Professional Documents
Culture Documents
7. LA01_DCP_2021-03-10-133708
7. LA01_DCP_2021-03-10-133708
Executive Summary
The promising potential of modern Supply Chain Management (SCM) concepts is
attracting the attention of the whole automotive industry. These concepts address root-
causes of current limitations in many logistics networks. Efficient build-to-order strategies
and short time to delivery goals require fast, flexible and reliable supply networks. In this
context inter-company visibility and transparency of relevant data play a central role.
Modern SCM aims to complement current plant or company centric processes based on
ERP systems by linking together the different actors in supply networks and establishing
well defined collaboration processes. Thus SCM is a core element in overcoming the
local, company-centric view and enabling a global view on supply networks.
The Odette SCM is developing recommendations for selected SCM building blocks by
bringing together the know-how and experience of OEMs and major suppliers.
This recommendation describes the SCM building block “Demand Capacity Planning”
(DCP). It incorporates business process model, functionalities and the respective data
elements/messages. The goal of the recommendation is to set a de facto standard for
DCP in the automotive industry and to establish a basis for interoperability of DCP
applications from different software providers and marketplaces.
The goal of Demand Capacity Planning (DCP) is to avoid significant capacity
shortfalls and situations of serious under-utilisation. The emphasis is on potentially
serious misalignments beyond the time horizon covered in existing production planning
systems. Therefore DCP is positioned as a complement to existing ERP-systems.
A key element in DCP is the detection of potential misalignments (capacity shortfalls or
under-utilisation) early enough to take preventive actions. After receiving updated
demand forecast information, DCP highlights the time periods with serious under or over
capacity. In the first stage of problem solving, the supplier tries to adjusts his capacity to
the new demand situation with internal measures (e.g. banking, overtime, non-working
shifts). If these measures are not sufficient to solve the issue, the supplier will work with its
customer(s) to evaluate and decide on additional collaborative measures. These
measures (e.g. installation of additional shift, new tool, new line) are typically associated
with long lead-times for implementation, significant investment and risk and therefore
require approval of the commercial areas (purchasing / sales).
The proposed concept with its systematic, integrated and fast process and collaborative
elements leads to earlier and more reliable detection of capacity issues and will allow the
supplier to better adapt his capacity to the fluctuations of demand.
When Odette started the DCP project, several companies (e.g. Audi/VW, DC (MCG),
Ford, GM, PSA, Renault) had either already introduced or at least planned to introduce
DCP applications. GM Europe for example started in 1999 with a system called CAMAS.
In 2002 1.800 suppliers with 50.000 part numbers were using the solution. And this is just
one example.
The drivers to standardise the basic functionality and processes of DCP are:
! Suppliers want to avoid having to implement individual solutions with every customer
and want to see consolidated demands for capacity planning
! Customers want to minimise the effort for roll-out of the DCP process to their suppliers
! From the standpoint of a single company, the implementation of individual DCP
systems with all relevant business partners is very time consuming and inefficient.
Page: 2 / 37
Demand Capacity Planning – V 1
Overview
Project participation
The following companies were part of the Demand Capacity Planning Project working
group:
In addition it provides presentations, e.g. for training purposes (to be found in appendix).
Page: 3 / 37
Demand Capacity Planning – V 1
Table of Contents
Table of Contents
Page: 4 / 37
Demand Capacity Planning – V 1.1
Chap 1 Philosophy of Supply Chain Management
Page: 5 / 37
Demand Capacity Planning – V 1.1
Chap 2 Introduction to DCP
2. Introduction to DCP
Capacity alignment has always been an important issue in business. Industrial
companies have therefore established procedures to align their capacities (production
equipment, personnel, etc.) to the volatility of market/customer demand.
The traditional process is usually carried out internally without the direct involvement of
external business partners. Recent developments in the automotive industry (e.g.
globalisation, platform strategies, process standardisation, higher number of model
variants, longer machine running times, shorter product life-cycles) have increased the
difficulties associated with this approach.
