Professional Documents
Culture Documents
M11- Applying Site Surveys and Set Out Procedures to Building Level 4
M11- Applying Site Surveys and Set Out Procedures to Building Level 4
ADDIS COLLEGE
Learning Guide
Unit of Competence:-Apply Site Surveys and Set-Out Procedures to Building Projects
Module Title:-Applying Site Surveys and Set-Out Procedures to Building Projects
LG Code: EIS SCW4 11 0322
2015 E.C
Identify site information and dimensions from site plan and check against plan drawings.
Measure survey pegs to ensure correct identification occur before pilot pegs are positioned.
Set up profiles pegs on site at a working distance from pilot pegs and parallel to pilot line.
Make marks to indicate outside of building or other structural members following safety
procedures.
Conduct cut and fill calculations without error
Learning Activities
1. Read the specific objectives of this Learning Guide”1”
2. Read the information written in the “Information Sheet 1, 2,3&4”
3 Accomplish the “Self-check 1” in pages 13”
4. Submit your accomplished Self-check. This will form part of your training portfolio
6.operation sheet in page “29”
7. Lap test in page “30”
8. If you earned a satisfactory evaluation proceed to “Learning Guide 2”. However, if your rating is unsatisfactory,
see your teacher for further instructions or go back to Learning Activity #1.
6. Request you teacher to observe your demonstration of the exercises and give you feedback
*Your teacher will evaluate your output either satisfactory or unsatisfactory. If
Unsatisfactory, your teacher shall advice you on additional work. But if satisfactory you can proceed to the next
topic. Learning Guide
The details of Setting-out Profile Set-up for Building Works are essential to proper construction
of a building. Layout prepares the site for the foundation which must be planned and completed for each
building being constructed. This chapter introduces the carpenter to the tools, materials, and techniques used
in the effective accomplishment of these vital Setting-out Profile Set-ups for Building Works.
LAYOUT
Layout techniques are described in the following paragraphs. The following are the most commonly used
layout tools and materials:
A string line is used to distinguish the dimensions of the building layout.
A sledgehammer is used to sink corner stakes or batter boards and posts.
A posthole auger is used to dig the holes required to set posts properly in some soils.
A handsaw is used to cut batter boards and posts.
An ax or a hatchet is used to sharpen batter-board posts and stakes.
A hammer is used for building batter boards.
A chalk line is used to deposit chalk on the surface in order to make a straight guideline.
A 100-foot/30-meter tape is used for measuring diagonally (usually in a 100 foot length) and for laying out
excavation or foundation lines.
Tracing tape is used for laying out excavation or foundation lines. The tape is made of cotton cloth
approximately 1 inch wide. It usually comes in a 200 foot length.
A carpenter's level is used to level a surface and to sight level lines. It may be used directly on the surface
or with a straightedge.
A line level has a spirit bubble to show levelness. The level is hung from a taut line. It gives the greatest
accuracy when it is placed halfway between the points to be leveled.
An automatic level measures approximate differences in elevation and can establish grades over limited
distances. The landscape, level bubble, and index line are seen in the tube.
8d nails are used to secure string line to batter boards.
A plumbing bob is used to locate the corners of the building dimensions.
A framing square is used to check the squareness of lines.
Stretch a line tightly from point O to O. This line will mark the project's frontage. Measure in from
lines AC and BD along line OO one-half the difference between the length of line OO and the desired length
of the project. The points (X and X) will constitute the front corners of the project. The two distances OX and
XO establish the distances E and F. Extend lines from the two front corners X and X, parallel to AC and BD
at the distances established as E and F for the required depth of the project. This provides the side lines of
the project (XG and XH).Joining the extreme ends of side XH will provide the rear line (GH) of the project.
After the four corners (X, X, G. and H) have been located, drive stakes at each corner. Batter boards may be
erected at these points either after the stakes have been set or while they are being set. Dimensions are
determined accurately during each step.
Where the outline of the building is other than a rectangle, the procedure in establishing each point
is the same as described for laying out a simple rectangle. However, more points have to be located, and the
final provingof the work is more likely toreveal a small error. Whenthe building is an irregularshape, it is
advisable to firstlay out a large rectanglewhich will comprise theentire building or the greaterpart of it. This
is shown inFigure 4-2 as HOPQWhenthis is established, the remaining portion of the layout will consist of
small rectangles, each of which can be laid out and proved separately. These rectangles are shown as
LMNPABCQ,DEFG, and IJKO in Figure4-2.
