Professional Documents
Culture Documents
PWD Skelton-excel
PWD Skelton-excel
PWD Skelton-excel
Contd ...........
EARTH WORK AND EXCAVATION
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
254 Add to items 251-253 for every additional 30 m lead or part of 30 m. or for for every additional 1.50 m.lift or
part of 1.50 m.
Coolies Per day 2.00 no. Rs 110.00 Rs 220.00
T&P L.S. Rs 6.77
Total Rs 226.77
Contractor s profit @ 10% Rs 22.68
Rate for 28.32 Cum Rs 249.45
Rate for 1.00 Cum Rs 8.81
Say Rs 8.80 Per Cum
255 Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8 km. From
the site of work and including watering, dressing etc. Rate to include cost of all material, labor and T & P etc.
required for proper completion of the work.
Material - 28.03 Cum
Local sand Per cum 28.030 no. Rs 275.00 Rs 7708.25
Labour
Beldar Per day 3.00 no. Rs 110.00 Rs 330.00
Coolie Per day 5.00 no. Rs 110.00 Rs 550.00
Bhisti Per day 0.75 no. Rs 130.00 Rs 97.50
T&P L.S. Rs 16.92
Total Rs 994.42
Contractor s profit @ 10% Rs 99.44
Rs 1093.86
Rate for 28.32 Cum Rs 8802.11
Rate for 1.00 Cum Rs 310.81
Say Rs 310.80 Per Cum
256 Same as item no 251 above but excavation in soil mixed with gravel amd boulder. { Skelton analysis based
on hill schedule of rate P.W.D. sl.no. 157 }
Mistri Per day 0.125 no. Rs 210.00 Rs 26.25
Beldar Per day 10.00 no. Rs 110.00 Rs 1100.00
Coolie Per day 7.00 no. Rs 110.00 Rs 770.00
Blacksmith for sharpening Tools etc. Per day 0.25 no. Rs 200.00 Rs 50.00
T & P and Basket etc. L.S. Rs 50.8
Total Rs 1997.02
Contractor s profit @ 10% Rs 199.7
Rate for 28.32 Cum Rs 2196.72
Rate for 1.00 Cum Rs 77.57
Say Rs 77.60 Per Cum
257 As in item 251 above but excavation in black cotton soil in Bundelkhand area requiring use of special tools
and plant such as pick axes sabbal etc.
Mistri Per day 0.125 no. Rs 210.00 Rs 26.25
Beldar Per day 8.00 no. Rs 110.00 Rs 880.00
Coolie Per day 6.00 no. Rs 110.00 Rs 660.00
Blacksmith for sharpening Tools etc. Per day 0.17 no. Rs 200.00 Rs 33.33
T & P and Basket etc. L.S. Rs 50.8
Contd ...........
EARTH WORK AND EXCAVATION
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
Total Rs 1650.35
Contractor s profit @ 10% Rs 165.04
Rate for 28.32 Cum Rs 1815.39
Rate for 1.00 Cum Rs 64.10
Say Rs 64.10 Per Cum
258 Extra rate for quantity of work excuted under
(a) In or Under water and or Liquid mud 20 % above as in CPWD schedule 1962
259 Clearing jungle including uprooting of rank vegetations grass, bush, wood trees and sapling of grith up to 30
cm measured at a height of 1.00 m above ground level & removal of rubbish up to a distance of 50 m. out side
the periphery of area cleared.
( Analysis of rates on the basis of item 41 of C P W D analysis
of 1955 schedule)
Take 92.9 Sqm
Labour
Beldar Per day 1.00 no. Rs 120.00 Rs 120.00
Coolie Per day 0.50 no. Rs 110.00 Rs 55.00
T & P and Basket etc. L.S. Rs 36.9
Total Rs 211.92
Contractor s profit @ 10% Rs 21.19
Rs 233.11
Rate for 92.9 sqm. Rs 233.11
Contd ...........
CHAPER-2
LABOUR
S.No. Description Unit Rates
37 Tractor trolly Water Tanker for 8 Hrs including Per day 900.00
Driver with Fuel
38 Floor cutting machine with driver without grinding Per day 450.00
stone
39 Welding Plant with oprator without Rod & Power Per day 450.00
770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE
273 Concrete with 40 mm. gauge brick ballast, Fine local sand of 1.25 Fineness modulous and
cement in foundations and under floors in the proportions of 12:6:1, including supply of all
materials, labor and T & P etc.required for completion of the work.
(A ) Materials :
Brick ballast Per cum 2.83 cum Rs 700.00 Rs 1982.18
Fine sand Per cum 1.36 cum Rs 410.00 Rs 557.27
Cement Per bag 6.40 bag Rs 210.00 Rs 1344.00
Add 2.5% wastage on cement and sand Rs 47.53
Total Rs 3930.98
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Beldar Per day 3 no. Rs 110.00 Rs 330.00
Coolie Per day 3 no. Rs 110.00 Rs 330.00
Bhisti Per day 1 no. Rs 130.00 Rs 130.00
Blacksmith Per day 1/8 no. Rs 200.00 Rs 25.00
T & P and Sundries etc. L.S. Rs 372.3
Total Rs 1276.89
Water charges 1.5% of (A+B) Rs 78.12
Total Rs 5285.99
Contractor s profit @ 10% Rs 528.6
Rate for 2.83 Cum Rs 5814.59
Rate for 1.00 Cum Rs 2054.63
Say Rs 2054.60
274 As in item 273 above but in the proportion of 10:5:1
(A ) Materials :
770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE
770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE
770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE
282 Cast cement concrete door sills, chaukhats boundry post, shelves and similar small work with
cement,approved course sand and 20 mm. Gauge approved stone ballast including its fixing
and binding the same with 24 B.W.G. G.I. Binding wire , and including the cost of binding wire ,
moulds and all other materials, labours and T & P etc. required for completion of the work.
770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE
283 R.C.C work with cement,approved course sand and 20 mm. gauge approved stone ballast in
the proportion of 1:2:4 in lintels of doors and windows excluding supply of reinforcement and its
bending but including its fixing and binding the same with 24 B.W.G. G.I. binding wire , and
including neccessary centering and shuttering etc. and also including the supply of binding
wire , moulds and all other materials, labours and T & P etc. required for completion of the work.
(A ) Materials :
770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE
288 As in item no. 283 but in R.C.C. T- beams and slab roofs and columns.
Rate as per S.I. 283 Rs 4678.70
Add extra for bricks or ballies supports
stronger shuttering L.S. Rs 463.78
Contractor s profit @ 10% on Rs 463.780 Rs 46.38
Total Rs 5188.86
770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 5
CONCRETE
770200762.xlsxCONCRETE07/05/202412:16:44
CHAPTER - 6
BRICK WORK
(A ) Materials :
304 First class bricks work in 1:5 in cement and fine sand of 1.25 F.M. mortar in foundation and plinth
including supply of all materials, labor and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Fine sand of F.M. 1.25 Per cum 0.76 cum Rs 410.00 Rs 311.60
Cement Per bag 4.50 bag Rs 210.00 Rs 945.00
Total Rs 5156.60
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 91.53
Total Rs 6193.51
Contractor s profit @ 10% Rs 619.35
Rate for 2.83 Cum Rs 6812.86
Rate for 1.00 Cum Rs 2407.37
Say Rs 2407.40
305 First class bricks work in 1:4 in cement and fine sand of 1.25 F.M. mortar in foundation and plinth
including supply of all materials, labor and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Fine sand of F.M. 1.25 Per cum 0.76 cum Rs 410.00 Rs 311.60
Cement Per bag 5.25 bag Rs 210.00 Rs 1102.50
Total Rs 5314.10
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 93.89
Total Rs 6353.38
Contractor s profit @ 10% Rs 635.34
Rate for 2.83 Cum Rs 6988.72
Rate for 1.00 Cum Rs 2469.51
CHAPTER - 6
BRICK WORK
306 First class bricks work in 1:3 in cement and fine sand of 1.25 F.M. mortar in foundation and plinth
including supply of all materials, labor and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Fine sand of F.M. 1.25 Per cum 0.76 cum Rs 410.00 Rs 311.60
Cement Per bag 7.50 bag Rs 210.00 Rs 1575.00
Total Rs 5786.60
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 120.00 Rs 240.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 27.7
Total Rs 967.69
Water charges 1.5% of (A+B) Rs 101.31
Total Rs 6855.61
Contractor s profit @ 10% Rs 685.56
Rate for 2.83 Cum Rs 7541.17
Rate for 1.00 Cum Rs 2664.72
Say Rs 2664.70
307 First class bricks work in 1:3 in cement and course sand mortar in foundation and plinth including
supply of all materials, labor and T&P etc. required for completion of the work.
