Professional Documents
Culture Documents
ecfn-3_test_A0_format_v02 1
ecfn-3_test_A0_format_v02 1
ecfn-3_test_A0_format_v02 1
G-M-GN-7800 3rd Filter Mechanical Completion 0 27-Mar-25 3rd Filter Mechanical Completion
G-M-GN-7700 Jameson Cells System Completion 0 31-Mar-25 Jameson Cells System Completion
G-M-GN-8000 Finish Construction 0 04-Apr-25 Finish Construction
Construction 27 14-Jun-24 A 01-Aug-24 01-Aug-24, Construction
G-M-CC-8010 Indirect - Plant Fabrication start 0 14-Jun-24 A Indirect - Plant Fabrication start
G-M-CC-6050 Courrierr System planned start (6310) 0 28-Jun-24 A Courrierr System planned start (6310)
G-M-CC-6100 TIP protecton planned start (6470) 0 06-Jul-24* TIP protecton planned start (6470)
G-M-CC-9000 3WLA planned activity - to be relocated 0 15-Jul-24* 3WLA planned activity - to be relocated
G-M-CC-6000 Start inside plant 0 23-Jul-24* Start inside plant
G-M-CC-6020 Tie-ins with out SHUT DOWN - planned by construction site 0 01-Aug-24* Tie-ins with out SHUT DOWN - planned by construction site
G-M-CC-6010 Tie-ins when 3810 pipe is complete 0 01-Aug-24 Tie-ins when 3810 pipe is complete
Detailed Engineering 42 01-May-24 A 09-Aug-24 09-Aug-24, Detailed Engineering
P-CI-P002A-7030 2 CI - P002A - Reinforcment Steel - ETA date - 6470 3rd Filter 0 05-Jun-24 A 2 CI - P002A - Reinforcment Steel - ETA date - 6470 3rd Filter
P-MC-C302-4000 MC - C302 - SMPEI - Award & PO Issued 0 14-May-24 A 04-Jun-24 A MC - C302 - SMPEI - Award & PO Issued
P-MC-C302-6000 MC - C302 - SMPEI - Transport 0 12-Jun-24 A 24-Jun-24 A MC - C302 - SMPEI - Transport
P-MC-C302-7000 MC - C302 - SMPEI - ETA at Site 0 24-Jun-24 A MC - C302 - SMPEI - ETA at Site
MC-P300 - Process Plant Water
Wa Pumps 163 01-Mar-24 A 20-Nov-24 20-Nov-24, MC-P300 - Process Plant Water Pumps
Mechanical 163 01-Mar-24 A 20-Nov-24 20-Nov-24, Mechanical
P-MC-P300-1000 MC - P300 - Process Plant Water Pumps - Engineering SOW/MTO; RFP 0 01-Mar-24 A 29-Apr-24 A MC - P300 - Process Plant Water Pumps - Engineering SOW/MTO; RFP
P-MC-P300-2000 MC - P300 - Process Plant Water Pumps - Bid Period: TEV 0 30-Apr-24 A 20-May-24 A MC - P300 - Process Plant Water Pumps - Bid Period: TEV
P-MC-P300-3000 MC - P300 - Process Plant Water Pumps - Bid Evaluation and 0 21-May-24 A 29-May-24 A MC - P300 - Process Plant Water Pumps - Bid Evaluation and Recommendation: TCM; GTC; CBE
Recommendation: TCM; GTC; CBE
P-MC-P300-4000 MC - P300 - Process Plant Water Pumps - Award & PO Issued 9 30-May-24 A 21-Jun-24 MC - P300 - Process Plant Water Pumps - Award & PO Issued
P-MC-P300-5000 MC - P300 - Process Plant Water Pumps - Fabrication Time (Mississauga 95 22-Jun-24 24-Sep-24 MC - P300 - Process Plant Water Pumps - Fabrication Time (Mississauga Canada)
Canada)
P-MC-P300-6000 MC - P300 - Process Plant Water Pumps - Transport 50 25-Sep-24 13-Nov-24 MC - P300 - Process Plant Water Pumps - Transport
P-MC-P300-7000 MC - P300 - Process Plant Water Pumps - ETA at Site 0 20-Nov-24 MC - P300 - Process Plant Water Pumps - ETA at Site
MC-P301 - Water Filters. Tekleen
Tek 156 03-Jan-24 A 13-Nov-24 13-Nov-24, MC-P301 - Water Filters. Tekleen
Mechanical 156 03-Jan-24 A 13-Nov-24 13-Nov-24, Mechanical
P-MC-P300-8010 MC - P301 - Water Filters - Engineering DSH; RFP 0 03-Jan-24 A 09-Feb-24 A neering DSH; RFP
P-MC-P300-8020 MC - P301 - Water Filters - Bid Period: TEV 0 10-Feb-24 A 26-Feb-24 A Water Filters - Bid Period: TEV
P-MC-P300-8030 MC - P301 - Water Filters - Bid Evaluation and Recommendation: TCM; GTC; 0 27-Feb-24 A 26-Mar-24 A MC - P301 - Water Filters - Bid Evaluation and Recommendation: TCM; GTC; CBE
CBE
P-MC-P300-8040 MC - P301 - Water Filters - PR & PO Issued 0 27-Mar-24 A 02-May-24 A MC - P301 - Water Filters - PR & PO Issued
P-MC-P300-8050 MC - P301 - Water Filters- Fabrication Time 121 12-Jun-24 A 09-Oct-24 MC - P301 - Water Filters- Fabrication Time
P-MC-P300-8060 MC - P301 - Water Filters - Transport 28 10-Oct-24 06-Nov-24 MC - P301 - Water Filters - Transport
P-MC-P300-8070 MC - P301 - Water Filters - ETA (3710-FLT-001/002) 0 13-Nov-24 MC - P301 - Water Filters - ETA (3710-FLT-001/002)
MC-P302 - Fusion Machine ((only procurement ask if has to ber removed) 120 15-Jan-24 A 02-Dec-24 02-Dec-24, MC-P302 - Fusion Machine (only procurement ask if has to ber removed)
Mechanical 120 15-Jan-24 A 02-Dec-24 02-Dec-24, Mechanical
P-MC-P302-1000 MC - P302 - Fusion Machine - Engineering SOW/MTO; RFP 0 15-Jan-24 A 29-Feb-24 A 2 - Fusion Machine - Engineering SOW/MTO; RFP
P-MC-P302-3000 MC - P302 - Fusion Machine - Bid Evaluation and Recommendation: TCM; 0 01-Mar-24 A 08-Mar-24 A MC - P302 - Fusion Machine - Bid Evaluation and Recommendation: TCM; GTC; CBE
GTC; CBE
P-MC-P302-2000 MC - P302 - Fusion Machine - Bid Period: TEV 0 01-Mar-24 A 08-Mar-24 A MC - P302 - Fusion Machine - Bid Period: TEV
P-MC-P302-4000 MC - P302 - Fusion Machine - Award & PO Issued 0 11-Mar-24 A 11-Jun-24 MC - P302 - Fusion Machine - Award & PO Issued
P-MC-P302-5000 MC - P302 - Fusion Machine - Fabrication Time 90 11-Jun-24 18-Oct-24 MC - P302 - Fusion Machine - Fabrication Time
P-MC-P302-6000 MC - P302 - Fusion Machine - Transport 30 21-Oct-24 02-Dec-24 MC - P302 - Fusion Machine - Transport
P-MC-P302-7000 MC - P302 - Fusion Machine - ETA at Site 0 02-Dec-24 MC - P302 - Fusion Machine - ETA at Site
MC-P303 - Apron Feeders (Parts
(P Only): Astec 197 03-Jan-24 A 05-Jan-25 05-Jan-25, MC-P303 - Apron Feeders (Parts Only): Astec
Mechanical 197 03-Jan-24 A 05-Jan-25 05-Jan-25, Mechanical
P-MC-P303-1000 MC - P303 - Apron Feeders - Engineering MTO; RFP 0 03-Jan-24 A 18-Jan-24 A
P-MC-P303-2000 MC - P303 - Apron Feeders - Bid Period: TEV 0 19-Jan-24 A 01-Apr-24 A MC - P303 - Apron Feeders - Bid Period: TEV
P-MC-P303-3000 MC - P303 - Apron Feeders - Bid Evaluation and Recommendation: TCM; GTC; 0 02-Apr-24 A 18-May-24 A MC - P303 - Apron Feeders - Bid Evaluation and Recommendation: TCM; GTC; CBE
CBE
P-MC-P303-4000 MC - P303 - Apron Feeders - PR & PO Issued 0 05-Apr-24 A 29-May-24 A MC - P303 - Apron Feeders - PR & PO Issued
P-MC-P303-5000 MC - P303 - Apron Feeders- Fabrication Time 192 29-May-24 A 19-Dec-24 MC - P303 - Apron Feeders- Fabrication Time
P-MC-P303-6000 MC - P303 - Apron Feeders - Transport (from Ecuador) 5 20-Dec-24 05-Jan-25 MC - P303 - Apron Feeders - Transport (from Ecuador)
P-MC-P303-7000 MC - P303 - Apron Feeders - ETA (6110-FEA-001) 0 05-Jan-25 MC - P303 - Apron Feeders - ETA (6110-FEA-001)
MC-P308 - Compressed Air System:
S Emcovele 44 03-Jan-24 A 24-Jul-24 24-Jul-24, MC-P308 - Compressed Air System: Emcovele
Mechanical 44 03-Jan-24 A 24-Jul-24 24-Jul-24, Mechanical
P-MC-P-C308-8010 MC - P308 - Compressed Air System - Engineering DSH; RFP 0 03-Jan-24 A 05-Feb-24 A m - Engineering DSH; RFP
P-MC-P-C3083-8020 MC - P308 - Compressed Air System - Bid Period: TEV 0 06-Feb-24 A 15-Feb-24 A d Air System - Bid Period: TEV
P-MC-P-C308-8030 MC - P308 - Compressed Air System - Bid Evaluation and Recommendation: 0 16-Feb-24 A 29-Feb-24 A 8 - Compressed Air System - Bid Evaluation and Recommendation: TCM; GTC; CBE
TCM; GTC; CBE
P-MC-P-C308-8040 MC - P308 - Compressed Air System - PR & PO Issued 0 01-Mar-24 A 06-Mar-24 A - P308 - Compressed Air System - PR & PO Issued
P-MC-P-C308-8050 MC - P308 - Compressed Air System - Fabrication Time 39 07-Mar-24 A 19-Jul-24 MC - P308 - Compressed Air System - Fabrication Time
P-MC-P-C308-8060 MC - P308 - Compressed Air System - Transport (from Belgium) - Transport 5 20-Jul-24 24-Jul-24 MC - P308 - Compressed Air System - Transport (from Belgium) - Transport incharge of Emcovele
incharge of Emcovele
P-MC-P-C308-8070 MC - P308 - Compressed Air System - ETA (6470-DDC-003/004 0 24-Jul-24 MC - P308 - Compressed Air System - ETA (6470-DDC-003/004 6470-AIR-003/004)
6470-AIR-003/004)
MC-P315 - Filter Press: Metso 128 29-Oct-23 A 16-Oct-24 16-Oct-24, MC-P315 - Filter Press: Metso
Mechanical 128 29-Oct-23 A 16-Oct-24 16-Oct-24, Mechanical
P-MC-P315-1000 MC - P315 - LOR 0 29-Oct-23 A
P-MC-P315-2500 MC - P315 - 3rd Filter Engineering 0 06-Dec-23 A 13-Mar-24 A MC - P315 - 3rd Filter Engineering
P-MC-P315-2000 MC - P315 - Award & PO Issued 0 06-Dec-23 A
P-MC-P315-3000 MC - P315 - Fabrication Time 58 07-Feb-24 A 07-Aug-24 MC - P315 - Fabrication Time
P-MC-P315-4000 MC - P315 - Transport (from Finland) 70 08-Aug-24 16-Oct-24 MC - P315 - Transport (from Finland)
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 1 of 7 28-Jun-24 ECFN-3 Master schedule weekly report - for information MF
Actual Level of Effort Critical Remaining Work
TASK filters: so_changes_not_red, so_show_into_report.
Actual Work Milestone
Fruta del Norte 3
Master Schedule Draft
Activity ID Activity Name Remaining Start Finish 2024 2025
Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
P-MC-P315-5000 MC - P315 - Filter Press - ETA (6470-PWS-003 6470-FLP-003 6470-HYU-003 0 16-Oct-24 MC - P315 - Filter Press - ETA (6470-PWS-003 6470-FLP-003 6470-HYU-003 6470-CLP-003)
6470-CLP-003)
MC-P316 - Ultra Fine Cells (Jameson
(J Cells): Glencore 49 29-Oct-23 A 29-Jul-24 29-Jul-24, MC-P316 - Ultra Fine Cells (Jameson Cells): Glencore
Mechanical 49 29-Oct-23 A 29-Jul-24 29-Jul-24, Mechanical
P-MC-P316-1000 MC - P316 - LOR 0 29-Oct-23 A
P-MC-P316-2000 MC - P316 - Award & PO 0 08-Jan-24 A
P-MC-P316-2500 MC - P316 - Jameson Cells Engineering 31 09-Jan-24 A 25-Jul-24 MC - P316 - Jameson Cells Engineering
P-MC-P316-3000 MC - P316 - Fabrication Time - 1 x B5400/18 Rougher Tail (Colombia) 0 12-Feb-24 A 04-Jun-24 A MC - P316 - Fabrication Time - 1 x B5400/18 Rougher Tail (Colombia)
P-MC-P316-4000 MC - P316 - Fabrication Time - 1 x B5400/18 Rougher Scalper (Colombia) 0 12-Feb-24 A 04-Jun-24 A MC - P316 - Fabrication Time - 1 x B5400/18 Rougher Scalper (Colombia)
P-MC-P316-5000 MC - P316 - Fabrication Time - 1 x B4500/12 Cleaner Scalper (Colombia) 5 16-Feb-24 A 15-Jun-24 MC - P316 - Fabrication Time - 1 x B4500/12 Cleaner Scalper (Colombia)
P-MC-P316-3500 MC - P316 - Fabrication Time - 1 x B5400/18 Rougher Tail (Melbourne) 19 16-Feb-24 A 29-Jun-24 MC - P316 - Fabrication Time - 1 x B5400/18 Rougher Tail (Melbourne)
P-MC-P316-4500 MC - P316 - Fabrication Time - 1 x B5400/18 Rougher Scalper (Melbourne) 19 16-Feb-24 A 29-Jun-24 MC - P316 - Fabrication Time - 1 x B5400/18 Rougher Scalper (Melbourne)
P-MC-P316-5500 MC - P316 - Fabrication Time - 1 x B4500/12 Cleaner Scalper (Melbourne) 19 16-Feb-24 A 29-Jun-24 MC - P316 - Fabrication Time - 1 x B4500/12 Cleaner Scalper (Melbourne)