Supply Chain
Monitoring
Page: 6 / 37
Demand Capacity Planning – V 1.1
Chap 2 Introduction to DCP
Page: 7 / 37
Demand Capacity Planning – V 1.1
Chap 2 Introduction to DCP
[t] [t]
Alert ? No
action
-15% ! Yes
Multicustomer scenario : Supplier
internal measures /
The process is more complex.
action plan
"
Alert ? No !
action
-10% !! Yes
Customer Supplier
collaborative measures /
" action plan "
Alert ? No !!
action Legend:
Yes
!! = back-end
-5% !!! system,
" = DCP-Screen
with custo-
mised view
Picture 2-2: Two-Stage Approach to Problem Solving
Page: 8 / 37
Demand Capacity Planning – V 1.1
Chap 2 Introduction to DCP
! Focus:
Focus on early detection and resolution of the crucial issues that require long lead
times.
The process to define measures to resolve alerts is:
• create incremental capacity ,
• synchronise the implementation of the measure with the demand, taking into
account the implementation reaction time
• give priority to resolving issues with the least amount of slack between now
and the latest date for taking the decision to implement the measure .
WE shifts
Increase material supply for parts
Priority should be given to
Current capacity resolving issues with the least
amount of slack
demand Slack available BEFORE
initiating the measure
[units/w.]
0 2 4 6 8 10 20 30 week [time]
Page: 9 / 37
Demand Capacity Planning – V 1.1
Chap 2 Introduction to DCP
DCP
collaboration
layer
DCP
private data
C1 area S1 area C2 area S2 area
holding layer
! Collaboration & Confidentiality : Each company has full control over which information
will be made available to which collaboration partner (see picture below)
DCP S1
Customer 1
Customer 2
DCP DCP
C1 C2
DCP S2
Page: 10 / 37
Demand Capacity Planning – V 1.1
Chap 3 Business Process Description
! Problem solving :
" MONO-customer scenario
" MULTI-customer scenario
3.1 Initialisation
Initialisation Processes describe the activities that have to be completed before the day
to day operative processes can start.
The customer and supplier each have their own initialisation tasks to perform. Some
collaboration is required between the customer and supplier to ensure that both party’s
have their systems set up in a complementing and compatible way (for instance time
buckets).
Page: 11 / 37
Demand Capacity Planning – V 1.1
Chap 3 Business Process Description
A feature/option generally requires a set of product types (example: the option “park
pilot” requires the product types “park sensor” and “wiring harness”, “Electronic
Control Unit for park pilot” and “display”).
In order to establish meaningful information for suppliers the demand at
feature/option/car model/powertrain level needs to be broken down to product type
level (see Picture 3-2: Demand at feature/option/car model/powertrain level).
The product types need to be defined in such a way that the supplier can map them
unambiguously to capacity constraints.
Multi sourcing quotas need to be applied by the customer prior to sending the
demand information.
sensors
rain distance
sensors sensors
A 187 320
A 187 322
features/
options 100 “rain- 150 “park-
tronic” pilot”
Page: 12 / 37
Demand Capacity Planning – V 1.1
Chap 3 Business Process Description
A key-point in DCP is the definition of the available capacity that will be used as the
main reference in the system.
Page: 13 / 37
Demand Capacity Planning – V 1.1
Chap 3 Business Process Description
demand
available capacity
Q supplier offers potential increase incremental capac
capacity
∆Q incr. cap. 2
already agreed/planned
∆Q incremental capacity 1
capacity adjustment
0 10 20 30 40 [t]
Depending on the level of collaboration required between the customer and the
supplier, available capacity can be determined as:
! Contracted capacity and flexibility, based on contract
! Feasibility or best-can-do capacity, based on detailed production planning (usually
ERP-based)
! Resource-based capacity, usually derived from current and/or future bottleneck
resources (manually or extracted from ERP system)
The capacity model is defining the mapping structure linking the “items” with the
“resources”. (see Picture 3-4: Example for Capacity Model for Resource based
Capacity Information)
Only a very limited number of bottleneck resources (usually 1 or 2 per product type)
determine the capacity in terms of products. As a consequence, rather simple capacity
models allow a sufficient level of accuracy in DCP. This keeps the complexity low and
the focus on the relevant issues.
