CHAPTER - 4

EARTH WORK AND EXCAVATION


SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Taken = 28.32 Cum


251 Excavatiopn in foundation in ordinary soil ( Loam clay ,sand ) includdding filling lift up to 1.5 m and lead up to
30 m & including filling ,watering and ramming of excavated earth into the trenches or into the space between
the building and the side offoundation trenches or plinth and removal and disposal of surplus earth as directed
by the Engineer - in - charge upto a distance of 30 m from the foundation trenches.

Taken = 28.32 Cum


Mistri Per day 0.125 no. Rs 210.00 Rs 26.25
Beldar Per day 6.00 no. Rs 110.00 Rs 660.00
Coolie Per day 7.00 no. Rs 110.00 Rs 770.00
Blacksmith for sharpening Tools etc. Per day 0.13 no. Rs 200.00 Rs 25.00

T & P and Basket etc. L.S. Rs 25.4


Total Rs 1506.63
Contractor s profit @ 10% Rs 150.66
Rate for 28.32 Cum Rs 1657.29
Rate for 1.00 Cum Rs 58.52
Say Rs 58.50 Per Cum
252 As in above item no. 251 but excavation in soil mixed with mooram/single/kankar requiring the use of special T
& P such as pickaxes,subbals etc.
Bhisti Per day 0.125 no. Rs 130.00 Rs 16.25
Beldar Per day 8.00 no. Rs 110.00 Rs 880.00
Coolie Per day 7.00 no. Rs 110.00 Rs 770.00
Blacksmith for sharpening Tools etc. Per day 0.17 no. Rs 200.00 Rs 33.33
T & P and Basket etc. L.S. Rs 50.8
Total Rs 1750.35
Contractor s profit @ 10% Rs 175.04
Rate for 28.32 Cum Rs 1925.39
Rate for 1.00 Cum Rs 67.99
Say Rs 68.00 Per Cum
253 Earthwork in cutting or in embankmentin ordinary soil , excavation to be in the form or regular pits not
exceeding 0.50m in depth and earthwork in embankment to be in 20 cm layers, including ramming & dressing
the surface to required levels and slopes and also including lift up to 1.5 m and lead up to 30 m. The earth
cutting to be used in making embankment or to be deposited as spoil banks within 30m distance as directed
by the Engineer - in - charge.
Mate Per day 0.100 no. Rs 130.00 Rs 13.00
Beldar Per day 2.00 no. Rs 110.00 Rs 220.00
Coolie Per day 3.00 no. Rs 110.00 Rs 330.00
Blacksmith for sharpening Tools etc. Per day 0.13 no. Rs 200.00 Rs 25.00
Dressing Beldar Per day 0.13 no. Rs 110.00 Rs 13.75
T & P and Basket etc. L.S. Rs 13.5
Coolie Per day 6.00 no. Rs 110.00 Rs 660.00
Total Rs 1275.29
Contractor s profit @ 10% Rs 127.53
Rate for 28.32 Cum Rs 1402.82
Rate for 1.00 Cum Rs 49.53
Say Rs 49.50 Per Cum

Contd ...........
EARTH WORK AND EXCAVATION
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

254 Add to items 251-253 for every additional 30 m lead or part of 30 m. or for for every additional 1.50 m.lift or
part of 1.50 m.
Coolies Per day 2.00 no. Rs 110.00 Rs 220.00
T&P L.S. Rs 6.77
Total Rs 226.77
Contractor s profit @ 10% Rs 22.68
Rate for 28.32 Cum Rs 249.45
Rate for 1.00 Cum Rs 8.81
Say Rs 8.80 Per Cum
255 Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8 km. From
the site of work and including watering, dressing etc. Rate to include cost of all material, labor and T & P etc.
required for proper completion of the work.
Material - 28.03 Cum
Local sand Per cum 28.030 no. Rs 275.00 Rs 7708.25
Labour
Beldar Per day 3.00 no. Rs 110.00 Rs 330.00
Coolie Per day 5.00 no. Rs 110.00 Rs 550.00
Bhisti Per day 0.75 no. Rs 130.00 Rs 97.50
T&P L.S. Rs 16.92
Total Rs 994.42
Contractor s profit @ 10% Rs 99.44
Rs 1093.86
Rate for 28.32 Cum Rs 8802.11
Rate for 1.00 Cum Rs 310.81
Say Rs 310.80 Per Cum
256 Same as item no 251 above but excavation in soil mixed with gravel amd boulder. { Skelton analysis based
on hill schedule of rate P.W.D. sl.no. 157 }
Mistri Per day 0.125 no. Rs 210.00 Rs 26.25
Beldar Per day 10.00 no. Rs 110.00 Rs 1100.00
Coolie Per day 7.00 no. Rs 110.00 Rs 770.00
Blacksmith for sharpening Tools etc. Per day 0.25 no. Rs 200.00 Rs 50.00
T & P and Basket etc. L.S. Rs 50.8
Total Rs 1997.02
Contractor s profit @ 10% Rs 199.7
Rate for 28.32 Cum Rs 2196.72
Rate for 1.00 Cum Rs 77.57
Say Rs 77.60 Per Cum
257 As in item 251 above but excavation in black cotton soil in Bundelkhand area requiring use of special tools
and plant such as pick axes sabbal etc.
Mistri Per day 0.125 no. Rs 210.00 Rs 26.25
Beldar Per day 8.00 no. Rs 110.00 Rs 880.00
Coolie Per day 6.00 no. Rs 110.00 Rs 660.00
Blacksmith for sharpening Tools etc. Per day 0.17 no. Rs 200.00 Rs 33.33
T & P and Basket etc. L.S. Rs 50.8

Contd ...........
EARTH WORK AND EXCAVATION
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Total Rs 1650.35
Contractor s profit @ 10% Rs 165.04
Rate for 28.32 Cum Rs 1815.39
Rate for 1.00 Cum Rs 64.10
Say Rs 64.10 Per Cum
258 Extra rate for quantity of work excuted under
(a) In or Under water and or Liquid mud 20 % above as in CPWD schedule 1962

(a) In or Under Foul position 25 % above as in CPWD schedule 1962


Note :- The extra in rate is applicable in respect of each item but to limited quantities of work
excavated in these difficult conditions.

259 Clearing jungle including uprooting of rank vegetations grass, bush, wood trees and sapling of grith up to 30
cm measured at a height of 1.00 m above ground level & removal of rubbish up to a distance of 50 m. out side
the periphery of area cleared.
( Analysis of rates on the basis of item 41 of C P W D analysis
of 1955 schedule)
Take 92.9 Sqm
Labour
Beldar Per day 1.00 no. Rs 120.00 Rs 120.00
Coolie Per day 0.50 no. Rs 110.00 Rs 55.00
T & P and Basket etc. L.S. Rs 36.9
Total Rs 211.92
Contractor s profit @ 10% Rs 21.19
Rs 233.11
Rate for 92.9 sqm. Rs 233.11

Rate for 1.00 sqm Rs 2.51


Say Rs 2.50 Per Sqm

Contd ...........
CHAPER-2
LABOUR
S.No. Description Unit Rates

1 Hot Beldar/ Skilled Beldar Per day 120.00


2 Beldar Skiled/ Bandhani Per day 110.00
3 Beldar ( Unskiled) Granolithic cutter Per day 110.00
4 Coolie Per day 110.00
5 Chaukidar Per day 110.00
6 Mate/ Per day 130.00
7 Black smith Per day 200.00
8 Mistri Per day 210.00
9 Mason ( Masonary will upto 2 brick thickness Per day 200.00
Foundation Conc.) Grade 1

10 Mason ( Masonary Exceeding 2 brick thickness Per day 190.00


Foundation Conc.) Grade 2

11 Carpenter Per day 230.00


12 Carpenter II Per day 210.00
13 Fitter Grade 1 Per day 160.00
14 Fitter Grade 2 Per day 150.00
15 Plumber/Electriciad( Licenced with kit) Grade 1 Per day 200.00

16 Plumber/Electriciad( Licenced with kit) Grade 2 Per day 180.00

17 Painter( Distemper emulsion paints sandex ,att Per day 180.00


lettring work) Grade 1
18 Painter( Normal painting work) Grade 2 Per day 160.00

19 White washerman Per day 140.00


20 Rivetter Per day 210.00
21 Welder Per day 200.00
22 Hammer man Per day 110.00
23 Glazer Per day 180.00
24 Stone Cutter Per day 200.00
25 Rock hole Driller Per day 190.00
26 Rock excavator Per day 130.00
27 Rock Breaker Per day 130.00
28 Amin / Tracer Per day 170.00
29 Jeep / Truck / Tractor / Roller Driver Per day 140.00
30 Driver Pump Oprator / C.C.Mix / Mixaul Oprator / Per day 140.00
Generator Oprator
31 Computer Oprator Per day 200.00
32 Farrash Per day 110.00
33 Two Donkys with Driver Per day
34 Buggi with one Driver & Bhainsa Per day
35 Bullock Cart with two Bullock & Driver Per day 400.00
36 Tractor with trolly for 8 Hrs including Driver with Per day 800.00
Fuel
CHAPER-2
LABOUR
S.No. Description Unit Rates

37 Tractor trolly Water Tanker for 8 Hrs including Per day 900.00
Driver with Fuel
38 Floor cutting machine with driver without grinding Per day 450.00
stone
39 Welding Plant with oprator without Rod & Power Per day 450.00

40 Rikshaw trolly puller ( Capacity 0.25 m) Per day 250.00


41 Sweeper per pair with tools Per day 200.00
Sweeper ( Full time with Broom and T&P Per day 110.00
42
Sweeper ( Part time with Broom and T&P Per day 70.00
43
44 Bhisti with mashak Per day 130.00
45 Cleaner Per day 100.00
46 110.00
47
CHAPTER - 5
CONCRETE

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Taken 2.83 Cum
271 Concrete with 40 mm. gauge brick ballast and kankar lime, in foundations and under floors,
including supply of all materials, labor and T & P etc.required for completion of the work.
(A ) Materials :

Brick ballast Per cum 2.83 cum Rs 700.00 Rs 1982.18


Kankar Lime Per cum 0.93 cum Rs 3185.00 Rs 2976.24
Total Rs 4958.41
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Beldar Per day 3 no. Rs 110.00 Rs 330.00
Coolie Per day 3 no. Rs 110.00 Rs 330.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
Blacksmith Per day 1/8 no. Rs 200.00 Rs 25.00
T & P and Sundries etc. L.S. Rs 96.9
Total Rs 936.51
Water charges 1.5% of (A+B) Rs 88.42
Total Rs 5983.34
Contractor s profit @ 10% Rs 598.33
Rate for 2.83 Cum Rs 6581.67
Rate for 1.00 Cum Rs 2325.68
Say Rs 2325.70
272 Concrete with 40 mm. gauge brick ballast, white lime and surkhi in foundations and under
floors in the proportions of 100:16:32, including supply of all materials, labor and T & P
etc.required for completion of the work.
(A ) Materials :
Brick ballast Per cum 2.83 cum Rs 700.00 Rs 1982.18
White Lime Per cum 0.42 cum Rs 3185.00 Rs 1352.84
Surkhi Per cum 0.85 cum Rs 400.00 Rs 339.80
Total Rs 3335.01
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Beldar Per day 3 no. Rs 110.00 Rs 330.00
Coolie Per day 3 no. Rs 110.00 Rs 330.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
Blacksmith Per day 1/8 no. Rs 200.00 Rs 25.00
T & P and Sundries etc. L.S. Rs 50.8
Total Rs 890.35
Water charges 1.5% of (A+B) Rs 63.38
Total Rs 4288.74
Contractor s profit @ 10% Rs 428.87
Rate for 2.83 Cum Rs 4717.61

770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Rate for 1.00 Cum Rs 1667.00
Say Rs 1667.00

273 Concrete with 40 mm. gauge brick ballast, Fine local sand of 1.25 Fineness modulous and
cement in foundations and under floors in the proportions of 12:6:1, including supply of all
materials, labor and T & P etc.required for completion of the work.
(A ) Materials :
Brick ballast Per cum 2.83 cum Rs 700.00 Rs 1982.18
Fine sand Per cum 1.36 cum Rs 410.00 Rs 557.27
Cement Per bag 6.40 bag Rs 210.00 Rs 1344.00
Add 2.5% wastage on cement and sand Rs 47.53
Total Rs 3930.98
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Beldar Per day 3 no. Rs 110.00 Rs 330.00
Coolie Per day 3 no. Rs 110.00 Rs 330.00
Bhisti Per day 1 no. Rs 130.00 Rs 130.00
Blacksmith Per day 1/8 no. Rs 200.00 Rs 25.00
T & P and Sundries etc. L.S. Rs 372.3
Total Rs 1276.89
Water charges 1.5% of (A+B) Rs 78.12
Total Rs 5285.99
Contractor s profit @ 10% Rs 528.6
Rate for 2.83 Cum Rs 5814.59
Rate for 1.00 Cum Rs 2054.63
Say Rs 2054.60
274 As in item 273 above but in the proportion of 10:5:1
(A ) Materials :

Brick ballast Per cum 2.83 cum Rs 700.00 Rs 1982.18


Fine sand Per cum 1.42 cum Rs 410.00 Rs 580.49
Cement Per bag 8.00 bag Rs 210.00 Rs 1680.00
Add 2.5% wastage on cement and sand Rs 56.51
Total Rs 4299.18
(B) Labour :

Mistri Per day 1/8 no. Rs 210.00 Rs 26.25

770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Beldar Per day 3 no. Rs 110.00 Rs 330.00
Coolie Per day 3 no. Rs 110.00 Rs 330.00
Bhisti Per day 1 no. Rs 130.00 Rs 130.00
Blacksmith
Per day 1/8 no. Rs 200.00 Rs 25.00
T & P and Sundries etc. L.S. Rs 372.3
Total Rs 1276.89
Water charges 1.5% of (A+B) Rs 83.64
Total Rs 5659.71
Contractor s profit @ 10% Rs 565.97
Rate for 2.83 Cum Rs 6225.68
Rate for 1.00 Cum Rs 2199.89
Say Rs 2199.90
275 As in item 273 above but in the proportion of 8:4:1
(A ) Materials :
Brick ballast Per cum 2.83 cum Rs 700.00 Rs 1982.18
Fine sand Per cum 1.42 cum Rs 410.00 Rs 580.49
Cement Per bag 9.30 bag Rs 210.00 Rs 1953.00
Add 2.5% wastage on cement and sand Rs 63.34
Total Rs 4579.01
(B) Labour :