(A ) Materials :
Bricks Per %0 No 1300.00 no. Rs 3000.00 Rs 3900.00
Course sand Per cum 0.76 cum Rs 635.00 Rs 482.60
Cement Per bag 7.50 bag Rs 210.00 Rs 1575.00
Total Rs 5957.60
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 2 no. Rs 190.00 Rs 380.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/2 no. Rs 130.00 Rs 65.00
T & P and Sundries etc. L.S. Rs 25.4
Total Rs 945.38
Water charges 1.5% of (A+B) Rs 103.54
Total Rs 7006.53
Contractor s profit @ 10% Rs 700.65
Rate for 2.83 Cum Rs 7707.18
Rate for 1.00 Cum Rs 2723.38
Say Rs 2723.40
CHAPTER - 6
BRICK WORK
309 As in item (301 to 304) above but in super-structure, including necessary cutting and moulding of
bricks as required and also including honey comb brick work . Thickness of wall not to be less than 1.5
brick thick.Add for extra labor to above items.
Extra Labor required :
314 First class brick work in arch including shuttering and centering add to items ( 301 to 307 ). Extra
labour, centering and shuttering required,
315 As in item 314 above but First class brick work in Jack arch, including shuttering and centering add to
items ( 301 to 307 ). Extra labour, centering and shuttering required,
316 As in item 314 above but in well steining with ordinary bricks, including shuttering and centering add
to items ( 301 to 307 ). Extra labour, centering and shuttering required,
317 As in item 316 above but in well steining but with specially moulded bricks, including shuttering and
centering add to items ( 301 to 307 ). Extra labour, centering and shuttering required,
318 11.5 cm. Thick string or drip course with 6 cm projection of first class brick in kankar lime including 12
mmthick lime plastering with simple moulding and cuttig drip notch as required and including supply of
all material ,labor and T & P etc required for completion of work
For 30.48 Rm
(A ) Materials :
Bricks Per %0 No 100.00 no. Rs 3000.00 Rs 300.00
Kanker Lime Per %0 No 0.17 no. Rs 3185.00 Rs 0.54
Total Rs 300.54
(B) Labour :
Mistri Per day 1/50 no. Rs 210.00 Rs 4.20
Mason Per day 3 1/2 no. Rs 190.00 Rs 665.00
Coolies Per day 2 no. Rs 110.00 Rs 220.00
Bhisti Per day 1/12 no. Rs 130.00 Rs 10.83
CHAPTER - 6
BRICK WORK
324 Laying reinforced brick work in sunshade with first class brick laid in cement and approved coarse
sand mortar 1:3 excluding supply of reinforcement and its bending but including its fixing in position
and binding the same with 24 B.W.G.I. Binding wire and including all centering and shuttering etc and
curring and also including cost of binding wire, supply of all materials labour and T & P etc required for
proper completion of the work.
(A ) Materials :
Coarse sand Per cum 0.18 cum Rs 635.00 Rs 112.38
Cement Per bag 2.60 bag Rs 210.00 Rs 546.00
Water proofing compound as
specified by the manufactures
Per kg 3.40 kg Rs 50.00 Rs 170.00
Total Rs 828.38
(B) Labour :
Mistri Per day 1/20 no. Rs 210.00 Rs 10.50
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Beldar Per day 1/4 no. Rs 110.00 Rs 27.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/8 no. Rs 130.00 Rs 16.25
T & P and Sundries etc. L.S. Rs 16.9
Total Rs 146.17
Water charges 1.5% of (A+B) Rs 14.62
Total Rs 989.17
Contractor s profit @ 10% Rs 98.92
Rs 1088.09
Rate for 9.29 Sqm 1088.09
Rate for 1.00 Sqm Rs 117.12
Say Rs 117.10
361 2.5cm thick damp proof coarse with cement, approved coase sand and 13mm graded stome grit in1:1.5:3
with and including water proofing materials as ordered by the Engineer-in charge in the proportion as
specified by the manufactures, including supply of all materials, labour, T & P etc. required for completion of
work and including proper curing and shuttering as necessary.
(A ) Materials :
Stone ballast Per cum 0.212 cum Rs 1250.00 Rs 265.47
Coarse sand Per cum 0.106 cum Rs 635.00 Rs 67.43
Cement Per bag 2.30 bag Rs 210.00 Rs 483.00
Water proofing compound as Per kg 2.60 kg Rs 50.00 Rs 130.00
specified by the manufactures Total Rs 945.90
(B) Labour :
Mistri Per day 1/16 no. Rs 210.00 Rs 13.13
Mason Per day 1 1/2 no. Rs 190.00 Rs 285.00
Beldar Per day 1 1/2 no. Rs 110.00 Rs 165.00
Bhisti Per day 1/8 no. Rs 130.00 Rs 16.25
T & P and Sundries etc. L.S. Rs 33.8
Total Rs 513.22
Water charges 1.5% of (A+B) Rs 21.89
Total Rs 1481.01
Contractor s profit @ 10% Rs 148.10
Rs 1629.11
Rate for 9.29 Sqm 1629.11
Rate for 1.00 Sqm Rs 175.36
Say Rs 175.40
CHAPTER - 10
MILD STEEL & IRON WORK
(b) Same as above but heavy section , i.e. exceeding 300 kg.( 6 cwt) in
weight and upto 7.5 metre ( 24 ft) in height.
503 Mild steel or iron work in heavy sizes such as trusses, builts up gates, door frames ,records
racks roof work ,gates etc. wrought to required form, including drilling holes, rivetting or welding
where necessary, and also including supply of steel ,bolts, nuts and wastages etc. and their
fixing required for completion of the work.
Unit =Per Qtls
(A ) Materials :
Cost of steel Per qtl 0.51 qtl Rs 3560.00 Rs 1808.48
Wastages 2.5% on steel Per qtl 0.0127 qtl Rs 3560.00 Rs 45.21
Total Rs 1853.69
(B) Labour :
Black smith Per day 1 no. Rs 200.00 Rs 200.00
Hammer man Per day 1 no. Rs 110.00 Rs 110.00
Rivetter Per day 1/4 no. Rs 180.00 Rs 45.00
CHAPTER - 10
MILD STEEL & IRON WORK
(A ) Materials :
Bricks Per %0 No 432.00 no. Rs 3000.00 Rs 1296.00
Cement Per bag 3.60 bag Rs 210.00 Rs 756.00
Course sand Per cum 0.34 cum Rs 635.00 Rs 215.77
Total Rs 2052.00
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 3/4 no. Rs 190.00 Rs 142.50
Beldar Per day 3/4 no. Rs 110.00 Rs 82.50
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Total Rs 402.50
Centering Ballies 5 nos. 3.60m
length & 10cm. Dia 18.29 Rm Rs 45.00 Rs 822.96
Ballies 15 nos. 3.60m length
& 10cm. Dia 54.86 Rm Rs 45.00 Rs 2468.88
538 Supply and laying complete 4 cm ( 1 1/2 " ) thick insulation layer of sand and clay over Jack arch,
Reinforced Brick or reinforced cement concrete roof.
Take a Area 9.29 Sqm
(A ) Materials :
Cost of Earth Per Cum 0.20 Cum Rs 49.50 Rs 0.01
Cost of Sand Per Cum 0.20 Cum Rs 275.00 Rs 56.20
Total Rs 0.01
(B) Labour :
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Beldar Per day 1/4 no. Rs 110.00 Rs 27.50
Total Rs 75.00
Total (A+B) Rs 75.01
Contractor s profit @ 10% Rs 7.5
Rate for 9.29 Sqm Rs 82.51
Rate for 1.00 Sqm Rs 8.88
Say Rs 8.90
CHAPTER - 13
PLASTER and POINTING
(B) Labour :
(a) Raking and washing surface
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for pointing
Mason Per day 1 1/2 no. Rs 190.00 Rs 285.00
Coolies Per day 1 1/2 no. Rs 110.00 Rs 165.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
T & P and Sundries ,
scaffolding etc. L.S. Rs 15.8
Total Rs 586.33
TOTAL ( A+B) Rs 777.43
Water charges 1.5% of (A+B) Rs 11.66
Total Rs 789.09
Contractor s profit @ 10% Rs 78.91
Rs 868.00
Rate for 9.29 Sqm 868.00
Rate for 1.00 Sqm Rs 93.43
Say Rs 93.40
574 As in item no. 571 above but with cement mortar consisting of one part cement & two parts of
Fine sand of 1.25 F.M.
