Professional Documents
Culture Documents
Risk Assessment Workshop Rev.2
Risk Assessment Workshop Rev.2
Rev.2
COURSE MATERIALS
Please make sure that below described materials are provided to you
throughout the course:
3. Risk assessment form and risk assessment matrix sample; which will be
used for all group activities and audited by trainer by the end of the
course.
2
COURSE INFORMATION MAP
Course Elements
Feedback Form
Why do we need Steps 1 – 4 +
Course Introduction Risk Assessments? Group Activity Updating the HIRA
form
Audits
3
BEFORE WE BEGIN
4
INTRODUCTION
• Hazards identification and risk assessments are essential processes for any
organization to prevent accidents and to achieve highest standards of
safety.
Hazard Identification, Risk Assessment and Risk Management procedure covers all
risk management processes applicable in QS.
5
OBJECTIVE
The purpose of this training is not to discuss the risk management procedure. Reading
and understanding the procedure is still mandatory and a pre-requisite.
6
UNIT A: INTRODUCTION TO RISK ASSESSMENT
7
DEFINITIONS
Risk Assessment: the process of analyzing and rating risks associated with
hazards and determining efficient controls to mitigate them.
Residual Risk: the risk remaining, associated with a job or an activity
after the precautions are taken.
Risk Ranking: numerical value given to the level of risk based on risk assessment.
The process of hazard identification must be carried out inside the plant.
8
DEFINITIONS
Spilled
oil on
the
ground
Other examples?
9
WHY DO WE NEED RISK ASSESSMENTS?
10
WHAT SHOULD RISK ASSESSMENTS COVER?
11
WHEN DOES RISK ASSESSMENTS BECOME INEFFECTIVE?
Risk assessments are live documents and must be updated when required.
Other examples?
12
WHAT IS OUR RESPONSIBILITY?
Assessment Team
Engineer/Section
Department
Process Step
Manager
Head
Define scope of the assessment A R I
Legend Form the assessment team A R I
13
UNIT B: RISK ASSESSMENT PROCESS
14
HAZARD IDENTIFICATION & RISK ASSESSMENT STEPS
15
STEPS 1,2 – IDENTIFY THE JOB & DESCRIBE IT
If any part of the activity is not determined, all hazards and controls
associated with the job will not reflect in the risk assessment.
16
STEPS 3,4 – IDENTIFY THE HAZARDS, RISKS & CONSEQUENCES
17
EXERCISE
30
5 minmin
18
STEP 5 – IDENTIFY THE EXISTING CONTROLS
19
STEP 5 – IDENTIFY THE EXISTING CONTROLS
20
STEP 5 – IDENTIFY THE EXISTING CONTROLS
21
EXERCISE
30
5 minmin
22
STEP 6 – EVALUATE CURRENT RISK RATING
Asset
People
Damage
Environment Reputation
23
STEP 6 – EVALUATE CURRENT RISK RATING
Potential probability:
Potential
Reputation Description
Severity
A No impact Never heard of in the Steel Industry.
24
STEP 6 – EVALUATE CURRENT RISK RATING
Potential
People Description
Severity
0 No injury No injury or health effect.
First Aid cases or minor discomfort cases e.g. Headache, dust /
1 Slight injury or health effect fumes / gases having irritation in the nose when inhaled - a
person can return back to work after a rest.
Reversible injuries or illnesses requiring Medical Treatment
(MTC) or Restricted Workday Cases (RWC) for 5 days or but not
2 Minor injury or health effect LTI's. E.g. loss of consciousness from medical reasons only (e.g.
diabetes, epilepsy, narcolepsy etc.), needle stick injuries and cuts
from sharp objects.
Reversible injuries or illnesses resulting in RWCs for more than 5
days or LTIs e.g. punctured ear drums, fractured ribs or toes,
3 Major injury or health effect
chronic back injuries, loss of consciousness from work-related
activities e.g. blow to the head, heat induced.
Single Fatality or permanent total Single fatality, permanent disability or irreversible illness such as
4
disability corrosive burns, amputation.
25
STEP 6 – EVALUATE CURRENT RISK RATING
Potential
Environment Description
Severity
0 No effect No impact to the environment.
No lasting effect.
Low-level impacts on biological or physical environment, local
1 Slight effect
environmental risk within the fence and within the system.
Clean up within days.
Minor short-medium term damage to small area of limited
significance.
2 Minor effect Single exceeding of statutory or prescribed limits; single
complaint; no permanent effect on the environment.
Clean up within weeks.
Moderate short-medium term widespread impacts, repeated
3 Local effect exceeding of statutory or prescribed limits and beyond fence or
neighborhood. Clean up within months.
Severe environmental damage; Qatar Steel is required to take
extensive measures to restore the contaminated environment to
4 Major effect
its original state; extended exceeding of statutory or prescribed
limits. Clean up within months – years.
26
STEP 6 – EVALUATE CURRENT RISK RATING
Potential
Assets and Production Description
Severity
0 No damage No financial impact.
27
STEP 6 – EVALUATE CURRENT RISK RATING
Potential
Reputation Description
Severity
0 No impact No reputational impact.
1 Slight impact Public awareness may exist but there is no public concern.
28
STEP 6 – EVALUATE CURRENT RISK RATING
29
EXERCISE
30
5 minmin
30
STEP 7,8 – ASSIGN ADDITIONAL ACTIONS
2. The risk rating is still high and more controls in order to reduce the
risk to either medium or low;
When the target date is passed, the action status has to be changed.
31
STEP 9 – EVALUATE RESIDUAL RISK RATING
1. The risk rating after both current and additional controls are
identified;
2. The residual risk indicates the acceptable risk which should be minor;
32
EXERCISE
30
5 minmin
33
UNIT C: FURTHER CONSIDERATIONS
34
FINALIZING THE RISK ASSESSMENT FORM
Risk assessments are live documents and must be updated when required.
35
FINALIZING THE RISK ASSESSMENT FORM
36
ADDITIONAL INFORMATION
4. Job Safety Analysis must be updated after every 6 months for both
company and contractors. For employees, if activity is new and JSA is
used, it must be converted to a HIRA before execution of same activity.
37
ADDITIONAL INFORMATION
38
SUMMARY
2. The first step of the hazard identification and risk assessment process is
to identify the job. If not done correctly, hazards may be missed.
4. Residual risk rating indicates whether our current controls are effective,
or whether we require additional controls (remedial actions).
39