Mistri Per day 1/8 no. Rs 210.00 Rs 26.25


Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Beldar Per day 3 no. Rs 110.00 Rs 330.00
Coolie Per day 3 no. Rs 110.00 Rs 330.00
Bhisti Per day 1 no. Rs 130.00 Rs 130.00
Blacksmith Per day 1/8 no. Rs 200.00 Rs 25.00
T & P and Sundries etc. L.S. Rs 372.3
Total Rs 1276.89
Water charges 1.5% of (A+B) Rs 87.84
Total Rs 5943.74
Contractor s profit @ 10% Rs 594.37
Rate for 2.83 Cum Rs 6538.11
Rate for 1.00 Cum Rs 2310.29
Say Rs 2310.30
278 Concrete with 40 mm.(1") gauge brick ballast, white lime and surkhi in the proportions of
100:18:36in roof terracing, including supply of all materials, labor and T & P etc.required for
completion of the work.
(A ) Materials :
Brick ballast Per cum 2.83 cum Rs 700.00 Rs 1982.18
White lime Per cum 0.42 cum Rs 3185.00 Rs 1352.84
Bail, Gur etc L.S. 424.67
Surkhi Per bag 0.85 bag Rs 400.00 Rs 339.80
Add 2.5% wastage on cement and sand Rs 42.32
Total Rs 4141.80

770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Beldar Per day 4 no. Rs 110.00 Rs 440.00
Coolie Per day 6 no. Rs 110.00 Rs 660.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
Blacksmith Per day 1/8 no. Rs 200.00 Rs 25.00
T & P and Sundries etc. L.S. Rs 76.2
Total Rs 1355.74
Water charges 1.5% of (A+B) Rs 82.46
Total Rs 5580.00
Contractor s profit @ 10% Rs 558
Rate for 2.83 Cum Rs 6138.00
Rate for 1.00 Cum Rs 2168.90
Say Rs 2168.90
279 Concrete with 40 mm. gauge approved stone ballast, approved course sand and cement in
the proportions of 4:2:1, including supply of all materials, labor and T & P etc.required for
completion of the work.
(A ) Materials :

Stone ballast 40 mm gauge Per cum 2.55 cum Rs 1225.00 Rs 3121.93


Course sand Per cum 1.27 cum Rs 635.00 Rs 809.15
Cement Per bag 18.90 bag Rs 210.00 Rs 3969.00
Add 2.5% wastage on cement and sand Rs 119.45
Total Rs 8019.53
(B) Labour :
Mistri Per day 1/10 no. Rs 210.00 Rs 21.00
Mason Per day 1/2 no. Rs 190.00 Rs 95.00
Beldar Per day 4 no. Rs 110.00 Rs 440.00
Coolie Per day 4 no. Rs 110.00 Rs 440.00
Bhisti Per day 2 no. Rs 130.00 Rs 260.00
Blacksmith Per day 1/10 no. Rs 200.00 Rs 20.00
T & P and Sundries etc. L.S. Rs 355.4
Total Rs 1631.38
Water charges 1.5% of (A+B) Rs 144.76
Total Rs 9795.68
Contractor s profit @ 10% Rs 979.57
Rate for 2.83 Cum Rs 10775.25
Rate for 1.00 Cum Rs 3807.51
Say Rs 3807.50

280 As in item 279 above but in the proportion of 6:3:1

770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
(A ) Materials :
Stone ballast 40 mm gauge Per cum 2.61 cum Rs 1225.00 Rs 3191.30
Course sand Per cum 1.32 cum Rs 635.00 Rs 836.12
Cement Per bag 12.70 bag Rs 210.00 Rs 2667.00
Add 2.5% wastage on cement and sand Rs 87.58
Total Rs 6782.01
(B) Labour :
Mistri Per day 1/10 no. Rs 210.00 Rs 21.00
Mason Per day 1/2 no. Rs 190.00 Rs 95.00
Beldar Per day 4 no. Rs 110.00 Rs 440.00
Coolie Per day 4 no. Rs 110.00 Rs 440.00
Bhisti Per day 2 no. Rs 130.00 Rs 260.00
Blacksmith Per day 1/10 no. Rs 200.00 Rs 20.00
T & P and Sundries etc. L.S. Rs 355.4
Total Rs 1631.38
Water charges 1.5% of (A+B) Rs 126.20
Total Rs 8539.59
Contractor s profit @ 10% Rs 853.96
Rate for 2.83 Cum Rs 9393.55
Rate for 1.00 Cum Rs 3319.28
Say Rs 3319.30

282 Cast cement concrete door sills, chaukhats boundry post, shelves and similar small work with
cement,approved course sand and 20 mm. Gauge approved stone ballast including its fixing
and binding the same with 24 B.W.G. G.I. Binding wire , and including the cost of binding wire ,
moulds and all other materials, labours and T & P etc. required for completion of the work.

1. Cost of 1:2:4 as per item 279 Rs 10775.25

2. Add difference in cost of 40


mm gauge 20 mm gauge Per cum 2.55 cum Rs 115.00 Rs 293.08
ballast
3. Blacksmith for binding &
fixing reinforcement Per day 4 no. Rs 200.00 Rs 800.00
Total Rs 11868.33
4. Cost of mould & extra cement and labor for floating coat L. S. Rs 500.00
etc.
5. Binding wire and wastage of steel L. S. Rs 270.00
Total Rs 12638.33
Water charges 1.5% of (2+3+4+5) Rs 27.95
Total Rs 12666.28
Contractor s profit @ 10% Rs 189.1
Rate for 2.83 Cum Rs 12855.38
Rate for 1.00 Cum Rs 4542.54
Say Rs 4542.50

770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6

283 R.C.C work with cement,approved course sand and 20 mm. gauge approved stone ballast in
the proportion of 1:2:4 in lintels of doors and windows excluding supply of reinforcement and its
bending but including its fixing and binding the same with 24 B.W.G. G.I. binding wire , and
including neccessary centering and shuttering etc. and also including the supply of binding
wire , moulds and all other materials, labours and T & P etc. required for completion of the work.

(A ) Materials :

1. Cost of 1:2:4 as per item 279 Rs 10775.25

2. Add difference in cost of 40


mm gauge 20 mm gauge Per cum 2.55 cum Rs 115.00 Rs 293.08
ballast
3. Blacksmith for binding &
fixing reinforcement Per day 2 no. Rs 200.00 Rs 400.00
Total Rs 11468.33
4. Cost of binding wire & extra cement and labor for floating
coat etc. L. S. Rs 890.00
5. Cost of centering etc. with extra labor.. L. S. Rs 625.00
Total Rs 12983.33
Water charges 1.5% of (2+3+4+5) Rs 33.12
Total Rs 13016.45
Contractor s profit @ 10% Rs 224.12
Rate for 2.83 Cum Rs 13240.57
Rate for 1.00 Cum Rs 4678.65
Say Rs 4678.70
284 As in item no. 283 but for slabs.
Rate as per S.I. 283 Rs 4678.70
Add extra cost of centering and shuttering Rs 272.00
Contractor s profit @ 10% on Rs 272.000 Rs 27.20
Total Rs 4977.90
Rate for 1.00 cum Rs 4977.90
Say Rs 4977.9
285 As in item no. 283 but in lighter beams, having spans up to 6.00m
Rate as per S.I. 283 Rs 4678.70
Add extra for bricks or ballies supports L.S. Rs 442.04
Contractor s profit @ 10% on Rs 442.040 Rs 44.20
Total Rs 5164.94

770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Rate for 1.00 cum Rs 5164.94
Say Rs 5164.9
286 As in item no. 283 but in heavier beams, having spans above 6.00m
Rate as per S.I. 283 Rs 4678.70
Add for masonary or ballies supports
and stronger shuttering
L.S. Rs 628.97
Contractor s profit @ 10% on Rs 628.970 Rs 62.90
Total Rs 5370.57
Rate for 1.00 cum Rs 5370.57
Say Rs 5370.6
287 As in item no. 283 but in R.C.C. Raft foundation and footing with 4 cm (1 1/2")
gauge approved stone ballast.

Rate as per S.I. 279 Rs 3807.50


Blacksmith for binding and
reinforcement Per day 1 no. Rs 200.00 Rs 170.00
Cost of binding wire , pumping
out of water if any L.S.
L. S. Rs 50.00
Total Rs 4027.50
Contractor s profit @ 10% on Rs 4027.500 Rs 22.00
Total Rs 4049.50

Rate for 1.00 cum Rs 4049.50


Say Rs 4049.5

288 As in item no. 283 but in R.C.C. T- beams and slab roofs and columns.
Rate as per S.I. 283 Rs 4678.70
Add extra for bricks or ballies supports
stronger shuttering L.S. Rs 463.78
Contractor s profit @ 10% on Rs 463.780 Rs 46.38
Total Rs 5188.86

Rate for 1.00 cum Rs 5188.86


Say Rs 5188.9

289 As in item no. 283 but on columns in 1:1.5:3


Rate as per S.I. 288 above Rs 14684.59
Add difference in cost of material to be used
Stone ballast Per cum 0.14 cum Rs 1340.00 Rs 189.72
coarse sand Per cum 0.07 cum Rs 635.00 Rs 44.95
Cement Per bag 4.65 bag Rs 210.00 Rs 976.50
Total Rs 1211.18
Water charges 1.50 % on Rs. 698.46 Rs 121.12
Total Rs 16016.88

770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Rate for 1.00 cum Rs 5659.67
Say Rs 5659.7

770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 6
BRICK WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Taken 2.83 Cum
301 First class brick work in kakar lime in foundation and plingth including supply of all materials, labor
and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Kankar Lime Per cum 0.85 cum Rs 3185.00 Rs 2707.25
Total Rs 6607.25
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 113.29
Total Rs 7665.92
Contractor s profit @ 10% Rs 766.59
Rate for 2.83 Cum Rs 8432.51
Rate for 1.00 Cum Rs 2979.69
Say Rs 2979.70
302 First class brick work in white lime & surhi mortar in 1:2 in foundation and plinth including supply of
all materials, labor and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Surkhi Per cum 0.62 cum Rs 400.00 Rs 248.00
White Lime Per cum 0.31 cum Rs 3185.00 Rs 987.35
Total Rs 5135.35
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 91.21
Total Rs 6171.95
Contractor s profit @ 10% Rs 617.19
Rate for 2.83 Cum Rs 6789.14
Rate for 1.00 Cum Rs 2398.99
Say Rs 2399.00
CHAPTER - 6
BRICK WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
302 First class brick work in white lime & surhi mortar in 1:3 in foundation and plinth including supply of
(a) all materials, labor and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Surkhi Per cum 0.68 cum Rs 400.00 Rs 272.00
White Lime Per cum 0.23 cum Rs 3185.00 Rs 732.55
Total Rs 4904.55
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 87.75
Total Rs 5937.68
Contractor s profit @ 10% Rs 593.77
Rate for 2.83 Cum Rs 6531.45
Rate for 1.00 Cum Rs 2307.93
Say Rs 2307.90
303 First class bricks work in 1:6 in cement and fine sand of 1.25 F.M. mortar in foundation and plinth
including supply of all materials, labor and T&P etc. required for completion of the work.

(A ) Materials :

Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00


Fine sand of F.M. 1.25 Per cum 0.76 cum Rs 410.00 Rs 311.60
Cement Per bag 3.75 bag Rs 210.00 Rs 787.50
Total Rs 4211.60
(B) Labour :

Mistri Per day 1/6 no. Rs 210.00 Rs 35.00


Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 77.35
Total Rs 5234.34
Contractor s profit @ 10% Rs 523.43
Rate for 2.83 Cum Rs 5757.77
Rate for 1.00 Cum Rs 2034.55
CHAPTER - 6
BRICK WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Say Rs 2034.60

304 First class bricks work in 1:5 in cement and fine sand of 1.25 F.M. mortar in foundation and plinth
including supply of all materials, labor and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Fine sand of F.M. 1.25 Per cum 0.76 cum Rs 410.00 Rs 311.60
Cement Per bag 4.50 bag Rs 210.00 Rs 945.00
Total Rs 5156.60
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 91.53
Total Rs 6193.51
Contractor s profit @ 10% Rs 619.35
Rate for 2.83 Cum Rs 6812.86
Rate for 1.00 Cum Rs 2407.37
Say Rs 2407.40

305 First class bricks work in 1:4 in cement and fine sand of 1.25 F.M. mortar in foundation and plinth
including supply of all materials, labor and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Fine sand of F.M. 1.25 Per cum 0.76 cum Rs 410.00 Rs 311.60
Cement Per bag 5.25 bag Rs 210.00 Rs 1102.50
Total Rs 5314.10
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 93.89
Total Rs 6353.38
Contractor s profit @ 10% Rs 635.34
Rate for 2.83 Cum Rs 6988.72
Rate for 1.00 Cum Rs 2469.51
CHAPTER - 6
BRICK WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Say Rs 2469.50

306 First class bricks work in 1:3 in cement and fine sand of 1.25 F.M. mortar in foundation and plinth
including supply of all materials, labor and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Fine sand of F.M. 1.25 Per cum 0.76 cum Rs 410.00 Rs 311.60
Cement Per bag 7.50 bag Rs 210.00 Rs 1575.00
Total Rs 5786.60
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 120.00 Rs 240.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 27.7
Total Rs 967.69
Water charges 1.5% of (A+B) Rs 101.31
Total Rs 6855.61
Contractor s profit @ 10% Rs 685.56
Rate for 2.83 Cum Rs 7541.17
Rate for 1.00 Cum Rs 2664.72
Say Rs 2664.70

307 First class bricks work in 1:3 in cement and course sand mortar in foundation and plinth including
supply of all materials, labor and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Course sand Per cum 0.76 cum Rs 635.00 Rs 482.60
Cement Per bag 7.50 bag Rs 210.00 Rs 1575.00
Total Rs 5957.60
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 103.54
Total Rs 7006.53
Contractor s profit @ 10% Rs 700.65
Rate for 2.83 Cum Rs 7707.18
Rate for 1.00 Cum Rs 2723.38
Say Rs 2723.40
CHAPTER - 6
BRICK WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
308 First class bricks work in mud mortar in foundation and plinth including supply of all materials, labor
and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Earth Per cum 0.85 cum Rs 49.50 Rs 42.07
Total Rs 3942.08
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 73.31
Total Rs 4960.77
Contractor s profit @ 10% Rs 496.08
Rate for 2.83 Cum Rs 5456.85
Rate for 1.00 Cum Rs 1928.22
Say Rs 1928.20

309 As in item (301 to 304) above but in super-structure, including necessary cutting and moulding of
bricks as required and also including honey comb brick work . Thickness of wall not to be less than 1.5
brick thick.Add for extra labor to above items.
Extra Labor required :

Mason Per day 1 no. Rs 190.00 Rs 190.00


Coolies Per day 1 no. Rs 110.00 Rs 110.00
Scaffolding etc. L.S. Rs 47.5
Total Rs 347.50
Water charges 1.5% of (A+B) Rs 5.21
Total Rs 352.71
Contractor s profit @ 10% Rs 35.27125
Rate for 2.83 Cum Rs 387.98
Rate for 1.00 Cum Rs 137.10
Say Rs 137.10
310 As in item 309 above but one brick thick.Add for extra labor to above items.
Extra Labor required :
Mason Per day 1 no. Rs 190.00 Rs 190.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Total Rs 300.00
Water charges 1.5% of (A+B) Rs 4.50
Total Rs 304.50
Contractor s profit @ 10% Rs 30.45
Rate for 2.83 Cum Rs 334.95
Rate for 1.00 Cum Rs 118.36
Say Rs 118.40
CHAPTER - 6
BRICK WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
310(a) As in item 309 above but half brick thick.Add for extra labor over item no. 310 .
Extra Labor required :