Page: 14 / 37
Demand Capacity Planning – V 1.1
Chap 3 Business Process Description
Electronic
Control
Unit (ECU) Rain Sensor
Type A B C 1 2
Items
x1 x1 x1
coefficient for
resource usage x2 = x3 =
Allocation of items 30 sec. 45 sec.
to resources C3 C5
Resources ⌧ ⌧
testing moulding
capacity constraint 620 hours / month
Page: 15 / 37
Demand Capacity Planning – V 1.1
Chap 3 Business Process Description
We have
Can you supply us ? "100 people,
"2 production lines,
•in April : 1000 navigation systems
"8000 material sets
•in May : 1200 navigation systems
"we can work 5 days in 2 shifts
The picture below illustrates how the “demand view” and the “capacity/resource view” are
mapped in DCP:
! Every item is associated to one or several resources / capacity constraints
! For every item-resource link, the coefficient of resource usage has to be defined.
Customer 1 Customer 2
D
Car platform Y2 Car platform Y1
E
Customer defined Electronic Sensors M
grouping* Control
A
Unit Rain Distance
ECU N
(ECU) Sensor Sensor D
Demand Structure
x1 x1 x1 x1 x1 x1 x1 x1 x2 x3 x1 x1 x1 x2
MAPPING Demand/Resources x1 x1 x1
Coefficient for resource usage
Allocation of items to resources
Picture 3-5: Building up the DCP Model - Linking Demand Structure with Capacity
Structure
Page: 16 / 37
Demand Capacity Planning – V 1.1
Chap 3 Business Process Description
The standard time period in DCP has to be defined by the supplier and agreed by
the customers.
Incoming demand and capacity information must be transformed into the agreed time
period.
Customer 1 Customer 2
D
E
Customer defined M
grouping* week month quarter A
12 1 2 3 123 72 3 4 8 3 N
D
Demand Time buckets
transformation
transformation
Resources Time buckets ⌧C1 ⌧C2 C3 ⌧ C4 ⌧ C5 ⌧ C6 ⌧ C7 ⌧ C
A
123 P
A
C
week e.g. based on production calendar I
T
Supplier Y
Page: 17 / 37
Demand Capacity Planning – V 1.1
Chap 3 Business Process Description
DCP analyses regularly and automatically whether demand forecasts and capacity
plans are aligned. It checks whether
! the demand forecast coming from the customer side and
! the available capacity (actual and/or planned) coming from the supplier side
are balanced. The DCP application highlights the time periods with under and over
capacity.
• Second stage : If the internal adjustment measures are not sufficient to align
capacity and demand, customer and supplier should collaborate and agree on
further alignment measures, cost and time scales. In this case the customer
may adjust its demand forecast and/or the supplier may adjust its capacity..
Alert ? No
action
-15% ! Yes
internal counter Supplier
measures /
action plan "
Alert ? No !
action
-10% !! Yes
Customer Supplier
collaborative counter
measures /
" action plan "
Alert ? No !!
action Legend:
Yes
!! = back-end
-5% !!! system,
" = DCP-Screen
with custo-
mised view
Picture 3-7: DCP process with two stage approach
Page: 18 / 37
Demand Capacity Planning – V 1.1
Chap 3 Business Process Description
Customer 2 No
Alert ?
demand
!! forecasts action
Yes
(quantities & dates) Supplier
internal counter
measures /
action plan "
Alert ? No
action
Yes
Supplier collaborates split + allocate Supplier
separately with customer 2 proposed capaci-
ties to customers " Supplier takes a business
decision (confidential)
Customer 2 Supplier
collaborative counter
measures / Supplier collaborates
" action plan " Legend:1
separately with customer
Supplier !! = back-end
Customer 1 system,
collaborative counter
measures / " = DCP-Screen
" action plan " with custo-
mised view
This process reflects exactly what suppliers are doing without DCP.
