PROJECT: RPCL- 100MW SOLAR POWER PLANT

Madarganj - Jamalpur - Bangladesh.

REPORT DATE : 03.05.24 SAND DREDGING WEEKLY PROGRESS REPORT (By Joint Survey) JOINT SURVEY DATE : 04-05-2024

CUMMULATIVE
CALCULATED
SSEGMENT RUNNING POST FILLING FILLING QTY.
SEGMENT DYKE AREA CUMMULATIVE
SCOPE SURVEY PRE RL RL HEIGHT (CUM)
NO NO (SQM) VOLUME
QTY. (CUM) PART (M)
(CUM) As on Date :
04-05-2024
Dyke-5 Part-1 25557.300 13.226 15.581 2.355 60187.442
Part-1 13611.852 14.100 17.390 3.290 44782.993
Dyke-6
Part -2 8525.236 13.498 15.110 1.612 13742.680
Part-1 14574.032 14.243 17.202 2.959 43124.561
Dyke-7
Part-2 14815.587 14.448 16.498 2.050 30371.953
Part-1 29886.000 14.490 17.390 2.900 86669.400
SEG - 1 1020628 Dyke-1 425,103
Part-2 2825.303 14.136 17.390 3.254 9193.536
part-1 16040.521 14.477 16.708 2.231 35786.402
Dyke-4
part-2 5018.041 14.198 17.390 3.192 16017.587
Dyke-2 18449.205 14.517 17.216 2.699 49794.404
Dyke-8 Part-1 6185.845 14.775 17.390 2.615 16175.985
Dyke-3 11022.636 14.215 15.962 1.747 19256.545

Part-1 21963.54 14.724 17.095 2.371 52075.553


SEG - 3 1045699 Part-2 9034.48 13.133 15.050 1.917 17319.096 123,110
Part-3 26565.35 13.800 15.822 2.022 53715.128
Part-4 26853.57 13.654 15.749 2.095 56258.221

Part-1 6811.01 13.085 14.200 1.115 7594.276


Part-2 5495.50 12.949 14.705 1.756 9650.098
Part-3 6590.64 13.450 15.092 1.642 10821.831
Part-4 4468.34 13.228 14.990 1.762 7873.213
SEG - 2 1040593 Part-5 7471.65 13.614 15.289 1.675 12515.005 86,154
Part-6 7508.75 13.701 15.185 1.484 11142.991
Part-7 7450.10 14.363 15.389 1.026 7643.800
Part-8 9185.46 13.223 15.282 2.059 18912.862

SEG - 4 609353 0

TOTAL TOTAL OVERALL QUANTITY IN PROGRESS (CUM) = 634,367


SCOPE 3716273
QTY PER DAY AVEREGE PROGRESS (CUM) & PERCENTAGE (%) =

M/S. Shamim Enterprise (Pvt.) Rural Power


Amara Raja Infra Private Limited.
Agency Ltd. Company Ltd. /
(Surveyor)
(Surveyor) AFRY
Name

Signature