EXTENDING LINES
The following procedure applies to a simple layout as shown in Figure 4-4,
and must be amended to apply to different or more complex layout problems:
Step 1.After locating and sinking stakes A and B. erect batter boards1, 2, 3,
and 4. Extend a chalk line (X) from batter board 1 to batter board 3, over
stakes A and B.
Step2. After locating and sinking stake C, erect batter boards 5 and6. Extend
chalk line Y from batter board 2 over stakes A and C tobatter board 6.
Step 3. After locating and sinking stake D, erect batter boards 7 and8. Extend chalk line Z from batter board
5 to batter board 7, overstakes C and D.
Step 4. Extend line O from batter board 8 to batter board 4, over stakes D and B.Where foundation walls are
wide at the bottom and extend beyond the outside dimensions of the building, theexcavation must be larger
than the laid-out size. To lay out dimensions of this excavation, measure out as faras required from the
building line on each batter board and stretch lines between these points, outside the firstlayout.
1. Set out the front or building line in the usual manner with pegs or marks at the required distance.
2. Place the builder’s square so that front line touch one side if the square right through its length.
3. Stretch a line from the peg so that it is parallel to second side of the square and establish the third peg. A
corner of angle 90 degree is thus obtained.
4. With the aid of a tape measure mark out the length and breadth of the proposed building.
5. Transferring the builder’s square to the remaining corners and repeating the above operations; a simple
rectangular building can be set out.
6. After establishing the four corner pegs, profiles (separate or continuous) may be erected in the same way.
-to establish any boundary or survey line in this may be used `the material survey peg is:-
Pegs:-are made up of wood &used to make the position of stations or terminal point of the survey line.
They are made to penetrate in to the grained with the help of hammer around 10are used for mea cm at
the position of point.
-Tapes:-used for measuring accurate length on the grained.
-Tape may be classified in to:-
1. Steel tape 2, metallic tape 3, invar tape
The exact position of the boundary of building or two countries boundary is horizontally controlled by
the building line which is defined by the municipality of any town or city.
-the building line is set from edge or center line of the road.
1. Check the circular bubble over the top of the instrument. This will probably be found to be “off-
center”. To correct this release the tripod leg screws and adjust the instrument until the bubble
comes in to the center of the circle. When this is achieved, tighten the tripod leg secure. The
instrument is now ready to use.
2. When this position is obtained, measure the distance required to peg 3. Now by sighting through
the top telescope, taking care note to rotate the instrument to the right or left, signal and assistant
to move the peg side ways until it is “dead on” peg 3 is now positioned at an angle of 900.
3. By removing the site square to peg 3 and living up on peg 2, the removing corner peg, peg 4 can
be set out using the procedures already given.
4. Profiles can be marked easily by lifting the telescope upwards, having sighted on to the peg, and
having a nail in the ‘ dead on” position on the profile board.
STEP ACTION
1 Find out the radius of the building from the working drawings.
3 Place a stake securely on the ground at the end of the radius in the centre of
the building.
8 Loop a piece of rope, which is the length of the radius of the building over the
reinforcing bar. Measure the distance to the inner and outer sides of the
After measuring the radius and position the stake, place a 12 x 150mm board over the reinforcing bar.
This method can be used instead of setting out with rope. The board is called a trammel.
Note: - You should measure the width of the foundation and masonry walls and mark the top for further
use.
Objectives: - At the end of this course element the trainee will be able to carry out excavation work.
*Trial holes: A contractor will dig trial holes as part of excavation. For example, if water appears in the
trial holes, then the contractor may use pumps to keep them dry while the building workers are digging.
If the soil is very loose, then the contractor will want to put in timber supports to strengthen the sides of
the excavation.
The topsoil should be removed at least 200-300 mm depth. It is to remove the roots of bushes and trees
that are growing with in the boundary of the building; it must have to be excavated more than 300 mm.
