PROJECT: RPCL- 100MW SOLAR POWER PLANT

Madarganj - Jamalpur - Bangladesh.


REPORT DATE : 10-Jun-24 SAND DREDGING WEEKLY PROGRESS REPORT (By Joint Survey) JOINT SURVEY DATE : 08 & 09-06-2024
CUMMULATIVE PERCENTAGE PREVIOUS PROGRESS OF=
CALCULATED FILLING QTY. OF OVERALL CUMMULATIVE LAST - 7 DAY'S
SSEGMENT RUNNING TOP SOIL POST FILLING PERCENTAGE
SEGMENT DYKE AREA TOPO CUMMULATIVE (CUM) PROGRESS QTY. (CUM) (CUM)
SCOPE SURVEY CUTTING RL HEIGHT OF WEEKLY
NO NO (SQM) RL VOLUME
QTY. (CUM) PART (-400mm) (M) PROGRESS
(CUM) On Dated : From 01 & 02-05-2024
As on Date : 08 & 09-06-2024
01 & 02-05-2024 To 08 & 09-06-2024
Part-1 25557.300 14.042 13.642 15.847 2.205 56353.847
Dyke-5
Part-2 4992.648 13.608 13.208 14.482 1.274 6358.375
Part-1 13611.852 14.621 14.221 17.390 3.169 43139.611
Dyke-6
Part-2 9640.481 14.608 14.208 15.428 1.220 11761.881
Part-1 14574.032 14.734 14.334 17.202 2.868 41799.002
Dyke-7
Part-2 14815.587 14.977 14.577 16.991 2.414 35759.183
SEG - 1 1006496 Dyke-1
Part-1 29886.595 14.883 14.483 17.390 2.907 86884.601 432,614 42.39% 395,473 37,141 3.69%
Part-2 2825.303 15.112 14.712 17.390 2.678 7565.534
Part-1 19653.678 14.902 14.502 16.706 2.204 43314.803
Dyke-4
Part-2 5018.041 14.819 14.419 17.390 2.971 14906.719
Dyke-2 18449.205 15.130 14.730 17.216 2.486 45868.341
Dyke-8 Part-1 6185.845 15.175 14.775 17.390 2.615 16175.985
Dyke-3 11022.636 14.722 14.322 16.384 2.062 22725.831

Part-1 21963.543 14.759 14.359 17.095 2.736 60102.237


Part-2 9034.479 14.733 14.333 15.050 0.718 6482.239
Part-3 26565.345 14.563 14.163 16.444 2.281 60598.247
SEG - 3 1092620 Part-4 30776.819 14.806 14.406 15.729 1.323 40703.469 192,952 18.45% 146,711 46,241 4.23%
Part-5 10806.488 14.719 14.319 16.129 1.810 19559.743
Part-6 3747.277 14.888 14.488 15.957 1.469 5505.583

Part-1 10586.831 14.332 13.932 14.287 0.355 3761.854


Part-2 5808.414 13.977 13.577 15.072 1.495 8681.995
Part-3 6590.644 14.030 13.630 15.502 1.872 12337.686
Part-4 4468.339 14.043 13.643 14.990 1.347 6017.363
SEG - 2 1165010 Part-5 7471.645 13.965 13.565 15.678 2.113 15785.251 91,550 8.80% 77,440 14,110 1.21%
Part-6 7508.754 13.862 13.462 15.442 1.980 14866.891
Part-7 7450.097 14.150 13.750 15.678 1.928 14363.787
Part-8 9185.461 13.969 13.569 15.282 1.713 15735.351

SEG - 4 547914 0 0.00% 0 0 0.00%

TOTAL TOTAL OVERALL QUANTITY IN PROGRESS (CUM) = 717,115 19.30% 619,624 97,491 2.56%
SCOPE 3812040
QTY PER DAY AVEREGE PROGRESS (CUM) & PERCENTAGE (%) = 13,927 0.37%