P-MC-P316-7000 MC - P316 - Transport - Equipment from Colombia to site 30 16-Jun-24 15-Jul-24 MC - P316 - Transport - Equipment from Colombia to site
P-MC-P316-7500 MC - P316 - Transport - Equipment from Melbourne to site 30 30-Jun-24 29-Jul-24 MC - P316 - Transport - Equipment from Melbourne to site
P-MC-P316-8000 MC - P316 - ETA at Site - Equipment from Colombia 0 15-Jul-24 MC - P316 - ETA at Site - Equipment from Colombia
P-MC-P316-8500 MC - P316 - ETA at Site - Equipment from Melbourne 0 29-Jul-24 MC - P316 - ETA at Site - Equipment from Melbourne
MC-P317 - Linear Trash Screen:
Scre Roytec 87 09-Nov-23 A 05-Sep-24 05-Sep-24, MC-P317 - Linear Trash Screen: Roytec
Mechanical 87 09-Nov-23 A 05-Sep-24 05-Sep-24, Mechanical
P-MC-P317-1000 MC - P317 - Linear Trash - Engineering DSH; RFP 0 09-Nov-23 A 09-Feb-24 A neering DSH; RFP
P-MC-P317-2000 MC - P317 - Linear Trash - Bid Period: TEV 0 23-Jan-24 A 09-Feb-24 A Period: TEV
P-MC-P317-3000 MC - P317 - Linear Trash - Bid Evaluation and Recommendation: TCM; GTC; 0 10-Feb-24 A 22-Feb-24 A ar Trash - Bid Evaluation and Recommendation: TCM; GTC; CBE
CBE
P-MC-P317-4000 MC - P317 - Linear Trash - PR & PO Issued 0 23-Feb-24 A 15-Apr-24 A MC - P317 - Linear Trash - PR & PO Issued
P-MC-P317-5000 MC - P317 - Linear Trash - Fabrication Time (Linear Trash Screens and with out 66 09-Apr-24 A 15-Aug-24 MC - P317 - Linear Trash - Fabrication Time (Linear Trash Screens and with out motor)
motor)
P-MC-P317-6000 MC - P317 - Linear Trash - Transport (from South Africa) 21 16-Aug-24 05-Sep-24 MC - P317 - Linear Trash - Transport (from South Africa)
P-MC-P317-7000 MC - P317 - Linear Trash - ETA (6420-SCS-004) 0 05-Sep-24 MC - P317 - Linear Trash - ETA (6420-SCS-004)
MC-P317-1 - Linear Trash Screen
Sc (motor) - WEG 79 11-Jun-24 A 28-Aug-24 28-Aug-24, MC-P317-1 - Linear Trash Screen (motor) - WEG
Mechanical 79 11-Jun-24 A 28-Aug-24 28-Aug-24, Mechanical
P-MC-P317-8020 MC - P317-1 - Linear Trash Screen (motor) - Fabrication (Guayaquil) 74 11-Jun-24 23-Aug-24 MC - P317-1 - Linear Trash Screen (motor) - Fabrication (Guayaquil)
P-MC-P317-7010 MC - P317-1 - Linear Trash Screen (motor) - PO Award 0 28-Jun-24 A MC - P317-1 - Linear Trash Screen (motor) - PO Award
P-MC-P317-8010 MC - P317-1 - Linear Trash Screen (motor) - Transport (from Guayaquil) 5 24-Aug-24 28-Aug-24 MC - P317-1 - Linear Trash Screen (motor) - Transport (from Guayaquil)
P-MC-P317-8030 MC - P317-1 - Linear Trash Screen (motor) - ETA (6420-SCS-004) 0 28-Aug-24 MC - P317-1 - Linear Trash Screen (motor) - ETA (6420-SCS-004)
P-MC-P318-4000 MC - P318 - Award & PO Issued 0 16-Feb-24 A 04-Mar-24 A P318 - Award & PO Issued
P-MC-P318-5000 MC - P318 - Fabrication Time 71 06-Mar-24 A 20-Aug-24 MC - P318 - Fabrication Time
P-MC-P318-6000 MC - P318 - Transport (from South Africa) 21 21-Aug-24 10-Sep-24 MC - P318 - Transport (from South Africa)
P-MC-P318-7000 MC - P318 - ETA (6420-STC-001/007) 0 10-Sep-24 MC - P318 - ETA (6420-STC-001/007)
MC-P322 - Slurry Pumps: Aojin
Ao SSJ 120 07-Feb-24 A 08-Oct-24 08-Oct-24, MC-P322 - Slurry Pumps: Aojin SSJ
Mechanical 120 07-Feb-24 A 08-Oct-24 08-Oct-24, Mechanical
P-MC-P322-1000 MC - P322 - Slurry Pumps - Engineering SOW/DSH; RFP 0 07-Feb-24 A 16-Mar-24 A MC - P322 - Slurry Pumps - Engineering SOW/DSH; RFP
P-MC-P322-2000 MC - P322 - Slurry Pumps - Bid Period: TEV 0 22-Mar-24 A 28-Mar-24 A MC - P322 - Slurry Pumps - Bid Period: TEV
P-MC-P322-3000 MC - P322 - Slurry Pumps - Bid Evaluation and Recommendation: TCM; GTC; 0 29-Mar-24 A 08-Apr-24 A MC - P322 - Slurry Pumps - Bid Evaluation and Recommendation: TCM; GTC; CBE
CBE
P-MC-P322-4000 MC - P322 - Slurry Pumps - Award & PO Issued 0 08-Apr-24 A 29-Apr-24 A MC - P322 - Slurry Pumps - Award & PO Issued
P-MC-P322-5000 MC - P322 - Slurry Pumps - Fabrication Time 30 30-Apr-24 A 10-Jul-24 MC - P322 - Slurry Pumps - Fabrication Time
P-MC-P322-5010 MC - P322 - Slurry Pumps - 6390-PSL-009/010 - Fabrication 30 30-Apr-24 A 10-Jul-24 MC - P322 - Slurry Pumps - 6390-PSL-009/010 - Fabrication
P-MC-P322-5020 MC - P322 - Slurry Pumps - 6390-PSL-005/006 - Fabrication 30 30-Apr-24 A 10-Jul-24 MC - P322 - Slurry Pumps - 6390-PSL-005/006 - Fabrication
P-MC-P322-5030 MC - P322 - Slurry Pumps - 6390-PSL-001/002 - Fabrication 30 30-Apr-24 A 10-Jul-24 MC - P322 - Slurry Pumps - 6390-PSL-001/002 - Fabrication
P-MC-P322-5040 MC - P322 - Slurry Pumps - 6470-PSL-004/005 - Fabrication 30 30-Apr-24 A 10-Jul-24 MC - P322 - Slurry Pumps - 6470-PSL-004/005 - Fabrication
P-MC-P322-5050 MC - P322 - Slurry Pumps - 6310-PSL-008 - Fabrication 30 30-Apr-24 A 10-Jul-24 MC - P322 - Slurry Pumps - 6310-PSL-008 - Fabrication
P-MC-P322-5060 MC - P322 - Slurry Pumps - 6310-PSL-012 - Fabrication 30 29-May-24 A 10-Jul-24 MC - P322 - Slurry Pumps - 6310-PSL-012 - Fabrication
P-MC-P322-5070 MC - P322 - Slurry Pumps - 6310-PSL-006 - Fabrication 30 29-May-24 A 10-Jul-24 MC - P322 - Slurry Pumps - 6310-PSL-006 - Fabrication
P-MC-P322-6000 MC - P322 - Slurry Pumps - Transport (from China) 90 11-Jul-24 08-Oct-24 MC - P322 - Slurry Pumps - Transport (from China)
P-MC-P322-6020 MC - P322 - Slurry Pumps - 6390-009/0010/005/006/001/002, 6470-004/005, 90 11-Jul-24 08-Oct-24 MC - P322 - Slurry Pumps - 6390-009/0010/005/006/001/002, 6470-004/005, 6310-008 - Transport (from China)
6310-008 - Transport (from China)
P-MC-P322-7000 MC - P322 - Slurry Pumps - ETA at Site 0 08-Oct-24 MC - P322 - Slurry Pumps - ETA at Site
P-MC-P322-7020 MC - P322 - Slurry Pumps - 6390-009/0010/005/006/001/002, 6470-004/005, 0 08-Oct-24 MC - P322 - Slurry Pumps - 6390-009/0010/005/006/001/002, 6470-004/005, 6310-008 - ETA
6310-008 - ETA
P-MC-P323-2000 MC - P323 - Slurry Pumps Tailings - Bid Period: TEV 0 14-Feb-24 A 13-Mar-24 A MC - P323 - Slurry Pumps Tailings - Bid Period: TEV
P-MC-P323-3000 MC - P323 - Slurry Pumps Tailings - Bid Evaluation and Recommendation: 0 14-Mar-24 A 27-Mar-24 A MC - P323 - Slurry Pumps Tailings - Bid Evaluation and Recommendation: TCM; GTC; CBE
TCM; GTC; CBE
P-MC-P323-4000 MC - P323 - Slurry Pumps Tailings - Award & PO Issued 0 28-Mar-24 A 06-May-24 A MC - P323 - Slurry Pumps Tailings - Award & PO Issued
P-MC-P323-5000 MC-P323 - Slurry Pumps Tailings - Fabrication (Drive side casing liner, Suction 127 09-May-24 A 15-Oct-24 MC-P323 - Slurry Pumps Tailings - Fabrication (Drive side casing liner, Suction liner, Impeller gasket, Fixed-speed-V)
liner, Impeller gasket, Fixed-speed-V)
P-MC-P323-8010 MC - P323 - Slurry Pumps Tailings - Fabrication (Suction side casing liner, 0 09-May-24 A 24-Jun-24 A MC - P323 - Slurry Pumps Tailings - Fabrication (Suction side casing liner, Impeller-4 vane)
Impeller-4 vane)
P-MC-P323-6000 MC - P323 - Slurry Pumps Tailings - Transport (Tucson) 21 16-Oct-24 05-Nov-24 MC - P323 - Slurry Pumps Tailings - Transport (Tucson)
P-MC-P323-7000 MC - P323 - Slurry Pumps Tailings - ETA at Site 0 05-Nov-24 MC - P323 - Slurry Pumps Tailings - ETA at Site
MC-P323B - Slurry Pumps - T
Tailings (Engines) V.J. Pamensky Canada 78 08-Apr-24 A 27-Aug-24 27-Aug-24, MC-P323B - Slurry Pumps - Tailings (Engines) V.J. Pamensky Canada
Mechanical 78 08-Apr-24 A 27-Aug-24 27-Aug-24, Mechanical
P-MC-P323B-8005 MC - P323B - Slurry Pumps Tailings - PO 0 08-Apr-24 A MC - P323B - Slurry Pumps Tailings - PO
P-MC-P323B-8010 MC - P323B - Slurry Pumps Tailings - Fabrication Time 36 09-Apr-24 A 16-Jul-24 MC - P323B - Slurry Pumps Tailings - Fabrication Time
P-MC-P323B-8020 MC - P323B - Slurry Pumps Tailings - Transport (Brazil) 42 17-Jul-24 27-Aug-24 MC - P323B - Slurry Pumps Tailings - Transport (Brazil)
P-MC-P323B-8030 MC - P323B - Slurry Pumps Tailings - ETA at Site 0 27-Aug-24 MC - P323B - Slurry Pumps Tailings - ETA at Site
MC-P324 - Slurry Pumps - Pumps
Pu Overhaul 166 04-Oct-23 A 03-Jan-25 03-Jan-25, MC-P324 - Slurry Pumps - Pumps Overhaul
Mechanical 166 04-Oct-23 A 03-Jan-25 03-Jan-25, Mechanical
P-MC-P324-1000 MC - P324 - Slurry Pumps - Pumps Overhaul - Engineering SOW/MTO; RFP 0 04-Oct-23 A 28-Mar-24 A MC - P324 - Slurry Pumps - Pumps Overhaul - Engineering SOW/MTO; RFP
P-MC-P324-3000 MC - P324 - Slurry Pumps - Pumps Overhaul - Bid Evaluation and 0 29-Mar-24 A 14-May-24 A MC - P324 - Slurry Pumps - Pumps Overhaul - Bid Evaluation and Recommendation: TCM; GTC; CBE
Recommendation: TCM; GTC; CBE
P-MC-P324-2000 MC - P324 - Slurry Pumps - Pumps Overhaul- Bid Period: TEV 0 29-Mar-24 A 17-Apr-24 A MC - P324 - Slurry Pumps - Pumps Overhaul- Bid Period: TEV
P-MC-P324-4000 MC - P324 - Slurry Pumps - Pumps Overhaul - Award & PO Issued 0 14-May-24 A 11-Jun-24 A MC - P324 - Slurry Pumps - Pumps Overhaul - Award & PO Issued
P-MC-P324-5000 MC - P324 - Slurry Pumps - Pumps Overhaul - Fabrication Time 69 10-Jul-24* 16-Sep-24 MC - P324 - Slurry Pumps - Pumps Overhaul - Fabrication Time
P-MC-P324-6000 MC - P324 - Slurry Pumps - Pumps Overhaul - Transport (China) 90 17-Sep-24 15-Dec-24 MC - P324 - Slurry Pumps - Pumps Overhaul - Transport (China)
P-MC-P324-7000 MC - P324 - Slurry Pumps - Pumps Overhaul - ETA at Site 0 03-Jan-25 MC - P324 - Slurry Pumps - Pumps Overhaul - ETA at Site
MC-P334 - Third Concentrate Filter Hoist: Konecrane 70 03-Jan-24 A 19-Aug-24 19-Aug-24, MC-P334 - Third Concentrate Filter Hoist: Konecrane
Mechanical 70 03-Jan-24 A 19-Aug-24 19-Aug-24, Mechanical
P-MC-P334-8090 MC - P334 - Third Concentrate Filter Hoist- Engineering MTO; RFP 0 03-Jan-24 A 20-Feb-24 A oncentrate Filter Hoist- Engineering MTO; RFP
P-MC-P334-8100 MC - P334 - Third Concentrate Filter Hoist - Bid Period: TEV 0 21-Feb-24 A 22-Mar-24 A MC - P334 - Third Concentrate Filter Hoist - Bid Period: TEV
P-MC-P334-8110 MC - P334 - Third Concentrate Filter Hoist - Bid Evaluation and 0 23-Mar-24 A 12-Apr-24 A MC - P334 - Third Concentrate Filter Hoist - Bid Evaluation and Recommendation: TCM; GTC; CBE
Recommendation: TCM; GTC; CBE
P-MC-P334-8120 MC - P334 - Third Concentrate Filter Hoist - PR & PO Issued 0 15-Apr-24 A 01-May-24 A MC - P334 - Third Concentrate Filter Hoist - PR & PO Issued
P-MC-P334-8130 MC - P334 - Third Concentrate Filter Hoist - Fabrication Time 65 01-May-24 A 14-Aug-24 MC - P334 - Third Concentrate Filter Hoist - Fabrication Time
P-MC-P334-8140 MC - P334 - Third Concentrate Filter Hoist - Transport (Ecuador) 5 15-Aug-24 19-Aug-24 MC - P334 - Third Concentrate Filter Hoist - Transport (Ecuador)
P-MC-P334-8150 MC - P334 - Third Concentrate Filter Hoist - ETA (6470-CNH-002) 0 19-Aug-24 MC - P334 - Third Concentrate Filter Hoist - ETA (6470-CNH-002)
MC-P361 - Shop Fabricated Plate Work: Alfering S.A.S. 83 08-Nov-23 A 01-Sep-24 01-Sep-24, MC-P361 - Shop Fabricated Plate Work: Alfering S.A.S.