Note: Do not use the soil to backfill holes that are created by excavating roots in the topsoil. The soil
may settle to a different level in the over site concrete. You should pack hard core tightly in the holes or
use a weak concrete mixture or filler
Excavated soil should be removed from the trench. You can use some of the excavated soil to fill in
around the foundation brickwork, but the rest should be removed from the site. After the excavation is
completed, the building inspect may want to check that the sub soil in the bottom of the trench will
support the building load.
3.4 Deep excavation
3.4.1 Excavating pit for column or piers
Excavation for the base of a column or pier is called a pit. Pit is usually square. Mark a
position and dig around the central point of the column or pier. You can dig pits by hand or use a
back actor. Any water should remove and the sides of doubt about their suitability
. 3.4.2 Digging holes for piles
A short-board pile is usually used for small buildings. They are circular concrete columns
formed in holes in the ground. An auger, which is a spiral-shaped hand tool, is used to drill a hole in
the ground. As it rotates it drills dawn in to the soil. When you pull out the auger, if brings out the
soil with it create a circular hole. You repeat the process until to support a building load.
Augers can be turned by hand or by machine. Manual augers are usually suitable for small
job s. Bigger and deeper piles require mechanical augers, which to put in piles, then the ground be
soft enough to drill in to with an auger.
Fig 9-1
Most building sites are mot perfectly level. The design for a sloping may have different floor
levels or a basement to cope with the changes in levels. You use the cut and fill method of
excavation. If you want to keep a level ground floor in spite of a slope. In this method the soil from
the upper part of the slope is cut out and deposited on the lower part of the slope. This crate a level
base for the construction of the floor. The base must be well packed so that the building is stable.
Digging a basement on sloping site you may want to make a basement. In a house on sloping
wall to support the side of the remaining slope, near the building.
As a rule, the looser the soil, the more it needs to b supported. Excavation on confined site may also
need support in case heavy loads are placed or driven too close to the edge of trench or pits. The live of
the workers digging in the excavation are at risk unless the contractor takes proper precautions. The
timber struts, which are wedged, between planks support, the side of excavation. These supports consist
of: -
1. Poling:-which are vertical planks supporting the soil. In sand or gravel, they should be placed
closed enough together to form a continuous timber wall. Depending on the soil type and working
condition they be placed about 900mm apart. The purpose of poling is to keep the soil on the side
of excavation from falling in.
2. Waling; - Which are horizontal timber strips supporting the poling.
3. Strut; - Are timber that span across the trench between the waling. The struts hold the opposite
wall of the excavation in place.
4. Wedges; - Which are pieces of timber used to maintain the pressure of poling against the soil. If
the soil expands or shrinks, while the work is carried out, then you may need to adjust the wedge
again
A trial hole may show that the water is normally present in the ground on site. The level of water in
the hole is called water table. It varies according to the season and the amount of rainfall. Water also
inters the excavation when it rains. If the rainwater does not drain away naturally, then you should pump
it out so those, the work can continue in the excavation.
- If you use a pump, then the end of the hose line should be below the bottom of excavations in a
small depression called sump.
- -The hose should have filter to prevent dirt from coming up in to the pump.
- -If you remove the water by hand, then you must dig a swamp that is large enough for bucket.
When the water removed, it should be drained away so that it does not run backing to the
excavation.
Site clearing and excavation
Objectives: - At the end of this course element the trainee will be able to carry out excavation work.
1. Site clearing
The preliminary site works for a construction project usually begins after the site facilities are set up.
All vegetation’s such as bushes and scrub; should be removed; the roots of trees and bushes must
be dug out and cleared away. If the new building is to be built on an area of already existing, the old
building has to be demolished, the debris cleared away and existing services disconnected and removed.
Virgin site have to be cleared of grasses, trees, rocks and old vehicles.
Site clearing used to be carried out using manual labors with pickaxes and spades. Due to the
mechanization of building operations, there are mechanical plants, which can carry out site clearance
operation with comparative ease and safely. These plants are only medium and large sized firms can
afford to own them. Site clearance is therefore largely done using manual labors (especially for housing
projects).
The building sits area and surrounding areas should be inspected for termites as part of the
process of clearing the site.
The ground a termite nest is usually treated with toxic chemicals and powders should be
mixed in the open air.
*Trial holes: A contractor will dig trial holes as part of excavation. For example, if water appears in the
trial holes, then the contractor may use pumps to keep them dry while the building workers are digging.