Mason Per day 1/2 no. Rs 190.00 Rs 95.00


Coolies Per day 1/2 no. Rs 110.00 Rs 55.00
Total Rs 150.00
Water charges 1.50% Rs 2.25
Total Rs 152.25
Contractor s profit @ 10% Rs 15.225
Rate for 2.83 Cum Rs 167.48
Rate for 1.00 Cum Rs 59.18
Say Rs 59.20
310(b) As in item 309 above but 3" brick thick.Add for extra labor over item no. 310(a) .
Extra Labor required :
Mason Per day 1/2 no. Rs 190.00 Rs 95.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Total Rs 205.00
Water charges 1.50% Rs 3.07
Total Rs 208.08
Contractor s profit @ 10% Rs 20.8075
Rate for 2.83 Cum Rs 228.88
Rate for 1.00 Cum Rs 80.88
Say Rs 80.90

314 First class brick work in arch including shuttering and centering add to items ( 301 to 307 ). Extra
labour, centering and shuttering required,

Mason Per day 2 no. Rs 190.00 Rs 380.00


Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Centering and Shuttering Etc L.S. Rs 158.33
Total Rs 710.00
Water charges 1.50% Rs 10.65
Total Rs 720.65
Contractor s profit @ 10% Rs 72.07
Rate for 2.83 Cum Rs 792.72
Rate for 1.00 Cum Rs 280.11
Say Rs 280.10

315 As in item 314 above but First class brick work in Jack arch, including shuttering and centering add to
items ( 301 to 307 ). Extra labour, centering and shuttering required,

Mason Per day 2 no. Rs 190.00 Rs 380.00


Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 2 1/2 no. Rs 110.00 Rs 275.00
Centering and Shuttering Etc L.S. Rs 253.33
CHAPTER - 6
BRICK WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Total Rs 765.00
Water charges 1.50% Rs 11.48
Total Rs 776.48
Contractor s profit @ 10% Rs 77.65
Rate for 2.83 Cum Rs 854.13
Rate for 1.00 Cum Rs 301.81
Say Rs 301.80

316 As in item 314 above but in well steining with ordinary bricks, including shuttering and centering add
to items ( 301 to 307 ). Extra labour, centering and shuttering required,

Mason Per day 2 1/2 no. Rs 190.00 Rs 475.00


Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 3 no. Rs 110.00 Rs 330.00
Centering and Shuttering Etc L.S. Rs 253.33
Total Rs 915.00
Water charges 1.50% Rs 13.73
Total Rs 928.73
Contractor s profit @ 10% Rs 92.87
Rate for 2.83 Cum Rs 1021.60
Rate for 1.00 Cum Rs 360.99
Say Rs 361.00

317 As in item 316 above but in well steining but with specially moulded bricks, including shuttering and
centering add to items ( 301 to 307 ). Extra labour, centering and shuttering required,

Mason Per day 1/2 no. Rs 450.00 Rs 225.00


Beldar Per day 2 no. Rs 140.00 Rs 280.00
Total Rs 505.00
Water charges 1.50% Rs 7.57
Total Rs 512.58
Contractor s profit @ 10% Rs 51.26
Rate for 2.83 Cum Rs 563.84
Rate for 1.00 Cum Rs 199.23
Say Rs 199.20

318 11.5 cm. Thick string or drip course with 6 cm projection of first class brick in kankar lime including 12
mmthick lime plastering with simple moulding and cuttig drip notch as required and including supply of
all material ,labor and T & P etc required for completion of work
For 30.48 Rm
(A ) Materials :
Bricks Per %0 No 100.00 no. Rs 3000.00 Rs 300.00
Kanker Lime Per %0 No 0.17 no. Rs 3185.00 Rs 0.54
Total Rs 300.54

(B) Labour :
Mistri Per day 1/50 no. Rs 210.00 Rs 4.20
Mason Per day 3 1/2 no. Rs 190.00 Rs 665.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/12 no. Rs 130.00 Rs 10.83
CHAPTER - 6
BRICK WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
T & P and Sundries etc. L.S. Rs 12.7
Total Rs 912.70
Water charges 1.5% of (A+B) Rs 18.20
Total Rs 1231.44
Contractor s profit @ 10% Rs 123.14
Rate for 30.48 Rm Rs 1354.58
Rate for 1.00 Rm Rs 44.44
Say Rs 44.40

324 Laying reinforced brick work in sunshade with first class brick laid in cement and approved coarse
sand mortar 1:3 excluding supply of reinforcement and its bending but including its fixing in position
and binding the same with 24 B.W.G.I. Binding wire and including all centering and shuttering etc and
curring and also including cost of binding wire, supply of all materials labour and T & P etc required for
proper completion of the work.

For 2.83 Cum


Rate for R.B.slab per 2.83 cum as per S.I.No 535 CHAPTER -11 Rs 7022.07

Deduct for Less cost of Per 1.019


centering materials 10 % on Rs. 3432.36 cum or 9528.72 0.00
Deduct for Less 1 1/2 % Water -10.68
Charges on
Deduct for above.
Less 10 % -1.06
Contractor' s Profit on above TOTAL Rs 7010.33
Rate for 2.83 Cum 7010.33
Rate for 1.00 Cum Rs 2475.68
Say Rs 2475.70

325 As in item 324 above but in lintels.


For 2.83 Cum
as per S.I.No 324 CHAPTER -6 Rs 7010.33

Deduct for Less Labour -561.66


required due to less cost of TOTAL Rs 6448.67
Rate for 2.83 Cum 6448.67
Rate for 1.00 Cum Rs 2277.33
Say Rs 2277.30
CHAPTER - 7
DAMP COARSING

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Taken 9.29 Sqm
360 2cm thick damp proof coarse with cement and approved coase sand 1:2 with and including water proofing
materials as ordered by the Engineer-in charge in the proportion as specified by the manufactures,
including supply of all materials, labour, T & P etc. required for completion of work and including proper
curing and shuttering as necessary.

(A ) Materials :
Coarse sand Per cum 0.18 cum Rs 635.00 Rs 112.38
Cement Per bag 2.60 bag Rs 210.00 Rs 546.00
Water proofing compound as
specified by the manufactures
Per kg 3.40 kg Rs 50.00 Rs 170.00
Total Rs 828.38
(B) Labour :
Mistri Per day 1/20 no. Rs 210.00 Rs 10.50
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Beldar Per day 1/4 no. Rs 110.00 Rs 27.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/8 no. Rs 130.00 Rs 16.25
T & P and Sundries etc. L.S. Rs 16.9
Total Rs 146.17
Water charges 1.5% of (A+B) Rs 14.62
Total Rs 989.17
Contractor s profit @ 10% Rs 98.92
Rs 1088.09
Rate for 9.29 Sqm 1088.09
Rate for 1.00 Sqm Rs 117.12
Say Rs 117.10

361 2.5cm thick damp proof coarse with cement, approved coase sand and 13mm graded stome grit in1:1.5:3
with and including water proofing materials as ordered by the Engineer-in charge in the proportion as
specified by the manufactures, including supply of all materials, labour, T & P etc. required for completion of
work and including proper curing and shuttering as necessary.
(A ) Materials :
Stone ballast Per cum 0.212 cum Rs 1250.00 Rs 265.47
Coarse sand Per cum 0.106 cum Rs 635.00 Rs 67.43
Cement Per bag 2.30 bag Rs 210.00 Rs 483.00
Water proofing compound as Per kg 2.60 kg Rs 50.00 Rs 130.00
specified by the manufactures Total Rs 945.90
(B) Labour :
Mistri Per day 1/16 no. Rs 210.00 Rs 13.13
Mason Per day 1 1/2 no. Rs 190.00 Rs 285.00
Beldar Per day 1 1/2 no. Rs 110.00 Rs 165.00
Bhisti Per day 1/8 no. Rs 130.00 Rs 16.25
T & P and Sundries etc. L.S. Rs 33.8
Total Rs 513.22
Water charges 1.5% of (A+B) Rs 21.89
Total Rs 1481.01
Contractor s profit @ 10% Rs 148.10
Rs 1629.11
Rate for 9.29 Sqm 1629.11
Rate for 1.00 Sqm Rs 175.36
Say Rs 175.40
CHAPTER - 10
MILD STEEL & IRON WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Taken 0.508 Qtls (Per cwt)
501 Rolled steel Joists fixed in position excluding cost of joists which will be supplied free at site but
including all labour in handling and hoisting and including hire etc of necessary T & P.
Unit =Per Qtls
(a) Light section , i.e. not exceeding 300 kg.( 6 cwt) in weight and upto
7.5 metre ( 24 ft) in height.
Peshraj(Beldar) Per day 1/20 no. Rs 120.00 Rs 6.00
Mason Per day 1/10 no. Rs 190.00 Rs 19.00
Beldar Per day 1/2 no. Rs 110.00 Rs 55.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Ropes T & P etc. L.S. Rs 11.08
Total Rs 195.08
Contractor s profit @ 10% Rs 19.51
Total Rs 214.59
Rate for 0.51 Qtls Rs 214.59
Rate for 1.00 Qtls Rs 422.42
Say Rs 422.40

(b) Same as above but heavy section , i.e. exceeding 300 kg.( 6 cwt) in
weight and upto 7.5 metre ( 24 ft) in height.

Peshraj(Beldar) Per day 1/20 no. Rs 120.00 Rs 6.00


Mason Per day 1/10 no. Rs 190.00 Rs 19.00
Beldar Per day 1/2 no. Rs 110.00 Rs 55.00
Coolies Per day 1 1/2 no. Rs 110.00 Rs 165.00
Hire of pulley & tackle L.S. Rs 27.69
Ropes T & P etc. L.S. Rs 36.92
Total Rs 303.62
Contractor s profit @ 10% Rs 30.36
Total Rs 333.98
Rate for 0.51 Qtls Rs 333.98
Rate for 1.00 Qtls Rs 657.43
Say Rs 657.40
© Add to item 501(a) and 501(b) for height beyond 7.5 metre ( 24
ft) in height.
Extra Beldar Per day 1/2 no. Rs 110.00 Rs 55.00
Coolies Per day 1/2 no. Rs 110.00 Rs 55.00
Extra for Ropes L.S. Rs 16.92
Total Rs 71.92
Contractor s profit @ 10% Rs 7.19
CHAPTER - 10
MILD STEEL & IRON WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Total Rs 79.11
Rate for 0.51 Qtls Rs 79.11
Rate for 1.00 Qtls Rs 155.73
Say Rs 155.70
502 Mild steel or iron work of small sizes and sections and such as holding down bolts, hold fasts, tie
rods ,gratings etc. ( when not incuded in an over all rates ) wrought to required form, including
supply of steel ,bolts, nuts and wastages etc. and their fixing required for completion of the
work.
Unit =Per Qtls
(A ) Materials :

Cost of steel Per qtl 0.51 qtl Rs 3560.00 Rs 1808.48


Wastages 2.5% on steel Per qtl 0.0127 qtl Rs 3560.00 Rs 45.21
Total Rs 1853.69
(B) Labour :

Black smith Per day 1 no. Rs 200.00 Rs 200.00


Hammer man Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Coal & T & P etc. Rs 27.27
Total Rs 2300.96
Contractor s profit @ 10% Rs 230.10
Total Rs 4384.75
Rate for 0.51 Qtls Rs 4384.75
Rate for 1.00 Qtls Rs 8631.40
Say Rs 8631.40

503 Mild steel or iron work in heavy sizes such as trusses, builts up gates, door frames ,records
racks roof work ,gates etc. wrought to required form, including drilling holes, rivetting or welding
where necessary, and also including supply of steel ,bolts, nuts and wastages etc. and their
fixing required for completion of the work.
Unit =Per Qtls
(A ) Materials :
Cost of steel Per qtl 0.51 qtl Rs 3560.00 Rs 1808.48
Wastages 2.5% on steel Per qtl 0.0127 qtl Rs 3560.00 Rs 45.21
Total Rs 1853.69
(B) Labour :
Black smith Per day 1 no. Rs 200.00 Rs 200.00
Hammer man Per day 1 no. Rs 110.00 Rs 110.00
Rivetter Per day 1/4 no. Rs 180.00 Rs 45.00
CHAPTER - 10
MILD STEEL & IRON WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Coal & T & P etc. Rs 27.27
Hoisting & welding L. S. Rs 163.64
Total Rs 2509.60
Contractor s profit @ 10% Rs 250.96
Total Rs 4614.25
Rate for 0.51 Qtls Rs 4614.25
Rate for 1.00 Qtls Rs 9083.18
Say Rs 9083.20
504 Mild steel or ironin plain work such as reinforced concrete or reinforced brick work (when not
included in over all rates ) wrought to required shape as necessary including bending , and
also including supply of steel and wastages and overlapping and hookes required for completion
of the work.
Unit =Per Qtls
(A ) Materials :

Cost of steel Per qtl 0.51 qtl Rs 3560.00 Rs 1808.48


Wastages 5% on steel Per qtl 0.0254 qtl Rs 3560.00 Rs 90.42
Total Rs 1898.90
(B) Labour :

Black smith Per day 1 no. Rs 200.00 Rs 200.00


Coolies Per day 1 1/2 no. Rs 110.00 Rs 165.00
T & P etc. Rs 14.55
Total Rs 2278.45
Contractor s profit @ 10% Rs 227.84
Total Rs 4405.20
Rate for 0.51 Qtls Rs 4405.20 Rs 4405.20
Rate for 1.00 Qtls Rs 8671.65
Say Rs 8671.70
511 Providing and fixing 10 cm. Dia C.I. Down pipe complete with rose, bends with eye hole, shoes
andgratings etc. fixed to wallswith suitable clamps as directed by the Engineer-in - charge
Unit= per Rm
Assuming 30 ft height. C.I. Pipes in 6' length.
Taking 9.14 m height C.I. Pipes in 1.80m length.
9.00 m
(A ) Materials :
height C.I.
Pipes in C.I. Pipes Per Rm 9.14 Rm Rs 40.00 Rs 365.76
Rose Per 1.00 no. Rs 8.00 Rs 8.00
Head Per 1.00 no. Rs 12.00 Rs 12.00
CHAPTER - 10
MILD STEEL & IRON WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Shoe Per 1.00 no. Rs 18.00 Rs 18.00
Bend with eye hole Per 1.00 no. Rs 22.00 Rs 22.00
Bolts L.S. Rs 200.00
Clamps L.S. Rs 200.00
Total Rs 825.76
(B) Labour :
Mason Per day 1/2 no. Rs 190.00 Rs 95.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Mortar etc. L.S. Rs 47.50
Total Rs 1078.26
Contractor s profit @ 10% Rs 107.83
Total Rs 2011.85