Mechanical 83 08-Nov-23 A 01-Sep-24 01-Sep-24, Mechanical
P-MC-P361-1000 MC-P361 - Shop Fabricated Plate Work - Engineering SOW; RFP 0 08-Nov-23 A 08-Jan-24 A
P-MC-P361-2000 MC-P361 - Shop Fabricated Plate Work - Bid Period: TEV 0 09-Jan-24 A 08-Feb-24 A te Work - Bid Period: TEV
P-MC-P361-3000 MC-P361 - Shop Fabricated Plate Work - Bid Evaluation and Recommendation: 0 05-Feb-24 A 08-Feb-24 A te Work - Bid Evaluation and Recommendation: TCM; GTC; CBE
TCM; GTC; CBE
P-MC-P361-4000 MC-P361 - Shop Fabricated Plate Work - PR & PO Issued 0 09-Feb-24 A 22-Feb-24 A Fabricated Plate Work - PR & PO Issued
P-MC-P361-5000 MC-P361 - Shop Fabricated Plate Work - Fabrication Time - Lot #1 (Gravity) 16 02-Apr-24 A 26-Jun-24 MC-P361 - Shop Fabricated Plate Work - Fabrication Time - Lot #1 (Gravity)
P-MC-P361-5100 MC-P361 - Shop Fabricated Plate Work - Fab - Lot #2 (Jameson Cells plate 62 02-Apr-24 A 11-Aug-24 MC-P361 - Shop Fabricated Plate Work - Fab - Lot #2 (Jameson Cells plate works- 6390-PPB-003/005/001, 6390-PSU-001)
works- 6390-PPB-003/005/001, 6390-PSU-001)
P-MC-P361-5200 MC-P361 - Shop Fabricated Plate Work - Fabrication Time - Lot #3 (All other 49 02-Apr-24 A 29-Jul-24 MC-P361 - Shop Fabricated Plate Work - Fabrication Time - Lot #3 (All other platework)
platework)
P-MC-P361-5300 MC-P361 - Shop Fabricated Plate Work - Fabrication 6470-TNK-009 49 02-Apr-24 A 29-Jul-24 MC-P361 - Shop Fabricated Plate Work - Fabrication 6470-TNK-009
P-MC-P361-5320 MC-P361 - Shop Fabricated Plate Work-Fabrication 6210-CFD-002 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6210-CFD-002
P-MC-P361-5340 MC-P361 - Shop Fabricated Plate Work-Fabrication 6210-PPB-001 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6210-PPB-001
P-MC-P361-5360 MC-P361 - Shop Fabricated Plate Work-Fabrication 6230-PPB-001 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6230-PPB-001
P-MC-P361-5380 MC-P361 - Shop Fabricated Plate Work-Fabrication 6220-LAU-001 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6220-LAU-001
P-MC-P361-5400 MC-P361 - Shop Fabricated Plate Work-Fabrication 6310-TNK-001 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6310-TNK-001
P-MC-P361-5420 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-DIB-004 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-DIB-004
P-MC-P361-5440 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-CFD-008 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-CFD-008
P-MC-P361-5460 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-CFD-009 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-CFD-009
P-MC-P361-5480 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-CFD-007 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-CFD-007
P-MC-P361-5500 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-DIB-003 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-DIB-003
P-MC-P361-5520 MC-P361 - Shop Fabricated Plate Work-Fabrication 6460-DIB-001 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6460-DIB-001
P-MC-P361-5540 MC-P361 - Shop Fabricated Plate Work-Fabrication 6720-PPB-002 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6720-PPB-002
P-MC-P361-5560 MC-P361 - Shop Fabricated Plate Work-Fabrication 6470-CFD-007 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6470-CFD-007
P-MC-P361-5580 MC-P361 - Shop Fabricated Plate Work-Fabrication 6470-CFD-008 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6470-CFD-008
P-MC-P361-5600 MC-P361 - Shop Fabricated Plate Work-Fabrication 6470-CFD-009 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6470-CFD-009
P-MC-P361-5620 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-DIB-005 50 02-Apr-24 A 30-Jul-24 MC-P361 - Shop Fabricated Plate Work-Fabrication 6420-DIB-005
P-MC-P361-5050 MC-P361 - Shop Fabricated Plate Work - Transport - Lot #1 (from Colombia) 21 27-Jun-24 17-Jul-24 MC-P361 - Shop Fabricated Plate Work - Transport - Lot #1 (from Colombia)
P-MC-P361-6000 MC-P361 - Shop Fabricated Plate Work - ETA Lot #1 (6230-DIB-004) 0 17-Jul-24 MC-P361 - Shop Fabricated Plate Work - ETA Lot #1 (6230-DIB-004)
P-MC-P361-5250 MC-P361 - Shop Fabricated Plate Work - Transport - Lot #3 (from Colombia) 28 30-Jul-24 26-Aug-24 MC-P361 - Shop Fabricated Plate Work - Transport - Lot #3 (from Colombia)
P-MC-P361-7030 MC-P361 - Shop Fabricated Plate Workk - Transport -6470-TNK-009 (Colombia) 21 30-Jul-24 19-Aug-24 MC-P361 - Shop Fabricated Plate Workk - Transport -6470-TNK-009 (Colombia)
P-MC-P361-6320 MC-P361 - Shop Fabricated Plate Work-Transport 6210-CFD-002 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6210-CFD-002
P-MC-P361-6340 MC-P361 - Shop Fabricated Plate Work-Transport 6210-PPB-001 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6210-PPB-001
P-MC-P361-6360 MC-P361 - Shop Fabricated Plate Work-Transport 6230-PPB-001 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6230-PPB-001
P-MC-P361-6380 MC-P361 - Shop Fabricated Plate Work-Transport 6220-LAU-001 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6220-LAU-001
P-MC-P361-6400 MC-P361 - Shop Fabricated Plate Work-Transport 6310-TNK-001 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6310-TNK-001
P-MC-P361-6420 MC-P361 - Shop Fabricated Plate Work-Transport 6420-DIB-004 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6420-DIB-004
P-MC-P361-6440 MC-P361 - Shop Fabricated Plate Work-Transport 6420-CFD-008 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6420-CFD-008
P-MC-P361-6460 MC-P361 - Shop Fabricated Plate Work-Transport 6420-CFD-009 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6420-CFD-009
P-MC-P361-6480 MC-P361 - Shop Fabricated Plate Work-Transport 6420-CFD-007 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6420-CFD-007
P-MC-P361-6500 MC-P361 - Shop Fabricated Plate Work-Transport 6420-DIB-003 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6420-DIB-003
P-MC-P361-6520 MC-P361 - Shop Fabricated Plate Work-Transport 6460-DIB-001 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6460-DIB-001
P-MC-P361-6540 MC-P361 - Shop Fabricated Plate Work-Transport 6720-PPB-002 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6720-PPB-002
P-MC-P361-6560 MC-P361 - Shop Fabricated Plate Work-Transport 6470-CFD-007 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6470-CFD-007
P-MC-P361-6580 MC-P361 - Shop Fabricated Plate Work-Transport 6470-CFD-008 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6470-CFD-008
P-MC-P361-6600 MC-P361 - Shop Fabricated Plate Work-Transport 6470-CFD-009 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6470-CFD-009
P-MC-P361-6620 MC-P361 - Shop Fabricated Plate Work-Transport 6420-DIB-005 21 31-Jul-24 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-Transport 6420-DIB-005
P-MC-P361-5150 MC-P361 - Shop Fabricated Plate Work - Transp - (Jameson Cells plate works- 21 12-Aug-24 01-Sep-24 MC-P361 - Shop Fabricated Plate Work - Transp - (Jameson Cells plate works- 6390-PPB-003/005/001, 6390-PSU-001)
6390-PPB-003/005/001, 6390-PSU-001)
P-MC-P361-7040 MC-P361 - Shop Fabricated Plate Work - ETA -6470-TNK-009 0 19-Aug-24 MC-P361 - Shop Fabricated Plate Work - ETA -6470-TNK-009
P-MC-P361-7320 MC-P361 - Shop Fabricated Plate Work-ETA 6210-CFD-002 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6210-CFD-002
P-MC-P361-7340 MC-P361 - Shop Fabricated Plate Work-ETA 6210-PPB-001 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6210-PPB-001
P-MC-P361-7360 MC-P361 - Shop Fabricated Plate Work-ETA 6230-PPB-001 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6230-PPB-001
P-MC-P361-7380 MC-P361 - Shop Fabricated Plate Work-ETA 6220-LAU-001 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6220-LAU-001
P-MC-P361-7400 MC-P361 - Shop Fabricated Plate Work-ETA 6310-TNK-001 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6310-TNK-001
P-MC-P361-7420 MC-P361 - Shop Fabricated Plate Work-ETA 6420-DIB-004 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6420-DIB-004
P-MC-P361-7440 MC-P361 - Shop Fabricated Plate Work-ETA 6420-CFD-008 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6420-CFD-008
P-MC-P361-7460 MC-P361 - Shop Fabricated Plate Work-ETA 6420-CFD-009 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6420-CFD-009
P-MC-P361-7480 MC-P361 - Shop Fabricated Plate Work-ETA 6420-CFD-007 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6420-CFD-007
P-MC-P361-7500 MC-P361 - Shop Fabricated Plate Work-ETA 6420-DIB-003 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6420-DIB-003
P-MC-P361-7520 MC-P361 - Shop Fabricated Plate Work-ETA 6460-DIB-001 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6460-DIB-001
P-MC-P361-7540 MC-P361 - Shop Fabricated Plate Work-ETA 6720-PPB-002 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6720-PPB-002
P-MC-P361-7560 MC-P361 - Shop Fabricated Plate Work-ETA 6470-CFD-007 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6470-CFD-007
P-MC-P361-7580 MC-P361 - Shop Fabricated Plate Work-ETA 6470-CFD-008 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6470-CFD-008
P-MC-P361-7600 MC-P361 - Shop Fabricated Plate Work-ETA 6470-CFD-009 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6470-CFD-009
P-MC-P361-7620 MC-P361 - Shop Fabricated Plate Work-ETA 6420-DIB-005 0 20-Aug-24 MC-P361 - Shop Fabricated Plate Work-ETA 6420-DIB-005
P-MC-P361-8320 MC-P361 - Shop Fabricated Plate Work-RAS 6210-CFD-002 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6210-CFD-002
P-MC-P361-8340 MC-P361 - Shop Fabricated Plate Work-RAS 6210-PPB-001 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6210-PPB-001
P-MC-P361-8360 MC-P361 - Shop Fabricated Plate Work-RAS 6230-PPB-001 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6230-PPB-001
P-MC-P361-8380 MC-P361 - Shop Fabricated Plate Work-RAS 6220-LAU-001 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6220-LAU-001
P-MC-P361-8400 MC-P361 - Shop Fabricated Plate Work-RAS 6310-TNK-001 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6310-TNK-001
P-MC-P361-8420 MC-P361 - Shop Fabricated Plate Work-RAS 6420-DIB-004 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6420-DIB-004
P-MC-P361-8440 MC-P361 - Shop Fabricated Plate Work-RAS 6420-CFD-008 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6420-CFD-008
P-MC-P361-8460 MC-P361 - Shop Fabricated Plate Work-RAS 6420-CFD-009 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6420-CFD-009
P-MC-P361-8480 MC-P361 - Shop Fabricated Plate Work-RAS 6420-CFD-007 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6420-CFD-007
P-MC-P361-8500 MC-P361 - Shop Fabricated Plate Work-RAS 6420-DIB-003 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6420-DIB-003
P-MC-P361-8520 MC-P361 - Shop Fabricated Plate Work-RAS 6460-DIB-001 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6460-DIB-001
P-MC-P361-8540 MC-P361 - Shop Fabricated Plate Work-RAS 6720-PPB-002 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6720-PPB-002
P-MC-P361-8560 MC-P361 - Shop Fabricated Plate Work-RAS 6470-CFD-007 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6470-CFD-007
P-MC-P361-8580 MC-P361 - Shop Fabricated Plate Work-RAS 6470-CFD-008 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6470-CFD-008
P-MC-P361-8600 MC-P361 - Shop Fabricated Plate Work-RAS 6470-CFD-009 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6470-CFD-009
P-MC-P361-8620 MC-P361 - Shop Fabricated Plate Work-RAS 6420-DIB-005 0 21-Aug-24 MC-P361 - Shop Fabricated Plate Work-RAS 6420-DIB-005
P-MC-P361-6030 MC-P361 - Shop Fabricated Plate Work - ETA Lot #3 0 26-Aug-24 MC-P361 - Shop Fabricated Plate Work - ETA Lot #3
P-MC-P361-6010 MC-P361 - Shop Fabricated Plate Work - ETA Lot #2 0 01-Sep-24 MC-P361 - Shop Fabricated Plate Work - ETA Lot #2
EL-P305 - LV MCC & Remote Starter: Schneider 251 07-Feb-24 A 28-Feb-25 28-Feb-25, EL-P305 - LV MCC & Remote Starter: Schneider
Electrical & Instrumentation
Instrumentati 251 07-Feb-24 A 28-Feb-25 28-Feb-25, Electrical & Instrumentation
P-EL-P305-1000 EL - P305 - Engineering SOW/MTO; RFP 0 07-Feb-24 A 15-Feb-24 A SOW/MTO; RFP
P-EL-P305-2000 EL - P305 - Bid Period: TEV 0 16-Feb-24 A 12-Apr-24 A EL - P305 - Bid Period: TEV
P-EL-P305-3000 EL - P305 - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 15-Apr-24 A 03-May-24 A EL - P305 - Bid Evaluation and Recommendation: TCM; GTC; CBE
P-EL-P305-5010 EL - P305 - Fabrication ECFN-3-EL-P305-BID-0007 (6 VFDs 2340)) 112 20-May-24 A 18-Oct-24 EL - P305 - Fabrication ECFN-3-EL-P305-BID-0007 (6 VFDs 2340))
P-EL-P305-5020 EL - P305 - Fabrication ECFN-3-EL-P305-BID-0010 (4VFD-3817, 4VFD-6720, 161 20-May-24 A 06-Dec-24 EL - P305 - Fabrication ECFN-3-EL-P305-BID-0010 (4VFD-3817, 4VFD-6720, 4VFD-6320, 2VFD Columns)
4VFD-6320, 2VFD Columns)
P-EL-P305-5030 EL - P305 - Fabrication ECFN-3-EL-P305-BID-0012 (2340-MCC-001) 226 20-May-24 A 21-Feb-25 EL - P305 - Fabrication ECFN-3-EL-P305-BID-0012 (2340-MCC-001)
P-EL-P305-5040 EL - P305 - Fabrication ECFN-3-EL-P305-BID-0013 (Buckets to be installed in 132 20-May-24 A 07-Nov-24 EL - P305 - Fabrication ECFN-3-EL-P305-BID-0013 (Buckets to be installed in existing MCC)
existing MCC)
P-EL-P305-5050 EL - P305 - Fabrication ECFN-3-EL-P305-BID-0014 (E-room) 162 20-May-24 A 07-Dec-24 EL - P305 - Fabrication ECFN-3-EL-P305-BID-0014 (E-room)
P-EL-P305-4500 EL - P305 - Advance Payment 13 31-May-24 A 28-Jun-24 EL - P305 - Advance Payment
P-EL-P305-6000 EL - P305 - Transport (from Colombia) 28 01-Feb-25 28-Feb-25 EL - P305 - Transport (from Colombia)
P-EL-P305-7000 EL - P305 - ETA at Site 0 28-Feb-25 EL - P305 - ETA at Site
EL-P306 - MV To LV Transformer