If the soil is very loose, then the contractor will want to put in timber supports to strengthen the sides of
the excavation.
minimal profiles
CONDITIONS OF SITUATION
TOOLS AND MTERIALS
Materials
Tape
Page
huselevel
Tri square
String line
Sledge hammer
Hand level
Chelk line
Plum bobEtc
PROCEDURE:
1. Calculate the depth from the top of the profile to the desired level of the excavation. The working
drawings and measurements on site.
2. Make a measuring staff called boning rod, which is the same length as the distance between the top of
the profiles and the bottom of the trench.
3. Place the boning rod in the trench.
4. Dig down until the top of the “T” on the boning rod lines up with the top of the profiles.
Name:_____________________________Date: _________________
Time Started: ______________________Time Finished: ________________
ADDIS COLLEGE
Learning Guide
Unit of Competence:-Apply Site Surveys and Set-Out Procedures to Building Projects
Module Title:-Applying Site Surveys and Set-Out Procedures to Building Projects
LG Code: EIS SCW4 11 0322
Unsatisfactory, your teacher shall advice you on additional work. But if satisfactory you can proceed to the
next topic. Learning Guide
Information Sheet- 1 Prepare and test leveling devices
Testing levels
1. The axis of the circular bubble should be parallel to the instrument’s vertical axis
Test: By rotating the leveling screws bring the bubble into the central position. Rotate the instrument
halfway around. If the bubble remains centred the condition is fulfilled. If it has been displaced, correct
one-half of the error with the use of adjusting screws (screw drivers) of the bubble and half of the error
by means of the leveling screws. Repeat the same method of procedure until the bubble remains centred.
3. The telescope’s line of sight should be true level for instruments with compensators
This test involves leveling by two-rod technique (peg test). Two wooden pegs are driven in to the
ground at a distance d of approximately 50m-70m apart. With the level set up at the mid-point between
the pegs, a back sight reading (BS) “a” is taken at the rod at peg A, and a fore sight reading (FS) “b” is
taken at peg B (see fig.3). Assuming that the error due to the inclined line of sight is x1 the correct height
difference h between the two pegs is computed as follows:
h = (a + x1) – (b + x1) = a – b
Figure 10
Next the level is moved near to peg A and the back sight (BS) reading “c” is taken at the rod at peg
A(fig 4). Then a fore sight (FS) reading “d” is taken at the rod held at B. Let x2 represent the error in
fore sight (FS) reading due to inclination of the line of sight. Then x2 can be computed from the
following:
Figure 11
h=c-(d+x2) = (a-b)
X2= (c-d)-(a-b)
The line of sight is inclined downward if x2is positive and upward if x2 is negative. The error introduced
by this source can be completely eliminated by balancing the back sight (BS) and fore sight (FS)
distances.
1. __________________________________________________________________
_________________________________________________________________
__________________________________________________________________
__________________________________________________________________
____________________________________________________________________
___________________________________________________________________
__________________________________________________________________
2. __________________________________________________________________
__________________________________________________________________
__________________________________________________________________
___________________________________________________________________
________
ADDIS COLLEGE
Carry out temporary adjustments to 'set up' leveling equipment in accordance with
standard operatingprocedures.
Determine horizontal and vertical angles using leveling devices.
of this Learning Guide, you will be able to
Set out site to specifications using leveling device.Conductcut and fill calculations
without error
Learning Activities
1. Read the specific objectives of this Learning Guide”3”
2. Read the information written in the “Information Sheet 1,
3 Accomplish the “Self-check 1” in pages 46”
4. Submit your accomplished Self-check. This will form part of your training portfolio
5.operation sheet in page “47”
6. Lap test in page “49”
7. If you earned a satisfactory evaluation proceed to “Learning Guide 2”. However, if your rating is unsatisfactory,
see your teacher for further instructions or go back to Learning Activity #1.
8.Request you teacher to observe your demonstration of the exercises and give you
feedback
Leveling is the process of measuring vertical distances above or below a given reference surface and a
point on near or below the earth’s surface. It can also be defined as the processes of determining
elevation differences between various points on, near or below the surface of the earth. The elevation of
a point is its vertical distance above or below a reference level, called datum. The most commonly used
datum is the mean sea level (M.S.L)
Leveling is an important method of surveying for many engineering works and construction projects.
