Detention period of inlet chamber :- = 1.50 Hours
Storage for raw water tank :- = 16.00 Hours
Detention period of pre-settling tank :- = 1.50 Hours
Surface loading rate :- = 35.00 m3/m2/day
Slope of hopper :- = 55.00 deg.to Horizontal
Free Board (F.B.) :- = 0.30 metre
Velocity of flow in mixing channel :- = 0.60 metre/sec.
Detention period of Flocculator :- = 30.00 Minutes.
Range = 10.00 to 40.00 min.
Velocity Gradient :- = 30.00 Per seconds.
Range = 10.00 to 75.00 per sec.
Value of G X T :- = 50000.00
Range = 40000.00 to 60000.00
Velocity of blades :- = 0.40 metre/sec.
Range = 0.20 to 0.60 per sec.
Detention period of Settling tank :- = 2.00 Hours
Surface loading rate :- = 35.00 m3/m2/day
Slope of hopper :- = 55.00 deg.to Horizontal
Rate of filteration (Rapid Sand Filters) :- = 80.00 LPM/m 2
Rate of back wash :- = 600.00 LPM/m2for7min for
proper back wash.
INLET DISCHARGE :-
Design discharge :- = 1.920 MLD
Add 5%for wastage = 0.096 MLD
Total = 2.016 MLD
or = 2016.00 m3/day
or = 0.023333 m3/sec.
or = 23.3333 LPS
INLET CHAMBER :- = 0.0233 m3/sec.
Detention period of inlet chamber = 60.00 Seconds.
Volume required = 1.40 m3
Assume depth of chamber = 1.00 Metre
Assuming square size,then one side = 1.18 Metre
Say = 1.20 Metre
Hence the size = "L" "B" "SWD" "F.B." Total depth
1.20 1.20 1.00 0.30 1.30 Metre.
PRE-SETTLING TANK :-
Design discharge :- = 0.023333 m3/sec.
Detention period of pre-settling tank = 1.50 Hours
Surface loading rate = 35.00 m3/m2/day
Slope of hopper = 55.00 deg.to Horizontal
Shape = Rectangular
Volume required = 126.00 m3
Surface area required = 57.60 m2 (i)
Hence depth required = 2.19 Metre
Say = 2.20 Mtr.above hopper
Ratio of length to width = 3.00 : 1.00
Assume width of tank = "B"
Therefore area of tank = 3 B2 (ii)
Equiting the values (i) & (ii) "B" = 6.48 Metre
Say"B"= 6.80 Metre
Therefore length of tank "L" = 20.40 Metre
Hence the size = "L" "B" "SWD" "F.B." Total depth
20.40 6.80 2.20 0.30 2.50 Metre.
with hopper bottom.
V - Notch :- A V - Notch will be provided for measurement of flow. The notch will be
made of non - corossive material such as brass.The approach channel shall be required width,
length & depth.
INLET STRUCTURE :-
Length of channel = 3.00 Metre
Design discharge :- = 0.023333 m3/sec.
Bed Slope = 1 : 100
Assume the size of channel = Rectangular
Assume depth of channel = "d"
Assume width of channel ("b") = "d"
Area of channel = dxd= d2
Wetted perimeter of channel("P") = 3d= 3d
Hydraulic mean depth ("R")=A/P = d 2/3d 0.3333 d
Velocity of flow = 0.30 metre/sec. (i)
Discharge (Q) = Area of channel x velocity (V)
Therefore velocity = Q/ A = 0.0233 /d2 (ii)
Equiting the values (i) & (ii) "d" = 0.28
Say"d"= 0.30 Metre
F.B. = 0.15 Metre
Total"d"= 0.45 Metre
Therefore width of channel ("B") = 0.28 Metre
Say"b"= 0.30 Metre
Hence the size = "b" "d"
0.30 0.45 Metre
Hence channel shall be provided with inlet ports in the beds having dia. 80
mm @ 300 mm centre to centre.
OUTLET STRUCTURE :-
Surface weir loading rate = 300.00 m3/m/day
Weir length required = 6.72 Metre
Say = 6.80 Metre
Hence provide outlet structure in the weir having total length as 6.80 Metre
MIXING CHANNEL :- A 3.00 mtr.mixing channel with attracting type diagonal baffle
(at an angle 45 Degrees) will be provided for mixing of alum with water. The velocity of flow
will be 0.60 metre/sec.
Length of channel = 3.00 Metre
Design discharge :- = 0.0233 m3/sec.