Transfor for Jameson Cell Electrical Room 2340 - HITACHI 223 05-Mar-24 A 31-Jan-25 31-Jan-25, EL-P306 - MV To LV Transformer for Jameson Cell Electrical Room 2340 - HITACHI
Electrical & Instrumentation
Instrumentati 223 05-Mar-24 A 31-Jan-25 31-Jan-25, Electrical & Instrumentation
P-EL-P306-1000 EL - P306 - Engineering SOW/MTO; RFP 0 05-Mar-24 A 05-Apr-24 A EL - P306 - Engineering SOW/MTO; RFP
P-EL-P306-2000 EL - P306 - Bid Period: TEV 0 05-Apr-24 A 23-May-24 A EL - P306 - Bid Period: TEV
P-EL-P306-3000 EL - P306 - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 23-May-24 A 31-May-24 A EL - P306 - Bid Evaluation and Recommendation: TCM; GTC; CBE
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 2 of 7 28-Jun-24 ECFN-3 Master schedule weekly report - for information MF
Actual Level of Effort Critical Remaining Work
TASK filters: so_changes_not_red, so_show_into_report.
Actual Work Milestone
Fruta del Norte 3
Master Schedule Draft
Activity ID Activity Name Remaining Start Finish 2024 2025
Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Electrical & Instrumentation
Instrumentati 156 29-Apr-24 A 13-Nov-24 13-Nov-24, Electrical & Instrumentation
P-EL-P307-1000 EL - P307 - Electrical Motors - Engineering SOW/MTO; RFP 0 29-Apr-24 A 06-May-24 A EL - P307 - Electrical Motors - Engineering SOW/MTO; RFP
P-EL-P307-2000 EL - P307 - Electrical Motors - Bid Period: TEV 0 06-May-24 A 22-May-24 A EL - P307 - Electrical Motors - Bid Period: TEV
P-EL-P307-3000 EL - P307 - Electrical Motors - Bid Evaluation and Recommendation: TCM; 0 22-May-24 A 23-May-24 A EL - P307 - Electrical Motors - Bid Evaluation and Recommendation: TCM; GTC; CBE
GTC; CBE
P-EL-P307-4000 EL - P307 - Electrical Motors - PR & PO Issued 9 23-May-24 A 21-Jun-24 EL - P307 - Electrical Motors - PR & PO Issued
P-EL-P307-5000 EL - P307 - Electrical Motors - Fabrication Time 115 22-Jun-24 14-Oct-24 EL - P307 - Electrical Motors - Fabrication Time
P-EL-P307-6000 EL - P307 - Electrical Motors - Transport (from Brazil) 30 15-Oct-24 13-Nov-24 EL - P307 - Electrical Motors - Transport (from Brazil)
P-EL-P307-7000 EL - P307 - Electrical Motors- ETA at Site 0 13-Nov-24 EL - P307 - Electrical Motors- ETA at Site
EL-R315 - LV Power Cables - LUMEN 136 15-Feb-24 A 24-Oct-24 24-Oct-24, EL-R315 - LV Power Cables - LUMEN
Electrical & Instrumentation
Instrumentati 136 15-Feb-24 A 24-Oct-24 24-Oct-24, Electrical & Instrumentation
P-EL-R315-1000 EL - R315 - Engineering MTO; RFP 0 15-Feb-24 A 14-Mar-24 A EL - R315 - Engineering MTO; RFP
P-EL-R315-2000 EL - R315 - Bid Period: TEV 0 15-Mar-24 A 28-Mar-24 A EL - R315 - Bid Period: TEV
P-EL-R315-3000 EL - R315 - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 28-Mar-24 A 18-Apr-24 A EL - R315 - Bid Evaluation and Recommendation: TCM; GTC; CBE
P-IN-P301-1010 IN-P301 - Plant Automation Panel Assembly - Bid Period: TEV 0 02-Apr-24 A 10-Apr-24 A IN-P301 - Plant Automation Panel Assembly - Bid Period: TEV
P-IN-P301-1020 IN-P301 - Plant Automation Panel Assembly - Bid Evaluation and 0 10-Apr-24 A 22-Apr-24 A IN-P301 - Plant Automation Panel Assembly - Bid Evaluation and Recommendation: TCM; GTC; CBE
Recommendation: TCM; GTC; CBE
P-IN-P301-1030 IN-P301 - Plant Automation Panel Assembly - Award & PO Issued 0 23-Apr-24 A 06-May-24 A IN-P301 - Plant Automation Panel Assembly - Award & PO Issued
P-IN-P301-1040 IN-P301 - Plant Automation Panel Assembly - Fabrication Time 154 11-Jun-24* 11-Nov-24 IN-P301 - Plant Automation Panel Assembly - Fabrication Time
P-IN-P301-1050 IN-P301 - Plant Automation Panel Assembly - Transport 20 12-Nov-24 01-Dec-24 IN-P301 - Plant Automation Panel Assembly - Transport
P-IN-P301-1060 IN-P301 - Plant Automation Panel Assembly - ETA at Site 0 01-Dec-24 IN-P301 - Plant Automation Panel Assembly - ETA at Site
IN-P302 - Plant Automation SCADA,
S PC & SERVER: Adius 0 18-Jan-24 A 11-Jun-24 11-Jun-24, IN-P302 - Plant Automation SCADA, PC & SERVER: Adius
Electrical & Instrumentation
Instrumentati 0 18-Jan-24 A 11-Jun-24 11-Jun-24, Electrical & Instrumentation
P-IN-P302-1000 IN - P302 - Award & PO Issued 0 18-Jan-24 A
P-IN-P302-1500 IN - P302 - KOM at Site 0 29-Jan-24 A 02-Feb-24 A
P-IN-P302-2000 IN - P302 - Fabrication & FAT Tests 0 05-Feb-24 A 03-Jun-24 A IN - P302 - Fabrication & FAT Tests
P-IN-P302-1600 IN - P302 - Design 0 05-Feb-24 A 01-Apr-24 A IN - P302 - Design
P-IN-P302-3000 IN - P302 - Transport (from South Africa) 0 03-Jun-24 A 11-Jun-24 IN - P302 - Transport (from South Africa)
P-IN-P302-4000 IN - P302 - Plant Automation SCADA, PC & Server - ETA 0 11-Jun-24 IN - P302 - Plant Automation SCADA, PC & Server - ETA
IN-P302A - Particles Analyzer
Analyze - Cyclones - MOLYCOP 173 30-Jan-24 A 30-Nov-24 30-Nov-24, IN-P302A - Particles Analyzer - Cyclones - MOLYCOP
Electrical & Instrumentation
Instrumentati 173 30-Jan-24 A 30-Nov-24 30-Nov-24, Electrical & Instrumentation
P-IN-P302A-1000 IN - P302A - Engineering MTO; RFP 0 30-Jan-24 A 05-Feb-24 A
P-IN-P302A-1010 IN - P302A - Bid Period: TEV 0 08-Mar-24 A 03-May-24 A IN - P302A - Bid Period: TEV
P-IN-P302A-1020 IN - P302A - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 06-May-24 A 30-May-24 A IN - P302A - Bid Evaluation and Recommendation: TCM; GTC; CBE
P-IN-P302A-1030 IN - P302A - Award & PO Issued 13 30-May-24 A 28-Jun-24 IN - P302A - Award & PO Issued
P-IN-P302A-1040 IN - P302A - Fabrication Time (Chile) 140 29-Jun-24 15-Nov-24 IN - P302A - Fabrication Time (Chile)
P-IN-P302A-1050 IN - P302A - Transport 15 16-Nov-24 30-Nov-24 IN - P302A - Transport
P-IN-P302A-1060 IN - P302A - ETA at Site 0 30-Nov-24 IN - P302A - ETA at Site
IN-P302B - Vibration Sensor - Sag Mill - MOLYCOP 147 30-Jan-24 A 04-Nov-24 04-Nov-24, IN-P302B - Vibration Sensor - Sag Mill - MOLYCOP
Electrical & Instrumentation
Instrumentati 147 30-Jan-24 A 04-Nov-24 04-Nov-24, Electrical & Instrumentation
P-IN-P302B-1000 IN - P302B - Engineering MTO; RFP 0 30-Jan-24 A 05-Feb-24 A
P-IN-P302B-1010 IN - P302B - Bid Period: TEV 0 08-Mar-24 A 08-May-24 A IN - P302B - Bid Period: TEV
P-IN-P302B-1020 IN - P302B - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 08-May-24 A 30-May-24 A IN - P302B - Bid Evaluation and Recommendation: TCM; GTC; CBE
P-IN-P302B-1030 IN - P302B - Award & PO Issued 13 30-May-24 A 28-Jun-24 IN - P302B - Award & PO Issued
P-IN-P302B-1040 IN - P302B - Fabrication Time 84 29-Jun-24 20-Sep-24 IN - P302B - Fabrication Time
P-IN-P302B-1050 IN - P302B - Transport 45 21-Sep-24 04-Nov-24 IN - P302B - Transport
P-IN-P302B-1060 IN - P302B - ETA at Site 0 04-Nov-24 IN - P302B - ETA at Site
IN-P302C - Cameras (Sag Mill
Mi Feed) - Stone Three 116 30-Jan-24 A 04-Oct-24 04-Oct-24, IN-P302C - Cameras (Sag Mill Feed) - Stone Three
Electrical & Instrumentation
Instrumentati 116 30-Jan-24 A 04-Oct-24 04-Oct-24, Electrical & Instrumentation
P-IN-P302C-1000 IN - P302C - Engineering MTO; RFP 0 30-Jan-24 A 05-Feb-24 A
P-IN-P302C-1010 IN - P302C - Bid Period: TEV 0 08-Mar-24 A 29-Mar-24 A IN - P302C - Bid Period: TEV
P-IN-P302C-1020 IN - P302C - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 30-Mar-24 A 07-May-24 A IN - P302C - Bid Evaluation and Recommendation: TCM; GTC; CBE
P-IN-P302C-1030 IN - P302C - Award & PO Issued 9 07-May-24 A 21-Jun-24 IN - P302C - Award & PO Issued
P-IN-P302C-1040 IN - P302C - Fabrication Time 60 22-Jun-24 20-Aug-24 IN - P302C - Fabrication Time
P-IN-P302C-1050 IN - P302C - Transport 45 21-Aug-24 04-Oct-24 IN - P302C - Transport
P-IN-P302C-1060 IN - P302C - ETA at Site 0 04-Oct-24 IN - P302C - ETA at Site
IN-P302D - Camera Box Fabrication
Fab - INSELEC 81 11-Mar-24 A 30-Aug-24 30-Aug-24, IN-P302D - Camera Box Fabrication - INSELEC
Electrical & Instrumentation
Instrumentati 81 11-Mar-24 A 30-Aug-24 30-Aug-24, Electrical & Instrumentation
P-IN-P302D-1000 IN - P302D - Engineering MTO; RFP 0 11-Mar-24 A 10-Apr-24 A IN - P302D - Engineering MTO; RFP
P-IN-P302D-1010 IN - P302D - Bid Period: TEV 0 10-Apr-24 A 02-May-24 A IN - P302D - Bid Period: TEV
P-IN-P302D-1020 IN - P302D - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 02-May-24 A 06-Jun-24 A IN - P302D - Bid Evaluation and Recommendation: TCM; GTC; CBE
P-IN-P302D-1030 IN - P302D - Award & PO Issued 9 06-Jun-24 A 21-Jun-24 IN - P302D - Award & PO Issued
P-IN-P302D-1040 IN - P302D - Fabrication Time (Ecuador) 60 22-Jun-24 20-Aug-24 IN - P302D - Fabrication Time (Ecuador)
P-IN-P302D-1050 IN - P302D - Transport 10 21-Aug-24 30-Aug-24 IN - P302D - Transport
P-IN-P302D-1060 IN - P302D - ETA at Site 0 30-Aug-24 IN - P302D - ETA at Site
IN-P304 - Instrument ( Belt S
Scales) - SCALE INTERNATIONAL SERVICE SAC 252 01-Jun-24 A 01-Mar-25 01-Mar-25, IN-P304 - Instrument ( Belt Scales) - SCALE INTERNATIONAL SERVICE SAC
Electrical & Instrumentation
Instrumentati 252 01-Jun-24 A 01-Mar-25 01-Mar-25, Electrical & Instrumentation
P-IN-P304-1080 IN-P304 - Instrument (Belt Scales) - Award & PO Issued 9 01-Jun-24 A 21-Jun-24 IN-P304 - Instrument (Belt Scales) - Award & PO Issued
P-IN-P304-1090 IN-P304 - Instrument (Belt Scales) - Fabrication Time 196 22-Jun-24 15-Jan-25 IN-P304 - Instrument (Belt Scales) - Fabrication Time
P-IN-P304-1100 IN-P304 - Instrument (Belt Scales) - Transport 45 16-Jan-25 01-Mar-25 IN-P304 - Instrument (Belt Scales) - Transport
P-IN-P304-1110 IN-P304 - Instrument (Belt Scales) - ETA at Site 0 01-Mar-25 IN-P304 - Instrument (Belt Scales) - ETA at Site
IN-P304A - Instrument (Sump Pump PT) - Kytola 0 03-Apr-24 A 01-Jun-24 A 01-Jun-24 A, IN-P304A - Instrument (Sump Pump PT) - Kytola
Electrical & Instrumentation
Instrumentati 0 03-Apr-24 A 01-Jun-24 A 01-Jun-24 A, Electrical & Instrumentation
P-IN-P304A-1030 IN - P304A - Award & PO Issued 0 03-Apr-24 A IN - P304A - Award & PO Issued
P-IN-P304A-1040 IN - P304A - Fabrication Time 0 04-Apr-24 A 01-May-24 A IN - P304A - Fabrication Time
P-IN-P304A-1050 IN - P304A - Transport (from Canada) 0 02-May-24 A 01-Jun-24 A IN - P304A - Transport (from Canada)
P-IN-P304A-1060 IN - P304A - ETA at Site 0 01-Jun-24 A IN - P304A - ETA at Site
IN-P304B - Instrument (LIT-PIT)
(LIT-P - Everst Automation 108 31-May-24 A 26-Sep-24 26-Sep-24, IN-P304B - Instrument (LIT-PIT) - Everst Automation
Electrical & Instrumentation
Instrumentati 108 31-May-24 A 26-Sep-24 26-Sep-24, Electrical & Instrumentation
P-IN-P304B-1030 IN - P304B - Award & PO Issued 0 31-May-24 A IN - P304B - Award & PO Issued
P-IN-P304B-1040 IN - P304B - Fabrication Time 63 03-Jun-24 A 12-Aug-24 IN - P304B - Fabrication Time
P-IN-P304B-1050 IN - P304B - Transport (from Canada) 45 13-Aug-24 26-Sep-24 IN - P304B - Transport (from Canada)
P-IN-P304B-1060 IN - P304B - ETA at Site 0 26-Sep-24 IN - P304B - ETA at Site
IN-P304C - Instruments (Flow Transmitter) 179 22-Apr-24 A 06-Dec-24 06-Dec-24, IN-P304C - Instruments (Flow Transmitter)
Electrical & Instrumentation
Instrumentati 179 22-Apr-24 A 06-Dec-24 06-Dec-24, Electrical & Instrumentation
P-IN-P304C-1000 IN - P304C - Engineering MTO; RFP 0 22-Apr-24 A 02-May-24 A IN - P304C - Engineering MTO; RFP
P-IN-P304C-1010 IN - P304C - Bid Period: TEV 0 02-May-24 A 30-May-24 A IN - P304C - Bid Period: TEV
P-IN-P304C-1020 IN - P304C - Bid Evaluation and Recommendation: TCM; GTC; CBE 9 30-May-24 A 21-Jun-24 IN - P304C - Bid Evaluation and Recommendation: TCM; GTC; CBE
P-IN-P304C-1030 IN - P304C - Award & PO Issued 10 25-Jun-24 09-Jul-24 IN - P304C - Award & PO Issued
P-IN-P304C-1040 IN - P304C - Fabrication Time 105 10-Jul-24 22-Oct-24 IN - P304C - Fabrication Time
P-IN-P304C-1050 IN - P304C - Transport (from Colombia) 45 23-Oct-24 06-Dec-24 IN - P304C - Transport (from Colombia)
P-IN-P304C-1060 IN - P304C - ETA at Site 0 06-Dec-24 IN - P304C - ETA at Site
IN-P304D - Instruments (Pres
(Pressure Indicator) 126 24-Apr-24 A 15-Oct-24 15-Oct-24, IN-P304D - Instruments (Pressure Indicator)
Electrical & Instrumentation
Instrumentati 126 24-Apr-24 A 15-Oct-24 15-Oct-24, Electrical & Instrumentation
P-IN-P304D-1000 IN - P304D - Engineering MTO; RFP 0 24-Apr-24 A 12-Jun-24 A IN - P304D - Engineering MTO; RFP
P-IN-P304D-1010 IN - P304D - Bid Period: TEV 13 12-Jun-24 A 28-Jun-24 IN - P304D - Bid Period: TEV
P-IN-P304D-1040 IN - P304D - Fabrication Time 60 02-Jul-24 31-Aug-24 IN - P304D - Fabrication Time
P-IN-P304D-1020 IN - P304D - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 02-Jul-24 02-Jul-24 IN - P304D - Bid Evaluation and Recommendation: TCM; GTC; CBE
P-IN-P304E-1030 IN - P304E - Award & PO Issued 10 03-Jul-24 16-Jul-24 IN - P304E - Award & PO Issued
P-IN-P304E-1040 IN - P304E - Fabrication Time 60 17-Jul-24 14-Sep-24 IN - P304E - Fabrication Time
P-IN-P304E-1050 IN - P304E - Transport (from Canada) 45 15-Sep-24 29-Oct-24 IN - P304E - Transport (from Canada)
P-IN-P304E-1060 IN - P304E - ETA at Site 0 29-Oct-24 IN - P304E - ETA at Site
IN-P305 - Valves (actuated and
an ON/OFF) - Multotec 78 18-Sep-23 A 03-Oct-24 03-Oct-24, IN-P305 - Valves (actuated and ON/OFF) - Multotec
Electrical & Instrumentation
Instrumentati 78 18-Sep-23 A 03-Oct-24 03-Oct-24, Electrical & Instrumentation
P-IN-P305-1000 IN - P305 - Engineering MTO; RFP 0 18-Sep-23 A 25-Jan-24 A
P-IN-P305-2000 IN - P305 - Bid Period: TEV 0 25-Jan-24 A 29-Feb-24 A - Bid Period: TEV
P-IN-P305-3000 IN - P305 - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 29-Feb-24 A 17-Apr-24 A IN - P305 - Bid Evaluation and Recommendation: TCM; GTC; CBE
P-IN-P305B-1-2000 IN-P305B-1 - Valves (Water Addition) - Bid Period: TEV 0 21-Mar-24 A 25-Apr-24 A IN-P305B-1 - Valves (Water Addition) - Bid Period: TEV
P-IN-P305B-1-3000 IN-P305B-1 - Valves (Water Addition) - Bid Evaluation and Recommendation: 0 25-Apr-24 A 24-May-24 A IN-P305B-1 - Valves (Water Addition) - Bid Evaluation and Recommendation: TCM; GTC; CBE