Leveling is needed for the design of highways, railways, and canals etc and for locating the gradient
lines.
The results of leveling can be used to determine the catchments area, volume of the reservoir.
Basic Definitions
The following are a few introductory definitions that are necessary for the understanding of this chapter
I. A vertical line- is the line parallel to the direction of gravity. At a particular point it is the
direction assumed by a plumb-bob sting if the plumb-bob is allowed to swing freely.
Because of the earth’s curvature, plumb-bob lines at points some distance apart are not
parallel, but in plane surveying they are assumed to be.
II. A level surface- is a surface of constant elevation that is perpendicular to a plumb line at
every point. It is best represented by the shape that a large body of still water would take
if it were unaffected by tide.
Figure 1
III. The elevation of a particular point- is the vertical distance above or below a reference
level surface (normally, sea level)
IV. A level line- is a curved line in a level surface all points of which are of equal
elevation.Every element of the line is perpendicular to gravity.
V. A horizontal line- is a straight line tangent to a level line at one point.
When the leveling instrument has been properly levelled, the bubble tube axis and the line of sight are
horizontal and the vertical axis of the instrument is truly vertical. When the telescope of the instrument
is rotated, the line of sight remains in the horizontal plane.
In practice, the leveling instrument is set up at a convenient position, and the one staff is kept at a point
of known elevation. The reading is taken on the staff and the level of the line of sight is determined.
Now the 2nd staffs are kept on the point of the unknown elevation and a reading is taken. The level of
the point is determined from the level of the line of sight already computed and from the 2 nd staff
reading.
Figure 2
4.3 Terms used in direct leveling
1. Station. The station is the point where the staff is held for taking reading (observation) from a
leveling instrument.
The point where the instrument is set up is not important so far the booking of the readings in a
level field book is concerned.
2. Height of the instrument. (H.I): It is the elevation of the line of sight with respect to the datum.
It should be noted that the height of instrument is not the height of the line of sight above the
ground where the leveling instrument is set up.
3. Back sight (B.S.): It is the reading taken on a staff held at point of known elevation or at the
point whose elevation has already been determined. The back sight is usually the first reading
taken after setting up the instrument. The back sight is taken on a bench Mark (B.M) for the
first setting of the instrument and on a turning point (T.P.) for the subsequent settings because
the level of turning point can be determined before the shifting of the instrument.
4. Fore sight (F.S.): It is the reading taken on the staff either held at the last point whose elevation
is required or held at the turning point just before shifting the instrument.
5. Turning point. (T.P.): For leveling over a long distance, the instrument has to be set up a
number of times. A turning point is the point selected on the route before shifting the
instrument. The turning point should be selected on a firm ground or rock.
Figure 3
6. Intermediate sight. (I.S.): It is the reading taken on a staff held at point whose elevations is
required, but which is not a turning point or the last point.
7. Balancing of sight: To reduce the effect of instrumental and other errors, the distance of the
point where a back sight is taken and the distance of the point where a fore sight is taken, as
measured from the instrument station, should be approximately equal. This is known as
balancing of sights.
Leveling Instruments
Levels
Levels are categorized in to three groups.
1) Dumpy levels 2) Tilting levels 3) and Automatic levels
1. Dumpy levels
In dumpy level, the line of sight is perpendicular the vertical axis. Once the instrument is levelled the
line of sight becomes horizontal and the vertical axis becomes truly vertical provided the instrument in
adjacent.
2. Tilting levels
It has the telescope that can be tilted about a horizontal axis. This design enables the operator to quickly
and accurately centre the bubble and brings the line of sight in to a horizontal plane. In tilting levels the
line of sight is or should be parallel to the axis of the telescope. It is only horizontal when the bubble of
the spirit level is central.
3. Automatic levels
One of the most significant improvements in leveling instrumentation has been automatic level or self-
leveling levels. It has an internal compensatory that automatically makes horizontal the line of sight and
maintains the position through the application of the force of gravity. As soon as the instrument is
leveled by a means of a circular bubble, the movable component of the compensatory swings free to a
position that makes the line of sight horizontal. The compensatory can operate within the range of 10
minutes of arc from the horizontal.
1. Tripods
A tripod is a three- legged stand used to support a level or other surveying instrument during field
measurements. There are two models of tripods.