Page: 19 / 37
Demand Capacity Planning – V 1.1
Chap 4 Functionality
4. Functionality
This chapter describes the basic elements of DCP in detail.
The Power Point presentation related to Chapter 4 shows in details the content and
process related to the Alerts & Measures Board. The following part of the
recommendation is only a brief abstract of the main functionalities described in the
document.
The DCP process is managed in separate views of the Alerts & Measures Board:
• The supplier internal consolidated view (will be described later in this chapter)
• The collaborative view shared by the customer and the supplier
Parameters
The Power Point presentation related to Chapter 4 describes in details the various
parts of the Alerts & Measures Board.
Page: 20 / 37
Demand Capacity Planning – V 1.1
Chap 4 Functionality
Parameters
Press Working Hour Alert thresholds -10% 0% +5%
Unit
(% of demand)
! For a capacity constraint, both demand and capacity need to be expressed in the
same unit for the same time period and horizon. (see Chap 3.1-Initialisation)
! A regular update of demand and capacity information
! A list of capacity adjustment measures, agreed in advance if possible, so that
actions can then be suggested by the DCP ‘suggestion algorithm’
Page: 21 / 37
Demand Capacity Planning – V 1.1
Chap 4 Functionality
Initialisation phase
Approval of actions
Problem solving area
(automatic approval,
manual approval, removal)
The Power Point presentation related to Chapter 4 describes a proposal for the
calculation process.
Validation process
After the calculation process is performed, both partners have to validate the measures
they wish to take to solve the issues. To do so, they can either agree or reject each
suggested measure.
Note : some measures selected by the automatic calculation could be pre-approved.
Page: 22 / 37
Demand Capacity Planning – V 1.1
Chap 4 Functionality
Supplier and customer can also add or remove manually, if necessary, some measures
in the Collaborative problem solving area. This is especially important when, for
instance, a measure previously approved is no longer needed because of a decrease
in the demand
Only the approved actions should remain on the Alerts & Measures board from one
period to the next .
Demand t
Capacity and demand Data
relationships
Data adjustment
based on
Pre-defined Automatic 'suggestion experience
measures/actions algorithm' $ Suggestions
Approval of actions
(automatic approval,
manual approval, removal)
Only
Demand t+1 approved
actions
Same actions as Capacity and demand
previously + new actions
based on experience
Approval of actions
(automatic approval,
manual approval, removal)
DCP Dashboard
The DCP Dashboard is a common user interface that includes all the Alerts &
Measures Boards (Collaborative view) for the capacity constraints managed in the DCP
tool.
It reflects the same information from a customer or a supplier point of view.
Page: 23 / 37
Demand Capacity Planning – V 1.1
Chap 4 Functionality
Distance ⌧ Machining x2
Parameters
Unit Press Working Hour Alert thresholds -10% 0% +5%
Sensor (% of demand)
⌧
Available Capacity - Demand 100 -30 -70 50 100 0 -150 -200 -400
Assembly x1 Updated: 05/01/2003 Contracted Capacity 600 600 600 600 600 600 600 600 600
⌧ !!