TCM; GTC; CBE
P-IN-P305B-1-4000 IN-P305B-1 - Valves (Water Addition) - PR & PO Issued 13 24-May-24 A 28-Jun-24 IN-P305B-1 - Valves (Water Addition) - PR & PO Issued
P-IN-P305B-1-5000 IN-P305B-1 - Valves (Water Addition) - Fabrication Time (Johannesburg, RSA) 48 02-Jul-24 06-Sep-24 IN-P305B-1 - Valves (Water Addition) - Fabrication Time (Johannesburg, RSA)
P-IN-P305B-1-6000 IN-P305B-1 - Valves (Water Addition) - Transport 30 09-Sep-24 21-Oct-24 IN-P305B-1 - Valves (Water Addition) - Transport
P-IN-P305B-1-7000 IN-P305B-1 - Valves (Water Addition) - ETA at Site 0 21-Oct-24 IN-P305B-1 - Valves (Water Addition) - ETA at Site
IN-P305B-2 - Valves (Water Addition
A Valves) 121 06-Mar-24 A 03-Dec-24 03-Dec-24, IN-P305B-2 - Valves (Water Addition Valves)
Electrical & Instrumentation
Instrumentati 121 06-Mar-24 A 03-Dec-24 03-Dec-24, Electrical & Instrumentation
P-IN-P305B-2-1000 IN-P305B-2 - Valves (Water Addition) - Engineering MTO; RFP 0 06-Mar-24 A 21-Mar-24 A IN-P305B-2 - Valves (Water Addition) - Engineering MTO; RFP
P-IN-P305B-2-2000 IN-P305B-2 - Valves (Water Addition) - Bid Period: TEV 0 21-Mar-24 A 25-Apr-24 A IN-P305B-2 - Valves (Water Addition) - Bid Period: TEV
P-IN-P305B-2-3000 IN-P305B-2 - Valves (Water Addition) - Bid Evaluation and Recommendation: 0 25-Apr-24 A 24-May-24 A IN-P305B-2 - Valves (Water Addition) - Bid Evaluation and Recommendation: TCM; GTC; CBE
TCM; GTC; CBE
P-IN-P305B-2-4000 IN-P305B-2 - Valves (Water Addition) - PR & PO Issued 13 24-May-24 A 28-Jun-24 IN-P305B-2 - Valves (Water Addition) - PR & PO Issued
P-IN-P305B-2-5000 IN-P305B-2 - Valves (Water Addition) - Fabrication Time 48 02-Jul-24 06-Sep-24 IN-P305B-2 - Valves (Water Addition) - Fabrication Time
P-IN-P305B-2-6000 IN-P305B-2 - Valves (Water Addition) - Transport 60 09-Sep-24 03-Dec-24 IN-P305B-2 - Valves (Water Addition) - Transport
P-IN-P305B-2-7000 IN-P305B-2 - Valves (Water Addition) - ETA at Site 0 03-Dec-24 IN-P305B-2 - Valves (Water Addition) - ETA at Site
IN-P305C - Valves (Gland Seal
Se Valves) 91 06-Mar-24 A 21-Oct-24 21-Oct-24, IN-P305C - Valves (Gland Seal Valves)
Electrical & Instrumentation
Instrumentati 91 06-Mar-24 A 21-Oct-24 21-Oct-24, Electrical & Instrumentation
P-IN-P305C-1000 IN-P305C - Valves (Gland Seal Valves) - Engineering MTO; RFP 0 06-Mar-24 A 21-Mar-24 A IN-P305C - Valves (Gland Seal Valves) - Engineering MTO; RFP
P-IN-P305C-2000 IN-P305C - Valves (Gland Seal Valves) - Bid Period: TEV 0 21-Mar-24 A 17-May-24 A IN-P305C - Valves (Gland Seal Valves) - Bid Period: TEV
P-IN-P305C-3000 IN-P305C - Valves (Gland Seal Valves) - Bid Evaluation and Recommendation: 0 17-May-24 A 07-Jun-24 A IN-P305C - Valves (Gland Seal Valves) - Bid Evaluation and Recommendation: TCM; GTC; CBE
TCM; GTC; CBE
P-IN-P305C-4000 IN-P305C - Valves (Gland Seal Valves) - PR & PO Issued 13 07-Jun-24 A 28-Jun-24 IN-P305C - Valves (Gland Seal Valves) - PR & PO Issued
P-IN-P305C-5000 IN-P305C - Valves (Gland Seal Valves) - Fabrication Time 48 02-Jul-24 06-Sep-24 IN-P305C - Valves (Gland Seal Valves) - Fabrication Time
P-IN-P305C-6000 IN-P305C - Valves (Gland Seal Valves) - Transport 30 09-Sep-24 21-Oct-24 IN-P305C - Valves (Gland Seal Valves) - Transport
P-IN-P305C-7000 IN-P305C - Valves (Gland Seal Valves) - ETA at Site 0 21-Oct-24 IN-P305C - Valves (Gland Seal Valves) - ETA at Site
IN-P305D - Valves (Control Valves)
V 101 06-Mar-24 A 04-Nov-24 04-Nov-24, IN-P305D - Valves (Control Valves)
Electrical & Instrumentation
Instrumentati 101 06-Mar-24 A 04-Nov-24 04-Nov-24, Electrical & Instrumentation
P-IN-P305D-1000 IN-P305D - Valves (Control Valves) - Engineering MTO; RFP 0 06-Mar-24 A 21-Mar-24 A IN-P305D - Valves (Control Valves) - Engineering MTO; RFP
P-IN-P305D-2000 IN-P305D - Valves (Control Valves) - Bid Period: TEV 3 21-Mar-24 A 13-Jun-24 IN-P305D - Valves (Control Valves) - Bid Period: TEV
P-IN-P305D-3000 IN-P305D - Valves (Control Valves)- Bid Evaluation and Recommendation: TCM; 10 14-Jun-24 28-Jun-24 IN-P305D - Valves (Control Valves)- Bid Evaluation and Recommendation: TCM; GTC; CBE
GTC; CBE
P-IN-P305D-4000 IN-P305D - Valves (Control Valves)es) - PR & PO Issued 10 02-Jul-24 15-Jul-24 IN-P305D - Valves (Control Valves)es) - PR & PO Issued
P-IN-P305D-5000 IN-P305D - Valves (Control Valves) - Fabrication Time 48 16-Jul-24 20-Sep-24 IN-P305D - Valves (Control Valves) - Fabrication Time
P-IN-P305D-6000 IN-P305D - Valves (Control Valves) - Transport 30 23-Sep-24 04-Nov-24 IN-P305D - Valves (Control Valves) - Transport
P-IN-P305D-7000 IN-P305D - Valves (Control Valves) - ETA at Site 0 04-Nov-24 IN-P305D - Valves (Control Valves) - ETA at Site
IN-P320 - Control Cable and Fiber 205 26-Oct-23 A 11-Apr-25 11-Apr-25, IN-P320 - Control Cable and Fiber
Electrical & Instrumentation
Instrumentati 205 26-Oct-23 A 11-Apr-25 11-Apr-25, Electrical & Instrumentation
P-IN-P320-1000 IN-P320 - Control Cable and Fiber - Engineering MTO; RFP 0 26-Oct-23 A 19-Mar-24 A IN-P320 - Control Cable and Fiber - Engineering MTO; RFP
P-IN-P320-2000 IN-P320 - Control Cable and Fiber - Bid Period: TEV 0 21-Mar-24 A 28-Mar-24 A IN-P320 - Control Cable and Fiber - Bid Period: TEV
P-IN-P320-3000 IN-P320 - Control Cable and Fiber - Bid Evaluation and Recommendation: 0 22-Mar-24 A 22-Apr-24 A IN-P320 - Control Cable and Fiber - Bid Evaluation and Recommendation: TCM; GTC; CBE
TCM; GTC; CBE
P-IN-P320-4000 IN-P320 - Control Cable and Fiber - PR & PO Issued 0 22-Apr-24 A 06-May-24 A IN-P320 - Control Cable and Fiber - PR & PO Issued
P-IN-P320-5000 IN-P320 - Control Cable and Fiber - Fabrication Time 175 11-Jun-24* 28-Feb-25 IN-P320 - Control Cable and Fiber - Fabrication Time
P-IN-P320-6000 IN-P320 - Control Cable and Fiber - Transport 30 03-Mar-25 11-Apr-25 IN-P320 - Control Cable and Fiber - Transport
P-IN-P320-7000 IN-P320 - Control Cable and Fiber - ETA at Site 0 11-Apr-25 IN-P320 - Control Cable and Fiber - ETA at Site
PI-P303 - Rubber Lined Steel
Stee Pipe & Fittings. Fastpack (Chile) 126 18-Jan-24 A 14-Oct-24 14-Oct-24, PI-P303 - Rubber Lined Steel Pipe & Fittings. Fastpack (Chile)
Piping 126 18-Jan-24 A 14-Oct-24 14-Oct-24, Piping
P-PI-P303-1000 PI - P303 - Engineering Outline Drawings 60%; RFP 0 18-Jan-24 A 23-Feb-24 A neering Outline Drawings 60%; RFP
P-PI-P303-2000 PI - P303 - Bid Period: TEV 0 23-Feb-24 A 21-Mar-24 A PI - P303 - Bid Period: TEV
P-PI-P303-3000 PI - P303 - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 21-Mar-24 A 12-Apr-24 A PI - P303 - Bid Evaluation and Recommendation: TCM; GTC; CBE
P-PI-P303-1500 PI - P303 - Engineering Outline Drawings 100%; RFP 15 11-Jun-24 03-Jul-24 PI - P303 - Engineering Outline Drawings 100%; RFP
P-PI-P303-6000 PI-P303 - Rubber Lined Steel Pipe & Fittings - Transport 30 15-Sep-24 14-Oct-24 PI-P303 - Rubber Lined Steel Pipe & Fittings - Transport
P-PI-P303-7000 PI-P303 - Rubber Lined Steel Pipe & Fittings - ETA at Site 0 14-Oct-24 PI-P303 - Rubber Lined Steel Pipe & Fittings - ETA at Site
PI-P306 - Slurry Valves - Tech
Tech-Pro Heavy Industrial 133 15-Jan-24 A 21-Oct-24 21-Oct-24, PI-P306 - Slurry Valves - Tech-Pro Heavy Industrial
Piping 133 15-Jan-24 A 21-Oct-24 21-Oct-24, Piping
P-PI-P306-1000 PI - P306 - Engineering MTO; RFP 0 15-Jan-24 A 29-Feb-24 A - Engineering MTO; RFP
P-PI-P306-2000 PI - P306 - Bid Period: TEV 0 29-Apr-24 A 13-May-24 A PI - P306 - Bid Period: TEV
P-PI-P306-3000 PI - P306 - Bid Evaluation and Recommendation: TCM; GTC; CBE 0 13-May-24 A 16-May-24 A PI - P306 - Bid Evaluation and Recommendation: TCM; GTC; CBE
Process Plant Shutdown 174 15-Feb-24 A 05-Dec-24 05-Dec-24, Process Plant Shutdown
General 174 15-Feb-24 A 05-Dec-24 05-Dec-24, General
C-SHUTDOWN-1000 February, 2024 Shutdown 0 15-Feb-24 A n
C-SHUTDOWN-1010 March, 2024 Shutdown 0 07-Mar-24 A arch, 2024 Shutdown
C-SHUTDOWN-1020 April, 2024 Long Shutdown 0 19-Apr-24 A 23-Apr-24 A April, 2024 Long Shutdown
C-SHUTDOWN-1030 May, 2024 Shutdown (16h) 0 06-May-24 A May, 2024 Shutdown (16h)
C-SHUTDOWN-1040 Jun, 2024 Shutdown (12h) 0 14-Jun-24* Jun, 2024 Shutdown (12h)
C-SHUTDOWN-1050 Jul, 2024 Shutdown (24h) 0 23-Jul-24* Jul, 2024 Shutdown (24h)
C-3330-PI-1020 3000 Water & Tailings SHUT DOWN coordination 0 01-Sep-24* 3000 Water & Tailings SHUT DOWN coordination
C-SHUTDOWN-1060 Aug, 2024 Shutdown (no maintenance programmed) 0 06-Sep-24 Aug, 2024 Shutdown (no maintenance programmed)
C-SHUTDOWN-1070 Sep, 2024 Shutdown (24h) 0 06-Sep-24* Sep, 2024 Shutdown (24h)
C-SHUTDOWN-1080 Oct, 2024 Shutdown (72h) 21-23 oct 0 21-Oct-24* Oct, 2024 Shutdown (72h) 21-23 oct
C-SHUTDOWN-1090 Nov, 2024 Shutdown (no maintenance programmed) 0 05-Dec-24 Nov, 2024 Shutdown (no maintenance programmed)
C-SHUTDOWN-1100 Dec, 2024 Shutdown (24h) 0 05-Dec-24* Dec, 2024 Shutdown (24h)
2000 - POWER & ELECTRICAL
ELECTRIC 252 15-Jul-24 04-Apr-25 04-Apr-25, 2000 - POWER & ELECTRICAL
2300 - Process Plant Electrical
Electric 252 15-Jul-24 04-Apr-25 04-Apr-25, 2300 - Process Plant Electrical
2310 - Crushing Electrical Room
R 10 21-Mar-25 30-Mar-25 30-Mar-25, 2310 - Crushing Electrical Room
Area Milestones 0 30-Mar-25 30-Mar-25 30-Mar-25, Area Milestones
C-2310-MA-1050 2310 - Crushing Electrical Room - Electrical Complete 0 30-Mar-25 2310 - Crushing Electrical Room - Electrical Complete
C-2310-MA-1000 2310 - Crushing Electrical Room - Complete 0 30-Mar-25 2310 - Crushing Electrical Room - Complete
Electrical & Instrumentation
Instrumentati 10 21-Mar-25 30-Mar-25 30-Mar-25, Electrical & Instrumentation
C-2310-EL-1000 2310 - Crushing Electrical Room - Electrical 5 21-Mar-25 25-Mar-25 2310 - Crushing Electrical Room - Electrical
C-2310-EL-1010 2310 - Crushing Electrical Room - Cable installation 5 21-Mar-25 25-Mar-25 2310 - Crushing Electrical Room - Cable installation
C-2310-EL-1020 2310 - Crushing Electrical Room - MCC bucket modification 5 26-Mar-25 30-Mar-25 2310 - Crushing Electrical Room - MCC bucket modification
2320 - Process & Grinding Electrical
E Room 35 01-Mar-25 04-Apr-25 04-Apr-25, 2320 - Process & Grinding Electrical Room
Area Milestones 0 04-Apr-25 04-Apr-25 04-Apr-25, Area Milestones
C-2320-MA-1050 2320 - Process & Grinding Electrical Room - Electrical Complete 0 04-Apr-25 2320 - Process & Grinding Electrical Room - Electrical Complete
C-2320-MA-1000 2320 - Process & Grinding Electrical Room - Complete 0 04-Apr-25 2320 - Process & Grinding Electrical Room - Complete
Electrical & Instrumentation
Instrumentati 35 01-Mar-25 04-Apr-25 04-Apr-25, Electrical & Instrumentation
C-2320-EL-1000 2320 - Process & Grinding Electrical Room - Electrical 25 01-Mar-25 25-Mar-25 2320 - Process & Grinding Electrical Room - Electrical
C-2320-EL-1030 2320 - Process & Grinding Electrical Room - Cable tray installation 5 01-Mar-25 05-Mar-25 2320 - Process & Grinding Electrical Room - Cable tray installation
C-2320-EL-1010 2320 - Process & Grinding Electrical Room - Cable installation 20 06-Mar-25 25-Mar-25 2320 - Process & Grinding Electrical Room - Cable installation
C-2320-EL-1020 2320 - Process & Grinding Electrical Room - MCC bucket modification 10 26-Mar-25 04-Apr-25 2320 - Process & Grinding Electrical Room - MCC bucket modification
C-2320-EL-1040 2320 - Process & Grinding Electrical Room - MCC new VFD colum lifting 2 26-Mar-25 27-Mar-25 2320 - Process & Grinding Electrical Room - MCC new VFD colum lifting
2330 - CIL Electrical Room 47 17-Feb-25 04-Apr-25 04-Apr-25, 2330 - CIL Electrical Room
Area Milestones 0 04-Apr-25 04-Apr-25 04-Apr-25, Area Milestones
C-2330-MA-1050 2330 - CIL Electrical Room - Electrical Complete 0 04-Apr-25 2330 - CIL Electrical Room - Electrical Complete
C-2330-MA-1000 2330 - CIL Electrical Room - Complete 0 04-Apr-25 2330 - CIL Electrical Room - Complete
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 3 of 7 28-Jun-24 ECFN-3 Master schedule weekly report - for information MF
Actual Level of Effort Critical Remaining Work
TASK filters: so_changes_not_red, so_show_into_report.
Actual Work Milestone
Fruta del Norte 3
Master Schedule Draft
Activity ID Activity Name Remaining Start Finish 2024 2025
Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Electrical & Instrumentation
Instrumentati 47 17-Feb-25 04-Apr-25 04-Apr-25, Electrical & Instrumentation
C-2330-EL-1000 2330 - CIL Electrical Room - Electrical --- To be removed when chk with Pascal 25 17-Feb-25 13-Mar-25 2330 - CIL Electrical Room - Electrical --- To be removed when chk with Pascal
C-2330-EL-1010 2330 - CIL Electrical Room - Electrical - Floor drilling 5 01-Mar-25 05-Mar-25 2330 - CIL Electrical Room - Electrical - Floor drilling
C-2330-EL-1020 2330 - CIL Electrical Room - Electrical - Cable Installation 20 06-Mar-25 25-Mar-25 2330 - CIL Electrical Room - Electrical - Cable Installation
C-2330-EL-1030 2330 - CIL Electrical Room - Electrical - MCC bucket modification 10 26-Mar-25 04-Apr-25 2330 - CIL Electrical Room - Electrical - MCC bucket modification
C-2330-EL-1040 2330 - CIL Electrical Room - Electrical - MCC new VFD colum lifting 2 26-Mar-25 27-Mar-25 2330 - CIL Electrical Room - Electrical - MCC new VFD colum lifting
C-2340-MA-1050 2340 - Ultra-Fine Flotation Cell Electrical Room - Electrical Complete 0 30-Mar-25 2340 - Ultra-Fine Flotation Cell Electrical Room - Electrical Complete
C-2340-MA-1000 2340 - Ultra-Fine Flotation Cell Electrical Room - Complete 0 30-Mar-25 2340 - Ultra-Fine Flotation Cell Electrical Room - Complete
Earthworks 3 15-Jul-24 17-Jul-24 17-Jul-24, Earthworks
C-2340-EW-1000 2340 - Cable Detection and Setout 1 15-Jul-24 15-Jul-24 2340 - Cable Detection and Setout