Bed Slope = 1 : 100
Assume the size of channel = Rectangular
Assume depth of channel = "d"
Assume width of channel ("b") = "d"
Area of channel = dxd= d2
Wetted perimeter of channel("P") = 3d= 3d
Hydraulic mean depth ("R")=A/P = d 2/3d 0.3333 d
Velocity of flow = 0.60 metre/sec. (i)
Discharge (Q) = Area of channel x velocity (V)
Therefore velocity = Q/ A = 0.023333 / d 2 (ii)
Equiting the values (i) & (ii) "d" = 0.20
Say"d"= 0.25 Metre
F.B. = 0.15 Metre
Total"d"= 0.40 Metre
Therefore width of channel ("B") = 0.20 Metre
Say"b"= 0.30 Metre
Hence the size = "b" "d"
0.30 0.40 Metre
Dimensions of paddles :-
Total power input to flocculator,P =G2m (Vol.)
= 48.45 Watts
or = 0.04 HP
Say = 0.50 HP
Power input = 0.50 x CD x p x Ap x (V - v )3 =
= 24.2271 A P
AP = 2.00 m3
Ratio of area of paddles to X - sectional area of flocculator
= 0.1989
or = 19.89 %
This is within the prescribed limits of 10 to 25 %.Hence.it is safe.
Provide 4.00 No's paddles each having size of 2.00 x 0.40
metre wide of 5.00 mm thickness.
Assume RPM of the assembly"n" = 5.00 RPM
Distance of paddles edge from centreline of shaft = 60 x v/2 x p x n
= 0.95 Metre
Say = 1.00 Metre
Assume the velocity of water below the partition wall between the flocculator & carifier be
0.30 mtr/min.Therefore area of opening required for a velocity 0.30 mtr/min.
below the partition wall will be
Area = Q (in m3/hour) /(v x 60) = 4.67 m2
Depth below partition wall = Area / ( p x side of flocculators)
= 0.39 metre
Provide 25 % addititional depth for the storage of sludge in case the mechanical scraper is
out of order.
Depth provided for sludge storage = 0.75 metre
Provide 8 % slope for the bottom.
Total depth of tank at the partition will assuming a free board of 0.30 metre.
= 4.44
Say = 4.50 Metre
SETTLING TANK :-
Design discharge :- = 0.0233 m3/sec.
Detention period of pre-settling tank = 2.00 Hours
Surface loading rate = 35.00 m3/m2/day
Slope of hopper = 55.00 deg.to Horizontal
Shape = Rectangular
Volume required = 168.00 m3
Surface area required = 57.60 m2 (i)
Hence depth required = 2.92 Metre
Say = 3.00 Mtr.above hopper
Ratio of length to width = 3.00 : 1.00
Assume width of tank = "B"
Therefore area of tank = 3 B2 (ii)
Equiting the values (i) & (ii) "B" = 7.48 Metre
Say"B"= 7.50 Metre
Therefore length of tank "L" = 22.50 Metre
Hence the size = "L" "B" "SWD" "F.B." Total depth
22.50 7.50 3.00 0.30 3.30 Metre.
with hopper bottom.
INLET STRUCTURE :-
Length of channel = 3.00 Metre
Design discharge :- = 0.0233 m3/sec.
Bed Slope = 1 : 100
Assume the size of channel = Rectangular
Assume depth of channel = "d"
Assume width of channel ("b") = "d"
Area of channel = dxd= d2
Wetted perimeter of channel("P") = 3d= 3d
Hydraulic mean depth ("R")=A/P = d 2/3d 0.3333 d
Velocity of flow = 0.30 metre/sec. (i)
Discharge (Q) = Area of channel x velocity (V)
Therefore velocity = Q/ A = 0.0233 /d 2
(ii)
Equiting the values (i) & (ii) "d" = 0.28
Say"d"= 0.30 Metre
F.B. = 0.15 Metre
Total"d"= 0.45 Metre
Therefore width of channel ("B") = 0.28 Metre
Say"b"= 0.30 Metre
Hence the size = "b" "d"
0.30 0.45 Metre
Hence the channel shall be provided with inlet ports in the beds having dia. 80 mm @
300 mm centre to centre.