Alert situation (confirmed actions only) 25% 0% -4% 11% 25% 0% -15% -29% -39%
Unit (ECU) Testing x1
List of general Capacity Adjustment Measures BY SUPPLIER
Potential incremental capacity
P-1 1 yes yes yes yes 0 3 2 10% (on avail. capa) Overtime, NOT charged 50 &
⌧ ECU 1.2 x1 P-1
P-3
1
6
approve 3 = approve approve 3 = approve €
approve 4 = approve approve 4 = approve €€
5
6
2 10% (on avail. capa) Overtime, charged
3 Add one shift
50
250 250 250
&
&
P-5 ∞ approve 5 = approve approve 5 = approve €€€ 7 4 Invest in new machine 200 200 200 &
P-6 ∞ approve 6 = approve approve 6 = approve €€€€ 8 4 Invest in new line 500 500 500 &
P-3 4 approve 7 = approve approve 7 = approve €€ - 3 Remove one shift -250 -250 -250 &
(customer view)
Machining Parameters
-10% 0% +5%
Press Working Hour Alert thresholds
⌧
Unit
(% of demand)
C7
Sensors Time period Month
Month Horizon (period) 9
⌧
? Updated: 05/01/2003 Contracted Capacity 600 600 600 600 600 600 600 600 600
Moulding
Europe C5 Collaborative problem solving area
Proposed Solutions
Date Impl. Supplier Customer Supplier Customer
Cost Priority Rule Solution P0 P1 P2 P3 P4 P5 P6 P7 P8 P9 P++ Valid
(decision) Time approval approval removal removal
P-1 1 yes yes yes yes 0 3 2 10% (on avail. capa) Overtime, NOT charged 30 1
Lacquering C4
P-1 1 yes yes yes yes 0 3 2 10% (on avail. capa) Overtime, NOT charged 48 1
P-1 1 approve 3 = approve approve 3 = approve € 5 2 10% (on avail. capa) Overtime, charged 22 0
⌧
P-1 1 yes yes yes yes 0 3 2 10% (on avail. capa) Overtime, NOT charged 50 1
P-1 1 approve 3 = approve approve 3 = approve € 5 2 10% (on avail. capa) Overtime, charged 50 0
!! Selection of a capacity
P-3 6 approve 4 = approve approve 4 = approve €€ 6 3 Add one shift 250 250 250 250 0
P-1 1 yes yes yes yes 0 3 2 10% (on avail. capa) Overtime, NOT charged 50 1
Electronics constraint/resource
P-1 1 approve 3 = approve approve 3 = approve € 5 2 10% (on avail. capa) Overtime, charged 50 0
P-3 6 approve 4 = approve approve 4 = approve €€ 6 3 Add one shift 250 250 0
ECU
Incremental capacity (total: approved and not approved actions) 100 0 0 50 100 0 200 50 200
Type 2 Incremental capacity (approved actions only) 100 0 -22 50 100 0 -100 -200 -350
!!
⌧
Alert situation (confirmed actions only) 25% 0% -4% 11% 25% 0% -15% -29% -39%
Testing
C3 List of general Capacity Adjustment Measures BY SUPPLIER
Potential incremental capacity
Date Impl. Supplier Customer Supplier Customer
Cost Priority Rule Solution P0 P1 P2 P3 P4 P5 P6 P7 P8 P9 P++ Insert
(decision) Time approval approval removal removal
P-1 1 yes yes yes yes 0 3 2 10% (on avail. capa) Overtime, NOT charged 50 &
P-1 1 approve 3 = approve approve 3 = approve € 5 2 10% (on avail. capa) Overtime, charged 50 &
P-3 6 approve 4 = approve approve 4 = approve €€ 6 3 Add one shift 250 250 250 &
ECU 1.2 C2 P-5 ∞ approve 5 = approve approve 5 = approve €€€ 7 4 Invest in new machine 200 200 200 &
⌧
P-6 ∞ approve 6 = approve approve 6 = approve €€€€ 8 4 Invest in new line 500 500 500 &
P-3 4 approve 7 = approve approve 7 = approve €€ - 3 Remove one shift -250 -250 -250 &
P-x x yes yes approve approve 0 - - Disregard alert on month "x" TBD TBD TBD TBD TBD TBD TBD TBD TBD ALERT &
⌧
P-x x yes yes approve approve 0 - - Demand adjustment for month "x" TBD TBD TBD TBD TBD TBD TBD TBD TBD VALUE &
ECU 1.1
(supplier view)
Page: 24 / 37
Demand Capacity Planning – V 1.1
Chap 4 Functionality
DCP Dashboard also allows the definition of roles and responsibilities for the
workflow process. This process should be kept as simple as possible as quick
reaction is necessary.