(A ) Materials :
Cement Per no. 0.43 bag Rs 210.00 Rs 90.30
Fine sand Per cum 0.03 cum Rs 410.00 Rs 11.48
Total Rs 101.78
(B) Labour :
(a) Raking and washing surface
Mason Per day 1/4 no. Rs 200.00 Rs 50.00
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for pointing
Mason Per day 1 1/2 no. Rs 200.00 Rs 300.00
Coolies Per day 1 1/2 no. Rs 110.00 Rs 165.00
Bhisti Per day 1 1/2 no. Rs 130.00 Rs 195.00
T & P and Sundries ,
scaffolding etc. L.S. Rs 16.7
Finishing by Iron Trowal L.S. Rs 13.3
Total Rs 767.17
TOTAL ( A+B) Rs 868.95
Water charges 1.5% of (A+B) Rs 13.03
Total Rs 881.98
Contractor s profit @ 10% Rs 88.20
Rs 970.18
Rate for 9.29 Sqm 970.18
Rate for 1.00 Sqm Rs 104.43
Say Rs 104.40
575 As in item no 574 above but flush pointing deduct from item 574.
Labour :
Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Coolies Per day 1/3 no. Rs 110.00 Rs 36.67
Water charges Rs 1.50
101.50
Contractor s profit @ 10% Rs 10.15
Rs 111.65
Rate for 9.29 Sqm 111.65
Rate for 1.00 Sqm Rs 12.02
Say Rs 12.00
576 As in item no 574 and 575 above but in floors deduct from item 574. and 575.
Labour :
Mason Per day 1/3 no. Rs 190.00 Rs 63.33
Coolies Per day 1/3 no. Rs 110.00 Rs 36.67
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
Water charges Rs 1.69
114.70
Contractor s profit @ 10% Rs 11.47
Rs 126.16
Rate for 9.29 Sqm 126.16
Rate for 1.00 Sqm Rs 13.58
Say Rs 13.60
577 Raised pointing with cement and Fine sand of 1.25F.M. mortar on brick work in proportion of 1:2,
including supply of all materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 1.00 bag Rs 210.00 Rs 210.00
Fine sand Per cum 0.04 cum Rs 410.00 Rs 14.51
Total Rs 224.51
(B) Labour :
(a) Raking and washing surface
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for pointing
Mason Per day 1 1/3 no. Rs 190.00 Rs 253.33
Coolies Per day 1 1/3 no. Rs 110.00 Rs 146.67
Bhisti Per day 1/3 no. Rs 130.00 Rs 43.33
Scaffolding etc. L.S. Rs 15.8
Total Rs 547.17
TOTAL ( A+B) Rs 771.68
Water charges 1.5% of (A+B) Rs 11.58
Total Rs 783.25
Contractor s profit @ 10% Rs 78.33
Rs 861.58
Rate for 9.29 Sqm 861.58
Rate for 1.00 Sqm Rs 92.74
Say Rs 92.70
578 Struck cement pointing 1:2 with colour in mortar to match the brick work colour including supply
of all materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 0.43 bag Rs 210.00 Rs 89.25
Fine sand Per cum 0.03 cum Rs 410.00 Rs 11.61
Total Rs 100.86
(B) Labour :
(a) Raking and washing surface
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for pointing
Mason Per day 1 1/2 no. Rs 190.00 Rs 285.00
Coolies Per day 1 1/2 no. Rs 110.00 Rs 165.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Scaffolding etc. L.S. Rs 15.8
Finishing by Iron Trowal L.S. Rs 31.7
Total Rs 618.00
TOTAL ( A+B) Rs 718.86
Water charges 1.5% of (A+B) Rs 10.78
Total Rs 729.64
Contractor s profit @ 10% Rs 72.96
Rs 802.61
Rate for 9.29 Sqm 802.61
Rate for 1.00 Sqm Rs 86.39
Say Rs 86.40
580 12 mm thick plaster with cement mortar in proportion of 1:2 cement and fine sand of 1.25 F.M.
over brick work minimum thickness not to be less than 10 mm thick including supply of all
materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 2.12 bag Rs 210.00 Rs 445.20
Fine sand Per cum 0.14 cum Rs 410.00 Rs 58.05
Total Rs 503.25
(B) Labour :
(a) Raking and washing surface; same as S.I.Nos 578
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for Plastering : same as S.I.Nos 579
Mason Per day 3/4 no. Rs 190.00 Rs 142.50
Coolies Per day 3/4 no. Rs 110.00 Rs 82.50
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Scaffolding etc. L.S. Rs 15.8
Total Rs 361.33
TOTAL ( A+B) Rs 864.58
Water charges 1.5% of (A+B) Rs 12.97
Total Rs 877.55
Contractor s profit @ 10% Rs 87.76
Rs 965.31
Rate for 9.29 Sqm 965.31
Rate for 1.00 Sqm Rs 103.91
Say Rs 103.90
581 12 mm thick plaster with cement mortar in proportion of 1:2 cement and app. Coarse sand of
above 2.25 F.M., over brick work minimum thickness not to be less than 10 mm thick including
supply of all materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 2.12 bag Rs 210.00 Rs 445.20
Coarse sand Per cum 0.14 cum Rs 635.00 Rs 89.91
Total Rs 535.11
(B) Labour :
(a) Raking and washing surface; same as S.I.Nos 578
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for Plastering : same as S.I.Nos 579
Mason Per day 3/4 no. Rs 190.00 Rs 142.50
Coolies Per day 3/4 no. Rs 110.00 Rs 82.50
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Scaffolding etc. L.S. Rs 15.8
Total Rs 361.33
TOTAL ( A+B) Rs 896.44
Water charges 1.5% of (A+B) Rs 13.45
Total Rs 909.89
Contractor s profit @ 10% Rs 90.99
Rs 1000.87
Rate for 9.29 Sqm 1000.87
Rate for 1.00 Sqm Rs 107.74
Say Rs 107.70
582 12 mm thick plaster with cement mortar in proportion of 1:3 cement and fine sand of 1.25 F.M.
over brick work minimum thickness not to be less than 10 mm thick including supply of all
materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 1.42 bag Rs 210.00 Rs 298.20
Fine sand Per cum 0.14 cum Rs 410.00 Rs 58.05
Total Rs 356.25
(B) Labour :
Labour for Raking and
washing surface and Plastering same as S.I.Nos 580 or 581 361.33
etc ;
Total Rs 361.33
TOTAL ( A+B) Rs 717.58
Water charges 1.5% of (A+B) Rs 10.76
Total Rs 728.35
Contractor s profit @ 10% Rs 72.83
Rs 801.18
Rate for 9.29 Sqm 801.18
Rate for 1.00 Sqm Rs 86.24
Say Rs 86.20
583 12 mm thick plaster with cement mortar in proportion of 1:3 cement and appr. Coarse sand of
above 2.25 F.M. over brick work minimum thickness not to be less than 10 mm thick including
supply of all materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 1.42 bag Rs 210.00 Rs 298.20
Coarse sand Per cum 0.14 cum Rs 635.00 Rs 89.91
Total Rs 388.11
(B) Labour :
Labour for Raking and
washing surface and Plastering same as S.I.Nos 580 or 581 361.33
etc ;
Total Rs 361.33
TOTAL ( A+B) Rs 749.44
Water charges 1.5% of (A+B) Rs 11.24
Total Rs 760.68
Contractor s profit @ 10% Rs 76.07
Rs 836.75
Rate for 9.29 Sqm 836.75
Rate for 1.00 Sqm Rs 90.07
Say Rs 90.10
584 12 mm thick plaster with cement mortar in proportion of 1:4 cement and fine sand of 1.25 F.M.
over brick work minimum thickness not to be less than 10 mm thick including supply of all
materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 1.06 bag Rs 210.00 Rs 222.60
Fine sand Per cum 0.14 cum Rs 410.00 Rs 58.05
Total Rs 280.65
(B) Labour :
Labour for Raking and
washing surface and Plastering same as S.I.Nos 580 or 581 361.33
etc ;
Total Rs 361.33
TOTAL ( A+B) Rs 641.98
Water charges 1.5% of (A+B) Rs 9.63
Total Rs 651.61
Contractor s profit @ 10% Rs 65.16
Rs 716.77
Rate for 9.29 Sqm 716.77
Rate for 1.00 Sqm Rs 77.16
Say Rs 77.20
586 12 mm thick plaster with cement mortar in proportion of 1:6 cement and fine sand of 1.25 F.M.
over brick work minimum thickness not to be less than 10 mm thick including supply of all
materials, labour and T & P etc required for proper completion of the work.