Rate for 9.14 Rm Rs 2011.85


Rate for 1.00 Rm Rs 220.02
Say Rs 220.00
CHAPTER - 11
ROOF WORK

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Unit 2.83 Cum
535 Laying reinforced brick slab with and including supply of first class bricks laid in cement mortar 1:3 consisting
of one part cement and three part coarse sand excluding supply of reinforcement and its bending but
including its fixing in position and binding the same with 24 B W G I binding wire & including centering and
shuttering and necessary curing and also incuding cost of binding wire, supply of all material , labour & T & P
etc. requred for completion of work.
Taking roof area - 3.60m x 2.40m Height of roof slab - 3.60m
Taken 1.0368 Cum (3.60x2.40x0.12)m

(A ) Materials :
Bricks Per %0 No 432.00 no. Rs 3000.00 Rs 1296.00
Cement Per bag 3.60 bag Rs 210.00 Rs 756.00
Course sand Per cum 0.34 cum Rs 635.00 Rs 215.77
Total Rs 2052.00
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 3/4 no. Rs 190.00 Rs 142.50
Beldar Per day 3/4 no. Rs 110.00 Rs 82.50
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50

Total Rs 402.50
Centering Ballies 5 nos. 3.60m
length & 10cm. Dia 18.29 Rm Rs 45.00 Rs 822.96
Ballies 15 nos. 3.60m length
& 10cm. Dia 54.86 Rm Rs 45.00 Rs 2468.88

Planking - 3.60m x 2.40m x 0.04m 0.346 cum Rs 10.00 Rs 3.46


Total Rs 3295.30
Material can be used 25 times = 131.8118 131.81
Nails etc. L. S. Rs 5.25
Total Rs 3432.36
Erection and Dismentling
Carpenter Per day 1/2 no. Rs 210.00 Rs 105.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Black smith Per day 1/4 no. Rs 200.00 Rs 50.00
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Total Rs 402.50
Grand Total Rs 6289.36
Water charges 1.5% on above Rs 94.34
Total Rs 6383.70
Contractor s profit @ 10% Rs 638.37
Rate for 2.83 Cum Rs 7022.07
Rate for 1.00 Cum Rs 2481.30
Say Rs 2481.30

538 Supply and laying complete 4 cm ( 1 1/2 " ) thick insulation layer of sand and clay over Jack arch,
Reinforced Brick or reinforced cement concrete roof.
Take a Area 9.29 Sqm

(A ) Materials :
Cost of Earth Per Cum 0.20 Cum Rs 49.50 Rs 0.01
Cost of Sand Per Cum 0.20 Cum Rs 275.00 Rs 56.20
Total Rs 0.01
(B) Labour :
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Beldar Per day 1/4 no. Rs 110.00 Rs 27.50
Total Rs 75.00
Total (A+B) Rs 75.01
Contractor s profit @ 10% Rs 7.5
Rate for 9.29 Sqm Rs 82.51
Rate for 1.00 Sqm Rs 8.88
Say Rs 8.90
CHAPTER - 13
PLASTER and POINTING

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Taken 9.29 Sqm
571 Stuck pointing with kakar lime on brick work including supply of all materials, labor and T&P etc.
required for completion of the work.
(A ) Materials :

Kankar Lime Per cum 0.06 cum Rs 3185.00 Rs 191.10


Total Rs 191.10

(B) Labour :
(a) Raking and washing surface
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for pointing
Mason Per day 1 1/2 no. Rs 190.00 Rs 285.00
Coolies Per day 1 1/2 no. Rs 110.00 Rs 165.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
T & P and Sundries ,
scaffolding etc. L.S. Rs 15.8
Total Rs 586.33
TOTAL ( A+B) Rs 777.43
Water charges 1.5% of (A+B) Rs 11.66
Total Rs 789.09
Contractor s profit @ 10% Rs 78.91
Rs 868.00
Rate for 9.29 Sqm 868.00
Rate for 1.00 Sqm Rs 93.43
Say Rs 93.40

574 As in item no. 571 above but with cement mortar consisting of one part cement & two parts of
Fine sand of 1.25 F.M.
(A ) Materials :
Cement Per no. 0.43 bag Rs 210.00 Rs 90.30
Fine sand Per cum 0.03 cum Rs 410.00 Rs 11.48
Total Rs 101.78

(B) Labour :
(a) Raking and washing surface
Mason Per day 1/4 no. Rs 200.00 Rs 50.00
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for pointing
Mason Per day 1 1/2 no. Rs 200.00 Rs 300.00
Coolies Per day 1 1/2 no. Rs 110.00 Rs 165.00
Bhisti Per day 1 1/2 no. Rs 130.00 Rs 195.00
T & P and Sundries ,
scaffolding etc. L.S. Rs 16.7
Finishing by Iron Trowal L.S. Rs 13.3
Total Rs 767.17
TOTAL ( A+B) Rs 868.95
Water charges 1.5% of (A+B) Rs 13.03
Total Rs 881.98
Contractor s profit @ 10% Rs 88.20
Rs 970.18
Rate for 9.29 Sqm 970.18
Rate for 1.00 Sqm Rs 104.43
Say Rs 104.40

575 As in item no 574 above but flush pointing deduct from item 574.
Labour :
Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Coolies Per day 1/3 no. Rs 110.00 Rs 36.67
Water charges Rs 1.50
101.50
Contractor s profit @ 10% Rs 10.15
Rs 111.65
Rate for 9.29 Sqm 111.65
Rate for 1.00 Sqm Rs 12.02
Say Rs 12.00

576 As in item no 574 and 575 above but in floors deduct from item 574. and 575.
Labour :
Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Coolies Per day 1/3 no. Rs 110.00 Rs 36.67
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
Water charges Rs 1.69
114.70
Contractor s profit @ 10% Rs 11.47
Rs 126.16
Rate for 9.29 Sqm 126.16
Rate for 1.00 Sqm Rs 13.58
Say Rs 13.60

577 Raised pointing with cement and Fine sand of 1.25F.M. mortar on brick work in proportion of 1:2,
including supply of all materials, labour and T & P etc required for proper completion of the work.

(A ) Materials :
Cement Per no. 1.00 bag Rs 210.00 Rs 210.00
Fine sand Per cum 0.04 cum Rs 410.00 Rs 14.51
Total Rs 224.51

(B) Labour :
(a) Raking and washing surface
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for pointing
Mason Per day 1 1/3 no. Rs 190.00 Rs 253.33
Coolies Per day 1 1/3 no. Rs 110.00 Rs 146.67
Bhisti Per day 1/3 no. Rs 130.00 Rs 43.33
Scaffolding etc. L.S. Rs 15.8
Total Rs 547.17
TOTAL ( A+B) Rs 771.68
Water charges 1.5% of (A+B) Rs 11.58
Total Rs 783.25
Contractor s profit @ 10% Rs 78.33
Rs 861.58
Rate for 9.29 Sqm 861.58
Rate for 1.00 Sqm Rs 92.74
Say Rs 92.70

578 Struck cement pointing 1:2 with colour in mortar to match the brick work colour including supply
of all materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 0.43 bag Rs 210.00 Rs 89.25
Fine sand Per cum 0.03 cum Rs 410.00 Rs 11.61
Total Rs 100.86

(B) Labour :
(a) Raking and washing surface
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for pointing
Mason Per day 1 1/2 no. Rs 190.00 Rs 285.00
Coolies Per day 1 1/2 no. Rs 110.00 Rs 165.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Scaffolding etc. L.S. Rs 15.8
Finishing by Iron Trowal L.S. Rs 31.7
Total Rs 618.00
TOTAL ( A+B) Rs 718.86
Water charges 1.5% of (A+B) Rs 10.78
Total Rs 729.64
Contractor s profit @ 10% Rs 72.96
Rs 802.61
Rate for 9.29 Sqm 802.61
Rate for 1.00 Sqm Rs 86.39
Say Rs 86.40

580 12 mm thick plaster with cement mortar in proportion of 1:2 cement and fine sand of 1.25 F.M.
over brick work minimum thickness not to be less than 10 mm thick including supply of all
materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 2.12 bag Rs 210.00 Rs 445.20
Fine sand Per cum 0.14 cum Rs 410.00 Rs 58.05
Total Rs 503.25

(B) Labour :
(a) Raking and washing surface; same as S.I.Nos 578
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for Plastering : same as S.I.Nos 579
Mason Per day 3/4 no. Rs 190.00 Rs 142.50
Coolies Per day 3/4 no. Rs 110.00 Rs 82.50
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Scaffolding etc. L.S. Rs 15.8
Total Rs 361.33
TOTAL ( A+B) Rs 864.58
Water charges 1.5% of (A+B) Rs 12.97
Total Rs 877.55
Contractor s profit @ 10% Rs 87.76
Rs 965.31
Rate for 9.29 Sqm 965.31
Rate for 1.00 Sqm Rs 103.91
Say Rs 103.90

581 12 mm thick plaster with cement mortar in proportion of 1:2 cement and app. Coarse sand of
above 2.25 F.M., over brick work minimum thickness not to be less than 10 mm thick including
supply of all materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 2.12 bag Rs 210.00 Rs 445.20
Coarse sand Per cum 0.14 cum Rs 635.00 Rs 89.91
Total Rs 535.11

(B) Labour :
(a) Raking and washing surface; same as S.I.Nos 578
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for Plastering : same as S.I.Nos 579
Mason Per day 3/4 no. Rs 190.00 Rs 142.50
Coolies Per day 3/4 no. Rs 110.00 Rs 82.50
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Scaffolding etc. L.S. Rs 15.8
Total Rs 361.33
TOTAL ( A+B) Rs 896.44
Water charges 1.5% of (A+B) Rs 13.45
Total Rs 909.89
Contractor s profit @ 10% Rs 90.99
Rs 1000.87
Rate for 9.29 Sqm 1000.87
Rate for 1.00 Sqm Rs 107.74
Say Rs 107.70

582 12 mm thick plaster with cement mortar in proportion of 1:3 cement and fine sand of 1.25 F.M.
over brick work minimum thickness not to be less than 10 mm thick including supply of all
materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 1.42 bag Rs 210.00 Rs 298.20
Fine sand Per cum 0.14 cum Rs 410.00 Rs 58.05
Total Rs 356.25
(B) Labour :
Labour for Raking and
washing surface and Plastering same as S.I.Nos 580 or 581 361.33
etc ;
Total Rs 361.33
TOTAL ( A+B) Rs 717.58
Water charges 1.5% of (A+B) Rs 10.76
Total Rs 728.35
Contractor s profit @ 10% Rs 72.83
Rs 801.18
Rate for 9.29 Sqm 801.18
Rate for 1.00 Sqm Rs 86.24
Say Rs 86.20

583 12 mm thick plaster with cement mortar in proportion of 1:3 cement and appr. Coarse sand of
above 2.25 F.M. over brick work minimum thickness not to be less than 10 mm thick including
supply of all materials, labour and T & P etc required for proper completion of the work.

(A ) Materials :
Cement Per no. 1.42 bag Rs 210.00 Rs 298.20
Coarse sand Per cum 0.14 cum Rs 635.00 Rs 89.91
Total Rs 388.11
(B) Labour :
Labour for Raking and
washing surface and Plastering same as S.I.Nos 580 or 581 361.33
etc ;
Total Rs 361.33
TOTAL ( A+B) Rs 749.44
Water charges 1.5% of (A+B) Rs 11.24
Total Rs 760.68
Contractor s profit @ 10% Rs 76.07
Rs 836.75
Rate for 9.29 Sqm 836.75
Rate for 1.00 Sqm Rs 90.07
Say Rs 90.10

584 12 mm thick plaster with cement mortar in proportion of 1:4 cement and fine sand of 1.25 F.M.
over brick work minimum thickness not to be less than 10 mm thick including supply of all
materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 1.06 bag Rs 210.00 Rs 222.60
Fine sand Per cum 0.14 cum Rs 410.00 Rs 58.05
Total Rs 280.65
(B) Labour :
Labour for Raking and
washing surface and Plastering same as S.I.Nos 580 or 581 361.33
etc ;
Total Rs 361.33
TOTAL ( A+B) Rs 641.98
Water charges 1.5% of (A+B) Rs 9.63
Total Rs 651.61
Contractor s profit @ 10% Rs 65.16
Rs 716.77
Rate for 9.29 Sqm 716.77
Rate for 1.00 Sqm Rs 77.16
Say Rs 77.20

586 12 mm thick plaster with cement mortar in proportion of 1:6 cement and fine sand of 1.25 F.M.
over brick work minimum thickness not to be less than 10 mm thick including supply of all
materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 0.70 bag Rs 210.00 Rs 147.00
Fine sand Per cum 0.14 cum Rs 410.00 Rs 58.05
Total Rs 205.05
(B) Labour :
Labour for Raking and
washing surface and Plastering same as S.I.Nos 580 or 581 361.33
etc ;
Total Rs 361.33
TOTAL ( A+B) Rs 566.38
Water charges 1.5% of (A+B) Rs 8.50
Total Rs 574.88
Contractor s profit @ 10% Rs 57.49
Rs 632.37
Rate for 9.29 Sqm 632.37
Rate for 1.00 Sqm Rs 68.07
Say Rs 68.10

587 Add for extra labour to all items of plaster if done in ceiling.

Extra labour; Mason Per day 0.25 no. Rs 190.00 Rs 47.50


Extra for Scaffolding L.S. Rs 5.7
Wastage of mortar L.S. Rs 23.8
Water charges 1.50% Rs 1.15
Total Rs 78.10
Contractor s profit @ 10% Rs 7.81
Rs 85.91
Rate for 9.29 Sqm 85.91
Rate for 1.00 Sqm Rs 9.25
Say Rs 9.30

596 2 cm ( 3/4"') thick cement plasre in dado or skirting in 1:2 consisting of one part of cement and
tpart of approved coarse sand laid in panels, finished with 3 mm (1/8"') floating coat of neat
cement or cement and marble dust in ratio 5:1 including supply of all materials labour and T&P
etc. required for proper completion of the work.

(A ) Materials :
Cement Per no. 2.25 bag Rs 210.00 Rs 472.50
Coarse sand Per cum 0.17 cum Rs 635.00 Rs 107.89
Total Rs 580.39

(B) Labour :
(a) Raking and washing surface; same as S.I.Nos 578
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for Plastering : same as S.I.Nos 579
Mason Per day 1 no. Rs 190.00 Rs 190.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Bhisti Per day 3/8 no. Rs 130.00 Rs 48.75
Total Rs 436.75
TOTAL ( A+B) Rs 1017.14
Water charges 1.5% of (A+B) Rs 15.26
Total Rs 1032.39
Contractor s profit @ 10% Rs 103.24
Rs 1135.63
Rate for 9.29 Sqm 1135.63
Rate for 1.00 Sqm Rs 122.24
Say Rs 122.20

598 Engraving line in the plaster of outer face wall vertically and horizontally to display the surface as
stone facing as directed by the E / I including labour and T & P etc. required for proper
completion of the work .( Add for extra labour to all items of plaster.)