OUTLET STRUCTURE :-
Surface weir loading rate = 300.00 m3/m/day
Weir length required = 6.72 Metre
Say = 7.50 Metre
Hence provide outlet structure in the weir having total length as 7.50 Metre
DESIGN OF CLARIFIER :-
Assume a surface overflow rate = 40.00 m3/m2/day
Surface area of clarifier = 50.40 m2
Dia.of clariflocculators,D cf is as under :-
= 10.97 Metre
Length of weir = p x D c f = 34.47 Metre
Weir Loading =Q(in m3/hour x 24)/length of weir = 58.48 m3/m/day
(which is < than 300.00 m3/m/day
FILTERING MEDIA :-
Water depth over media = 1.50 Metre
Total depth of filter = 2.55 Metre
The thickness of various layers as per IS : 8419 (Part -I) 1977
Bottom layer 65 mm to 38 mm size gravel = 0.15 Metre thick.
Second layer 38 mm to 20 mm size gravel = 0.15 Metre thick.
Third layers 20 mm to 12 mm size gravel = 0.09 Metre thick.
Fourth layers 12 mm to 6 mm size gravel = 0.06 Metre thick.
Coursed sand layers = 0.60 Metre thick.
Total = 1.05 Mtr thick.
Specification of course sand shall be as under :-
Uniformity co - efficient = 13 to 17
Effective size = .045 to 0.70 mm
Silica content = 90.00 %
WASH WATER LIFTING PUMPS :- 2 No's wash water pumping sets will be provided
to lift water clear water tank to back wash water tank including all allied accessories such as
panel board,starters,cables,other electrical devices & sluice valves.The pumps will housed in a
pump house of plan 12.00 m2 as per requirement.
No's of pump sets = 2.00 No's(1 working & 1
standby)
Rate of pumping = 42.00 m3/hour
Head ( assumed) = 25.00 Metre
BHP Required = 6.48 HP
Say = 7.50 HP
Type of pump = Electrical driven centrifugal type
BYE PASS ARRANGEMENT:- Proper bye pass & scour arrangrment will be provided to bye
pass each unit with MS/GMS flanged pipes with proper control valves.
FENCING :- The barbed wire fencing & compound gate will be as per the requirement.
SITE DEVELOPMENT & RETAINING WALLS :- The site should be developed within
the battery limit of plant.The retaining walls/breast walls will be contructed wherever required.
The retaining walls will be of RCC or in plum concrete 1:3:6 as per the detailed design.
ELECTRICAL ITEMS :- Proper lighting arrangement ai all the buildings i/c filter house
& pump house & includes wiring,switches,light points,sockets & MCB's. In addition, 4 no's 500
watts flood lights fixed at suitable height & locations shall be provided to light up the area of
water treatment plant.
MECHANICAL ITEMS & PIPING ETC :- All the mechanical items such as sluice valves
etc.will be ISI marked & pipes should be flanged with suitable table.
ABSRACT OF COST
NAME OF WORK :- Providing LWSS Jubble Kharian,Singwin,Nara & Darkoti etc. in Tehsil Barsar
Distt. Hamirpur (HP)
(S/H :- C/O WTP OF 1.92 MLD
S.No. DESCRIPTION OF ITEM QTY. RATE UNIT AMOUNT
1) The scope of work includes the C/O
1.92 MLD Capacity WTP capa-
ble to treat the raw water of the qua-
lity specified in the basic design data
to produce clear water as per the re-
quirement of CPHEEO manual on WS
& treatment.The WTP shall be inclu-
de the C/O Raw water tank,inlet cha-
mber,V - Notch,mixing channel,Para-
shall flume,pre-settling tank,flocculat-
or,alum solution/mixing tanks & dosi-
ng arrangements,Settling tank,Rapid
sand filter complete with back wash
water arrangement,Clear warer tank,
compete disinfection arrangement with
bleaching powder,plant building ( for
chemical store cum dosing room,wat-
er testing laboratory cum attendent
room & toilet),supply of laboratory
equipement,piping,valves,mechanical/
electrical equipement,electric wiring &
panel board,sanitation,interconnecting
paths,site deveopment upto a min.
of 3.00 mtr.from edge of battery limit
og plant,retaining & breast walls and
fencing.
