Professional Documents
Culture Documents
Final Schedule -June 24
Final Schedule -June 24
G- General shift - 8.00 to 17.00 Hrs, D- Day shift 07.00 to 19.00, N- Night shift 19.00 to 07.00,PH-Public Holiday
WP-QFZ-RBF-OM-SC-014/24 - REV 00
WABAG PWMT JOINT VENTURE
OPERATION & MAINTENANCE OF WET UTILITIES AT QFZ
NIRMAL
5 QA117 KATHIRAVAN OPERATOR N N N OFF G G G N N N OFF G G N N N PH PH N OFF G G G N N N OFF G G G
G- General shift - 8.00 to 17.00 Hrs, D- Day shift 07.00 to 19.00, N- Night shift 19.00 to 07.00,PH-Public Holiday
WP-QFZ-RBF-OM-SC-014/24 - REV 00