(A ) Materials :
Cement Per no. 0.70 bag Rs 210.00 Rs 147.00
Fine sand Per cum 0.14 cum Rs 410.00 Rs 58.05
Total Rs 205.05
(B) Labour :
Labour for Raking and
washing surface and Plastering same as S.I.Nos 580 or 581 361.33
etc ;
Total Rs 361.33
TOTAL ( A+B) Rs 566.38
Water charges 1.5% of (A+B) Rs 8.50
Total Rs 574.88
Contractor s profit @ 10% Rs 57.49
Rs 632.37
Rate for 9.29 Sqm 632.37
Rate for 1.00 Sqm Rs 68.07
Say Rs 68.10
587 Add for extra labour to all items of plaster if done in ceiling.
596 2 cm ( 3/4"') thick cement plasre in dado or skirting in 1:2 consisting of one part of cement and
tpart of approved coarse sand laid in panels, finished with 3 mm (1/8"') floating coat of neat
cement or cement and marble dust in ratio 5:1 including supply of all materials labour and T&P
etc. required for proper completion of the work.
(A ) Materials :
Cement Per no. 2.25 bag Rs 210.00 Rs 472.50
Coarse sand Per cum 0.17 cum Rs 635.00 Rs 107.89
Total Rs 580.39
(B) Labour :
(a) Raking and washing surface; same as S.I.Nos 578
Mason Per day 1/4 no. Rs 190.00 Rs 47.50
Coolies Per day 1/4 no. Rs 110.00 Rs 27.50
Bhisti Per day 1/10 no. Rs 130.00 Rs 13.00
(b) for Plastering : same as S.I.Nos 579
Mason Per day 1 no. Rs 190.00 Rs 190.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Bhisti Per day 3/8 no. Rs 130.00 Rs 48.75
Total Rs 436.75
TOTAL ( A+B) Rs 1017.14
Water charges 1.5% of (A+B) Rs 15.26
Total Rs 1032.39
Contractor s profit @ 10% Rs 103.24
Rs 1135.63
Rate for 9.29 Sqm 1135.63
Rate for 1.00 Sqm Rs 122.24
Say Rs 122.20
598 Engraving line in the plaster of outer face wall vertically and horizontally to display the surface as
stone facing as directed by the E / I including labour and T & P etc. required for proper
completion of the work .( Add for extra labour to all items of plaster.)
599 Providing and fixing water proofing materials in cement mortar ( Skelton analysis as per for
plastering or in concrete work in the proportion recommended by the manufacturer - item 52
page 553 CPWD 1955 analysis of rates)
(A ) Materials :
Stone grit 20 mm gauge Per cum 0.21 cum Rs 1340.00 Rs 284.58
Coarse sand Per cum 0.10 cum Rs 635.00 Rs 66.53
Cement Per no. 2.03 bag Rs 210.00 Rs 426.30
Total Rs 777.41
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1/2 no. Rs 110.00 Rs 55.00
Coolies Per day 1/2 no. Rs 110.00 Rs 55.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
T & P and Sundries etc. L.S. Rs 48.5
Total Rs 417.21
Water charges 1.5% of (A+B) Rs 17.92
Total Rs 1212.55
Contractor s profit @ 10% Rs 121.25
Total Rs 1333.80
602 As in item no 601 above but with base concrete consisting of brick ballast , white lime and surkhi in
ratio of 100:16:32
Same as in item no 601 for 2.5 cm
thick C.C. floor Rs 1333.80
Add brick ballast 7.5 cm(3") thick
base concrete in Kankar lime as per
S.I.No 271 Per cum 0.71 cum Rs 2325.70 Rs 1646.41
TOTAL Rs 2980.21
Rate for 9.29 Sqm 2980.21
Rate for 1.00 Sqm Rs 320.80
Say Rs 320.80
604 As in item no 601 above but floor shall be 5 cm (2") thick instead of 2.5 cm (1") thick and proportion
of concrete 1:1 1/2:3 instead of 1:2:4.
(A ) Materials :
Stone grit 20 mm gauge Per cum 0.42 cum Rs 1340.00 Rs 569.17
Coarse sand Per cum 0.21 cum Rs 635.00 Rs 134.86
Cement Per no. 4.75 bag Rs 210.00 Rs 997.50
Total Rs 1701.53
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 1 1/2 no. Rs 200.00 Rs 300.00
Beldar Per day 3/4 no. Rs 110.00 Rs 82.50
Coolies Per day 3/4 no. Rs 110.00 Rs 82.50
Bhisti Per day 1/3 no. Rs 130.00 Rs 43.33
T & P and Sundries etc. L.S. Rs 116.3
Total Rs 650.89
Water charges 1.5% of (A+B) Rs 35.29
Total Rs 2387.70
Contractor s profit @ 10% Rs 238.77
Total Rs 2626.47
605 As in item no 601 above but floors shall be 4 cm (1 1/2") thick instead of 2.5 cm (1") thick and
without base concrete.
(A ) Materials :
Stone grit 20 mm gauge Per cum 0.37 cum Rs 1340.00 Rs 493.28
Coarse sand Per cum 0.18 cum Rs 635.00 Rs 116.88
Cement Per no. 2.75 bag Rs 210.00 Rs 577.50
Total Rs 1187.66
(B) Labour :
Mistri Per day 1 1/8 no. Rs 210.00 Rs 236.25
Mason Per day 1/4 no. Rs 200.00 Rs 50.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 3/4 no. Rs 110.00 Rs 82.50
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
T & P and Sundries etc. L.S. Rs 64.6
Total Rs 575.87
Water charges 1.5% of (A+B) Rs 26.45
Total Rs 1789.97
Contractor s profit @ 10% Rs 179.00
TOTAL Rs 1968.97
Rate for 9.29 Sqm 1968.97
Rate for 1.00 Sqm Rs 211.95
Say Rs 212.00
606 Add in item no 601 to 603 and 605 when floors are polished including supply of exta cement, chapra
bati, carborandum stone, all other materials, labour and T & P etc. required for proper completion fo
the work. Marble dust shall be added in floating coat in ratio of 5:1 ( Marble dust and cement) if
necessary but no exra amount will be paid for it. This includes final finish with french mansion polish
or other approved polish.
(A ) Materials :
Extra cement or cement & marble- Per 50
dust mortar. Kg bags 0.50 bag Rs 210.00 Rs 105.00
Polishing and rubbing materials L.S. Rs 60.00
Total Rs 165.00
(B) Labour :
For polishing and cutting - Beldar
Per day 8.00 no. Rs 110.00 Rs 880.00
Total Rs 880.00
Water charges 1.5% of (A+B) Rs 15.67
Total Rs 1060.68
Contractor s profit @ 10% Rs 106.07
TOTAL Rs 1166.74
Rate for 9.29 Sqm 1166.74
Rate for 1.00 Sqm Rs 125.59
Say Rs 125.60
612 First class brick on edge floor laid in cement mortar consisting of one part of cement & six part of fine
sand of 1.25 F.M. & pointed with cement mortar 1:2 over and including 8 cm (3") thick brick ballast
base concrete with Kankar lime mortar including supply of all materials, labour and T & P etc.
required for proper completion of the work.