C-2340-EW-1010 2340 - Ground Preparation 3 15-Jul-24 17-Jul-24 2340 - Ground Preparation
CSA 15 17-Jul-24 31-Jul-24 31-Jul-24, CSA
C-2340-CI-1010 2340 - Mud Slab 1 17-Jul-24 17-Jul-24 2340 - Mud Slab
C-2340-CI-1000 2340 - Rebars Preparation 5 18-Jul-24 22-Jul-24 2340 - Rebars Preparation
C-2340-CI-1020 2340 - Formwork 4 18-Jul-24 21-Jul-24 2340 - Formwork
C-2340-CI-1030 2340 - Concrete Foundation & Base Pour 1 22-Jul-24 22-Jul-24 2340 - Concrete Foundation & Base Pour
C-2340-CI-1040 2340 - Wall Rebars 4 23-Jul-24 26-Jul-24 2340 - Wall Rebars
C-2340-CI-1050 2340 - Wall Formwork 4 27-Jul-24 30-Jul-24 2340 - Wall Formwork
C-2340-CI-1060 2340 - Wall Pour 1 31-Jul-24 31-Jul-24 2340 - Wall Pour
Electrical & Instrumentation
Instrumentati 3 15-Jul-24 17-Jul-24 17-Jul-24, Electrical & Instrumentation
C-2340-EL-1100 2340 - Conduit Installation 1 15-Jul-24 15-Jul-24 2340 - Conduit Installation
C-2340-EL-1110 2340 - Ground Installation 3 15-Jul-24 17-Jul-24 2340 - Ground Installation
Electrical Tie-In 140 30-Oct-24 30-Mar-25 30-Mar-25, Electrical Tie-In
C-2340-EL-1000 TIP 2340-001 2320-SGM-001 - EL 5 30-Oct-24 04-Nov-24 TIP 2340-001 2320-SGM-001 - EL
C-2340-EL-1010 2340 - Ultra Fine Flotation Cell - EL - Electrical Room 30 01-Mar-25 30-Mar-25 2340 - Ultra Fine Flotation Cell - EL - Electrical Room
2350 - Booster Station Electrical
Elec Room 5 25-Oct-24 29-Oct-24 29-Oct-24, 2350 - Booster Station Electrical Room
Area Milestones 0 29-Oct-24 29-Oct-24 29-Oct-24, Area Milestones
C-2350-MA-1050 2350 - Booster Station Electrical Room - Electrical Complete 0 29-Oct-24 2350 - Booster Station Electrical Room - Electrical Complete
C-2350-MA-1000 2350 - Booster Station Electrical Room - Complete 0 29-Oct-24 2350 - Booster Station Electrical Room - Complete
Electrical & Instrumentation
Instrumentati 5 25-Oct-24 29-Oct-24 29-Oct-24, Electrical & Instrumentation
C-2350-EL-1000 2350 - Booster Station Electrical Room - Electrical 5 25-Oct-24 29-Oct-24 2350 - Booster Station Electrical Room - Electrical
2355 - Reclaim Water Electrical
Elect Room 0 14-Aug-24 14-Aug-24 14-Aug-24, 2355 - Reclaim Water Electrical Room
Area Milestones 0 14-Aug-24 14-Aug-24 14-Aug-24, Area Milestones
C-2355-MA-1050 2355 - Reclaim Water Electrical Room - Electrical Complete 0 14-Aug-24 2355 - Reclaim Water Electrical Room - Electrical Complete
C-2355-MA-1000 2355 - Reclaim Water Electrical Room - Complete 0 14-Aug-24 2355 - Reclaim Water Electrical Room - Complete
3000 - WATER & TAILINGS 183 08-Mar-24 A 10-Dec-24 10-Dec-24, 3000 - WATER & TAILINGS
3300 - Portal Area Water Services
Ser 5 15-Oct-24 19-Oct-24 19-Oct-24, 3300 - Portal Area Water Services
3330 - Domestic Water Treatment
Trea Plant (Process Plant) 5 15-Oct-24 19-Oct-24 19-Oct-24, 3330 - Domestic Water Treatment Plant (Process Plant)
Area Milestones 0 19-Oct-24 19-Oct-24 19-Oct-24, Area Milestones
C-3300-MA-1040 3300 - Domestic Water Treatment Plant (Process Plant) - Piping Complete 0 19-Oct-24 3300 - Domestic Water Treatment Plant (Process Plant) - Piping Complete
C-3300-MA-1000 3300 - Domestic Water Treatment Plant (Process Plant) - Complete 0 19-Oct-24 3300 - Domestic Water Treatment Plant (Process Plant) - Complete
C-3620-PI-1040 TIP 3620-003 150-WTR-C02-1298 Primary - PI 11 05-Sep-24 15-Sep-24 TIP 3620-003 150-WTR-C02-1298 Primary - PI
3700 - Reclaim Water 141 11-Mar-24 A 29-Oct-24 29-Oct-24, 3700 - Reclaim Water
3710 - Process Water 60 31-Aug-24 29-Oct-24 29-Oct-24, 3710 - Process Water
Area Milestones 0 29-Oct-24 29-Oct-24 29-Oct-24, Area Milestones
C-3710-MA-1040 3710 - Process Water - Piping Complete 0 29-Oct-24 3710 - Process Water - Piping Complete
C-3710-MA-1030 3710 - Process Water - Mechanical Complete 0 29-Oct-24 3710 - Process Water - Mechanical Complete
C-3710-MA-1000 3710 - Process Water - Complete 0 29-Oct-24 3710 - Process Water - Complete
Mechanical Tie-In 60 31-Aug-24 29-Oct-24 29-Oct-24, Mechanical Tie-In
C-3710-MC-1090 TIP 3710-004 Gland Seal & Cooling Water Filter (3710-FLT-001) Primary - MC 15 31-Aug-24 14-Sep-24 TIP 3710-004 Gland Seal & Cooling Water Filter (3710-FLT-001) Primary - MC
C-3710-MC-1130 TIP 3710-008 Gravity Circuit Water Filter (3710-FLT-002) Primary - MC 15 15-Oct-24 29-Oct-24 TIP 3710-008 Gravity Circuit Water Filter (3710-FLT-002) Primary - MC
C-3710-PI-1070 TIP 3710-004 Gland Seal & Cooling Water Filter (3710-FLT-001) Primary - PI 15 15-Oct-24 29-Oct-24 TIP 3710-004 Gland Seal & Cooling Water Filter (3710-FLT-001) Primary - PI
C-3710-PI-1080 TIP 3710-004 Gland Seal & Cooling Water Filter (3710-FLT-001) Primary - PI 15 15-Oct-24 29-Oct-24 TIP 3710-004 Gland Seal & Cooling Water Filter (3710-FLT-001) Primary - PI
C-3710-PI-1100 TIP 3710-008 Gravity Circuit Water Filter (3710-FLT-002) Primary - PI 15 15-Oct-24 29-Oct-24 TIP 3710-008 Gravity Circuit Water Filter (3710-FLT-002) Primary - PI
C-3710-PI-1110 TIP 3710-008 Gravity Circuit Water Filter (3710-FLT-002) Primary - PI 15 15-Oct-24 29-Oct-24 TIP 3710-008 Gravity Circuit Water Filter (3710-FLT-002) Primary - PI
C-3710-PI-1120 TIP 3710-008 Gravity Circuit Water Filter (3710-FLT-002) Primary - PI 15 15-Oct-24 29-Oct-24 TIP 3710-008 Gravity Circuit Water Filter (3710-FLT-002) Primary - PI
3720 - Gland Seal Water 66 15-Aug-24 19-Oct-24 19-Oct-24, 3720 - Gland Seal Water
Area Milestones 61 19-Aug-24 19-Oct-24 19-Oct-24, Area Milestones
C-3720-MA-1010 3720 - Gland Seal Water - Civil Complete 0 19-Aug-24 3720 - Gland Seal Water - Civil Complete
C-3720-MA-1020 3720 - Gland Seal Water - Steel Structure Complete 0 24-Aug-24 3720 - Gland Seal Water - Steel Structure Complete
C-3720-MA-1030 3720 - Gland Seal Water - Mechanical Complete 0 03-Sep-24 3720 - Gland Seal Water - Mechanical Complete
C-3720-MA-1040 3720 - Gland Seal Water - Piping Complete 0 19-Oct-24 3720 - Gland Seal Water - Piping Complete
C-3720-MA-1000 3720 - Gland Seal Water - Complete 0 19-Oct-24 3720 - Gland Seal Water - Complete
CSA 10 15-Aug-24 24-Aug-24 24-Aug-24, CSA
C-3720-CI-1000 3720 - Gland Seal Water - Civil 5 15-Aug-24 19-Aug-24 3720 - Gland Seal Water - Civil
C-3720-ST-1010 3720 - Gland Seal Water - Structural 5 20-Aug-24 24-Aug-24 3720 - Gland Seal Water - Structural
Mechanical 10 25-Aug-24 03-Sep-24 03-Sep-24, Mechanical
C-3720-MC-1000 3720 - Gland Seal Water - Mechanical 10 25-Aug-24 03-Sep-24 3720 - Gland Seal Water - Mechanical
Pipe Tie-In 5 15-Oct-24 19-Oct-24 19-Oct-24, Pipe Tie-In
C-3720-PI-1140 TIP 3720-001 100-WGS-C02-1062 Primary - PI 5 15-Oct-24 19-Oct-24 TIP 3720-001 100-WGS-C02-1062 Primary - PI
3750 - Reclaim Pipelines 127 11-Mar-24 A 15-Oct-24 15-Oct-24, 3750 - Reclaim Pipelines
Area Milestones 0 15-Oct-24 15-Oct-24 15-Oct-24, Area Milestones
C-3750-MA-1040 3750 - Reclaim Pipelines - Piping Complete 0 15-Oct-24 3750 - Reclaim Pipelines - Piping Complete
C-3750-MA-1000 3750 - Reclaim Pipelines - Complete 0 15-Oct-24 3750 - Reclaim Pipelines - Complete
Piping 55 11-Mar-24 A 04-Aug-24 04-Aug-24, Piping
C-3750-PI-1010 3750 - Reclaim Pipelines - Pipeline - From TSF. 5.8 KM pipeline 18 11-Mar-24 A 28-Jun-24 3750 - Reclaim Pipelines - Pipeline - From TSF. 5.8 KM pipeline
C-3750-PI-1020 3750 - Reclaim Pipelines - Pipeline - From 3710-TNK-001 0.3 KM pipeline 6 05-Jul-24 10-Jul-24 3750 - Reclaim Pipelines - Pipeline - From 3710-TNK-001 0.3 KM pipeline
C-3750-PI-1040 3750 - Reclaim Pipelines - Pipeline - Hydrostatic tests 11 05-Jul-24 15-Jul-24 3750 - Reclaim Pipelines - Pipeline - Hydrostatic tests
C-3750-PI-1030 3750 - Reclaim Pipelines - Pipeline - From Branch 50 m pipeline 11 10-Jul-24 20-Jul-24 3750 - Reclaim Pipelines - Pipeline - From Branch 50 m pipeline
C-3750-PI-4020 3750 - Reclaim Pipelines - Pipeline - Connection to the plant 15 21-Jul-24 04-Aug-24 3750 - Reclaim Pipelines - Pipeline - Connection to the plant
Pipe Tie-In 1 15-Oct-24 15-Oct-24 15-Oct-24, Pipe Tie-In
C-3750-PI-4000 TIP 3750-004 3760-110-WRE-H03-0753-PI 1 15-Oct-24 15-Oct-24 TIP 3750-004 3760-110-WRE-H03-0753-PI
C-3750-PI-4010 TIP 3750-005 3760-355-WRE-H03-1173-PI 1 15-Oct-24 15-Oct-24 TIP 3750-005 3760-355-WRE-H03-1173-PI
3760 - Reclaim Barge (Reclaim
(Recl Pipeline Installation (7 Km)) 127 11-Mar-24 A 15-Oct-24 15-Oct-24, 3760 - Reclaim Barge (Reclaim Pipeline Installation (7 Km))
Area Milestones 62 14-Aug-24 15-Oct-24 15-Oct-24, Area Milestones
C-3760-MA-1020 3760 - Reclaim Barge (Reclaim Pipeline Installation (7 Km)) - Steel Structure 0 14-Aug-24 3760 - Reclaim Barge (Reclaim Pipeline Installation (7 Km)) - Steel Structure Complete
Complete
C-3760-MA-1030 3760 - Reclaim Barge (Reclaim Pipeline Installation (7 Km)) - Mechanical 0 03-Sep-24 3760 - Reclaim Barge (Reclaim Pipeline Installation (7 Km)) - Mechanical Complete
Complete
C-3760-MA-1040 3760 - Reclaim Barge (Reclaim Pipeline Installation (7 Km)) - Piping Complete 0 15-Oct-24 3760 - Reclaim Barge (Reclaim Pipeline Installation (7 Km)) - Piping Complete
C-3760-MA-1000 3760 - Reclaim Barge (Reclaim Pipeline Installation (7 Km)) - Complete 0 15-Oct-24 3760 - Reclaim Barge (Reclaim Pipeline Installation (7 Km)) - Complete
C-3760-PI-3000 C - 3000 - PI - Reclaim Hydrostatic tests **chk 26 20-Jun-24 15-Jul-24 C - 3000 - PI - Reclaim Hydrostatic tests **chk
Pipe Tie-In 1 15-Oct-24 15-Oct-24 15-Oct-24, Pipe Tie-In
C-3760-PI-4020 TIP 3760-001 3760-300-WRE-C02-1727-PI 1 15-Oct-24 15-Oct-24 TIP 3760-001 3760-300-WRE-C02-1727-PI
C-3760-PI-4030 TIP 3760-002 3760-300-WRE-C02-1720-PI 1 15-Oct-24 15-Oct-24 TIP 3760-002 3760-300-WRE-C02-1720-PI
C-3760-PI-4040 TIP 3760-003 3760-300-WRE-C02-1720-PI 1 15-Oct-24 15-Oct-24 TIP 3760-003 3760-300-WRE-C02-1720-PI
3800 - Tailings Storage Facility
Facil (TSF) 183 08-Mar-24 A 10-Dec-24 10-Dec-24, 3800 - Tailings Storage Facility (TSF)
3810 - Tailings Pipelines 130 08-Mar-24 A 19-Oct-24 19-Oct-24, 3810 - Tailings Pipelines
Area Milestones 97 13-Jul-24 19-Oct-24 19-Oct-24, Area Milestones
C-3810-MA-1020 3810 - Tailings Pipelines - Steel Structure Complete 0 13-Jul-24 3810 - Tailings Pipelines - Steel Structure Complete
C-3810-MA-1040 3810 - Tailings Pipelines - Piping Complete 0 06-Aug-24 3810 - Tailings Pipelines - Piping Complete
C-3810-MA-1000 3810 - Tailings Pipelines - Complete 0 06-Aug-24 3810 - Tailings Pipelines - Complete
C-3810-MA-1060 3810 - Tailings Pipelines - Instrumentation Complete 0 19-Oct-24 3810 - Tailings Pipelines - Instrumentation Complete
CSA 16 15-Jun-24 A 13-Jul-24 13-Jul-24, CSA
C-3810--ST-1020 3810 - Tailings Pipelines - ST - Pipe support Adjustment 6 15-Jun-24 A 08-Jul-24 3810 - Tailings Pipelines - ST - Pipe support Adjustment
C-3810-EW-1010 3810 - Tailings Pipelines - CI - Road Excavation and Culvert Installation 16 22-Jun-24 A 13-Jul-24 3810 - Tailings Pipelines - CI - Road Excavation and Culvert Installation
C-3810-PI-4190 C-3810 - PI - Buttfusion and Flenges Connection, Valves Installation 23 28-Jun-24 A 20-Jul-24 C-3810 - PI - Buttfusion and Flenges Connection, Valves Installation
C-3817-MC-3700 3817 - Tailings Booster Station - Mechanical - Slurry Pumps Installation 15 06-Nov-24 20-Nov-24 3817 - Tailings Booster Station - Mechanical - Slurry Pumps Installation
C-3817-MC-4230 TIP 3817-008-M Tailings Feed Pump 4th Stage (3817-PSL-002) -MC 5 05-Dec-24 10-Dec-24 TIP 3817-008-M Tailings Feed Pump 4th Stage (3817-PSL-002) -MC
C-3817-MC-4250 TIP 3817-009-M Tailings Feed Pump 3rd Stage Standby (3817-PSL-003)-MC 5 05-Dec-24 10-Dec-24 TIP 3817-009-M Tailings Feed Pump 3rd Stage Standby (3817-PSL-003)-MC
C-3817-MC-4270 TIP 3817-010-M Tailings Feed Pump 4th Stage Standby (3817-PSL-004)-MC 5 05-Dec-24 10-Dec-24 TIP 3817-010-M Tailings Feed Pump 4th Stage Standby (3817-PSL-004)-MC
C-3817-EL-4220 TIP 3817-008-E Tailings Feed Pump 4th Stage (3817-PSL-002) -EL 5 05-Dec-24 10-Dec-24 TIP 3817-008-E Tailings Feed Pump 4th Stage (3817-PSL-002) -EL
C-3817-EL-4240 TIP 3817-009-E Tailings Feed Pump 3rd Stage Standby (3817-PSL-003)-EL 5 05-Dec-24 10-Dec-24 TIP 3817-009-E Tailings Feed Pump 3rd Stage Standby (3817-PSL-003)-EL
C-3817-EL-4260 TIP 3817-010-E Tailings Feed Pump 4th Stage Standby (3817-PSL-004)-EL 5 05-Dec-24 10-Dec-24 TIP 3817-010-E Tailings Feed Pump 4th Stage Standby (3817-PSL-004)-EL
6000 - PROCESS PLANT 264 01-Jun-24 A 13-Mar-25 13-Mar-25, 6000 - PROCESS PLANT
6100 - Crushing and Ore Handling
Han 138 30-Jul-24 15-Dec-24 15-Dec-24, 6100 - Crushing and Ore Handling
6110 - Primary Crusher 5 01-Nov-24 05-Nov-24 05-Nov-24, 6110 - Primary Crusher
Area Milestones 0 05-Nov-24 05-Nov-24 05-Nov-24, Area Milestones
C-6110-MA-1030 6110 - Crushing and Ore Handling - Mechanical Complete 0 05-Nov-24 6110 - Crushing and Ore Handling - Mechanical Complete
C-6110-MA-1000 6110 - Crushing and Ore Handling - Complete 0 05-Nov-24 6110 - Crushing and Ore Handling - Complete
Mechanical 5 01-Nov-24 05-Nov-24 05-Nov-24, Mechanical
C-6110-MC-1000 6110 - Crushing and Ore Handling - Mechanical 5 01-Nov-24* 05-Nov-24 6110 - Crushing and Ore Handling - Mechanical
Mechanical Tie-In 1 05-Nov-24 05-Nov-24 05-Nov-24, Mechanical Tie-In
C-6110-MC-1150 TIP 6110-001 ROM Apron Feeder (6110-FEA-001) Primary - MC 1 05-Nov-24 05-Nov-24 TIP 6110-001 ROM Apron Feeder (6110-FEA-001) Primary - MC
C-6210-MC-1200 TIP 6210-002 Sag Mill Discharge Pump Box (6210-PPB-001) Primary - MC 2 13-Sep-24 14-Sep-24 TIP 6210-002 Sag Mill Discharge Pump Box (6210-PPB-001) Primary - MC
6220 - Secondary Grinding (mechanical) 100 05-Sep-24 14-Dec-24 14-Dec-24, 6220 - Secondary Grinding (mechanical)
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 4 of 7 28-Jun-24 ECFN-3 Master schedule weekly report - for information MF
Actual Level of Effort Critical Remaining Work
TASK filters: so_changes_not_red, so_show_into_report.