Mason Per day 0.667 no. Rs 190.00 Rs 126.67


1.50 % Water charges on Rs. 126.67 Rs 1.90
Total Rs 128.57
Contractor s profit @ 10% Rs 12.86
Rs 141.42
Rate for 9.29 Sqm 141.42
Rate for 1.00 Sqm Rs 15.22
Say Rs 15.20

599 Providing and fixing water proofing materials in cement mortar ( Skelton analysis as per for
plastering or in concrete work in the proportion recommended by the manufacturer - item 52
page 553 CPWD 1955 analysis of rates)

Cost of water proofing material Per Kg 1.000 Kg Rs 140.00 Rs 140.00


Exrea labour for mixing L.S. Rs 8.80
1.50 % Water charges on Rs. 148.80 Rs 2.23
Total Rs 151.03
Contractor s profit @ 10% Rs 15.10
Rs 166.14
Rate for 9.29 Sqm 166.14
Rate for 1.00 Sqm Rs 17.88
Say Rs 17.90
CHAPTER - 14
FLOORING

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Unit 2.83 Cum
Taken 9.29 Sqm
601 25 mm thick 1:2:4 plain C.C Floor with cement , approved coarse sand and 20mm graded approved
stone laid in panels finished with 3 mm flooring coat of neat cement or cement and marble dust in 5:1
as specified over & including 8 cm thick base concrete consisting of cement, local sand and brick
ballast 4 cm gauge in the proportion of 1:4:8 and removing any over lapping mortar at the joints of
panels if any and given them a uniform finish including supply of all materials, labor and T&P etc.
required for completion of the work.

(A ) Materials :
Stone grit 20 mm gauge Per cum 0.21 cum Rs 1340.00 Rs 284.58
Coarse sand Per cum 0.10 cum Rs 635.00 Rs 66.53
Cement Per no. 2.03 bag Rs 210.00 Rs 426.30
Total Rs 777.41
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1/2 no. Rs 110.00 Rs 55.00
Coolies Per day 1/2 no. Rs 110.00 Rs 55.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
T & P and Sundries etc. L.S. Rs 48.5
Total Rs 417.21
Water charges 1.5% of (A+B) Rs 17.92
Total Rs 1212.55
Contractor s profit @ 10% Rs 121.25
Total Rs 1333.80

Add brick ballast 7.5cm base


concrete in 1:4:8 asper item no. 275 Per cum 0.71 cum Rs 2310.30 Rs 1635.51
TOTAL Rs 2969.31
Rate for 9.29 Sqm 2969.31
Rate for 1.00 Sqm Rs 319.62
Say Rs 319.60

601 ( A ) As in item no 601 above but without base concret.


(A ) Materials :
Stone grit 20 mm gauge Per cum 0.21 cum Rs 1340.00 Rs 284.58
Coarse sand Per cum 0.10 cum Rs 635.00 Rs 66.53
Cement Per no. 2.03 bag Rs 210.00 Rs 426.30
Total Rs 777.41
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1/2 no. Rs 110.00 Rs 55.00
Coolies Per day 1/2 no. Rs 110.00 Rs 55.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
T & P and Sundries etc. L.S. Rs 48.5
Total Rs 417.21
Water charges 1.5% of (A+B) Rs 17.92
Total Rs 1212.55
Contractor s profit @ 10% Rs 121.25
TOTAL Rs 1333.80
Rate for 9.29 Sqm 1333.80
Rate for 1.00 Sqm Rs 143.57
Say Rs 143.60

602 As in item no 601 above but with base concrete consisting of brick ballast , white lime and surkhi in
ratio of 100:16:32
Same as in item no 601 for 2.5 cm
thick C.C. floor Rs 1333.80
Add brick ballast 7.5 cm(3") thick
base concrete in Kankar lime as per
S.I.No 271 Per cum 0.71 cum Rs 2325.70 Rs 1646.41
TOTAL Rs 2980.21
Rate for 9.29 Sqm 2980.21
Rate for 1.00 Sqm Rs 320.80
Say Rs 320.80

604 As in item no 601 above but floor shall be 5 cm (2") thick instead of 2.5 cm (1") thick and proportion
of concrete 1:1 1/2:3 instead of 1:2:4.
(A ) Materials :
Stone grit 20 mm gauge Per cum 0.42 cum Rs 1340.00 Rs 569.17
Coarse sand Per cum 0.21 cum Rs 635.00 Rs 134.86
Cement Per no. 4.75 bag Rs 210.00 Rs 997.50
Total Rs 1701.53
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1 1/2 no. Rs 200.00 Rs 300.00
Beldar Per day 3/4 no. Rs 110.00 Rs 82.50
Coolies Per day 3/4 no. Rs 110.00 Rs 82.50
Bhisti Per day 1/3 no. Rs 130.00 Rs 43.33
T & P and Sundries etc. L.S. Rs 116.3
Total Rs 650.89
Water charges 1.5% of (A+B) Rs 35.29
Total Rs 2387.70
Contractor s profit @ 10% Rs 238.77
Total Rs 2626.47

Add brick ballast 7.5cm base


concrete in 1:4:8 asper item no. 275 Per cum 0.71 cum Rs 2310.30 Rs 1635.51
TOTAL Rs 4261.98
Rate for 9.29 Sqm 4261.98
Rate for 1.00 Sqm Rs 458.77
Say Rs 458.80

604(a)As in item no 604 above but without base concrete.


(A ) Materials :
Stone grit 20 mm gauge Per cum 0.42 cum Rs 1340.00 Rs 569.17
Coarse sand Per cum 0.21 cum Rs 635.00 Rs 134.86
Cement Per no. 4.75 bag Rs 210.00 Rs 997.50
Total Rs 1701.53
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1 1/2 no. Rs 200.00 Rs 300.00
Beldar Per day 3/4 no. Rs 110.00 Rs 82.50
Coolies Per day 3/4 no. Rs 110.00 Rs 82.50
Bhisti Per day 1/3 no. Rs 130.00 Rs 43.33
T & P and Sundries etc. L.S. Rs 116.3
Total Rs 650.89
Water charges 1.5% of (A+B) Rs 35.29
Total Rs 2387.70
Contractor s profit @ 10% Rs 238.77
TOTAL Rs 2626.47
Rate for 9.29 Sqm 2626.47
Rate for 1.00 Sqm Rs 282.72
Say Rs 282.70

605 As in item no 601 above but floors shall be 4 cm (1 1/2") thick instead of 2.5 cm (1") thick and
without base concrete.
(A ) Materials :
Stone grit 20 mm gauge Per cum 0.37 cum Rs 1340.00 Rs 493.28
Coarse sand Per cum 0.18 cum Rs 635.00 Rs 116.88
Cement Per no. 2.75 bag Rs 210.00 Rs 577.50
Total Rs 1187.66
(B) Labour :
Mistri Per day 1 1/8 no. Rs 210.00 Rs 236.25
Mason Per day 1/4 no. Rs 200.00 Rs 50.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 3/4 no. Rs 110.00 Rs 82.50
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
T & P and Sundries etc. L.S. Rs 64.6
Total Rs 575.87
Water charges 1.5% of (A+B) Rs 26.45
Total Rs 1789.97
Contractor s profit @ 10% Rs 179.00
TOTAL Rs 1968.97
Rate for 9.29 Sqm 1968.97
Rate for 1.00 Sqm Rs 211.95
Say Rs 212.00

606 Add in item no 601 to 603 and 605 when floors are polished including supply of exta cement, chapra
bati, carborandum stone, all other materials, labour and T & P etc. required for proper completion fo
the work. Marble dust shall be added in floating coat in ratio of 5:1 ( Marble dust and cement) if
necessary but no exra amount will be paid for it. This includes final finish with french mansion polish
or other approved polish.

(A ) Materials :
Extra cement or cement & marble- Per 50
dust mortar. Kg bags 0.50 bag Rs 210.00 Rs 105.00
Polishing and rubbing materials L.S. Rs 60.00
Total Rs 165.00
(B) Labour :
For polishing and cutting - Beldar
Per day 8.00 no. Rs 110.00 Rs 880.00
Total Rs 880.00
Water charges 1.5% of (A+B) Rs 15.67
Total Rs 1060.68
Contractor s profit @ 10% Rs 106.07
TOTAL Rs 1166.74
Rate for 9.29 Sqm 1166.74
Rate for 1.00 Sqm Rs 125.59
Say Rs 125.60

612 First class brick on edge floor laid in cement mortar consisting of one part of cement & six part of fine
sand of 1.25 F.M. & pointed with cement mortar 1:2 over and including 8 cm (3") thick brick ballast
base concrete with Kankar lime mortar including supply of all materials, labour and T & P etc.
required for proper completion of the work.
(A ) Materials :
3" base concrete in Kankar lime
mortar as per item No-271 cum 0.708 cum Rs 2325.70 Rs 1646.41
1class brick Per 0/00 530.00 no. Rs 3000.00 Rs 1590.00
Cement Per bag 1.25 bag Rs 210.00 Rs 262.50
Fine sand Per cum 0.241 cum Rs 410.00 Rs 98.68
Cement pointing 1:2 cement and
local sand mortor (item no-
574-576) Sqm 9.290 Sqm Rs 90.80 Rs 843.53
Total Rs 4441.13

(B) Labour :
Mistri Per day 1/10 no. Rs 210.00 Rs 21.00
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Total Rs 473.50
Water charges 1.5% of (A+B) Rs 73.72
Total Rs 547.22
Total(A+B) Rs 4988.34
Contractor s profit @ 10%
Rs 498.83
TOTAL Rs 5487.18
Rate for 9.29 Sqm 5487.18
Rate for 1.00 Sqm Rs 590.65
Say Rs 590.70

613 As in item no 612 above but with 8 cm( 3") thick base concrete consisting of brick ballast white lime
and surkhi in ratio of 100:16:32.
(A ) Materials :
3" base concrete in Brick ballast,
white lime and surkhi mortar in ratio
of 100:16:32 as per item No-272
cum 0.708 cum Rs 1667.00 Rs 1180.10
1class brick Per 0/00 530.00 no. Rs 3000.00 Rs 1590.00
Cement Per bag 1.25 bag Rs 210.00 Rs 262.50
Fine sand Per cum 0.241 cum Rs 410.00 Rs 98.68
Cement pointing 1:2 cement and
local sand mortor (item no-
574-576) Sqm 9.290 Sqm Rs 90.80 Rs 843.53
Total Rs 3974.82

(B) Labour :
Mistri Per day 1/10 no. Rs 210.00 Rs 21.00
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Total Rs 473.50
Water charges 1.5% of (A+B) Rs 66.72
Total Rs 4515.04
Contractor s profit @ 10% Rs 451.50
TOTAL Rs 4966.55
Rate for 9.29 Sqm 4966.55
Rate for 1.00 Sqm Rs 534.61
Say Rs 534.60

614 As in item no 612 above but with 8 cm( 3") thick base concrete consisting of one part of cement four
part of fine sand of 1.25 F.M. and eight part of brick ballast( 1:4:8).
(A ) Materials :
3" base concrete in 1:4:8 cement ,
fine sand and Brick ballast, as per
item No-275
cum 0.708 cum Rs 2310.30 Rs 1635.51
1class brick Per 0/00 530.00 no. Rs 3000.00 Rs 1590.00
Cement Per bag 1.25 bag Rs 210.00 Rs 262.50
Fine sand Per cum 0.241 cum Rs 410.00 Rs 98.68
Cement pointing 1:2 cement and
local sand mortor (item no-
574-576) Sqm 9.290 Sqm Rs 90.80 Rs 843.53
Total Rs 4430.22

(B) Labour :
Mistri Per day 1/10 no. Rs 210.00 Rs 21.00
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Total Rs 473.50
Water charges 1.5% of (A+B) Rs 73.56
Total Rs 4977.28
Contractor s profit @ 10%
Rs 497.73
TOTAL Rs 5475.01
Rate for 9.29 Sqm 5475.01
Rate for 1.00 Sqm Rs 589.34
Say Rs 589.30

615 First class brick on edge flooring laid dry joints sand filled including prepration of baseto proper slope
and its ramming and including supply of all materials, labour and T & P etc. required for proper
completion of the work.
(A ) Materials :
1class brick Per 0/00 530.00 no. Rs 3000.00 Rs 1590.00
Sand Per cum 0.283 cum Rs 275.00 Rs 77.87
Total Rs 1667.87

(B) Labour :
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1 1/2 no. Rs 110.00 Rs 165.00
Coolies Per day 1/2 no. Rs 110.00 Rs 55.00
Total Rs 420.00
Water charges 1.5% of (A+B) Rs 31.32
Total Rs 2119.19
Contractor s profit @ 10% except on cost of bricks & sand Rs 211.92
TOTAL Rs 2331.11
Rate for 9.29 Sqm 2331.11
Rate for 1.00 Sqm Rs 250.93
Say Rs 250.90

620 Granolithic marble flooring 2.5 cm(1") thick consisting of one part cement, two part of approved
coarse sand and 4 part of 2 cm(3/4") graded approved stone chips including 6 mm (1/4") thick
surface coat with ordinary cement black, white or grey or mixed marble chips passing 3 mm (1/8") but
retained on 1.5 mm (1/6") mesh screen in proportion of 1:2 as specified or directed by the E/I and
polished by hand or machine and finally finished with french manson polish or other approved polish
including 8 cm (3") Kankar lime concrete base including supply of all materials , labour and T & P etc
required for proper completion of the work.

(A ) Materials :
3" base concrete in Kankar lime
mortar as per item No-271 cum 0.708 cum Rs 2325.70 Rs 1646.41
3/4" C.C.stone chips 3/4" granite Cum 0.198 no. Rs 1340.00 Rs 0.27
Coarse sand Per cum 0.113 cum Rs 635.00 Rs 71.92
Cement Per bag 1.75 bag Rs 210.00 Rs 367.50
1/4" Granolithic chips: Marble chips Per qtls 0.25 qtls Rs 215.00 Rs 53.75
Cement Per bag 1.00 bag Rs 210.00 Rs 210.00
Sundries for rubbing and polishing L.S. Rs 150.00
Total Rs 2499.85

(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 2 no. Rs 200.00 Rs 400.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Beldar for cutting and polishing Per day 15 no. Rs 110.00 Rs 1650.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Sundries like phanties etc. L.S. Rs 89.49
Total Rs 2418.24
Water charges 1.50 % of (A+B) Rs 73.77
Total Rs 4991.86
Contractor s profit @ 10% except on cost of cement sand &
base concrete Rs 499.19
TOTAL Rs 5491.05
Rate for 9.29 Sqm 5491.05
Rate for 1.00 Sqm Rs 591.07
Say Rs 591.10

621 As in item no 620 above but when white cement is used in top 5 mm (1/4") layer instead of ordinary
cement.
Rate as per item no 620 above Rs 5491.05
Ded cost of grey cement Per bag 1.00 bag Rs 210.00 Rs -210.00
Add cost of white cement From
market Per bag 1.00 bag Rs 575.00 Rs 575.00
Contractor s profit @ 10% on Rs. 575.00 Rs 57.50
TOTAL Rs 5913.55
Rate for 9.29 Sqm 5913.55
Rate for 1.00 Sqm Rs 636.55
Say Rs 636.60

622 As in item no 620 above but when coloured floor are to be made.
Rate as per item no 620 above Rs 5491.05
Add cost of colour (Deep bluish) Per bag 4.00 Kg Rs 190.00 Rs 760.00
Contractor s profit @ 10% on Rs. 760.00 Rs 76.00
Water charges 1.50 % of Rs. 760.00 11.40
Ded cost of grey cement Per bag 4.00 bag Rs 210.00 Rs -840.00
TOTAL Rs 5498.45
Rate for 9.29 Sqm 5498.45
Rate for 1.00 Sqm Rs 591.87
Say Rs 591.90

624 As in item no 620 to 622 above but base cocrete consisting of one part of cement, 4 part of loacl
sand and 8 part of brick ballast.
Add Extra :- Difference in the cost of

3" base concrete wth brick ballast,


White lime and surkhi in100:16:32
mortar as per item No-272
Add. cum 0.708 cum Rs 4717.61 Rs 3339.69
3" base concrete in Kankar lime
mortar as per item No-271 Ded. cum 0.708 cum Rs 26.25 Rs -18.58

TOTAL Rs 3321.11
Rate for 9.29 Sqm 3321.11
Rate for 1.00 Sqm Rs 357.49
Say Rs 357.50
625 Granolithic marble dado 2 cm(3/4") thick consisting of 15 mm (9/16") thick layer of one part cement,
two part of approved coarse sand including 5 mm (3/16") thick surface coat with ordinary cement,
black, white or grey or mixed marble chips passing 3 mm (1/8") but retained on 1.5 mm (1/6") mesh
screen in proportion of 1:2 as specified or directed by the E/I and polished by hand or machine and
finally finished with french manson polish or other approved polish including 8 cm (3") Kankar lime
concrete base including supply of all materials , labour and T & P etc required for proper completion
of the work.