(A ) Materials :
3" base concrete in Kankar lime
mortar as per item No-271 cum 0.708 cum Rs 2325.70 Rs 1646.41
1class brick Per 0/00 530.00 no. Rs 3000.00 Rs 1590.00
Cement Per bag 1.25 bag Rs 210.00 Rs 262.50
Fine sand Per cum 0.241 cum Rs 410.00 Rs 98.68
Cement pointing 1:2 cement and
local sand mortor (item no-
574-576) Sqm 9.290 Sqm Rs 90.80 Rs 843.53
Total Rs 4441.13
(B) Labour :
Mistri Per day 1/10 no. Rs 210.00 Rs 21.00
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Total Rs 473.50
Water charges 1.5% of (A+B) Rs 73.72
Total Rs 547.22
Total(A+B) Rs 4988.34
Contractor s profit @ 10%
Rs 498.83
TOTAL Rs 5487.18
Rate for 9.29 Sqm 5487.18
Rate for 1.00 Sqm Rs 590.65
Say Rs 590.70
613 As in item no 612 above but with 8 cm( 3") thick base concrete consisting of brick ballast white lime
and surkhi in ratio of 100:16:32.
(A ) Materials :
3" base concrete in Brick ballast,
white lime and surkhi mortar in ratio
of 100:16:32 as per item No-272
cum 0.708 cum Rs 1667.00 Rs 1180.10
1class brick Per 0/00 530.00 no. Rs 3000.00 Rs 1590.00
Cement Per bag 1.25 bag Rs 210.00 Rs 262.50
Fine sand Per cum 0.241 cum Rs 410.00 Rs 98.68
Cement pointing 1:2 cement and
local sand mortor (item no-
574-576) Sqm 9.290 Sqm Rs 90.80 Rs 843.53
Total Rs 3974.82
(B) Labour :
Mistri Per day 1/10 no. Rs 210.00 Rs 21.00
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Total Rs 473.50
Water charges 1.5% of (A+B) Rs 66.72
Total Rs 4515.04
Contractor s profit @ 10% Rs 451.50
TOTAL Rs 4966.55
Rate for 9.29 Sqm 4966.55
Rate for 1.00 Sqm Rs 534.61
Say Rs 534.60
614 As in item no 612 above but with 8 cm( 3") thick base concrete consisting of one part of cement four
part of fine sand of 1.25 F.M. and eight part of brick ballast( 1:4:8).
(A ) Materials :
3" base concrete in 1:4:8 cement ,
fine sand and Brick ballast, as per
item No-275
cum 0.708 cum Rs 2310.30 Rs 1635.51
1class brick Per 0/00 530.00 no. Rs 3000.00 Rs 1590.00
Cement Per bag 1.25 bag Rs 210.00 Rs 262.50
Fine sand Per cum 0.241 cum Rs 410.00 Rs 98.68
Cement pointing 1:2 cement and
local sand mortor (item no-
574-576) Sqm 9.290 Sqm Rs 90.80 Rs 843.53
Total Rs 4430.22
(B) Labour :
Mistri Per day 1/10 no. Rs 210.00 Rs 21.00
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1 no. Rs 110.00 Rs 110.00
Coolies Per day 1 no. Rs 110.00 Rs 110.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Total Rs 473.50
Water charges 1.5% of (A+B) Rs 73.56
Total Rs 4977.28
Contractor s profit @ 10%
Rs 497.73
TOTAL Rs 5475.01
Rate for 9.29 Sqm 5475.01
Rate for 1.00 Sqm Rs 589.34
Say Rs 589.30
615 First class brick on edge flooring laid dry joints sand filled including prepration of baseto proper slope
and its ramming and including supply of all materials, labour and T & P etc. required for proper
completion of the work.
(A ) Materials :
1class brick Per 0/00 530.00 no. Rs 3000.00 Rs 1590.00
Sand Per cum 0.283 cum Rs 275.00 Rs 77.87
Total Rs 1667.87
(B) Labour :
Mason Per day 1 no. Rs 200.00 Rs 200.00
Beldar Per day 1 1/2 no. Rs 110.00 Rs 165.00
Coolies Per day 1/2 no. Rs 110.00 Rs 55.00
Total Rs 420.00
Water charges 1.5% of (A+B) Rs 31.32
Total Rs 2119.19
Contractor s profit @ 10% except on cost of bricks & sand Rs 211.92
TOTAL Rs 2331.11
Rate for 9.29 Sqm 2331.11
Rate for 1.00 Sqm Rs 250.93
Say Rs 250.90
620 Granolithic marble flooring 2.5 cm(1") thick consisting of one part cement, two part of approved
coarse sand and 4 part of 2 cm(3/4") graded approved stone chips including 6 mm (1/4") thick
surface coat with ordinary cement black, white or grey or mixed marble chips passing 3 mm (1/8") but
retained on 1.5 mm (1/6") mesh screen in proportion of 1:2 as specified or directed by the E/I and
polished by hand or machine and finally finished with french manson polish or other approved polish
including 8 cm (3") Kankar lime concrete base including supply of all materials , labour and T & P etc
required for proper completion of the work.
(A ) Materials :
3" base concrete in Kankar lime
mortar as per item No-271 cum 0.708 cum Rs 2325.70 Rs 1646.41
3/4" C.C.stone chips 3/4" granite Cum 0.198 no. Rs 1340.00 Rs 0.27
Coarse sand Per cum 0.113 cum Rs 635.00 Rs 71.92
Cement Per bag 1.75 bag Rs 210.00 Rs 367.50
1/4" Granolithic chips: Marble chips Per qtls 0.25 qtls Rs 215.00 Rs 53.75
Cement Per bag 1.00 bag Rs 210.00 Rs 210.00
Sundries for rubbing and polishing L.S. Rs 150.00
Total Rs 2499.85
(B) Labour :
Mistri Per day 1/8 no. Rs 210.00 Rs 26.25
Mason Per day 2 no. Rs 200.00 Rs 400.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Beldar for cutting and polishing Per day 15 no. Rs 110.00 Rs 1650.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Sundries like phanties etc. L.S. Rs 89.49
Total Rs 2418.24
Water charges 1.50 % of (A+B) Rs 73.77
Total Rs 4991.86
Contractor s profit @ 10% except on cost of cement sand &
base concrete Rs 499.19
TOTAL Rs 5491.05
Rate for 9.29 Sqm 5491.05
Rate for 1.00 Sqm Rs 591.07
Say Rs 591.10
621 As in item no 620 above but when white cement is used in top 5 mm (1/4") layer instead of ordinary
cement.
Rate as per item no 620 above Rs 5491.05
Ded cost of grey cement Per bag 1.00 bag Rs 210.00 Rs -210.00
Add cost of white cement From
market Per bag 1.00 bag Rs 575.00 Rs 575.00
Contractor s profit @ 10% on Rs. 575.00 Rs 57.50
TOTAL Rs 5913.55
Rate for 9.29 Sqm 5913.55
Rate for 1.00 Sqm Rs 636.55
Say Rs 636.60
622 As in item no 620 above but when coloured floor are to be made.
Rate as per item no 620 above Rs 5491.05
Add cost of colour (Deep bluish) Per bag 4.00 Kg Rs 190.00 Rs 760.00
Contractor s profit @ 10% on Rs. 760.00 Rs 76.00
Water charges 1.50 % of Rs. 760.00 11.40
Ded cost of grey cement Per bag 4.00 bag Rs 210.00 Rs -840.00
TOTAL Rs 5498.45
Rate for 9.29 Sqm 5498.45
Rate for 1.00 Sqm Rs 591.87
Say Rs 591.90
624 As in item no 620 to 622 above but base cocrete consisting of one part of cement, 4 part of loacl
sand and 8 part of brick ballast.
Add Extra :- Difference in the cost of
TOTAL Rs 3321.11
Rate for 9.29 Sqm 3321.11
Rate for 1.00 Sqm Rs 357.49
Say Rs 357.50
625 Granolithic marble dado 2 cm(3/4") thick consisting of 15 mm (9/16") thick layer of one part cement,
two part of approved coarse sand including 5 mm (3/16") thick surface coat with ordinary cement,
black, white or grey or mixed marble chips passing 3 mm (1/8") but retained on 1.5 mm (1/6") mesh
screen in proportion of 1:2 as specified or directed by the E/I and polished by hand or machine and
finally finished with french manson polish or other approved polish including 8 cm (3") Kankar lime
concrete base including supply of all materials , labour and T & P etc required for proper completion
of the work.
