Professional Documents
Culture Documents
414 Column procedure
414 Column procedure
PE-0414-RP-01
METHOD OF STATEMENT
Rev. No. 0
FOR
COLUMN SHELL REPLACEMENT
QA/QC DATE: 15th Oct 2019
1.0 PURPOSE:
This procedure describes the method of statement for rectification work with detailed activities to
be followed to shell replacement along with nozzle, tray support, internal & external attachments.
Page 1 of 3
ZPEC DOCUMENT No. PE-0414-RP-01
METHOD OF STATEMENT
Rev. No. 0
FOR
COLUMN SHELL REPLACEMENT
QA/QC DATE: 15th Oct 2019
7. After cutting the shell carryout bevel preparation as per the sketch shown in weld map, the
cut section shall be completely free from HAZ formed during oxy-acetylene cutting.
4.2 Fabrication of New Shell Segments (Column # 110-C-06; 110-C-09 & 110-C-11)
1. Identify the Equipment Tag No. (Column Tag No. 110-C—6; 110-C-9; 110-C-11) applicable for
each component
2. After clearance of receiving inspection, carryout material traceability and record the details in
traceability report for all pressure retaining components
3. Upon completion of material inspection, perform fitup as per drawing# and
welding of long seam, cir-seam and nozzle welds as per approved weld book no. PED-0414P
(Weld map shall be prepared and submitted as built after full column assessment)
4. Carry out Following NDE as minimum
5. Up on completion of All NDE and inspection from all parties, the shell segment shall be heat
treated as per approved heat treatment procedure# ZPEC-414-HT
6. After completion of PWHT repeat all NDE as same as before PWHT, additionally hardness shall
be ensured as per ZPEC-414-HM
4.3 Assembly of New Shell Segments with Column(Column # 110-C-06; 110-C-09 & 110-C-11)
1. After inspection completion by all party, the newly fabricated segment shall be fitup with old
column.
2. Care shall be take while performing fitup the heat treated area shall not be subject to any kind
of welding or heating.
3. Upon fitup completion (Closing joints # ), verify the column for water level, straightness
(verticality) and other dimension from previously marked reference line.
4. After successful inspection from all party, closing joint shall be welded as per approved WPS &
Weld map.
5. On completion, perform VT, MT, UT & RT of closing joints as applicable.
6. Where minor damage observed less than T/3 and not exceeding 100 Sq. mm in size shall be
welded/ repaired and MT/UT to be performed. Such spots shall be welded using WPS (without
PWHT) (Except newly fabricated shell segments)
7. Perform final visual and dimensional inspection of complete column for its suitability.
Page 2 of 3
ZPEC DOCUMENT No. PE-0414-RP-01
METHOD OF STATEMENT
Rev. No. 0
FOR
COLUMN SHELL REPLACEMENT
QA/QC DATE: 15th Oct 2019
1. After complete verification of documents and equipment’s, equipment shall be certified with R-
form as per the latest design condition for which hydrostatic examination carried out.
Records
1. Thickness mapping report
2. MPI report for all pressure retaining joints
3. RT report for newly welded category A, B & C joints
4. UT report for newly welded category A, B, C & D joints
5. Shop Hydrostatic report
6. Painting report
7. Traceability records for newly welded Pressure items
8. Alignment Verification & Dimensional report
9. Visual inspection report for complete column
10. Signed R2 Form for Alteration.
Page 3 of 3