ABSRACT OF COST
NAME OF WORK :- Providing LWSS Jubble Kharian,Singwin,Nara & Darkoti etc. in Tehsil Barsar
Distt. Hamirpur (HP)
(S/Head :- C/O OHSR 111400 Ltr.with 20 Mtr.staging height)
S.No. DESCRIPTION OF ITEM QTY. RATE UNIT AMOUNT
1) Consruction of RCC sector storage
over tank 111400 litres capacity
with 20 metres staging heights from
G.L.to bottom of the dome slab/ ring
beam comprising of Inlet,Outlet,Scour
& Over flow MS/GMS tubes as per the
relevants codes from G.L.to tank i/c
bends,valves of required sizes confor-
ming to relevants IS codes,MS clamps,
Spiral RCC stair cases of suitable width
with 32 mm GMS tubes railing as per
specifications,Steel ladders of 0.45 mtr.
wide usual heights as per site require-
ment for outer & inner side,MH Cover
i/c frame (Medium duty) of 500 mm
dia. & the weight of the same should
not be less than 116 Kg,ventilated
pipe,Water level indicator of float and
scale type,lightening conductor with
earthing arrangement i/c rendering/
plastering of the uneven exposed
surface inclussive of two coats of sno-
wcem paint & any other component
required for the completion of the job
into the entire satisfacton of the Eng-
inner-in-charge.The proper walkways
of suitable width should be provided
at bottom dome around the tank for
working space i/c railing complete.The
tank be based on raft foundation by
taking seismic forces & also include the
expansion joints & puddle collars.
Weight of chemicals per unit volume
% age of Alum Soda ash Cal.chloride
solution (Al2SO4)3 (Na2 CO2) (Ca2 Cl2)
gm/ltr. gm/ltr. gm/ltr.
1 10.09 10.09 10.06
2 20.39 20.38 20.30
4 41.62 41.59 41.26
6 63.71 63.64 62.92
8 86.70 86.53 85.27
10 110.60 110.30 108.40
12 135.50 134.90 132.20
14 161.40 160.50 156.80
16 188.30 0.00 182.20
Name of work: CONSTRUCTION OF LWSS AMB TOWN IN TEHSIL AMB, DISTT. UNA (HP)(UNDER AMRUT 2.0)
(SH C/O RCC COLLECTION TANK OF 605000 LTRS. CAPACITY AT NODE No. A
Input Data:-
Capacity of tank 605000.00 Lts.
Or = Volume of tank = 605.00 Cum.
Depth of tank (Assumed) i/c 0.20 mtr.as scour depth "H" = 4.50 Mts.
Area of the base of tank = Volume/Depth "A" = 140.70 Sqmt.
Let 'D' be the internal diameter of tank
Let 'D' be the internal diameter of tank "D" = ( Area x 4/ p ) 1/2
13.38 Mts.
Say 13.40 Mts.
Design constants for grade conc. " M - 30 " Tensile Strength
scbc = 10.00 10.00 10.00 1.50 N/mm2
sst = 230.00 130.00 130.00
m = 9.33 9.33 9.33
k = 0.289 0.418 0.418
j = 0.904 0.861 0.861
R = 1.304 1.798 1.798
H 2/Dt 6.00
The value of hoop tension = 0.6430 at 0.70 H
The value of Bending Moment = 0.0187 at 1.00 H
The value of Shear Force (V) = 0.2130
Tor steel (HYSD-415) Grade Direct Bending
S.No. Dia. of bar Weight Area(Af) ( in N/mm )2
( in N/mm2 )
in mm in kg in mm 2
M:15 1.10 1.50
1) 6 0.222 28.27 M:20 1.20 1.70
2) 8 0.395 50.27 M:25 1.30 1.80
3) 10 0.617 78.54 M:30 1.50 2.00
4) 12 0.889 113.10 M:35 1.60
5) 16 1.580 201.06 M:40 1.70
6) 20 2.469 314.16 Grade Modular Shear
7) 22 2.988 380.13 ratio(m) stress
8) 24 3.556 452.39 M:15 19.00 1.50
9) 28 4.840 615.75 M:20 13.00 1.70
M:25 11.00 1.90
M:30 9.00 2.20
Stress
Wall Thick. M.S.bar HYSD bar Remarks
<225 mm 115 150 Near face of members in contact
with liquid or away/other face
>225 mm 125 190 On face away from liquid
Capacity of Storage tank 605000 Lts.
Volume of the tank = 605.00 Cum.
Depth of tank (Assumed) i/c 0.20 mtr.as scour depth "H" = 4.50 Mts.
Free Board (Assumed) F.B. = 0.30 Mts.
Total ht.i/c F.B. 4.80 Mts.
Area of the base of tank = Volume/Depth "A" = 140.70 Sqmt.
Let 'D' be the internal diameter of tank "D" = (Area x 4/p) 0.50
= 13.38 Mts.
Say 13.40 Mts.
"h" = 1.10 Or 1.50 Mtr.
Hence"h"is taken,whichever is more = 1.50 Mts.