(1) The extension leg tripod and
(2) The fixed leg tripod.
They are used to measure the vertical distance between a line of sight and a survey point and a height
1. Setting up: Set up the tripod at a convenient height and press the tripod feet firmly into the
ground. The tripod head should be approximately horizontal. Fix the instrument on it.
2. Leveling up: Level the instrument with the foot screws until the circular bubble is in the centre.
Fig. 1 shows the procedure how to level an automatic level:
The movement of the circular bubble can be divided into two directions. One direction is parallel
to line joining any two of the foot screws. The second direction is then parallel to a perpendicular
line from the third foot screw to the line joining the two other foot screws.
Turn the instrument until the telescope axis is parallel to any two foot screws.
The screws are held by the thumb and forefinger of each hand and turned equally and
simultaneously in the opposite direction until the bubble has moved to the line AB (fig. 1a).
LineAB is perpendicular to the line through the two foot screws.
By using the third screw the bubble is moved towards the centre of the circle (fig. 1b). The
leveling procedure is completed when the bubble is in the centre of the circle (fig. 1c).
Left thumb rule: the bubble is always moving towards the direction of movement of the left
thumb!
3. Focusing: First focus the eyepiece until the cross hairs appear sharp and clear then point the
telescope towards the object (staff) and focus until you see clearly the graduation of the staff.
Leveling Methods
Differential leveling
Differential leveling is required for the determination of the difference of elevation of two points, which
are quite apart. A number of setting ups of the instrument are required in differential leveling.
In fig. 1 BM1 represents a point of known elevation (benchmark) and BM2 represents a benchmark to be
established some distance away. It is desired to determine the elevation of BM2. The level is placed in
such a location that a clear rod reading is obtainable, but no attempt is made to keep on the direct line
joining BM1 and BM2. A back sight is taken on BM1. The rod-man chooses a turning point TP1 at some
convenient spot with in the range of the telescope along the general route BM1 to BM2. It is desirable,
but not necessary, that each foresight distance as I1–TP1 is approximately equal to its corresponding back
sight distance as BM1-I1. The chief requirement is that the turning point shall be a stable object at an
elevation and in a location favourable to a rod reading of the required precision. The rod is held on a
turning point and a fore sight is taken. The observer then set up the instrument at some favourable point
as I2 and takes a back sight to the rod held on the turning point TP1. Then the rod-man establishes the
second turning point TP2 and the observer takes a fore sight. The process is repeated until finally a
foresight is taken on the terminal point BM2.
To check weather there is an error or not the leveling work should always be started from a known point
and should be finished at a known point.
The leveling field book should be checked immediately in the field.
Note: While taking the readings the staff rod has to be held vertically!
The process of determining the elevation of points at short measured intervals along a fixed line is called profile leveling. The
need of profile leveling arises during the location and construction of highways, railroads, canal, and sewers.
Note: While taking the readings the staff rod has to be held vertically!
A level field book or a level book is used for booking and reducing the levels of various points on the surface of the earth.
There are a lot of methods for reducing the levels: etc. The surveyor should select the level book according to the method of
reduction he proposes to use.
The following table shows a page of the more generalized level book.
Leveling
Inter mediate
Point Back sight sight Fore sight Ah Elevation Remarks
1 2 3 4 5 6 7
BM1 1.244 1680.20
TP1 0.662
2.101
TP2 1.021
1.000
BM.2 3.221
B.S= F.S=
Steps to be followed:
1. __________________________________________________________________
_________________________________________________________________
2.__________________________________________________________________
.__________________________________________________________________
3.____________________________________________________________________
___________________________________________________________________
.4.__________________________________________________________________
___________________________________________________________________
Steps to be followed:
The attached level field book contains seven columns. The first column indicates the point (station) at
which the staff is placed. The second column is for the back sight readings (BS) and the fourth column
is for the fore sight readings. For the illustration of differential leveling given in section 4.6 fig. 1 the
back sight-reading for the station BM 1 is 1.244. The elevation of BM 1 is 1680.20m. All the entries
are shown in the field book.