(A ) Materials :
Base 12 mm thick cement plaster
1:2 as base coat wth cement and
coarse sand as per S.I.Nos 581 Sqm 9.290 Sqm Rs 107.70 Rs 1000.53
3/8" thick rubbed to 1/4" marble
chip Per qtls 1.400 qtls Rs 215.00 Rs 0.30
Cement Per bag 1.00 bag Rs 210.00 Rs 210.00
Sundries for rubbing and polishing L.S. Rs 180.00
Total Rs 1390.83

(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 3/4 no. Rs 200.00 Rs 150.00
Beldar Per day 3/4 no. Rs 110.00 Rs 82.50
Beldar for cutting and polishing Per day 15 no. Rs 110.00 Rs 1650.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Total Rs 1950.00
Water charges 1.50 % of (A+B) Rs 50.11
Total Rs 3390.95
Contractor s profit @ 10% Rs 339.09
TOTAL Rs 3730.04
Rate for 9.29 Sqm 3730.04
Rate for 1.00 Sqm Rs 401.51
Say Rs 401.50

626 As in item no 625 above but when white cement is used in top 5 mm (3/16") layer instead of ordinary
cement.
Rate as per item no 625 above Rs 3730.04
Ded cost of grey cement Per bag 1.00 bag Rs 210.00 Rs -210.00
Add cost of white cement From
market Per bag 1.00 bag Rs 575.00 Rs 575.00
Contractor s profit @ 10% on Rs. 575.00 Rs 57.50
TOTAL Rs 4152.54
Rate for 9.29 Sqm 4152.54
Rate for 1.00 Sqm Rs 446.99
Say Rs 447.00

627 As in item no 620 above but when coloured dado are to be made.
Rate as per item no 625 above Rs 3730.04
Add cost of colour (Deep bluish) Per bag 4.00 Kg Rs 190.00 Rs 760.00
Contractor s profit @ 10% on Rs. 760.00 Rs 76.00
Water charges 1.50 % of Rs. 760.00 11.40
Ded cost of grey cement Per bag 4.00 bag Rs 210.00 Rs -840.00
TOTAL Rs 3737.44
Rate for 9.29 Sqm 3737.44
Rate for 1.00 Sqm Rs 402.31
Say Rs 402.30

628 Supply & fixing 6 mm (1/4") China white glazed in flooring or skirting dado laid with 1:3 cement and
approved coarse sand mortar finished with white cement slurry jointing and polishing complete
including supply of all materials, labour and T & p etc required for proper completion of the work.
( Taken an area of 12 sq yard - 108 sq.ft )
Or Taken 10.03 Sqm
(A ) Materials :
Tiles required Per doz 36.000 doz Rs 115.00 Rs 4140.00
Cement Per bag 3.20 bag Rs 210.00 Rs 672.00
Coarse sand Per cum 0.34 Cum Rs 635.00 Rs 215.77
White Cement Per bag 1.00 bag Rs 575.00 Rs 575.00
Marble dust Per cum 0.11 cum Rs 6000.00 Rs 679.60
Total Rs 6282.38

(B) Labour :
Mistri/ Tile Layers Per day 4 no. Rs 210.00 Rs 840.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Sundries L.S. Rs 45.00
Total Rs 1105.00
Water charges 1.50 % of (A+B) Rs 110.81
Total Rs 7498.19
Contractor s profit @ 10% Rs 749.82
TOTAL Rs 8248.01
Rate for 10.03 Sqm 8248.01
Rate for 1.00 Sqm Rs 822.33
Say Rs 822.30

630 Providing and fixing aluminium strips of 16" gauge in joints of floors & skirtings at the time of laying
floors flush with leavel, including labour and T & P etc complete. ( Skelton analysis as per S.I. No 20,
1962 CPWD analysis)

Taken 43.89 Rm
(a) of 2.5 cm (1") depth .
Details of cost of 144 rft.( or 43.89
Rm) Of aluminium sheet cut into
strips 16" gauge 1" depth wt=
4.91 Kg
Add wastage 5 % on above 0.25 Kg
Total 5.16 Kg

(A ) Materials :
Cost of strips Per kg 5.160 Kg Rs 150.00 Rs 774.00
Carriage of Strips L.S. 8.11
Total Rs 782.11
(B) Labour :
Mason Per day 1.00 no. Rs 200.00 Rs 200.00
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Sundries L.S. Rs 33.33
Total Rs 343.33
Water charges 1.50 % of (A+B) Rs 5.27
Total Rs 356.71
Contractor s profit @ 10% Rs 35.67
TOTAL Rs 392.39
Rate for 43.89 Rm 392.39
Rate for 1.00 Rm Rs 8.94
Say Rs 8.90

(b) of 4 cm (1 1/2") depth .


Details of cost of 144 rft.( or 43.89
Rm) Of aluminium sheet cut into
strips 16" gauge 1" depth wt=
7.37 Kg
Add wastage 5 % on above 0.37 Kg
Total 7.74 Kg

(A ) Materials :
Cost of strips Per kg 7.740 Kg Rs 150.00 Rs 1161.00
Carriage of Strips L.S. 8.11
Total Rs 1169.11
(B) Labour :
Mason Per day 1.00 no. Rs 200.00 Rs 200.00
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Sundries L.S. Rs 33.33
Total Rs 343.33
Water charges 1.50 % of (A+B) Rs 5.27
Total Rs 356.71
Contractor s profit @ 10% Rs 35.67
TOTAL Rs 392.39
Rate for 43.89 Rm 392.39
Rate for 1.00 Rm Rs 8.94
Say Rs 8.90

631 Providing and fixing glass strips of 3.15 mm(1/8") thickness in joints of floors & skirtings at the time
of laying floors flush with leavel, including labour and T & P etc complete.

Taken 43.89 Rm
(a) of 2.5 cm (1") depth .
Details of cost of 144 rft.( or 43.89
Rm) Of glass strips 1/8" thick

(A ) Materials :
Cost of strips Per Rm 43.890 Rm Rs 4.40 Rs 193.12
Carriage of Strips L.S. 0.28
Total Rs 193.40
(B) Labour :
Mason Per day 1.00 no. Rs 200.00 Rs 200.00
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Sundries L.S. Rs 33.33
Total Rs 343.33
Water charges 1.50 % of (A+B) Rs 5.15
Total Rs 348.77
Contractor s profit @ 10% Rs 34.88
TOTAL Rs 383.64
Rate for 43.89 Rm 383.64
Rate for 1.00 Rm Rs 8.74
Say Rs 8.70

(b) of 4 cm (1 1/2") depth .Details of cost of 144 rft.( or 43.89 Rm) Of Glass strips 3.15 mm
(1/8")

(A ) Materials :
Cost of strips Per Rm 43.890 Rm Rs 7.70 Rs 337.95
Carriage of Strips L.S. 0.42
Total Rs 338.37
(B) Labour :
Mason Per day 1.00 no. Rs 200.00 Rs 200.00
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Sundries L.S. Rs 33.33
Total Rs 343.33
Water charges 1.50 % of (A+B) Rs 5.16
Total Rs 348.91
Contractor s profit @ 10% Rs 34.89
TOTAL Rs 383.80
Rate for 43.89 Rm 383.80
Rate for 1.00 Rm Rs 8.74
Say Rs 8.70
CHAPTER - 15
PAINTING & DISTEMPRING

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Unit - 9.29 sqm
649 One priming coat & one coat oil ditemper on new work including supply of all materials, labour and
T&P etc. required for proper completion of the work.
(A ) Materials :
Painting coat whiting Per kg 1.000 kg Rs 4.00 Rs 4.00
Painter Per day 0.125 no. Rs 200.00 Rs 25.00
Coolies Per day 0.125 no. Rs 110.00 Rs 13.75

Distempering. Oil distemper in


paste Per kg 1.500 kg Rs 53.00 Rs 79.50
T & P and Sundries etc. L.S. Rs 20.00
Painter Per day 0.375 no. Rs 200.00 Rs 75.00
Coolies Per day 0.375 no. Rs 110.00 Rs 41.25
Total Rs 258.50
Contractor s profit @ 10% Rs 25.85
Total Rs 284.35
Rate 9.29 sqm Rs 284.35
Rate for 1.00 sqm Rs 30.61
Say Rs 30.6

Unit - 9.29 sqm


650 As in item no. 649 above but for every coat after the first coat.

(A ) Materials :
Distempering. Oil distemper in
paste Per kg 0.750 kg Rs 53.00 Rs 39.75
T & P and Sundries etc. L.S. Rs 20.00
Painter Per day 0.200 no. Rs 200.00 Rs 40.00
Coolies Per day 0.200 no. Rs 110.00 Rs 22.00
Total Rs 121.75
Contractor s profit @ 10% Rs 12.18
Total Rs 133.93
Rate 9.29 sqm Rs 133.93
Rate for 1.00 sqm Rs 14.42
Say Rs 14.4
Unit - 9.29 sqm
660 Finishing walls with water proofing cement paint of approved make and new work with two coats to
give an even shade, including supply of all materials, labour and T&P etc. required for proper
completion of the work.
(A ) Materials :
Snowcem powder Per kg 3.40 kg Rs 35.00 Rs 119.00
Painter Per day 0.30 no. Rs 200.00 Rs 60.00
Coolies Per day 0.30 no. Rs 110.00 Rs 33.00
Bhisti Per day 0.38 no. Rs 130.00 Rs 48.75
Scaffolding andT & P and
Sundries etc. L.S. Rs 20.00

Total Rs 280.75
Water charges @ 1.5% Rs 4.21

Total Rs 284.96
Contractor s profit @ 10% Rs 28.50
Total Rs 313.46
Rate 9.29 sqm Rs 313.46
Rate for 1.00 sqm Rs 33.74
Say Rs 33.7

Unit - 9.29 sqm


661 Same as in item no. 660 but for each coat of water proofing cement paint of approved make after
the first two coats to give an even shade, including supply of all materials, labour and T&P etc.
required for proper completion of the work.
(A ) Materials :
Snowcem powder Per kg 1.70 kg Rs 35.00 Rs 59.50
Painter Per day 0.08 no. Rs 200.00 Rs 15.00
Coolies Per day 0.08 no. Rs 110.00 Rs 8.25
Scaffolding andT & P and Per day
Bhisti 0.13 no. Rs 130.00 Rs 16.25
Sundries etc. L.S. Rs 20.00
Total Rs 119.00
Water charges @ 1.5% Rs 1.79

Total Rs 120.79
Contractor s profit @ 10% Rs 12.08
Total Rs 132.86
Rate 9.29 sqm Rs 132.86
Rate for 1.00 sqm Rs 14.30
Say Rs 14.3

Rate for Ist coat Rs 22.10


Rate for IInd coat Rs 10.30
Rate for IIIrd coat Rs 10.30
Total Rs 42.70
CHAPTER - 16
WHITE AND COLOUR WASHING

SI No. Item of work Unit Quantity Rate Cost


1 2 3 4 5 6
Unit - 9.29 sqm
671 White washing one coat including supply of all materials, labour and T&P etc. required for proper
completion of the work.
(A ) Materials :
White lime Per kg 1.00 kg Rs 5.50 Rs 5.50
White washer Per day 0.07 no. Rs 200.00 Rs 13.33
Helper (Coolies) Per day 0.07 no. Rs 110.00 Rs 7.33

T & P and
Sundries,gum ,ladder etc. L.S. Rs 20.00
Total Rs 46.17
Contractor s profit @ 10% Rs 4.62
Total Rs 50.78
Rate 9.29 sqm Rs 50.78
Rate for 1.00 sqm Rs 5.47
Say Rs 5.5

Unit - 9.29 sqm


672 As item no. 671 but for two coats.

(A ) Materials :
White lime Per kg 2.00 kg Rs 5.50 Rs 11.00
White washer Per day 0.07 no. Rs 200.00 Rs 13.33
Helper (Coolies) Per day 0.07 no. Rs 110.00 Rs 7.33
T & P and
Sundries,gum ,ladder etc. L.S. Rs 20.00
Total Rs 51.67
Contractor s profit @ 10% Rs 5.17
Total Rs 56.83
Rate 9.29 sqm Rs 56.83
Rate for 1.00 sqm Rs 6.12
Say Rs 6.1

673 As item no. 671 but for three coats.

two coats as per item no.672 Rs 6.12


Add difference in cost of one
additional coat. (672-671) Rs 0.65
Rate for 1.00 sqm Total Rs 6.77
CHAPTER - 20
ROAD WORK
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

751 Consolidation of kankar by hand rammer including opening out stacks , shorting kankar in to Three
sizes repairing patch in existing road surface with kankar, picking up old surface , spreading kankar
, making medhi to retain water and ramming and also including carriage of metal up to 30M (100').
carriage of water to 100M (1furlong) supply and maintenance of barrior , caution posts , light at
night and including all T&P etc. required for proper completion of the work, kankar to the supplied
to the contractor free of cost at site.