(A ) Materials :
Base 12 mm thick cement plaster
1:2 as base coat wth cement and
coarse sand as per S.I.Nos 581 Sqm 9.290 Sqm Rs 107.70 Rs 1000.53
3/8" thick rubbed to 1/4" marble
chip Per qtls 1.400 qtls Rs 215.00 Rs 0.30
Cement Per bag 1.00 bag Rs 210.00 Rs 210.00
Sundries for rubbing and polishing L.S. Rs 180.00
Total Rs 1390.83
(B) Labour :
Mistri Per day 1/6 no. Rs 210.00 Rs 35.00
Mason Per day 3/4 no. Rs 200.00 Rs 150.00
Beldar Per day 3/4 no. Rs 110.00 Rs 82.50
Beldar for cutting and polishing Per day 15 no. Rs 110.00 Rs 1650.00
Bhisti Per day 1/4 no. Rs 130.00 Rs 32.50
Total Rs 1950.00
Water charges 1.50 % of (A+B) Rs 50.11
Total Rs 3390.95
Contractor s profit @ 10% Rs 339.09
TOTAL Rs 3730.04
Rate for 9.29 Sqm 3730.04
Rate for 1.00 Sqm Rs 401.51
Say Rs 401.50
626 As in item no 625 above but when white cement is used in top 5 mm (3/16") layer instead of ordinary
cement.
Rate as per item no 625 above Rs 3730.04
Ded cost of grey cement Per bag 1.00 bag Rs 210.00 Rs -210.00
Add cost of white cement From
market Per bag 1.00 bag Rs 575.00 Rs 575.00
Contractor s profit @ 10% on Rs. 575.00 Rs 57.50
TOTAL Rs 4152.54
Rate for 9.29 Sqm 4152.54
Rate for 1.00 Sqm Rs 446.99
Say Rs 447.00
627 As in item no 620 above but when coloured dado are to be made.
Rate as per item no 625 above Rs 3730.04
Add cost of colour (Deep bluish) Per bag 4.00 Kg Rs 190.00 Rs 760.00
Contractor s profit @ 10% on Rs. 760.00 Rs 76.00
Water charges 1.50 % of Rs. 760.00 11.40
Ded cost of grey cement Per bag 4.00 bag Rs 210.00 Rs -840.00
TOTAL Rs 3737.44
Rate for 9.29 Sqm 3737.44
Rate for 1.00 Sqm Rs 402.31
Say Rs 402.30
628 Supply & fixing 6 mm (1/4") China white glazed in flooring or skirting dado laid with 1:3 cement and
approved coarse sand mortar finished with white cement slurry jointing and polishing complete
including supply of all materials, labour and T & p etc required for proper completion of the work.
( Taken an area of 12 sq yard - 108 sq.ft )
Or Taken 10.03 Sqm
(A ) Materials :
Tiles required Per doz 36.000 doz Rs 115.00 Rs 4140.00
Cement Per bag 3.20 bag Rs 210.00 Rs 672.00
Coarse sand Per cum 0.34 Cum Rs 635.00 Rs 215.77
White Cement Per bag 1.00 bag Rs 575.00 Rs 575.00
Marble dust Per cum 0.11 cum Rs 6000.00 Rs 679.60
Total Rs 6282.38
(B) Labour :
Mistri/ Tile Layers Per day 4 no. Rs 210.00 Rs 840.00
Beldar Per day 2 no. Rs 110.00 Rs 220.00
Sundries L.S. Rs 45.00
Total Rs 1105.00
Water charges 1.50 % of (A+B) Rs 110.81
Total Rs 7498.19
Contractor s profit @ 10% Rs 749.82
TOTAL Rs 8248.01
Rate for 10.03 Sqm 8248.01
Rate for 1.00 Sqm Rs 822.33
Say Rs 822.30
630 Providing and fixing aluminium strips of 16" gauge in joints of floors & skirtings at the time of laying
floors flush with leavel, including labour and T & P etc complete. ( Skelton analysis as per S.I. No 20,
1962 CPWD analysis)
Taken 43.89 Rm
(a) of 2.5 cm (1") depth .
Details of cost of 144 rft.( or 43.89
Rm) Of aluminium sheet cut into
strips 16" gauge 1" depth wt=
4.91 Kg
Add wastage 5 % on above 0.25 Kg
Total 5.16 Kg
(A ) Materials :
Cost of strips Per kg 5.160 Kg Rs 150.00 Rs 774.00
Carriage of Strips L.S. 8.11
Total Rs 782.11
(B) Labour :
Mason Per day 1.00 no. Rs 200.00 Rs 200.00
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Sundries L.S. Rs 33.33
Total Rs 343.33
Water charges 1.50 % of (A+B) Rs 5.27
Total Rs 356.71
Contractor s profit @ 10% Rs 35.67
TOTAL Rs 392.39
Rate for 43.89 Rm 392.39
Rate for 1.00 Rm Rs 8.94
Say Rs 8.90
(A ) Materials :
Cost of strips Per kg 7.740 Kg Rs 150.00 Rs 1161.00
Carriage of Strips L.S. 8.11
Total Rs 1169.11
(B) Labour :
Mason Per day 1.00 no. Rs 200.00 Rs 200.00
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Sundries L.S. Rs 33.33
Total Rs 343.33
Water charges 1.50 % of (A+B) Rs 5.27
Total Rs 356.71
Contractor s profit @ 10% Rs 35.67
TOTAL Rs 392.39
Rate for 43.89 Rm 392.39
Rate for 1.00 Rm Rs 8.94
Say Rs 8.90
631 Providing and fixing glass strips of 3.15 mm(1/8") thickness in joints of floors & skirtings at the time
of laying floors flush with leavel, including labour and T & P etc complete.
Taken 43.89 Rm
(a) of 2.5 cm (1") depth .
Details of cost of 144 rft.( or 43.89
Rm) Of glass strips 1/8" thick
(A ) Materials :
Cost of strips Per Rm 43.890 Rm Rs 4.40 Rs 193.12
Carriage of Strips L.S. 0.28
Total Rs 193.40
(B) Labour :
Mason Per day 1.00 no. Rs 200.00 Rs 200.00
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Sundries L.S. Rs 33.33
Total Rs 343.33
Water charges 1.50 % of (A+B) Rs 5.15
Total Rs 348.77
Contractor s profit @ 10% Rs 34.88
TOTAL Rs 383.64
Rate for 43.89 Rm 383.64
Rate for 1.00 Rm Rs 8.74
Say Rs 8.70
(b) of 4 cm (1 1/2") depth .Details of cost of 144 rft.( or 43.89 Rm) Of Glass strips 3.15 mm
(1/8")
(A ) Materials :
Cost of strips Per Rm 43.890 Rm Rs 7.70 Rs 337.95
Carriage of Strips L.S. 0.42
Total Rs 338.37
(B) Labour :
Mason Per day 1.00 no. Rs 200.00 Rs 200.00
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Sundries L.S. Rs 33.33
Total Rs 343.33
Water charges 1.50 % of (A+B) Rs 5.16
Total Rs 348.91
Contractor s profit @ 10% Rs 34.89
TOTAL Rs 383.80
Rate for 43.89 Rm 383.80
Rate for 1.00 Rm Rs 8.74
Say Rs 8.70
CHAPTER - 15
PAINTING & DISTEMPRING
(A ) Materials :
Distempering. Oil distemper in
paste Per kg 0.750 kg Rs 53.00 Rs 39.75
T & P and Sundries etc. L.S. Rs 20.00
Painter Per day 0.200 no. Rs 200.00 Rs 40.00
Coolies Per day 0.200 no. Rs 110.00 Rs 22.00
Total Rs 121.75
Contractor s profit @ 10% Rs 12.18
Total Rs 133.93
Rate 9.29 sqm Rs 133.93
Rate for 1.00 sqm Rs 14.42
Say Rs 14.4
Unit - 9.29 sqm
660 Finishing walls with water proofing cement paint of approved make and new work with two coats to
give an even shade, including supply of all materials, labour and T&P etc. required for proper
completion of the work.