Actual Work Milestone
Fruta del Norte 3
Master Schedule Draft
Activity ID Activity Name Remaining Start Finish 2024 2025
Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Area Milestones 90 14-Sep-24 14-Dec-24 14-Dec-24, Area Milestones
C-6220-MA-1030 6220 - Secondary Grinding - Mechanical Complete 0 14-Sep-24 6220 - Secondary Grinding - Mechanical Complete
C-6220-MA-1040 6220 - Secondary Grinding - Piping Complete 0 15-Oct-24 6220 - Secondary Grinding - Piping Complete
C-6220-MA-1050 6220 - Secondary Grinding - Electrical Complete 0 14-Dec-24 6220 - Secondary Grinding - Electrical Complete
C-6220-MA-1000 6220 - Secondary Grinding - Complete 0 14-Dec-24 6220 - Secondary Grinding - Complete
C-6220-MA-1060 6220 - Secondary Grinding - Instrumentation Complete 0 14-Dec-24 6220 - Secondary Grinding - Instrumentation Complete
Electrical & Instrumentation
Instrumentati 100 05-Sep-24 14-Dec-24 14-Dec-24, Electrical & Instrumentation
C-6220-IN-1000 6220 - Secondary Grinding - Instrumentation 10 05-Sep-24 14-Sep-24 6220 - Secondary Grinding - Instrumentation
C-6220-IN-1010 6220 - Secondary Grinding - Cyclone Instrumentation 10 02-Dec-24 12-Dec-24 6220 - Secondary Grinding - Cyclone Instrumentation
C-6220-IN-1020 6220 - Secondary Grinding - Valves - Instrumentation 10 04-Dec-24 14-Dec-24 6220 - Secondary Grinding - Valves - Instrumentation
Mechanical Tie-In 2 13-Sep-24 14-Sep-24 14-Sep-24, Mechanical Tie-In
C-6220-MC-1210 TIP 6220-001 Ball Mill Discharge Launder (6220-LAU-001) Primary - MC 2 13-Sep-24 14-Sep-24 TIP 6220-001 Ball Mill Discharge Launder (6220-LAU-001) Primary - MC
C-6230-IN-1010 6230 - Gravity Concentration - Valves - Instrumentation 10 20-Jan-25 30-Jan-25 6230 - Gravity Concentration - Valves - Instrumentation
Mechanical Tie-In 2 28-Aug-24 30-Aug-24 30-Aug-24, Mechanical Tie-In
C-6230-MC-1240 TIP 6230-001 Safety Screen Distribution Box (6230-DIB-004) Primary - MC 2 28-Aug-24 30-Aug-24 TIP 6230-001 Safety Screen Distribution Box (6230-DIB-004) Primary - MC
C-6230-MC-1300 TIP 6230-007 Cyclone Feed Pump Box (6230-PPB-001) Primary - MC 1 29-Aug-24 30-Aug-24 TIP 6230-007 Cyclone Feed Pump Box (6230-PPB-001) Primary - MC
C-6230-PI-1260 TIP 6230-003 250-SPR-L03-0169 Primary - PI 2 15-Oct-24 16-Oct-24 TIP 6230-003 250-SPR-L03-0169 Primary - PI
C-6230-PI-1270 TIP 6230-004 250-SPR-L03-0221 Primary - PI 2 15-Oct-24 16-Oct-24 TIP 6230-004 250-SPR-L03-0221 Primary - PI
C-6230-PI-1280 TIP 6230-005 Cyclone Feed Pump #1 (6230-PSL-001) Primary - PI 5 15-Oct-24 19-Oct-24 TIP 6230-005 Cyclone Feed Pump #1 (6230-PSL-001) Primary - PI
C-6230-PI-1290 TIP 6230-006 Cyclone Feed Pump #2 (6230-PSL-002) Primary - PI 5 15-Oct-24 19-Oct-24 TIP 6230-006 Cyclone Feed Pump #2 (6230-PSL-002) Primary - PI
C-6230-PI-1320 TIP 6230-013 150-WTR-C02-1190 Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6230-013 150-WTR-C02-1190 Primary - PI
Structural Tie-In 5 20-Aug-24 25-Aug-24 25-Aug-24, Structural Tie-In
C-6230-ST-1310 TIP 6230-008 400-SSP-MHX-2503 Primary - ST 5 20-Aug-24 25-Aug-24 TIP 6230-008 400-SSP-MHX-2503 Primary - ST
C-6230-ST-1330 TIP 6230-015 Not Applicable Primary - ST 4 20-Aug-24 24-Aug-24 TIP 6230-015 Not Applicable Primary - ST
6260 - Intensive Leach 55 15-Oct-24 09-Dec-24 09-Dec-24, 6260 - Intensive Leach
Area Milestones 54 15-Oct-24 09-Dec-24 09-Dec-24, Area Milestones
C-6260-MA-1040 6260 - Intensive Leach - Piping Complete 0 15-Oct-24 6260 - Intensive Leach - Piping Complete
C-6260-MA-1000 6260 - Intensive Leach - Complete 0 09-Dec-24 6260 - Intensive Leach - Complete
C-6260-MA-1060 6260 - Intensive Leach - Instrumentation Complete 0 09-Dec-24 6260 - Intensive Leach - Instrumentation Complete
Electrical & Instrumentation
Instrumentati 5 04-Dec-24 09-Dec-24 09-Dec-24, Electrical & Instrumentation
C-6260-IN-1000 6260 - Valves - Instrumentation 5 04-Dec-24 09-Dec-24 6260 - Valves - Instrumentation
Pipe Tie-In 1 15-Oct-24 15-Oct-24 15-Oct-24, Pipe Tie-In
C-6260-PI-1340 TIP 6260-002 ILR Area Sump Pump (6260-PSU-001) Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6260-002 ILR Area Sump Pump (6260-PSU-001) Primary - PI
6300 - Flotation & Regrinding 251 01-Jun-24 A 01-Mar-25 01-Mar-25, 6300 - Flotation & Regrinding
6310 - Flotation Circuit 230 26-Jun-24 A 07-Feb-25 07-Feb-25, 6310 - Flotation Circuit
Area Milestones 199 11-Jul-24 07-Feb-25 07-Feb-25, Area Milestones
C-6310-MA-1010 6310 - Flotation Circuit - Civil Complete 0 11-Jul-24 6310 - Flotation Circuit - Civil Complete
C-6310-MA-1020 6310 - Flotation Circuit - Steel Structure Complete 0 14-Sep-24 6310 - Flotation Circuit - Steel Structure Complete
C-6310-MA-1030 6310 - Flotation Circuit - Mechanical Complete 0 23-Jan-25 6310 - Flotation Circuit - Mechanical Complete
C-6310-MA-1040 6310 - Flotation Circuit - Piping Complete 0 28-Jan-25 6310 - Flotation Circuit - Piping Complete
C-6310-MA-1000 6310 - Flotation Circuit - Complete 0 07-Feb-25 6310 - Flotation Circuit - Complete
C-6310-MA-1060 6310 - Flotation Circuit - Instrumentation Complete 0 07-Feb-25 6310 - Flotation Circuit - Instrumentation Complete
Structure 96 28-Jun-24 A 14-Sep-24 14-Sep-24, Structure
C-6310-ST-1450 6310 - Flotation Circuit - Jonction Box Support Installation at Rougher Cells 16 28-Jun-24 A 30-Jun-24 6310 - Flotation Circuit - Jonction Box Support Installation at Rougher Cells
C-6310-ST-1100 6310 - Flotation Circuit - Support 6310-FLC-002 Rougher cell #8 23 28-Jun-24 A 03-Jul-24 6310 - Flotation Circuit - Support 6310-FLC-002 Rougher cell #8 (6310-GT-0192)
(6310-GT-0192)
C-6310-ST-1500 6310 - Flotation Circuit - Jonction Box Support Installation at 1st Cleaner Cells 3 30-Jun-24 02-Jul-24 6310 - Flotation Circuit - Jonction Box Support Installation at 1st Cleaner Cells
C-6310-ST-1150 6310 - Flotation Circuit - Support 6310-FLC-004 Rougher cell #10 6 01-Jul-24* 06-Jul-24 6310 - Flotation Circuit - Support 6310-FLC-004 Rougher cell #10 (6310-GT-0194)
(6310-GT-0194)
C-6310-ST-1550 6310 - Flotation Circuit - Jonction Box Support Installation at Scavenger 3 02-Jul-24 04-Jul-24 6310 - Flotation Circuit - Jonction Box Support Installation at Scavenger Flotation Cells
Flotation Cells
C-6310-ST-1200 6310 - Flotation Circuit - Support 6310-FLC-007 1ST Cleaner Cell #1 6 04-Jul-24 09-Jul-24 6310 - Flotation Circuit - Support 6310-FLC-007 1ST Cleaner Cell #1 (6310-GT-0291)
(6310-GT-0291)
C-6310-ST-1250 6310 - Flotation Circuit - Support 6310-FLC-009 1ST Cleaner Cell #3 6 07-Jul-24 12-Jul-24 6310 - Flotation Circuit - Support 6310-FLC-009 1ST Cleaner Cell #3 (6310-GT-0293)
(6310-GT-0293)
C-6310-ST-1300 6310 - Flotation Circuit - Support 6310-FLC-011 1ST Cleaner Cell #5 6 10-Jul-24 15-Jul-24 6310 - Flotation Circuit - Support 6310-FLC-011 1ST Cleaner Cell #5 (6310-GT-0295)
(6310-GT-0295)
C-6310-ST-1350 6310 - Flotation Circuit - Support 6310-FLC-013 Scavenger Cell # 2 6 13-Jul-24 18-Jul-24 6310 - Flotation Circuit - Support 6310-FLC-013 Scavenger Cell # 2 (6310-GT-0392)
(6310-GT-0392)
C-6310-ST-1400 6310 - Flotation Circuit - Support 6310-FLC-015 Scavenger Cell # 4 6 16-Jul-24 21-Jul-24 6310 - Flotation Circuit - Support 6310-FLC-015 Scavenger Cell # 4 (6310-GT-0394)
(6310-GT-0394)
C-6310-ST-1600 6310 - Flotation Circuit - Camera Box Installation 15 31-Aug-24 14-Sep-24 6310 - Flotation Circuit - Camera Box Installation
Mechanical 20 04-Jan-25 23-Jan-25 23-Jan-25, Mechanical
C-6310-MC-1000 6310 - Flotation Circuit - Mechanical 20 04-Jan-25 23-Jan-25 6310 - Flotation Circuit - Mechanical
Piping 5 24-Jan-25 28-Jan-25 28-Jan-25, Piping
C-6310-PI-1000 6310 - Flotation Circuit - Piping 5 24-Jan-25 28-Jan-25 6310 - Flotation Circuit - Piping
Electrical & Instrumentation
Instrumentati 226 28-Jun-24 A 07-Feb-25 07-Feb-25, Electrical & Instrumentation
C-6310-IN-1100 6310 - Flotation Circuit - Cable tray Installation 25 28-Jun-24 A 09-Jul-24 6310 - Flotation Circuit - Cable tray Installation
C-6310-IN-1150 6310 - Flotation Circuit - Power Cable pulling and Junction Connections 7 09-Jul-24 15-Jul-24 6310 - Flotation Circuit - Power Cable pulling and Junction Connections
C-6310-IN-1200 6310 - Flotation Circuit - Communication Cable Pulling and junction 7 15-Jul-24 21-Jul-24 6310 - Flotation Circuit - Communication Cable Pulling and junction Connections
Connections
C-6310-IN-1300 6310 - Flotation Circuit - TV Installation 1 15-Jul-24 15-Jul-24 6310 - Flotation Circuit - TV Installation
C-6310-IN-1250 6310 - Flotation Circuit - Breaker 20 AMP Installation 2320-PDS-0008 (THIS IS 1 22-Jul-24 22-Jul-24 6310 - Flotation Circuit - Breaker 20 AMP Installation 2320-PDS-0008 (THIS IS THE TIE IN)
THE TIE IN)
C-6310-IN-1020 6310 - Flotation Circuit - Valves - Instrumentation 10 29-Jan-25 07-Feb-25 6310 - Flotation Circuit - Valves - Instrumentation
Mechanical Tie-In 5 04-Jan-25 08-Jan-25 08-Jan-25, Mechanical Tie-In
C-6310-MC-1350 TIP 6310-001 Rougher Conditioning Tank (6310-TNK-001) Primary - MC 1 04-Jan-25 04-Jan-25 TIP 6310-001 Rougher Conditioning Tank (6310-TNK-001) Primary - MC
C-6310-MC-1370 TIP 6310-003 2nd Cleaner Concentrate Pump (6310-PSL-008) Primary - MC 1 04-Jan-25 04-Jan-25 TIP 6310-003 2nd Cleaner Concentrate Pump (6310-PSL-008) Primary - MC
C-6310-MC-1390 TIP 6310-005 Rougher Concentrate Transfer Feed Pumps (6310-PSL-003) 1 04-Jan-25 04-Jan-25 TIP 6310-005 Rougher Concentrate Transfer Feed Pumps (6310-PSL-003) Primary - MC
Primary - MC
C-6310-MC-1400 TIP 6310-006 Rougher Concentrate Transfer Feed Pumps (6310-PSL-004) 1 04-Jan-25 04-Jan-25 TIP 6310-006 Rougher Concentrate Transfer Feed Pumps (6310-PSL-004) Primary - MC
Primary - MC
C-6310-MC-1460 TIP 6310-012 3rd Cleaner Concentrate Pump (6310-PSL-012) - MC 5 04-Jan-25 08-Jan-25 TIP 6310-012 3rd Cleaner Concentrate Pump (6310-PSL-012) - MC
C-6310-MC-1570 TIP 6310-026 1st Cleaner Concentrate Pump (6310-PSL-006) Primary - MC 1 04-Jan-25 04-Jan-25 TIP 6310-026 1st Cleaner Concentrate Pump (6310-PSL-006) Primary - MC
C-6310-PI-1410 TIP 6310-007 3rd Cleaner Concentrate Launder (6310-LAU-005) Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6310-007 3rd Cleaner Concentrate Launder (6310-LAU-005) Primary - PI
C-6310-PI-1420 TIP 6310-008 3rd Cleaner Concentrate Launder (6310-LAU-005) Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6310-008 3rd Cleaner Concentrate Launder (6310-LAU-005) Primary - PI
C-6310-PI-1430 TIP 6310-009 400-SPR-L03-2361 Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6310-009 400-SPR-L03-2361 Primary - PI
C-6310-PI-1440 TIP 6310-010 Rougher Tailings Transfer Pumps (6310-PSL-001) - PI 5 15-Oct-24 19-Oct-24 TIP 6310-010 Rougher Tailings Transfer Pumps (6310-PSL-001) - PI
C-6310-PI-1450 TIP 6310-011 Rougher Tailings Transfer Pumps (6310-PSL-002) - PI 5 15-Oct-24 19-Oct-24 TIP 6310-011 Rougher Tailings Transfer Pumps (6310-PSL-002) - PI
C-6310-PI-1470 TIP 6310-014 2nd Cleaner Concentrate Pump (6310-PSL-008) Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6310-014 2nd Cleaner Concentrate Pump (6310-PSL-008) Primary - PI
C-6310-PI-1480 TIP 6310-015 Rougher Cell #7 (6310-FLC-001) Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6310-015 Rougher Cell #7 (6310-FLC-001) Primary - PI
C-6310-PI-1490 TIP 6310-016 1st Cleaner Concentrate Pump (6310-PSL-006) Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6310-016 1st Cleaner Concentrate Pump (6310-PSL-006) Primary - PI
C-6310-PI-1500 TIP 6310-017 1st Cleaner Concentrate Pump (6310-PSL-005) Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6310-017 1st Cleaner Concentrate Pump (6310-PSL-005) Primary - PI
C-6310-PI-1510 TIP 6310-018 150-SPR-L03-1724 Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6310-018 150-SPR-L03-1724 Primary - PI
C-6310-PI-1520 TIP 6310-019 1st Cleaners Conditioning Tank (6310-TNK-002) Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6310-019 1st Cleaners Conditioning Tank (6310-TNK-002) Primary - PI
C-6310-PI-1530 TIP 6310-020 Rougher Cell #7 (6310-FLC-001) - PI 5 15-Oct-24 19-Oct-24 TIP 6310-020 Rougher Cell #7 (6310-FLC-001) - PI
C-6310-PI-1540 TIP 6310-021 150-SPR-L03-1724 Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6310-021 150-SPR-L03-1724 Primary - PI
C-6310-PI-1550 TIP 6310-022 500-SPR-L03-1495 Primary - PI 5 15-Oct-24 19-Oct-24 TIP 6310-022 500-SPR-L03-1495 Primary - PI
C-6310-PI-1560 TIP 6310-023 Rougher Cells Feed Distribution Box (6310-DIB-005) Primary - 1 15-Oct-24 15-Oct-24 TIP 6310-023 Rougher Cells Feed Distribution Box (6310-DIB-005) Primary - PI
PI
Instrumentation Tie-In 26 15-Sep-24 10-Oct-24 10-Oct-24, Instrumentation Tie-In
C-6310-IN-1580 TIP 6310-027 Rougher Cell #7 (6310-FLC-001) - IN 1 15-Sep-24 15-Sep-24 TIP 6310-027 Rougher Cell #7 (6310-FLC-001) - IN
C-6310-IN-1590 TIP 6310-028 Rougher Cell #8 (6310-FLC-002) - IN 1 16-Sep-24 16-Sep-24 TIP 6310-028 Rougher Cell #8 (6310-FLC-002) - IN
C-6310-IN-1600 TIP 6310-029 Rougher Cell #9 (6310-FLC-003) - IN 1 17-Sep-24 17-Sep-24 TIP 6310-029 Rougher Cell #9 (6310-FLC-003) - IN
C-6310-IN-1610 TIP 6310-030 Rougher Cell #10 (6310-FLC-004) - IN 1 18-Sep-24 18-Sep-24 TIP 6310-030 Rougher Cell #10 (6310-FLC-004) - IN
C-6310-IN-1620 TIP 6310-031 Rougher Cell #11 (6310-FLC-005) - IN 1 19-Sep-24 19-Sep-24 TIP 6310-031 Rougher Cell #11 (6310-FLC-005) - IN
C-6310-IN-1630 TIP 6310-032 Rougher Cell #12 (6310-FLC-006) - IN 1 20-Sep-24 20-Sep-24 TIP 6310-032 Rougher Cell #12 (6310-FLC-006) - IN
C-6310-IN-1640 TIP 6310-033 1st Cleaner Cell #1 (6310-FLC-007) - IN 1 21-Sep-24 21-Sep-24 TIP 6310-033 1st Cleaner Cell #1 (6310-FLC-007) - IN
C-6310-IN-1650 TIP 6310-034 1st Cleaner Cell #2 (6310-FLC-008) - IN 1 22-Sep-24 22-Sep-24 TIP 6310-034 1st Cleaner Cell #2 (6310-FLC-008) - IN
C-6310-IN-1660 TIP 6310-035 1st Cleaner Cell #3 (6310-FLC-009) - IN 1 23-Sep-24 23-Sep-24 TIP 6310-035 1st Cleaner Cell #3 (6310-FLC-009) - IN
C-6310-IN-1670 TIP 6310-036 1st Cleaner Cell #4 (6310-FLC-010) - IN 1 24-Sep-24 24-Sep-24 TIP 6310-036 1st Cleaner Cell #4 (6310-FLC-010) - IN
C-6310-IN-1680 TIP 6310-037 1st Cleaner Cell #5 (6310-FLC-011) - IN 1 25-Sep-24 25-Sep-24 TIP 6310-037 1st Cleaner Cell #5 (6310-FLC-011) - IN
C-6310-IN-1690 TIP 6310-038 Scavenger Flotation Cell #1 (6310-FLC-012) - IN 1 26-Sep-24 26-Sep-24 TIP 6310-038 Scavenger Flotation Cell #1 (6310-FLC-012) - IN
C-6310-IN-1700 TIP 6310-039 Scavenger Flotation Cell #2 (6310-FLC-013) - IN 1 27-Sep-24 27-Sep-24 TIP 6310-039 Scavenger Flotation Cell #2 (6310-FLC-013) - IN
C-6310-IN-1710 TIP 6310-040 Scavenger Flotation Cell #2 (6310-FLC-014) - IN 1 28-Sep-24 28-Sep-24 TIP 6310-040 Scavenger Flotation Cell #2 (6310-FLC-014) - IN
C-6310-IN-1720 TIP 6310-041 Scavenger Flotation Cell #4 (6310-FLC-015) - IN 1 29-Sep-24 29-Sep-24 TIP 6310-041 Scavenger Flotation Cell #4 (6310-FLC-015) - IN
C-6310-IN-1730 TIP 6310-042 2nd Cleaner Cell #1 (6310-FLC-016) - IN 1 30-Sep-24 30-Sep-24 TIP 6310-042 2nd Cleaner Cell #1 (6310-FLC-016) - IN
C-6310-IN-1740 TIP 6310-043 2nd Cleaner Cell #2 (6310-FLC-017) - IN 1 01-Oct-24 01-Oct-24 TIP 6310-043 2nd Cleaner Cell #2 (6310-FLC-017) - IN
C-6310-IN-1750 TIP 6310-044 2nd Cleaner Cell #3 (6310-FLC-018) - IN 1 02-Oct-24 02-Oct-24 TIP 6310-044 2nd Cleaner Cell #3 (6310-FLC-018) - IN
C-6310-IN-1760 TIP 6310-045 3rd Cleaner Cell #1 (6310-FLC-019) - IN 1 03-Oct-24 03-Oct-24 TIP 6310-045 3rd Cleaner Cell #1 (6310-FLC-019) - IN
C-6310-IN-1770 TIP 6310-046 3rd Cleaner Cell #2 (6310-FLC-020) - IN 1 04-Oct-24 04-Oct-24 TIP 6310-046 3rd Cleaner Cell #2 (6310-FLC-020) - IN
C-6310-IN-1780 TIP 6310-047 Rougher Cell #1 (6310-FLC-021) - IN 1 05-Oct-24 05-Oct-24 TIP 6310-047 Rougher Cell #1 (6310-FLC-021) - IN
C-6310-IN-1790 TIP 6310-048 Rougher Cell #2 (6310-FLC-022) - IN 1 06-Oct-24 06-Oct-24 TIP 6310-048 Rougher Cell #2 (6310-FLC-022) - IN
C-6310-IN-1800 TIP 6310-049 Rougher Cell #3 (6310-FLC-023) - IN 1 07-Oct-24 07-Oct-24 TIP 6310-049 Rougher Cell #3 (6310-FLC-023) - IN