Taking up a length of 220x12' = 2640.00 sft kankar required 2640.00x3/8=990.00 cft Or 28.31
Cum
Taken for 28.01 Cum Unit Cum
Labour:-
Beldar for crish croos lines & Per day 220.00
Sweeping & taking out kankar
dug. 2.00 no. Rs 110.00 Rs
Preparing earth & making medhi Per day 110.00
mazdoor 1.00 no. Rs 110.00 Rs
Opening out stacks shorting in to
sizes.
Beldar Per day 2.00 no. Rs 110.00 Rs 220.00
Mazdoor Per day 2.00 no. Rs 110.00 Rs 220.00
Carriage of kankar & spreading
on surface
Mazdoor Per day 4.00 no. Rs 110.00 Rs 440.00
Hand packing Beldar Per day 6.00 no. Rs 110.00 Rs 660.00
Supply of water. Mazdoor Per day 8.00 no. Rs 110.00 Rs 880.00
Consolidation .
Head rammer man Per day 1.00 no. Rs 110.00 Rs 110.00
Rammer man Per day 11.00 no. Rs 110.00 Rs 1210.00
Basi chot Beldar Per day 2.00 no. Rs 110.00 Rs 220.00
Leakh katai L.S Rs 33.9
T&P and night light. L.S Rs 33.9
Total Rs 4357.70
Contractor s profit @ 10% Rs 435.77
Total Rs 4793.47
Rate per 28.01 Cum Rs 4793.47
Rate per 1 Cum Rs 171.13
Say Rs 171.10 150

752 As in item no-751 above but for consolidation by road roller including hire & fuel of the roller .
Taken for 28.01 Cum
As in item no-751 Rs 4793.47
Deduct for labour involve in
consolidation (A) Rs -1400.00
Add for hire charges of road Per day
roller. 1.00 no. Rs 0.00 Rs 0.00
Steam coal Per day 0.25 Ton Rs 0.00 Rs 0.00
Beldar Per day 2.00 no. Rs 110.00 Rs 220.00
Total Rs 3613.47
Contractor s profit @ 10% on Rs. -120
184.00 only Rs
Total Rs 3493.47

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Rate per 28.01 Cum Rs 3493.47

Rate per 1 Cum Rs 124.72


Say Rs 124.70 55
753 As in item no-752 above but for 12cm thick coat of brick ballast.
Taken for 28.01 Cum
As in item no-752 Rs 3493.47
Extra labour for providing
building material
Beldar Per day 0.50 no. Rs 110.00 Rs 55.00
Total Rs 3548.47
Contractor s profit @ 10% on Rs. 5
46.00 only Rs
Total Rs 3553.47
Rate per 28.01 Cum Rs 3553.47
Rate per 1 Cum Rs 126.86
Say Rs 126.90 55

754 As in item no-752 above but for 8 cm thick coat of brick ballast.
Taken for 28.01 Cum
As in item no-752 Rs 3037.69
Add diffrance in item no-755/756
36.40
Total Rs 3074.09
Rate per 28.01 Cum Rs 3074.09
Rate per 1 Cum Rs 109.75
Say Rs 109.80

755 As in item no-752 above but for 12 cm thick stone ballast.


Taken for 28.01 Cum
As in item no-752 Rs 3493.47
Extra labour for providing
building materials in excess
including 10% C.P
Beldar Per day 0.75 no. Rs 110.00 Rs 75.00
Add for extra coat to be used L.S Rs 20.3
Total Rs 3588.78
Contractor s profit @ 10% on Rs.
69.00 only Rs 7.50
Total Rs 3596.28
Rate per 28.01 Cum Rs 3596.28
Rate per 1 Cum Rs 128.39
Say Rs 128.40
756 As in item no-752 above but for 6cm to 8cm thick, stone ballast consider a length of 220 rft
materials required = 220x12x1/4 = 660.00cft (18.69 cum )
Taken Qtty 18.6846 Cum
Beldar Per day 2.00 no. Rs 110.00 Rs 220.00
Preparing earth & making medhi Per day 110.00
mazdoor 1.00 no. Rs 110.00 Rs
Opening out stacks carriage and
spreading on road surface Beldar
Per day 330.00

3.00 no. Rs 110.00 Rs

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Hand packing Beldar Per day 8.00 no. Rs 120.00 Rs 960.00

Supply of water. Mazdoor Per day


6.00 no. Rs 110.00
Rs 660.00
Consolidation roller charges Per day 1.00 day Rs 0.00Rs 0.00
coal (Market Rate ) Per Ton 1/6 ton Rs 0.00Rs 0.00
Beldar Per day 2.00 no. Rs 110.00
Rs 220.00
Blinding Beldar Per day 2.00 no. Rs 110.00
Rs 220.00
Leakh katai L.S Rs 50.8
T&P and night lanterns. L.S Rs 101.5
Total Rs 2872.31
Contractor s profit @ 10% 2872.31 - 0.00 2872.31 Rs 287.23
Total Rs 3159.54
Extra for corrcting sub grade L.S Rs 33.9
Rate per 18.6846 Cum Total Rs 3193.39
Rate per 1 Cum Rs 170.91
Say Rs 170.90

757 Water allowance to be allowed on item no-756 between 15 Nov. to 31 May


Taken Qtty 2.83 Cum (100cft)
Beldar Per day 0.75 no. Rs 110.00 Rs 82.50
Contractor s profit @ 10% Rs 8.25
Total Rs 90.75
Rate per 2.83 Cum Rs 90.75
Rate for 1.00 cum Rs 32.07
Say Rs 32.10

758 Digging kankar including breaking , cleaning and royalty as well as the cost of boring to fined
kankar strata excluding cartage and proper stacking.
Taken Qtty 2.83 Cum (100cft)
Royalty to villagers Rs 0.00
Indication (digging) Per day 1/8 no. Rs 130.00 Rs 16.25
Beldar Per day 4.00 no. Rs 110.00 Rs 440.00
Coolie Per day 3.00 no. Rs 110.00 Rs 330.00
Total Rs 786.25
For hundred cft . Of kankar 110cft. Of kankar as the quary will have to be dug.
Hence extra 10% on above but
excluding Royality Rs 78.63
Total Rs 864.88
Rate per 2.83 Cum Rs 864.88
Rate for 1.00 Cum Rs 305.61
Say Rs 305.60

759 Making mud tree gaurds 1M (3'-4') internal diameter and I meter (3'-4') high above.ground level
Unit = 1 Nos
Mason Per day 3/4 no. Rs 200.00 Rs 150.00
Coolie Per day 3/4 no. Rs 110.00 Rs 82.50
Sun dries etc. L.S Rs 5.28
Total Rs 237.78
Contractor s profit @ 10% on Rs. Rs 23.78
146 only

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Total Rs 349.34

Rate for Each Rs 349.34


Say Rs 349.30

760 Dag-belling 15 cm. Deep in one line alinged, with flags and jhandies as directed by the Engineer-in-
charge.
Unit = 1 Km
Taken Length 1.61 Km (1 Mile)
Mate Per day 1.00 no. Rs 130.00 Rs 130.00
Beldar Per day 9.00 no. Rs 110.00 Rs 990.00
Total Rs 1120.00
Contractor s profit @ 10% on Rs. Rs 112.00
146 only Total Rs 2222.00
Rate for . 1.61 Km Rs 2222.00
Rate for 1.00 Km Rs 1380.12
Say Rs 1380.10

761 Painting white traffic lines 8 cm. Wide in three coats with approved road marking paint (Spirit base)
As directed by E/I. including supply of all materials, labour and T&P etc. required for proper
completion of the work.
Unit = 1 Rm

Take an area of 100 sft / Lines

Road marking paint Per Lit 4.50 Lit Rs 0.00 Rs 0.00


Painter Per day 5.00 no. Rs 200.00 Rs 1000.00
Beldar Per day 5.00 no. Rs 110.00 Rs 550.00
Sundries L.S 150.00
Rate for 116.125 Rm Total Rs 1700.00
Rate per RM 14.64
Add @10% C.P Rs 1.46
Total Rs 16.10

Say Rs 16.1
762a
Brick soling with straight overburnt bricks laid flat and dry including preparation of subgrade to
prescribed camber and including supply of bricks, filling joints, with local earth spreading a blinding
coat of cm. (3/8") depth of local earth of P.I.5 to 7 or sand. over the entire surface & including
labour & T&P etc. required for proper completion of the work.

Unit = 1 Sqm
Taken 9.29 Sqm (100Sqft)
Bricks Per %0 350 no. Rs 2900.00 Rs 1015.00
Rate of preparing subgrade and
laying as per item No- 785 278.66
Total 1293.66
Contractor profit @ 10% on Rs. Rs 0.00
Total Rs 1293.66
Rate for 9.29 Sqm Rs 1293.66
Rate for 1.00 Sqm Rs 139.25
Say Rs 139.30

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

762 As in item no-762(a) but with bricks laid on edge.


(B)
Taken for 9.29 Sqm (100Sqft)
Bricks Per 0/00 550.00 nos Rs 2900.00 Rs 1595.00
Rate of preparing subgrade and
laying as per item No- 786
L.S 322.66
Total 1917.66
Contractor profit @ 10% on Rs.
Rs 159.50
Total Rs 2077.16
Rate for 9.29 Sqm Rs 2077.16
Rate for 1.00 Sqm Rs 223.59
Say Rs 223.60
763 Bricks on edge payement on patries with bricks laid dry , joints filled with local sand including
preparation of base to proper slope and its ramming , spreading a layer of cm. (3/8") depth of local
sand over the subgrade and including supply of all materials, labour and T&P etc. required for
proper completion of the work.

Unit = 1 Sqm
Taken for 9.29 Sqm (100Sqft)
As in item no-762(b) above Rs. 2077.16

Extra cost of labour and 10 cft


local sand, including
Local sand Per cum 0.283 cum Rs 275.00 Rs 77.83
Labour L.S Rs 100.00
Total 2254.99
Contractor profit @ 10% on Rs. Rs 10.00
Total Rs 2264.99
Rate for 9.29 Sqm Rs 2264.99
Rate for 1.00 Sqm Rs 243.81
Say Rs 243.80
764 Renewing patries 3 metre (10') wide including dressing surface filling up to 8 cm (3") depth &
making namunas at every 15 m.(50') apart on either side of the road true to patri templete with side
slopes 1:2 etc. for taking the earth to be so dug that form a continuous side drain at road boundry.
Take a length of 1 furlong.
Unit = 1 Km
Taken for 0.201 Km (1 Furlong or 660 Rft )
Mate
Diggers Per day 10.00 no. Rs 110.00 Rs 1100.00
Dressers Km 2.00 Rs 110.00 Rs 220.00
coolie Per day 12.00 no. Rs 110.00 Rs 1320.00
Baskeats Per day 4.00 no. Rs 15.00 Rs 60.00
String L.S Rs 25.00
T&P L.S Rs 20.00
Total Rs 2745.00
Contractor s profit @ 10% Rs 274.50

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Total Rs 3019.50
Rate for 0.201 Km Rs 3019.50
( 1.00 Furlong)
Rate for 1.00 Km Rs 15022.39
Say Rs 15022.40
765 Brick edging on both sides of roads of 1st clas bricks 8cm (3") wide & 12 cm (4.50") deep laid with
mud mortor including labour & suplly of bricks finished to required templete and in proper alignment
and also including dressing & ramming the excavated earth as directed by the E/I.
Unit = 1 Km
Take a strip of 1/2 furlong 2 x 330 = 660 rft.
2x 330 = 660 rft
Bricks Per %0 875.00 no. Rs 2900.00 Rs 2537.50
Mason Per day 1.00 no. Rs 200.00 Rs 200.00
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
coolie Per day 2.00 no. Rs 110.00 Rs 220.00
Dressing &
throwing
coolie Per day 2.00 no. Rs 110.00 Rs 220.00
T&Psurplus
, Baskets & other sundries L.S Rs 25.38
material
Total Rs 3312.88
Contractor s profit @ 10% Rs 331.29
Total Rs 3644.17
Rate for 0.201 Km Rs 3644.17
Rate for 1.00 Km Rs 18130.21
Say Rs 18130.20

766 Stacking of road metal to required templete after screening at road side including dressing of side
berms as required , were matel is to be stacked and including a lead up to 60M (200")
Unit = 1 Cum
Taken 2.83 Cum
Screening coolie Per day 0.20 no. Rs 120.00 Rs 24.00
Dressing, leveling , side burms , including filling.
coolie Per day 0.20 no. Rs 110.00 Rs 22.00
stacking beldar Per day 0.50 no. Rs 120.00 Rs 60.00
T&P & other sundries etc. L.S Rs 6.77
Total Rs 112.77
Contractor s profit @ 10% Rs 11.28
Total Rs 124.05
Rate per 2.83 Cum Rs 124.05
Rate for 1.00 Cum Rs 43.83
Say Rs 43.80

Taking area 367.884 Sqm


767 Bitumen painting (Labour only) over W.B surface (1st coat) excluding supply of paint & grit
including maintenance of side patries & watering them during opreation for proper completion of the
work As directed by the E/I. & excluding Roller charges & its fuel but including the wages of fire
man & Tar boiler man.
Unit = 1 Sqm
Taken Area 330x12 = 3960 Sqft
Or 367.88 Sqm
Celaning grit : Mazdoor Per day 1.00 no. Rs 110.00 Rs 110.00
Celaning sub grade : Mazdoor Per day 10.00 no. Rs 110.00 Rs 1100.00

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

coolie Per day 880.00


8.00 no. Rs 110.00 Rs
Tar heatting & spreading on
road.beldar
Hot Per day 7.00 no. Rs 120.00 Rs 840.00
Grit spreading beldar Per day 5.00 no. Rs 110.00 Rs 550.00
Diversion watering : Beldar Per day 2.00 no. Rs 110.00 Rs 220.00
Misce: Mate Per day 1.00 no. Rs 130.00 Rs 130.00

Work agent Per day 65.00


0.50 no. Rs 130.00 Rs
Tar boiler / Fair Man Per day 1.00 no. Rs 140.00 Rs 140.00
Sundries L.S L.S 330.00
Total Rs 4365.00
Rate per 367.880 Sqm Rs 4365.00
Rate for 1.00 Sqm Rs 11.87
Say Rs 11.90
768 As in item no 767 above but subsquent coat of painting over previously painted surface. The
above labour will make an output of double the area I.e, the same labour can do the painting of
one furlong .
Unit = 1 Sqm
Taken Area 330x12 = 3960 Sqft
Or 367.88 Sqm
Rate 1/2 of S.I. No 767 Rs 2182.50
Rate per 367.88 Sqm Total Rs 2182.50

Rate for 1.00 Sqm Rs 5.93


Say Rs 5.90
769 As in item no 767 above but cold emulsion in 2nd coat painting with bitumen covering one
furlong
Unit = 1 Sqm
Taken 9.29 Sqm (100Sqft)
(As per item no-767) 4365.00

Deduct labour for heating paint


not Required in this opreation as
in item 767 (-) 895.00
Eaxtra labour required for
opreation L.S Rs 169.23
Total Rs 3639.23
Rate per 735.760 Sqm Rs 3639.23
Rate for 1.00 Sqm Rs 4.95
Say Rs 5.00
770 As in item no- 767 above but with tar in first coat painting with bitumen 1/2 furlong
Unit = 1 Sqm
Taken 9.29 Sqm (100Sqft)
As per S.I.No 767 4365.00

Deduct less labour required for Per day 4.00 no. Rs 110.00 Rs -440.00
Heating Tar beldar Total Rs 3925.00
Rate per 367.880 Sqm Rs 3925.00

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Rate for 1.00 Sqm Rs 10.67


Say Rs 10.70

771 As in item 767 but with Tar in 2nd coat or other subsquent coats of painting over previously painted
surface . The above labour will make an output double the area I.e. the same labour can do the
painting of one furlong.