Inter mediate
Point Back sight sight Fore sight Ah Elevation Remarks
1 2 3 4 5 6 7
BM1 0.244
TP1 2.662
1.101
TP2 0.021 198.662
3.010
BM.2 1.821
B.S= F.S=
ADDIS COLLEGE
LO
Instruction Sheet Learning Guide #24 4
Mark and determine levels on a grid for contouring and volume calculations
1: 5000
1: 2000
Site Plan 1: 1000
(Topo Plan) 1: 500
1: 200
Site Plan or Topo Plan are made at large scale thereby it provide a very detailed information of
surveyed area, they are use for engineering proposes. Most of them are made by civil
engineers, surveyors, or architect for a specific land development project of relatively small
sites.
600 595
590
585
580
585
590
This is a pattern of large 590
scale map or topo plan in
which we can observe most
of terrain details
Three methods are applied to gather the necessary data for the subsequent preparation of a
topographic map or plans.
Transit stadia method: Also known as ground method. The collection of the data is done by
means of traditional surveying instruments such as levelling instruments, theodolites, total
station, GPS or ( (stadia tachometers), as well as with tapes etc. This method is economic
and suitable for relative small areas.
Photogrammetric method: Aerial photographs are used to gather the necessary ground data.
It is an economic method for larger areas and projects and it overcomes the sometimes-
difficult access problems (which is common in ground method) to the area to be mapped.
The accuracy of photogrammetric method mainly depends upon the scale of the aerial
photographs.
In photogrammetric method the terrestrial (ground) work is only limited to establishing
horizontal and vertical ground control points. (e.g. through traversing and levelling) that must
be clearly defined and well – distributed over the target area and a final terrestrial field check
should be made . The aerial photographs are interpreted and dimensions between required
points is measured stereoscopically (three-dimensionally) by means of a special instrument
called stereo-plotter. With the help of such stereo-plotters the contour lines and the planimetric
positions of all topographic features can be determined.
Plane table method: The measurements are made in the same way as those in the transit-
stadia method but the data are plotted in the field on term paper that is attached to a
drawing board mounted on a tripod. This device is called a plane table. This method is
going to be focus at this course since Transit stadia method will be cover in Topographic
Surveying II , nevertheless most of steps we have to follow for accomplishing topographic
surveying in both method are the same.
1.1 General tasks to carry out when ground methods are applying:
The general tasks involved in a topographic Surveying by mean of ground method are:
1) Information gathering of area to survey: It consist in collecting all the available
information about the area that are going to be surveyed such as:
o Existing maps or plane
o Existing geodesic control point (both planimetric and BM)
o Grade of complex of the area and ground features
o Property of parcels
o Field site facilities
The Ethiopian Mapping Authority (EMA)in Addis Ababa and the local surveying authorities
(such as the municipalities, town planning and water Resource development bureaux etc.. )
can be a helpful source of information.
2)Reconnaissance survey:This should be done by the survey team and the project sponsor
as a civil engineer. It has a main objective:
Establishing control points network (surveying base) At this stage a reconnaissance survey of
the area to be mapped is absolutely indispensable and should therefore be carried out
thoroughly.
The term reconnaissance means the first inspection of the target area in terms of existing
control points, possible sites for new observation stations as the permanent marking of those
stations, detection of possible obstacles and possible solutions to overcome them etc. With
other words, after the first inspection, one has got some ideas regarding the mental map
about the terrain and the features of the ground.
It is also necessary to estimate the duration of the whole field work.
All altimetric measurement (leveling) are carried out through the control points network by
applying a leveling method (usually differential leveling)
Thereby the vertical position (Z) of every control point is determined according to the adopted
plane of reference (the mean sea level).
10 cm
10 cm
10 cm
50 cm
60 cm
50 cm
60 cm
6) Detail surveying of the area: This is one of the most important stage since all feature of
terrain are surveyed by mean of polar coordinate, rectangular coordinates, intersection or by
plane table method. Different general methods could be apply such as:
o Tachometer method
o Taping method
o Plane table method
o Total Station Method
This detailed surveying is carried out by setting up the theodolite or Total station or tachometer
or plane table on every control point, the coordinates
(x; y;z) are taken at every detail according to the surveying scale.
7) Drawing the land features according to given scale: After collecting all data, which permit
the drawing of plan metric features, drawing sessions start by mean of conventional symbols
which represent each pattern according drawing scale an standard manual for symbols should
be used as well.