Each capacity constraint is allocated to an ‘approver’ who is responsible for decisions
at that level.
‘Approvers’ linked to upper nodes should be included in the work flow process. In
order to reduce the workflow loop and have a reactive process, these people should
take responsibility for decisions even if approval is required from other departments,
Car
⌧ Moulding x1
platform ⌧ Lacquering x3
Y2
? ⌧ Lacquering x2
Electronic ⌧ !! Testing x1
Control
Unit (ECU) ⌧ !! Testing x1
!! ⌧ !! Testing x1
⌧ ECU 1.2 x1
Picture 4-5 Roles and responsibilities for the Approval process through the DCP
Dashboard
The Power Point presentation related to Chapter 4 provides a description of the DCP
Dashboard.
Page: 25 / 37
Demand Capacity Planning – V 1.1
Chap 4 Functionality
The design of the view and the rules for the internal 'suggestion algorithm' should be
similar to the Collaborative view, but with no approval process from customer side.
Initialisation phase
Page: 26 / 37
Demand Capacity Planning – V 1.1
Chap 4 Functionality
From the collaborative point of view, the multi-customer scenario will (changer partout
(see JPC)) be translated into several mono-customer situations. The Power Point
presentation related to Chapter 4 describes the various steps in this process.
Initialisation phase
Picture 4-7: General process including the Supplier Internal view in the multi-
customer scenario
Page: 27 / 37
Demand Capacity Planning – V 1.1
Chap 4 Functionality
! Data query
' e.g. a list of capacity constraints with red alerts
' e.g. a list of all capacity constraints with red alerts ON periods between 1 and 3
' e.g. a list of all capacity constraints with “decision date” (yellow boxes) in month 1
AND “action validated by both partners”
' …
Page: 28 / 37
Demand Capacity Planning – V 1.1
Chap 5 Responsibilities
5. Responsibilities
5.2.1 Data
5.2.1.1 Demand Data
This is the responsibility of the customer and should be:
! in line with the definition in this DCP recommendation
! adjusted to supplier business allocation
! detailed at the lowest practical level (part number, if possible)
! able to be consolidated in different ways (users/usages)
! given with an adequate horizon
! regularly updated
Page: 29 / 37
Demand Capacity Planning – V 1.1
Chap 5 Responsibilities
5.2.2 Parameters
The operation of an effective DCP tool depends upon the setting of several parameters.
Some of these parameters can be set by the supplier and the customer independently whilst
others must be agreed collaboratively.
Page: 30 / 37
Demand Capacity Planning – V 1.1
Chap 6 Data Description
6. Data Description
This recommendation is too high level to define all data elements necessary to support all
DCP functionnalities.
It is assumed that the developers of DCP solutions will build a comprehensive data model.
Picture 6-1 bellow illustrates the information flow in a decentralised architecture. Further
information regarding interoperability can be found in chapter 7.
Legend:
!! = back-end system,
" = DCP-Screen
DCP
information flow
level DCP
back-end
systems " " " "
level
!!! !!! !!! !!!
material flow
Page: 31 / 37
Demand Capacity Planning – V 1.1
Chap 7 Technical Aspects
7. Technical Aspects
DCP
collaboration
DCP
private data
C1 area S1 area C2 area S2 area
7.2 Interoperability
A good example for existing interoperability is mobile telecommunications:
! We, as the users, select one telephone model (e.g. from Nokia, Sony, Alcatel) and
one service provider (e.g. Vodafone, Deutsche Telecom, Orange), that fits best to
our individual profile/requirements.
! Our service provider interoperates with the other service providers and builds up a
direct connection to every external conversational partner we want to talk to. The
basis for the interoperability between the service providers are international
standards (e.g. GSM for mobile phones).
! As a user we do not have to care what telephone model and what software release
our conversational partner has. Nor do we need to know his service provider to talk
to him, to send him a text message or to leave a voice message.
