Professional Documents
Culture Documents
13.1.06-CONCRETE BATCHING & MIXING-1
13.1.06-CONCRETE BATCHING & MIXING-1
1. Methods of Batching
Batching is the process of measuring and combining required ingredients of concrete by either by weight
or by volume as per the mix design and introducing them into a mixture to produce a uniform quality of
concrete.
In semi-automatic weigh batching, aggregates containers gates are lifted manually and it is
automatically closed after reaching the required quantity in weighing machine.
In full automatic weigh batcher, all the process will be done automatically. The benefit of this
type of equipment is, it is also measures the moisture content resent in the aggregates and
corrects the required quantity of water-cement with respect to the moisture content of the
aggregates.
To prepare 1:1:2 concrete mix using weigh batching, measures quantity of materials is 50kg of
cement, 50kg of fine aggregates and 100kgs of course aggregates
Hand mixing
Machine mixing
The mixing platform used should be level, water tight and clean before use. It can be;
i. Place the measured quantities of course and fine aggregates on a raised ground on site.
ii. Measure the correct portions of cement
iii. Put it on top of a heap of aggregates and spread evenly with a mixing shovel.
iv. A measured amount of water is then added while mixing.
However, the following is the most commonly used hand mixing procedure on construction sites:
i. Place the measured quantity of sand (fine aggregates) on the clean platform and spread it out in
a layer of uniform thickness
ii. Place cement over the sand and spread out uniformly.
iii. Mix the fine aggregates with cement using a shovel
iv. Turn the mix from side to side as many times as possible to produce a uniform color throughout.
Workers doing the mixing face each other from opposite sides of the heap and work from the
outside to the center.
v. After the uniform color is got, spread the mixture on the plat form and pour course aggregates on
top
vi. Use the watering can or a hose to add water while mixing. Care should be taken to ensure that
neither water by itself nor with cement can escape.
vii. When all the water has been absorbed, the mixing is continued until the mix is of uniform
consistency. No soil or other extraneous material must be allowed to become included in the
concrete.
Time consuming
It is sometimes hard to get a uniform mix
It is cost y for big jobs (in terms of labour)
Water is first added and this moistens the drums and removes any concrete adhering to the sides. The
remaining materials are then measured into the drum in their correct proportions. The loaded drum is
allowed to mix for about 2 – 5 minutes and concrete is then ready for discharge.
The concrete is released from the drum depending on the type of the drum. It is released to the cart or
wheel barrows or dumper and driven to the site for placing.
It is very fast
Produces a better mixture
1. It is an advantage to feed cement, sand and coarse aggregates in the mixer simultaneously and in
such a way that the flow of each extends over the same period.
2. The water should enter the mixer at the same time and over the same period like the other
materials. With many mixers, this is not possible since the rate of flow is limited. In such case it is
advisable to start the flow of water earlier.
3. Mixing should continue until the concrete is of uniform consistency and color.