(A ) Materials :
Snowcem powder Per kg 3.40 kg Rs 35.00 Rs 119.00
Painter Per day 0.30 no. Rs 200.00 Rs 60.00
Coolies Per day 0.30 no. Rs 110.00 Rs 33.00
Bhisti Per day 0.38 no. Rs 130.00 Rs 48.75
Scaffolding andT & P and
Sundries etc. L.S. Rs 20.00
Total Rs 280.75
Water charges @ 1.5% Rs 4.21
Total Rs 284.96
Contractor s profit @ 10% Rs 28.50
Total Rs 313.46
Rate 9.29 sqm Rs 313.46
Rate for 1.00 sqm Rs 33.74
Say Rs 33.7
Total Rs 120.79
Contractor s profit @ 10% Rs 12.08
Total Rs 132.86
Rate 9.29 sqm Rs 132.86
Rate for 1.00 sqm Rs 14.30
Say Rs 14.3
T & P and
Sundries,gum ,ladder etc. L.S. Rs 20.00
Total Rs 46.17
Contractor s profit @ 10% Rs 4.62
Total Rs 50.78
Rate 9.29 sqm Rs 50.78
Rate for 1.00 sqm Rs 5.47
Say Rs 5.5
(A ) Materials :
White lime Per kg 2.00 kg Rs 5.50 Rs 11.00
White washer Per day 0.07 no. Rs 200.00 Rs 13.33
Helper (Coolies) Per day 0.07 no. Rs 110.00 Rs 7.33
T & P and
Sundries,gum ,ladder etc. L.S. Rs 20.00
Total Rs 51.67
Contractor s profit @ 10% Rs 5.17
Total Rs 56.83
Rate 9.29 sqm Rs 56.83
Rate for 1.00 sqm Rs 6.12
Say Rs 6.1
751 Consolidation of kankar by hand rammer including opening out stacks , shorting kankar in to Three
sizes repairing patch in existing road surface with kankar, picking up old surface , spreading kankar
, making medhi to retain water and ramming and also including carriage of metal up to 30M (100').
carriage of water to 100M (1furlong) supply and maintenance of barrior , caution posts , light at
night and including all T&P etc. required for proper completion of the work, kankar to the supplied
to the contractor free of cost at site.
Taking up a length of 220x12' = 2640.00 sft kankar required 2640.00x3/8=990.00 cft Or 28.31
Cum
Taken for 28.01 Cum Unit Cum
Labour:-
Beldar for crish croos lines & Per day 220.00
Sweeping & taking out kankar
dug. 2.00 no. Rs 110.00 Rs
Preparing earth & making medhi Per day 110.00
mazdoor 1.00 no. Rs 110.00 Rs
Opening out stacks shorting in to
sizes.
Beldar Per day 2.00 no. Rs 110.00 Rs 220.00
Mazdoor Per day 2.00 no. Rs 110.00 Rs 220.00
Carriage of kankar & spreading
on surface
Mazdoor Per day 4.00 no. Rs 110.00 Rs 440.00
Hand packing Beldar Per day 6.00 no. Rs 110.00 Rs 660.00
Supply of water. Mazdoor Per day 8.00 no. Rs 110.00 Rs 880.00
Consolidation .
Head rammer man Per day 1.00 no. Rs 110.00 Rs 110.00
Rammer man Per day 11.00 no. Rs 110.00 Rs 1210.00
Basi chot Beldar Per day 2.00 no. Rs 110.00 Rs 220.00
Leakh katai L.S Rs 33.9
T&P and night light. L.S Rs 33.9
Total Rs 4357.70
Contractor s profit @ 10% Rs 435.77
Total Rs 4793.47
Rate per 28.01 Cum Rs 4793.47
Rate per 1 Cum Rs 171.13
Say Rs 171.10 150
752 As in item no-751 above but for consolidation by road roller including hire & fuel of the roller .
Taken for 28.01 Cum
As in item no-751 Rs 4793.47
Deduct for labour involve in
consolidation (A) Rs -1400.00
Add for hire charges of road Per day
roller. 1.00 no. Rs 0.00 Rs 0.00
Steam coal Per day 0.25 Ton Rs 0.00 Rs 0.00
Beldar Per day 2.00 no. Rs 110.00 Rs 220.00
Total Rs 3613.47
Contractor s profit @ 10% on Rs. -120
184.00 only Rs
Total Rs 3493.47
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
754 As in item no-752 above but for 8 cm thick coat of brick ballast.
Taken for 28.01 Cum
As in item no-752 Rs 3037.69
Add diffrance in item no-755/756
36.40
Total Rs 3074.09
Rate per 28.01 Cum Rs 3074.09
Rate per 1 Cum Rs 109.75
Say Rs 109.80
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
758 Digging kankar including breaking , cleaning and royalty as well as the cost of boring to fined
kankar strata excluding cartage and proper stacking.
Taken Qtty 2.83 Cum (100cft)
Royalty to villagers Rs 0.00
Indication (digging) Per day 1/8 no. Rs 130.00 Rs 16.25
Beldar Per day 4.00 no. Rs 110.00 Rs 440.00
Coolie Per day 3.00 no. Rs 110.00 Rs 330.00
Total Rs 786.25
For hundred cft . Of kankar 110cft. Of kankar as the quary will have to be dug.
Hence extra 10% on above but
excluding Royality Rs 78.63
Total Rs 864.88
Rate per 2.83 Cum Rs 864.88
Rate for 1.00 Cum Rs 305.61
Say Rs 305.60
759 Making mud tree gaurds 1M (3'-4') internal diameter and I meter (3'-4') high above.ground level
Unit = 1 Nos
Mason Per day 3/4 no. Rs 200.00 Rs 150.00
Coolie Per day 3/4 no. Rs 110.00 Rs 82.50
Sun dries etc. L.S Rs 5.28
Total Rs 237.78
Contractor s profit @ 10% on Rs. Rs 23.78
146 only
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
Total Rs 349.34
760 Dag-belling 15 cm. Deep in one line alinged, with flags and jhandies as directed by the Engineer-in-
charge.
Unit = 1 Km
Taken Length 1.61 Km (1 Mile)
Mate Per day 1.00 no. Rs 130.00 Rs 130.00
Beldar Per day 9.00 no. Rs 110.00 Rs 990.00
Total Rs 1120.00
Contractor s profit @ 10% on Rs. Rs 112.00
146 only Total Rs 2222.00
Rate for . 1.61 Km Rs 2222.00
Rate for 1.00 Km Rs 1380.12
Say Rs 1380.10
761 Painting white traffic lines 8 cm. Wide in three coats with approved road marking paint (Spirit base)
As directed by E/I. including supply of all materials, labour and T&P etc. required for proper
completion of the work.
Unit = 1 Rm
Say Rs 16.1
762a
Brick soling with straight overburnt bricks laid flat and dry including preparation of subgrade to
prescribed camber and including supply of bricks, filling joints, with local earth spreading a blinding
coat of cm. (3/8") depth of local earth of P.I.5 to 7 or sand. over the entire surface & including
labour & T&P etc. required for proper completion of the work.
Unit = 1 Sqm
Taken 9.29 Sqm (100Sqft)
Bricks Per %0 350 no. Rs 2900.00 Rs 1015.00
Rate of preparing subgrade and
laying as per item No- 785 278.66
Total 1293.66
Contractor profit @ 10% on Rs. Rs 0.00
Total Rs 1293.66
Rate for 9.29 Sqm Rs 1293.66
Rate for 1.00 Sqm Rs 139.25
Say Rs 139.30
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
Unit = 1 Sqm
Taken for 9.29 Sqm (100Sqft)
As in item no-762(b) above Rs. 2077.16
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
Total Rs 3019.50
Rate for 0.201 Km Rs 3019.50
( 1.00 Furlong)
Rate for 1.00 Km Rs 15022.39
Say Rs 15022.40
765 Brick edging on both sides of roads of 1st clas bricks 8cm (3") wide & 12 cm (4.50") deep laid with
mud mortor including labour & suplly of bricks finished to required templete and in proper alignment
and also including dressing & ramming the excavated earth as directed by the E/I.
Unit = 1 Km
Take a strip of 1/2 furlong 2 x 330 = 660 rft.