8) Plotting down the contour lines: The relief must to be represented by mean of contour lines
method according to a specific interval
9) Preparing plan for edition: All general information and texts have to be written and quality
controls are applied to check the technical requirements.
Finally a technical inform should be redacted by the surveyor in charge.
ADDIS COLLEGE
Learning Guide
Unit of Competence:-Apply Site Surveys and Set-Out Procedures to Building Projects
Module Title:-Applying Site Surveys and Set-Out Procedures to Building Projects
LG Code: EIS SCW4 11 0322
LO5:- compute coordinates, bearings and distances related to grids and general set
out work
The information necessary to set out a structure, using a site plan, is determined Demonstrate the angular
relationship between different bearings (whole circle).
Calculate the bearing and distance between coordinates.
Calculate the coordinates of a point given the bearing and distance from a point with known coordinates.
Determine offsets from a coordinated point given the bearing and distance from a point with known
coordinates.
Determine the information necessary to set out a structure, using a site plan.
Learning Guide,
1. Read the specific objectives of this Learning Guide”4”
2. Read the information written in the “Information Sheet 1,
3 Accomplish or interprets plan , map
4. Submit your accomplished Self-check. This will form part of your training portfolio
5. exercise plan reading and couture piloting “52 -55”
6. draw couture in page “52”
7. If you earned a satisfactory evaluation proceed to “Learning Guide 2”. However, if your rating is unsatisfactory,
see your teacher for further instructions or go back to Learning Activity #1.
8 .Request you teacher to observe your demonstration of the exercises and give you feedbac
*Your teacher will evaluate your output either satisfactory or unsatisfactory. If
Unsatisfactory, your teacher shall advice you on additional work. But if satisfactory you can proceed to the next
topic. Learning Guide
► Angles: Introduction
When angle is measured in horizontal plane it is horizontal angle when measured in a vertical plane it is
vertical angle.
Basic Components of an Angle
1.reference or starting line (A)
2.direction of turn (B)
3.angular value (C) usually in DMS
A
B
► Angles: Types
1. Interior
2. Exterior
3. Angle to right
4. Angle to Left
5. Right Deflection
6. Left Deflection
► Angles: Types
OUTSIDE
∡
INTERIOR AN- DEFLECTION AN-
GLES GLES
Bearing
N---W N---E
S---W S---E
QUADRANTS
N
N
N
WW E E
S
S
W S E
Bearing
BEARING
BEAR-
FACTS
Always mea-
BEAR- N 5ING =
ING =2
3°
N 53°
sured from
North or W
N 21°
1°6 E
BEAR-
E
South, never BEAR-
W 3 ING =
from East or ING = S S 38° E
7°
West. 8°
S 67°
Always < 90°.
W
Always pre-
ceded by N or
S and fol-
lowed by E or
W.
Lines lying on
an axis are
listed as
DUE NORTH,
DUE SOUTH,
DUE EAST, or
DUE WEST.
Azimuth:
FIRST
QUAD
2ND
QUAD
4TH
QUAD
3R
D
QU
AD
Azimuth Direction:
Clockwise only
Require only a numerical value
Range from 0-360 degrees
Back Bearing:
It can be said that every line
has two
directions: forward and back
Reversing a bearing direction
is reversing
direction letters
BEARING/AZIMUTH
AZIMUTH∡BEARING∡
CONVERSIONS QUADRANT
QUADRANT N 1
4
BRG = AZ
AZ W
BRG = 360°-
QUADRANT
E
QUADRANT
AZ3= 360°- 2
BRG= AZ -
BRG S BRG = 180°
- AZ
180° AZ = 180° -
AZ = 180° + BRG
BRG
Type of North
True North
Magnetic North
Grid North
Magnetic Declination
Direction
3. Grid North
4. Arbitrary
Different North
types of setting out
3-4-5 METHOD
USING THE LARGE SQUARE /Tri square method
- An arbitrary chosen line with a
Reference object
Survey Method
Types of survey method
directional value
Angle and assigned by the
distance method
Coordinate method
observer.
Prepared By: - Amare Tsegu
Level IV ADDIS COLLEGE
1)__________________________________________________________________
2)_________________________________________________________________
3)__________________________________________________________________
4)__________________________________________________________________
a.
b.
c.
d.
5)_________________________________________________________________
a.
b.
c.
d.
Reference:-