PROJECT: RPCL- 100MW SOLAR POWER PLANT

Madarganj - Jamalpur - Bangladesh.

REPORT DATE : 10.06.24 SAND DREDGING WEEKLY PROGRESS REPORT (By Joint Survey)

CUMMULATIVE
CALCULATED
SSEGMENT RUNNING POST FILLING FILLING QTY.
SEGMENT DYKE AREA CUMMULATIVE
SCOPE SURVEY PRE RL RL HEIGHT (CUM)
NO NO (SQM) VOLUME
QTY. (CUM) PART (M)
(CUM) As on Date :
09-06-2024
Part-1 25557.300 13.226 15.847 2.621 69251.009
Dyke-5
Part -2 4992.648 13.063 14.482 1.419 7084.568
Part-1 13611.852 14.100 17.390 3.290 44782.993
Dyke-6
Part -2 9640.481 13.498 15.428 1.930 18606.128
Part-1 14574.032 14.243 17.202 2.959 43124.561
Dyke-7
Part-2 14815.587 14.448 16.991 2.543 37676.037
SEG - 1 1020628 Part-1 29886.595 14.490 17.390 2.900 86671.126 466,094
Dyke-1
Part-2 2825.303 14.136 17.390 3.254 9193.536
part-1 19653.678 14.477 16.706 2.229 43808.047
Dyke-4
part-2 5018.041 14.198 17.390 3.192 16017.588
Dyke-2 18449.205 14.517 17.216 2.699 49794.404
Dyke-8 Part-1 6185.845 14.775 17.390 2.615 16175.985
Dyke-3 11022.636 14.215 16.384 2.169 23908.097

Part-1 21963.543 14.724 17.095 2.371 52075.560


Part-2 9034.479 13.133 15.050 1.917 17319.096
Part-3 26565.345 13.800 16.444 2.644 70238.772
SEG - 3 1045699 237,623
Part-4 30776.819 13.654 15.729 2.075 63861.899
Part-5 10806.488 13.342 16.129 2.787 30117.682
Part-6 3747.277 14.887 15.957 1.070 4009.587

Part-1 10586.831 13.085 14.287 1.202 12725.371


Part-2 5808.414 12.949 15.072 2.123 12331.263
Part-3 6590.644 13.450 15.502 2.052 13524.001
Part-4 4468.339 13.228 14.990 1.762 7873.213
SEG - 2 1040593 103,658
Part-5 7471.645 13.614 15.678 2.064 15421.475
Part-6 7508.754 13.701 15.442 1.741 13072.741
Part-7 7450.097 14.363 15.678 1.315 9796.878
Part-8 9185.461 13.223 15.282 2.059 18912.864

SEG - 4 609353 0

TOTAL
SCOPE 3716273 TOTAL OVERALL QUANTITY IN PROGRESS (CUM) = 807,374