2x 330 = 660 rft
Bricks Per %0 875.00 no. Rs 2900.00 Rs 2537.50
Mason Per day 1.00 no. Rs 200.00 Rs 200.00
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
coolie Per day 2.00 no. Rs 110.00 Rs 220.00
Dressing &
throwing
coolie Per day 2.00 no. Rs 110.00 Rs 220.00
T&Psurplus
, Baskets & other sundries L.S Rs 25.38
material
Total Rs 3312.88
Contractor s profit @ 10% Rs 331.29
Total Rs 3644.17
Rate for 0.201 Km Rs 3644.17
Rate for 1.00 Km Rs 18130.21
Say Rs 18130.20
766 Stacking of road metal to required templete after screening at road side including dressing of side
berms as required , were matel is to be stacked and including a lead up to 60M (200")
Unit = 1 Cum
Taken 2.83 Cum
Screening coolie Per day 0.20 no. Rs 120.00 Rs 24.00
Dressing, leveling , side burms , including filling.
coolie Per day 0.20 no. Rs 110.00 Rs 22.00
stacking beldar Per day 0.50 no. Rs 120.00 Rs 60.00
T&P & other sundries etc. L.S Rs 6.77
Total Rs 112.77
Contractor s profit @ 10% Rs 11.28
Total Rs 124.05
Rate per 2.83 Cum Rs 124.05
Rate for 1.00 Cum Rs 43.83
Say Rs 43.80
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
Deduct less labour required for Per day 4.00 no. Rs 110.00 Rs -440.00
Heating Tar beldar Total Rs 3925.00
Rate per 367.880 Sqm Rs 3925.00
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
771 As in item 767 but with Tar in 2nd coat or other subsquent coats of painting over previously painted
surface . The above labour will make an output double the area I.e. the same labour can do the
painting of one furlong.
Unit = 1 Sqm
772 Scraping old painted suface including disposal of all scraped material to a distance of 30m. (100')
as directed by E/I.
Unit = 1 Sqm
Taken 9.29 Sqm (100Sqft)
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Unit = 1 Cum
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
774 As in item no- 773 above but excluding supply of cement coarse sand and stone ballast (Labour
only)
Unit = 1 Cum
Labour as in item No- 773 including forms work. 4493.33
Contractor profit @ 10% 449.33
Total Rs 4942.66
Rate per 3.737 Cum Rs 4942.66
Rate for 1.00 Cum Rs 1322.66
Say Rs 1322.70
775 Blinding of water bound stone or kankar lime with local earth by spreading evenly to an average
depth of 1.5 cm (9/16)% & filling the intersticks of the road metal. The trenches to be so dug for
taking the earth that they form continuous side drain at road boundry.
Unit = 1 Km
Take a length of one furlong 1x660x12x 1/24 = 330 Say 300cft
Or 8.49504 Cum for (100.584 Rm )
Rate for earth work Per Cum 8.50 Cum Rs 40.00 Rs 339.80
Add 50% for small work 169.90
Total Rs 509.70
Rate per 0.201 Km Rs 509.70
Rate for 1.00 Km Rs 2533.80
Say Rs 2533.80
776 Earth work in edging of the painted or C.C miles in a width of 1/2m. (20") on either side according
to patri template including dressing ramming etc. the treches to be so dug for taking the earth that
they form a continuous side drain at road boundry.
Unit = 1 Km
Take a length of one furlong: Earth work to be done (average) say 380 cft (10.76 cum )
Rate for earth work Per Cum 10.76 Cum Rs 40.00 Rs 430.40
Add 50% for small work 215.20
Total Rs 645.60
Rate per 0.201 Km Rs 645.60
Rate for 1.00 Km Rs 3209.39
Say Rs 3209.40
777 Joint and other small cracks filling in C.C miles after racking out the joints and removing the old Tar
and other material with suitable materials as directed by E/I (Labour only) Total joints at every 33'
joints to be filled would be 5280 / 33
Unit = 1 Km
160 nos
Add 25% for other cracks 40 nos
Total 200 Say 200 joints would be attended .
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
778 Consolidation of kankar in patch repair from 1st june to 14 Nov. by hand rammer including opening
out stacks, picking out old surface up to 8cm (3") in a rectengular form, making 5cm. (2") wide drain
around the patch up to depth of 12cm (4 1/2") including carriage of kankar and water, but excluding
supply of kankar and including stacking the unserviceable materials & basi - chot mext day &
blinding the same as directed by the E/I.
Unit = 1 Cum
780 Patch repair of painted miles with tar & bitumen (Labouronly0 including heating of paint up to
required tempreature , pouring it on the surface spreading the necessary qnty of grit & ramming
hard with hand rammer and also including cleaning with brush etc. the existing surface after
scarifying it to the W.B srface in rectangular shape & spreading the dismantald materials on the
patries as directed by the E/I.
As per Ce's circular patch work is carried out up to a stage when 1/2 ton tar is used per year per
Mile
(6/4 surface to be treated by 1 1/2 ton in year 3360/12 = 10000 sft Girt to be consumed
Unit = 1 Cum
270 cft (7.6455 cum ) Taking 25 cft ( 0.708 cum )
Taken 0.71 Cum
Mate Per day 1.00 no. Rs 130.00 Rs 130.00
Beldar Per day 4.00 no. Rs 110.00 Rs 440.00
Coolie Per day 4.00 no. Rs 110.00 Rs 440.00
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
Total Rs 1010.00
Contractor's profit @ 10% 101
Total Rs 1111.00
Rate per 0.710 Cum Rs 1111.00
Rate for 1.00 Cum Rs 1564.79
Say Rs 1564.80
781 Cleaning of existing painted surface and laying premix 2 cm thick over a tack coat with graded
approved grit and bitumen( Labour only) including ……..
Unit = 1 Sqm
Take a length of 1/2 furlong 330 x 12 = 3960 sft. Taking area 367.884 Sqm
Taken Area = 367.88 Sqm
Labour for Celaning : Mazdoor Per day 6.00 no. Rs 110.00 Rs 660.00
coolie Per day 660.00
6.00 no. Rs 110.00 Rs
Tack coat heatting & spreading
on road.
Hot beldar Per day 4.00 no. Rs 120.00 Rs 480.00
Premixing , screening grit
Beldar Per day 1.00 no. Rs 110.00 Rs 110.00
Tar heating & mixing grit
Beldar Per day 5.00 no. Rs 120.00 Rs 600.00
Coolie Per day 330.00
3.00 no. Rs 110.00 Rs
Spreading the premixing &
mixing in to camber
Beldar Per day 15.00 no. Rs 120.00 Rs 1800.00
Diversion watering : Mazdoor Per day 2.00 no. Rs 110.00 Rs 220.00
Misce: Mate Per day 2.00 no. Rs 110.00 Rs 220.00
Work agent Per day 1.00 no. Rs 150.00 Rs 150.00
Tar, bitumen& Fire Man Per day 2.00 no. Rs 140.00 Rs 280.00
Sundries , cartage and T&P etc L.S L.S 338.46
Total Rs 5848.46
Rate per 367.880 Sqm Rs 5848.46
Rate for 1.00 Sqm Rs 15.90
Say Rs 15.90
782 As in item no 781 above but in patches labour required fpr the work when 25 cft grit is consumed
Unit = 1 Cum
Mate Per day 1.25 no. Rs 130.00 Rs 162.50
Hot Beldar Per day 4.00 no. Rs 120.00 Rs 480.00
Coolie Per day 4.00 no. Rs 110.00 Rs 440.00
Sundries L.S. Rs 108.31
Total Rs 1190.81
Rate per 0.70792 Cum Rs 1055.00
Rate for 1.00 Cum Rs 1490.28
Say Rs 1055.00
783 Cleaning the premix surface and laying seal coat with approved 6 mm graded grit and bitumen
( Labour only)…………..
Unit = 1 Sqm
Take a length of 1/2 furlong 330 x 12 = 3960 sft. Taking area 367.884 Sqm
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
785 Brick soling with straight overburnt bricks laid flat and dry ( Labour only) including preparation of
subgrade to prescribed camber filling, joints with local earth spreading a blinding coat of 1 cm.
(3/8") depth of local earth of P.I.5 to 7 over the entire surface & including labour and T&P etc.
required for proper completion of the work.
Unit = 1 Sqm
Contd..........
SI No. Item of work Unit Quantity Rate Cost
1 2 3 4 5 6
Contd..........
Analysis of Rate
1- Providing & Laying 80mm thick P.C.C Inter lock tiles over base concrete 100 mm thick
C.C 1:4:8 ( Cement : Fine Sand : 40mm Brick Ballast ) and 50mm thick custion of Ganga sand
including supply of all material , labour , T&P etc. required for proper completion of the work.
(iii) 80mm thick Inter lock vibratory tile rate at work shop
= 465.00xSqm @ Rs. 490.30 Per Sqm = Rs. 227989.50
770200762.xlsxSheet2