Lighting Submit

Megger Armature General Socket Function Submit


NO BUILDING Installation Control Perapian RFIT Status Notes
Test Lampu Switch Outlet Test RFIT Panel
Switch General
1 FILLING AND PACKING BUILDING
a). RTD Done Done Done Done Done Done Done 13/06/24 15/06/24 15/06/24
b). SCM Done Done Done Done Done Done Done 13/06/24 15/06/24 15/06/24
c). Corridor GF Done Done Done Done NA Done Done 13/06/24 15/06/24 15/06/24
d). Corridor First Floor Done Done Done Done NA Done Done 13/06/24 15/06/24 15/06/24
2 CRYSTALLIZATION BUILDING Done Done TBC Done NA Done TBC TBC TBC TBC Perlu Scafolding, ada lampu belum
terpasang 1 unit
3 PRODUCTION BUILDING
a). RTD & Alcove Done Done Done Done Done Done Done Done TBC TBC
b). SCM Done Done Done Done Done Done Done Done TBC TBC
c). Office Done Done Done Done Done Done Done Done TBC TBC
4 RAW MATERIAL STORAGE
a). RMS Warehouse Done Done TBC Done Done Done TBC TBC TBC TBC Terkendala di area gudang Tetra
b). RMS Office Done Done Done Done NA Done Done Done 13/06/24 13/06/24
5 MAIN DISTRIBUTION CENTRE
a). MDC Warehouse Done Done Done Done Done Done Done 18/06/24 19/06/24 19/06/24
b). MDC Office Done Done Done Done NA Done Done Done TBC TBC Panel blm datang
6 CAN MAKING BUILDING Done Done Done Done Done Done Done Done 14/06/24 14/06/24
7 SUGAR RECEIVING BUILDING Done Done Done Done Done Done Done Done 14/06/24 14/06/24
8 ENERGY BUILDING Done Done Done Done Done Done Done Done TBC TBC
9 MAIN OFFICE BUILDING Done Done Done Done NA Done Done 14/06/24 15/06/24 Done terkait panel DP-ESDP-OF-1-1
10 ANCHILLARY BUILDING
a). MOSQUE A 14/06/24 15/06/24 18/06/24 Done NA Done 19/06/24 19/06/24 Done 20/06/24 kurang di area Plasa
b). MOSQUE B Done Done Done Done Done Done Done Done 13/06/24 13/06/24
c). CHEMICAL WASTE Done Done Done Done Done Done Done Done Done 13/06/24
d). MICROLAB Done Done Done Done Done Done Done Done 12/06/24 12/06/24
e). PUMP ROOM A Done Done Done Done Done Done Done Done Done 12/06/24
f). DRIVER'S SHELTER A Done Done Done Done Done Done Done Done Done 12/06/24
g). DRIVER'S SHELTER B Done Done Done Done Done Done Done Done 13/06/24 13/06/24
h). DRIVER'S SHELTER C Done Done Done Done Done Done Done 21/06/24 22/06/24 22/06/24 terkait panel temporary
i). DRIVER'S SHELTER D Done Done Done Done Done Done Done 28/06/24 29/06/24 29/06/24 terkait kabel 4x95
j). GUARD HOUSES A Done Done Done Done Done Done Done Done 12/06/24 12/06/24 ada terminasi panel temporary (Tata)
k). GUARD HOUSES B Done Done Done Done Done Done Done Done 13/06/24 13/06/24
l). GUARD HOUSES C Done Done Done Done Done Done Done Done 14/06/24 14/06/24
m). GUARD HOUSES D Done Done Done Done Done Done Done Done 15/06/24 15/06/24
n). GUARD HOUSES E Done Done Done Done Done Done Done Done 15/06/24 15/06/24
o). GUARD HOUSES F Done Done Done Done Done Done Done Done 15/06/24 15/06/24
p). MOTORCYCLE PARKING BUILDING Done Done TBC Done Done Done Done Done TBC TBC Lampu emergency S1 lagi di order
q). RAW MILK LAB Done Done Done Done Done Done Done Done Done ?
r). RAW MILK RECEPTIONT Done Done Done Done Done NA Done Done Done ?
s). KOPERASI AND MILK Done Done Done Done Done Done Done Done 12/06/24 12/06/24
t). PUMP ROOM B Done Done Done Done Done Done Done Done 13/06/24 13/06/24