Unit = 1 Sqm

772 Scraping old painted suface including disposal of all scraped material to a distance of 30m. (100')
as directed by E/I.
Unit = 1 Sqm
Taken 9.29 Sqm (100Sqft)
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00

Contractor s profit @ 10% 11


Total Rs 121.00
Rate per 9.290 Sqm Rs 121.00
Rate for 1.00 Sqm Rs 13.02
Say Rs 13.00
773 Laying C.C road slab 10cm (4"0 thick consisting of 1:2:4 cement , coarse sand & approved 4cm (1
1/2") gauge stone ballast, over prepared sub grade after its rectifications & bringing it to proper
camber and including supply of all materials, labour T&P etc. required for proper completion of
work, finished to required templete as directed by E/I. but excluding cost of metal required for
reflection of the sub-grade. Take a slab length of 33 rft. and 4' in depth .Qnty. of work involved

Unit = 1 Cum

Taking qtty 3.7369 Cum


Stone ballast 1 1/2 " gauge Per Cum 3.37 Cum Rs 1225.00 Rs 4128.25
Course sand Per Cum 1.70 Cum Rs 635.00 Rs 1079.50
Cement bag Per Bag 25.00 Bag Rs 210.00 Rs 5250.00
Empty bag each 15.00 Bag Rs 2.00 Rs 30.00
Tar and other side forms etc. L.S Rs 30.00

Laying of C.C and putting forma Per day


and temping etc. Mistri 1/6 no. Rs 210.00 Rs 35.00

Mason Per day 2 no. Rs 200.00 Rs 400.00


Mate Per day 1 no. Rs 130.00 Rs 130.00
Beldar Per day 12 no. Rs 110.00 Rs 1320.00
Coolie Per day 2 no. Rs 110.00 Rs 220.00
Sub grade rectification etc Mason Per day 1/2 no. Rs 200.00 Rs 100.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolie Per day 1 no. Rs 110.00 Rs 110.00
Curing : Mate Per day 1 no. Rs 130.00 Rs 130.00
Coolie Per day 8 no. Rs 110.00 Rs 880.00
Diversion : Beldar Per day 1 no. Rs 110.00 Rs 110.00
Chowkidar Per day 2 no. Rs 110.00 Rs 220.00
Misce: Supervision. W/Agent Per day 1/3 no. Rs 130.00 Rs 43.33
Driver C.C.Mixer etc Per day 1/6 no. Rs 140.00 Rs 23.33
Cleaner Per day 1/6 no. Rs 100.00 Rs 16.67
Beldar Per day 3 no. Rs 105.00 Rs 315.00

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Coolie Per day 3 no. Rs 110.00 Rs 330.00


Total Rs 15011.08
Water chrges 1 1/2@ 225.17
Total Rs 15236.25
Contractor s profit @ 10% 1523.62
Total Rs 16759.87
Rate per 3.737 Cum Rs 16759.87
Rate for 1.00 Cum Rs 4484.97
Say Rs 4485.00

774 As in item no- 773 above but excluding supply of cement coarse sand and stone ballast (Labour
only)

Unit = 1 Cum
Labour as in item No- 773 including forms work. 4493.33
Contractor profit @ 10% 449.33
Total Rs 4942.66
Rate per 3.737 Cum Rs 4942.66
Rate for 1.00 Cum Rs 1322.66
Say Rs 1322.70
775 Blinding of water bound stone or kankar lime with local earth by spreading evenly to an average
depth of 1.5 cm (9/16)% & filling the intersticks of the road metal. The trenches to be so dug for
taking the earth that they form continuous side drain at road boundry.

Unit = 1 Km
Take a length of one furlong 1x660x12x 1/24 = 330 Say 300cft
Or 8.49504 Cum for (100.584 Rm )
Rate for earth work Per Cum 8.50 Cum Rs 40.00 Rs 339.80
Add 50% for small work 169.90
Total Rs 509.70
Rate per 0.201 Km Rs 509.70
Rate for 1.00 Km Rs 2533.80
Say Rs 2533.80
776 Earth work in edging of the painted or C.C miles in a width of 1/2m. (20") on either side according
to patri template including dressing ramming etc. the treches to be so dug for taking the earth that
they form a continuous side drain at road boundry.

Unit = 1 Km
Take a length of one furlong: Earth work to be done (average) say 380 cft (10.76 cum )
Rate for earth work Per Cum 10.76 Cum Rs 40.00 Rs 430.40
Add 50% for small work 215.20
Total Rs 645.60
Rate per 0.201 Km Rs 645.60
Rate for 1.00 Km Rs 3209.39
Say Rs 3209.40
777 Joint and other small cracks filling in C.C miles after racking out the joints and removing the old Tar
and other material with suitable materials as directed by E/I (Labour only) Total joints at every 33'
joints to be filled would be 5280 / 33

Unit = 1 Km
160 nos
Add 25% for other cracks 40 nos
Total 200 Say 200 joints would be attended .

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Mate Per day 0.75 no. Rs 130.00 Rs 97.50


Beldar Per day 6.00 no. Rs 110.00 Rs 660.00
Coolie Per day 1.00 no. Rs 110.00 Rs 110.00
Total Rs 867.50
Contractor profit @ 10% 86.75
Total Rs 954.25
Rate per 1.609 Km Rs 954.25
Rate for 1.00 Km Rs 592.96
Say Rs 593.00
Say Rs 593.0

778 Consolidation of kankar in patch repair from 1st june to 14 Nov. by hand rammer including opening
out stacks, picking out old surface up to 8cm (3") in a rectengular form, making 5cm. (2") wide drain
around the patch up to depth of 12cm (4 1/2") including carriage of kankar and water, but excluding
supply of kankar and including stacking the unserviceable materials & basi - chot mext day &
blinding the same as directed by the E/I.
Unit = 1 Cum

Taking a patch of 5x5 fresh metal to beused.


5 x 5 x 1/4 6 1/4 cft
Mate Per day 0.33 no. Rs 130.00 Rs 43.33
Beldar Per day 0.27 no. Rs 110.00 Rs 29.33
Coolie Per day 0.10 no. Rs 110.00 Rs 11.00
Total Rs 83.66
Contractor's profit @ 10% 8.37
Total Rs 92.03
Rate per 0.177 Cum Rs 92.03
Rate for 1.00 Cum Rs 520.21
Say Rs 520.20

779 As in item (778) above but from 15 Nov. to 31 May.


Unit = 1 Cum
As in item 778 520.2
Add for water allowance as in item 757 32.1
Total Rs 552.30

Rate for 1.00 cum Rs 552.30


Say Rs 552.30

780 Patch repair of painted miles with tar & bitumen (Labouronly0 including heating of paint up to
required tempreature , pouring it on the surface spreading the necessary qnty of grit & ramming
hard with hand rammer and also including cleaning with brush etc. the existing surface after
scarifying it to the W.B srface in rectangular shape & spreading the dismantald materials on the
patries as directed by the E/I.

As per Ce's circular patch work is carried out up to a stage when 1/2 ton tar is used per year per
Mile
(6/4 surface to be treated by 1 1/2 ton in year 3360/12 = 10000 sft Girt to be consumed
Unit = 1 Cum
270 cft (7.6455 cum ) Taking 25 cft ( 0.708 cum )
Taken 0.71 Cum
Mate Per day 1.00 no. Rs 130.00 Rs 130.00
Beldar Per day 4.00 no. Rs 110.00 Rs 440.00
Coolie Per day 4.00 no. Rs 110.00 Rs 440.00

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Total Rs 1010.00
Contractor's profit @ 10% 101
Total Rs 1111.00
Rate per 0.710 Cum Rs 1111.00
Rate for 1.00 Cum Rs 1564.79
Say Rs 1564.80

781 Cleaning of existing painted surface and laying premix 2 cm thick over a tack coat with graded
approved grit and bitumen( Labour only) including ……..
Unit = 1 Sqm
Take a length of 1/2 furlong 330 x 12 = 3960 sft. Taking area 367.884 Sqm
Taken Area = 367.88 Sqm
Labour for Celaning : Mazdoor Per day 6.00 no. Rs 110.00 Rs 660.00
coolie Per day 660.00
6.00 no. Rs 110.00 Rs
Tack coat heatting & spreading
on road.
Hot beldar Per day 4.00 no. Rs 120.00 Rs 480.00
Premixing , screening grit
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Tar heating & mixing grit
Beldar Per day 5.00 no. Rs 120.00 Rs 600.00
Coolie Per day 330.00
3.00 no. Rs 110.00 Rs
Spreading the premixing &
mixing in to camber
Beldar Per day 15.00 no. Rs 120.00 Rs 1800.00
Diversion watering : Mazdoor Per day 2.00 no. Rs 110.00 Rs 220.00
Misce: Mate Per day 2.00 no. Rs 110.00 Rs 220.00
Work agent Per day 1.00 no. Rs 150.00 Rs 150.00
Tar, bitumen& Fire Man Per day 2.00 no. Rs 140.00 Rs 280.00
Sundries , cartage and T&P etc L.S L.S 338.46
Total Rs 5848.46
Rate per 367.880 Sqm Rs 5848.46
Rate for 1.00 Sqm Rs 15.90
Say Rs 15.90

782 As in item no 781 above but in patches labour required fpr the work when 25 cft grit is consumed
Unit = 1 Cum
Mate Per day 1.25 no. Rs 130.00 Rs 162.50
Hot Beldar Per day 4.00 no. Rs 120.00 Rs 480.00
Coolie Per day 4.00 no. Rs 110.00 Rs 440.00
Sundries L.S. Rs 108.31
Total Rs 1190.81
Rate per 0.70792 Cum Rs 1055.00
Rate for 1.00 Cum Rs 1490.28
Say Rs 1055.00
783 Cleaning the premix surface and laying seal coat with approved 6 mm graded grit and bitumen
( Labour only)…………..
Unit = 1 Sqm
Take a length of 1/2 furlong 330 x 12 = 3960 sft. Taking area 367.884 Sqm

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Taking area 367.88 Sqm


Labour for Celaning : Mazdoor Per day 2.00 no. Rs 110.00 Rs 220.00
coolie Per day 2.00 no. Rs 110.00 Rs 220.00
Heatting & spreading
Hot beldar Per day 4.00 no. Rs 120.00 Rs 480.00
Premixing , screening grit
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Sreading grit
Beldar Per day 2.00 no. Rs 110.00 Rs 220.00

Misce: Mate Per day 1.00 no. Rs 130.00 Rs 130.00


Work agent Per day 0.25 no. Rs 150.00 Rs 37.50
Tar, bitumen& Fire Man Per day 1.00 no. Rs 140.00 Rs 140.00
Sundries , cartage and T&P etc L.S L.S 76.15
Total Rs 1633.65
Rate per 367.88 Sqm Rs 1633.65
Rate for 1.00 Sqm Rs 4.44
Say Rs 4.40

784 AS in item no 781 above but on water bound surface.


Unit = 1 Sqm
Taking area 367.88 Sqm
Labour for Celaning : Mazdoor Per day 10.00 no. Rs 110.00 Rs 1100.00
coolie Per day 10.00 no. Rs 110.00 Rs 1100.00
Tack coat heatting & spreading
on road.
Hot beldar Per day 6.00 no. Rs 120.00 Rs 720.00
Premixing , screening grit
Beldar Per day 1.00 no. Rs 120.00 Rs 120.00
Tar heating & mixing grit
Beldar Per day 5.00 no. Rs 120.00 Rs 600.00
Coolie Per day 330.00
3.00 no. Rs 110.00 Rs
Sreading the premixing & making
in to camber
Beldar Per day 15.00 no. Rs 110.00 Rs 1650.00
Diversion watering :Beldar Per day 2.00 no. Rs 110.00 Rs 220.00
Misce: Mate Per day 3.00 no. Rs 130.00 Rs 390.00
Work agent Per day 1.00 no. Rs 110.00 Rs 110.00
Tar, bitumen& Fire Man Per day 2.00 no. Rs 140.00 Rs 280.00
Sundries , cartage and T&P etc L.S L.S 338.46
Total Rs 6958.46
Rate per 367.88 Sqm Rs 6958.46
Rate for 1.00 Sqm Rs 18.92
Say Rs 18.90

785 Brick soling with straight overburnt bricks laid flat and dry ( Labour only) including preparation of
subgrade to prescribed camber filling, joints with local earth spreading a blinding coat of 1 cm.
(3/8") depth of local earth of P.I.5 to 7 over the entire surface & including labour and T&P etc.
required for proper completion of the work.

Unit = 1 Sqm

Taking area 9.29 Sqm (100Sqft)


Mazdoor Per day 1.00 no. Rs 110.00 Rs 110.00
Laying brick: Mason Per day 0.17 no. Rs 200.00 Rs 33.33

Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6

Mazdoor Per day 0.50 no. Rs 110.00 Rs 55.00


Spreading earth :Mazdoor Per day 0.50 no. Rs 110.00 Rs 55.00
Total Rs 253.33
Contractor s profit @ 10% 25.33
Total Rs 278.66
Rate for 9.29 Sqm Rs 278.66
Rate for 1.00 Sqm Rs 30.00
Say Rs 30.00

786 As in item no 785 above but brick laid on edge.


Unit = 1 Sqm
Taking area 9.29 Sqm (100Sqft)
Same as in item no 785 Rs 278.66
Add extra mason for laying Per day 0.20 no. Rs 200.00 Rs 40.00
Total Rs 318.66
Contractor s profit @ 10% on Rs
26.00 only 4.00
Total Rs 322.66
Rate for 9.29 Sqm Rs 322.66
Rate for 1.00 Sqm Rs 34.73
Say Rs 34.70

Contd..........
Analysis of Rate

1- Providing & Laying 80mm thick P.C.C Inter lock tiles over base concrete 100 mm thick
C.C 1:4:8 ( Cement : Fine Sand : 40mm Brick Ballast ) and 50mm thick custion of Ganga sand
including supply of all material , labour , T&P etc. required for proper completion of the work.

Taking Area 465 Sqm

(I) Base Concrete-


465.00x0.10 = 46.50 cum @ Rs. 1476.00 = Rs. 68634.00

(ii) P/L Fine Sand-


465.00x0.05 = 23.25 cum @ Rs. 550.00/ Cum = Rs. 12787.50

(iii) 80mm thick Inter lock vibratory tile rate at work shop
= 465.00xSqm @ Rs. 490.30 Per Sqm = Rs. 227989.50

Total = Rs. 309411.00


Workshop Rate= 395.00
4% T.T = 15.80
Labour charges= 40.00
Add 10% for Transit 450.80
490.30

Hence Rate Per Sqm = 309411 / 465.00


= 665.40

Say Rs. 665.40/Sqm