Page: 32 / 37
Demand Capacity Planning – V 1.1
Chap 7 Technical Aspects
! With one telephone and one service provider we are connected to everybody. We
only need to know the correct telephone numbers.
Another example is the World Wide Web:
! Servers from any brand, using any operating system (NT, XP, UNIX…) are
interconnected, and can be added/removed without notice.
! Messages are travelling in this network without any central co-ordination platform.
! Nobody has any control of this network, but everybody can enjoy the advantages of
easy, robust and cheap communications.
The Odette SCM Group is convinced that Interoperability is the only feasible way to
implement SCM concepts on a broad basis in the automotive industry. The
reasons for this opinion and our proposed solution to the problem are described below.
Many B2B concept types like Demand Capacity Planning , Supply Chain Monitoring,
Vendor Managed Inventory, eRFQ, etc. have been created and introduced in the past
couple of years, and every day new solutions are added. As a consequence,
customers, marketplaces, suppliers, logistics providers, etc. which have developed and
implemented those B2B solutions require their relevant business partners to connect to
their solutions.
As illustrated in Picture 7-1 below, a single company (“Company X”) has two way to
comply with the request to use a business partner’s DCP solution:
! Option 1: Company X integrates its own backend systems with the DCP solution
of the respective business partner
" own backend integration (1:1 connection) for every individual solution
" poor cost/benefit ratio due to limited number of transactions and high one-off
investment
! Option 2: Company X may use a browser access
" user needs to log-in, check the situation and effect transactions / key in data in
the application (1:1 connection)
" inefficient due to high manual effort in day-to-day business..
companies that
Business Business Business Business initiate a B2B
Partner A Partner B Partner C Partner D solution integrate
!! !! !! !! their backend
systems once
Page: 33 / 37
Demand Capacity Planning – V 1.1
Chap 7 Technical Aspects
Every organisational unit (e.g. Company X) selects and installs one interoperable
DCP application. Company X may choose a lean low-cost solution or a solution with
advanced backend integration features and user management functionality according
to their own needs and preferences. The application can be hosted internally or
externally (e.g. company portal, marketplace or ASP).
Company X’s DCP application (“instance”) is linked to the company’s back-end
systems (legacy, ERP, etc.). As stated above, the back-end systems remain the
leading systems for capacity information and parameters.
After a status change in the-back end system (e.g. a change in cycle time that affects
capacity) the company’s own DCP instance is updated via the EAI information flow.
To inform the relevant business partners about the new status, the interoperability
information flow is used to update (synchronise) the adjacent DCP instances. The
DCP instances of the different organisational units communicate via the Internet, ENX,
ANX or other appropriate networks.
Page: 34 / 37
Demand Capacity Planning – V 1.1
Chap 7 Technical Aspects
companies that
Business Business Business Business initiate a B2B
Partner A Partner B Partner C Partner D solution integrate
!! !! !! !! their backend
systems once (no
change)
" " " " B2B-SCM instances
interoperate
(based on respective
Odette Interoperability
" Recommendation)
company X
!! Interoperability is an efficient way to achieve
integrates its " full end-to-end integration (fast and
own backend
Company X reliable data flow) and
systems once
" full B2B functionality and business
process
!! = Backend System (e.g. ERP), " = B2B instance e.g. for SCMo or VMI
A separate project group will develop the necessary elements to realise interoperability
for B2B applications. The basis is likely be a general recursive interoperability
approach with three major objects as deliverables:
! a general Supply Chain Recursive Model (SCRM)
as a basis for mapping complex supply networks in decentralised IT applications
! a general Supply Chain Interoperability Protocol (SCIP)
where an interoperability message set is embedded in an XML protocol
! a general Supply Chain Interoperability Reference Architecture (SCIRA)
Page: 35 / 37
Demand Capacity Planning – V 1.1
Chap 7 Technical Aspects
Page: 36 / 37
Supply Chain Monitoring V1.0
Chap 8 Appendix
8. Appendix
Page: 37 / 37