Approximate thickness of wall is given by the formula :-
t = 30 x H + 50 or 150 mm, whichever is more. "t" = 185.00 mm
Say 200.00 mm
150.00 or 200.00 Adopt (Wall Thickness) at bottom = 270.00 mm
Refer IS:3370 (Part IV) Ratio (H 2/D x t) = 5.60
Adopt for design purposes = 6.00
Keeping in view of ratio,the maximum value of coefficient of hoop tension =
0.6970 which occur at depth of 0.70 x H = 3.15 mts.from top.
Therefore Max.hoop tension"T"= (Co-efficient) x w x H x D/2 = 210.15 kN
Refer IS:3370 (Part IV)
Keeping in view of ratio,the maximum value of coefficient of bending moment =
0.0146 which occur at depth of 1.00 x H = 3.75 mts.from top.
(The minus sign indicate tension on the inner face.)
Therefore Max.B. M. = (Co-efficient) x w x H3) KN-m 13.30 kN - m
Refer IS:3370 (Part IV)
Keeping in view of ratio,the max. value of coefficient of shear force = 0.2130
Therefore Shear force ( S.F.) = ( Coefficient ) x w x h2 in K N 43.13 kN
( acting inward)
Design of wall thickness:-
Design constants for "M-30" grade concrete.
scbc = 10.00 N/mm 2 m = 9.33 j = 0.861
sst = 230.00 N/mm 2 k = 0.289 R = 1.304
scbc = 10.00 N/mm 2 m = 9.33 j = 0.861
sst = 130.00 N/mm 2
k = 0.418 R = 1.798
scbc = 10.00 N/mm 2 m = 9.33 j = 0.861
sst = 130.00 N/mm 2
k = 0.418 R = 1.798
NOTE :-The outside soil ( H soil ) is assumed = 1.50 Mts.below ground level
PRESSURE OF SATURATED SOIL ACTING FROM OUTSIDE & NO WATER PRESSURE FROM INSIDE :-
Let the wt. of soil = 17.00 KN/m 3 or 17000.00 N/m3
Wt.of water = 10.00 KN/m 3
or 10000.00 N/m3
Angle of Repose f = 30.00 Degrees
Then, Ka = (1-sinf)/(1+sinf) = 1/3 or 0.3333
Then , p =10000 x H soil + ( 17000 -10000 ) x H soil x 1/3 18500.00 N/m 2
or = 18.50 KN/m 2
Check for bending :- ((Maximum BM x 106 x 6 / (1000 x Bottom wall width 2))
= 0.1825 N/mm2
which is < than 2.00 N/mm2 (safe)
As per IS:3370-2009, Part-2, Table-1
Check for shear :- Maximum shear force = 43.13 KN
Shear stress = ((Max.shear stress/(1000 x bottom wall width)) = 0.1598 N/mm2
which is < than 2.20 N/mm (safe)
2
Distribution reinforcement:-
Percentage of distribution bars = 0.3 - 0.10 (Wall Thick. - 100)/350 0.2514 %
Area of reinforcement (A.O.R.) = % age x wall thick.x1000/100 678.86 mm 2
reinforcement provided for cantilever action will serve the function of distribution bars and no
Say 593.00 mm 2
Say 180.00 mm 2
A f x 1000 / A st 218.63 mm
Sv =2.50 x Asv x fy/b 209.52 mm
218.63 or 209.52 Adopt Minimum Spacing = 209.52 mm
Say 150.00 mm
Provide 8 mm dia.Bar @ 150 mm c/c .
Design of base slab:-
Assumed thickness of base slab 4500 / 10 = 450 +2*cover
450 + 60 = 510 mm
Weight of water per m2 of slab = 4.5 1x1x 10000 45000 N
Self weight of slab 0.51 1x1x 25000 12750 N
Total weight 57750 N
Circumferential moment: (MF)c = +1.pa2/16 = 24182.8125 N-m
(MF)e = 0
Radial moment: (Mr)c =+1.pa²/16 = 24182.8125 N-m
(Mr)e=-2.pa²/16 = -48365.625 N-m
Shear force: Fr = 1pa/2 = 193462.5 N
The radial moment is Zero at radius given by
Mr = 0 = 1p(a3 - 3x r2)/16 ≈ r=a/√3
r = 3.868 m
(i.e. distance of point of contraflexures 2.832 m form edge)
D= √((Mr)cx1000/1000xR)
164.00 mm
using 12 mmf bars total thickness required=d + cover + f / 2
200.00 mm
Say 520 mm
Available d 484 mm