C-6310-IN-1810 TIP 6310-050 Rougher Cell #4 (6310-FLC-024) - IN 1 08-Oct-24 08-Oct-24 TIP 6310-050 Rougher Cell #4 (6310-FLC-024) - IN
C-6310-IN-1820 TIP 6310-051 Rougher Cell #5 (6310-FLC-025) - IN 1 09-Oct-24 09-Oct-24 TIP 6310-051 Rougher Cell #5 (6310-FLC-025) - IN
C-6310-IN-1830 TIP 6310-052 Rougher Cell #6 (6310-FLC-026) - IN 1 10-Oct-24 10-Oct-24 TIP 6310-052 Rougher Cell #6 (6310-FLC-026) - IN
Courier System 53 28-Jun-24 A 02-Aug-24 02-Aug-24, Courier System
Structure 49 28-Jun-24 A 29-Jul-24 29-Jul-24, Structure
C-6310-ST-1700 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-2415 support 20 28-Jun-24 A 30-Jun-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-2415 support
C-6310-ST-1710 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1531 support 3 01-Jul-24 03-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1531 support
C-6310-ST-1720 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1555 support 3 02-Jul-24 04-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1555 support
C-6310-ST-1730 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1533 support 3 03-Jul-24 05-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1533 support
C-6310-ST-1740 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1333 support 3 04-Jul-24 06-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1333 support
C-6310-ST-1750 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1337 support 3 05-Jul-24 07-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1337 support
C-6310-ST-1760 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1529 support 3 06-Jul-24 08-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1529 support
C-6310-ST-1770 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H01-1525 support 3 07-Jul-24 09-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H01-1525 support
C-6310-ST-1790 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1530 support 3 09-Jul-24 11-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1530 support
C-6310-ST-1800 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1360 support 3 10-Jul-24 12-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1360 support
C-6310-ST-1810 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1527 support 3 11-Jul-24 13-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1527 support
C-6310-ST-1820 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1362 support 3 12-Jul-24 14-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1362 support
C-6310-ST-1830 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1553 support 3 13-Jul-24 15-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1553 support
C-6310-ST-1840 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1526 support 3 14-Jul-24 16-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1526 support
C-6310-ST-1850 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1361 support 3 15-Jul-24 17-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1361 support
C-6310-ST-1860 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1556 support 3 16-Jul-24 18-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1556 support
C-6310-ST-1870 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1532 support 3 17-Jul-24 19-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1532 support
C-6310-ST-1880 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1363 support 3 18-Jul-24 20-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1363 support
C-6310-ST-1890 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1554 support 3 19-Jul-24 21-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1554 support
C-6310-ST-1900 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1528 support 3 20-Jul-24 22-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1528 support
C-6310-ST-1910 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1542 support 3 21-Jul-24 23-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1542 support
C-6310-ST-1920 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1543 support 3 22-Jul-24 24-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1543 support
C-6310-ST-1930 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1534 support 3 23-Jul-24 25-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1534 support
C-6310-ST-1940 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1564 support 3 24-Jul-24 26-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1564 support
C-6310-ST-1950 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1557 support 3 25-Jul-24 27-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1557 support
C-6310-ST-1960 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1535 support 3 26-Jul-24 28-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1535 support
C-6310-ST-1970 6311 - Flotation Circuit - Online Assay Analyser LINE 110-SPR-H03-1536 3 27-Jul-24 29-Jul-24 6311 - Flotation Circuit - Online Assay Analyser LINE 110-SPR-H03-1536 support
support
Piping 32 02-Jul-24 02-Aug-24 02-Aug-24, Piping
C-6310-PI-1700 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-2415 3 02-Jul-24 04-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-2415
C-6310-PI-1710 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1531 3 05-Jul-24 07-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1531
C-6310-PI-1720 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1555 3 06-Jul-24 08-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1555
C-6310-PI-1730 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1533 3 07-Jul-24 09-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1533
C-6310-PI-1740 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1333 3 08-Jul-24 10-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1333
C-6310-PI-1750 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1337 3 09-Jul-24 11-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1337
C-6310-PI-1760 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1529 3 10-Jul-24 12-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1529
C-6310-PI-1780 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1525 3 12-Jul-24 14-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1525
C-6310-PI-1790 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1530 3 13-Jul-24 15-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1530
C-6310-PI-1800 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1360 3 14-Jul-24 16-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1360
C-6310-PI-1810 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1527 3 15-Jul-24 17-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1527
C-6310-PI-1820 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1362 3 16-Jul-24 18-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1362
C-6310-PI-1830 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1553 3 17-Jul-24 19-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1553
C-6310-PI-1840 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1526 3 18-Jul-24 20-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1526
C-6310-PI-1850 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1361 3 19-Jul-24 21-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1361
C-6310-PI-1860 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1556 3 20-Jul-24 22-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1556
C-6310-PI-1870 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1532 3 21-Jul-24 23-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1532
C-6310-PI-1880 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1363 3 22-Jul-24 24-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1363
C-6310-PI-1890 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1554 3 23-Jul-24 25-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1554
C-6310-PI-1900 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1528 3 24-Jul-24 26-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1528
C-6310-PI-1910 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1542 3 25-Jul-24 27-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1542
C-6310-PI-1920 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1542 3 26-Jul-24 28-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1542
C-6310-PI-1930 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1534 3 27-Jul-24 29-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1534
C-6310-PI-1940 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1564 3 28-Jul-24 30-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H03-1564
C-6310-PI-1950 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1557 3 29-Jul-24 31-Jul-24 6310 - Flotation Circuit - Online Assay Analyser LINE 50-SPR-H03-1557
C-6310-PI-1960 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1535 3 30-Jul-24 01-Aug-24 6310 - Flotation Circuit - Online Assay Analyser LINE 90-SPR-H01-1535
C-6310-PI-1970 6311 - Flotation Circuit - Online Assay Analyser LINE 110-SPR-H03-1536 3 31-Jul-24 02-Aug-24 6311 - Flotation Circuit - Online Assay Analyser LINE 110-SPR-H03-1536
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 5 of 7 28-Jun-24 ECFN-3 Master schedule weekly report - for information MF
Actual Level of Effort Critical Remaining Work
TASK filters: so_changes_not_red, so_show_into_report.
Actual Work Milestone
Fruta del Norte 3
Master Schedule Draft
Activity ID Activity Name Remaining Start Finish 2024 2025
Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
6320 - Regrinding 149 17-Aug-24 25-Jan-25 25-Jan-25, 6320 - Regrinding
Area Milestones 144 21-Aug-24 25-Jan-25 25-Jan-25, Area Milestones
C-6320-MA-1010 6320 - Regrinding - Civil Complete 0 21-Aug-24 6320 - Regrinding - Civil Complete
C-6320-MA-1020 6320 - Regrinding - Steel Structure Complete 0 31-Aug-24 6320 - Regrinding - Steel Structure Complete
C-6320-MA-1040 6320 - Regrinding - Piping Complete 0 13-Jan-25 6320 - Regrinding - Piping Complete
C-6320-MA-1030 6320 - Regrinding - Mechanical Complete 0 18-Jan-25 6320 - Regrinding - Mechanical Complete
C-6320-MA-1000 6320 - Regrinding - Complete 0 25-Jan-25 6320 - Regrinding - Complete
C-6320-MA-1060 6320 - Regrinding - Instrumentation Complete 0 25-Jan-25 6320 - Regrinding - Instrumentation Complete
Civil 5 17-Aug-24 21-Aug-24 21-Aug-24, Civil
C-6320-CI-1000 6320 - Regrinding - Civil 5 17-Aug-24 21-Aug-24 6320 - Regrinding - Civil
Structure 5 22-Aug-24 26-Aug-24 26-Aug-24, Structure
C-6320-ST-1000 6320 - Regrinding - Structure 5 22-Aug-24 26-Aug-24 6320 - Regrinding - Structure
Mechanical 15 04-Jan-25 18-Jan-25 18-Jan-25, Mechanical
C-6320-MC-1000 6320 - Regrinding - Mechanical 15 04-Jan-25 18-Jan-25 6320 - Regrinding - Mechanical
Piping 10 04-Jan-25 13-Jan-25 13-Jan-25, Piping
C-6320-PI-1000 6320 - Regrinding - Piping 10 04-Jan-25 13-Jan-25 6320 - Regrinding - Piping
Electrical & Instrumentation
Instrumentati 5 20-Jan-25 25-Jan-25 25-Jan-25, Electrical & Instrumentation
C-6320-IN-1000 6320 - Regrinding - Instrument 5 20-Jan-25 25-Jan-25 6320 - Regrinding - Instrument
C-6320-IN-1020 6320 - Regrinding - Valves - Instrumentation 5 20-Jan-25 25-Jan-25 6320 - Regrinding - Valves - Instrumentation
Mechanical Tie-In 5 04-Jan-25 08-Jan-25 08-Jan-25, Mechanical Tie-In
C-6320-MC-1840 TIP 6320-001 Regrind Mill Feed Pump Box (6320-PPB-001) Primary - MC 1 04-Jan-25 04-Jan-25 TIP 6320-001 Regrind Mill Feed Pump Box (6320-PPB-001) Primary - MC
C-6320-MC-1850 TIP 6320-002 Regrind Mill Feed Pump #1 (6320-PSL-001) Primary - MC 1 04-Jan-25 04-Jan-25 TIP 6320-002 Regrind Mill Feed Pump #1 (6320-PSL-001) Primary - MC
C-6320-MC-1860 TIP 6320-003 Regrind Mill Feed Pump #2 (6320-PSL-002) Primary - MC 1 04-Jan-25 04-Jan-25 TIP 6320-003 Regrind Mill Feed Pump #2 (6320-PSL-002) Primary - MC
C-6320-MC-1870 TIP 6320-004 Scavenger Tails Pump (6320-PSL-006) Primary - MC 1 04-Jan-25 04-Jan-25 TIP 6320-004 Scavenger Tails Pump (6320-PSL-006) Primary - MC
C-6320-MC-1880 TIP 6320-005 Scavenger Tails Pump (6320-PSL-005) Primary - MC 1 04-Jan-25 04-Jan-25 TIP 6320-005 Scavenger Tails Pump (6320-PSL-005) Primary - MC
C-6320-MC-1990 TIP 6320-014 1st Cleaner Feed Pump (6320-PSL-003) Primary - MC 1 04-Jan-25 04-Jan-25 TIP 6320-014 1st Cleaner Feed Pump (6320-PSL-003) Primary - MC
C-6320-MC-2000 TIP 6320-015 1st Cleaner Feed Pump (6320-PSL-004) Primary - MC 1 04-Jan-25 04-Jan-25 TIP 6320-015 1st Cleaner Feed Pump (6320-PSL-004) Primary - MC
C-6320-MC-2070 TIP 6320-022 Static Screen O/S Chute (6320-CFD-001) Secondary - MC 5 04-Jan-25 08-Jan-25 TIP 6320-022 Static Screen O/S Chute (6320-CFD-001) Secondary - MC
C-6320-PI-1900 TIP 6320-006 Scavenger Tails Pump (6320-PSL-005) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-006 Scavenger Tails Pump (6320-PSL-005) Primary - PI
C-6320-PI-1910 TIP 6320-007 Scavenger Tails Pump (6320-PSL-005) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-007 Scavenger Tails Pump (6320-PSL-005) Primary - PI
C-6320-PI-1920 TIP 6320-008 Regrind Mill Feed Pump Box (6320-PPB-001) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-008 Regrind Mill Feed Pump Box (6320-PPB-001) Primary - PI
C-6320-PI-1930 TIP 6320-009 250-SPR-L03-0383 Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-009 250-SPR-L03-0383 Primary - PI
C-6320-PI-1940 TIP 6320-010 Scavenger Tails Pump (6320-PSL-006) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-010 Scavenger Tails Pump (6320-PSL-006) Primary - PI
C-6320-PI-1950 TIP 6320-011 Scavenger Tails Pump (6320-PSL-006) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-011 Scavenger Tails Pump (6320-PSL-006) Primary - PI
C-6320-PI-1960 TIP 6320-011 Scavenger Tailings Pump Box (6320-PPB-003) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-011 Scavenger Tailings Pump Box (6320-PPB-003) Primary - PI
C-6320-PI-1970 TIP 6320-012 1st Cleaner Feed Pump (6320-PSL-004) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-012 1st Cleaner Feed Pump (6320-PSL-004) Primary - PI
C-6320-PI-1980 TIP 6320-013 1st Cleaner Feed Pump (6320-PSL-003) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-013 1st Cleaner Feed Pump (6320-PSL-003) Primary - PI
C-6320-PI-2010 TIP 6320-016 Regrind Mill Feed Pump #2 (6320-PSL-002) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-016 Regrind Mill Feed Pump #2 (6320-PSL-002) Primary - PI
C-6320-PI-2020 TIP 6320-017 Regrind Mill Feed Pump #1 (6320-PSL-001) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-017 Regrind Mill Feed Pump #1 (6320-PSL-001) Primary - PI
C-6320-PI-2030 TIP 6320-018 Regrind Mill (6320-MLV-001) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-018 Regrind Mill (6320-MLV-001) Primary - PI
C-6320-PI-2040 TIP 6320-019 1st Cleaner Feed Pump Box (6320-PPB-002) Primary - PI 1 05-Dec-24 06-Dec-24 TIP 6320-019 1st Cleaner Feed Pump Box (6320-PPB-002) Primary - PI
C-6320-PI-2050 TIP 6320-020 1st Cleaner Feed Pump Box (6320-PPB-002) Primary - PI 5 05-Dec-24 10-Dec-24 TIP 6320-020 1st Cleaner Feed Pump Box (6320-PPB-002) Primary - PI
C-6390-ST-1005 C - 6390 - Structure - to be removed after distribute Labor 38 28-Jul-24 03-Sep-24 C - 6390 - Structure - to be removed after distribute Labor
C-6390-ST-3050 C-6390 - Structural Erection on the ground - Cell no 2 - 1 st (snug bolting 2 30-Jul-24 31-Jul-24 C-6390 - Structural Erection on the ground - Cell no 2 - 1 st (snug bolting ONLY)
ONLY)
C-6390-ST-3100 C-6390 - Structural Erection on the ground - North 1st (snug bolting ONLY) 2 01-Aug-24 02-Aug-24 C-6390 - Structural Erection on the ground - North 1st (snug bolting ONLY)
C-6390-ST-3150 C-6390 - Structural Erection 1st Floor 4 03-Aug-24 06-Aug-24 C-6390 - Structural Erection 1st Floor
C-6390-ST-3200 C-6390 - Structural Erection on the ground - Stairs 2 nd (snug bolting ONLY) 2 03-Aug-24 04-Aug-24 C-6390 - Structural Erection on the ground - Stairs 2 nd (snug bolting ONLY)
C-6390-ST-3250 C-6390 - Structural Erection on the ground - Cell no 2 - 2 nd (snug bolting 2 05-Aug-24 06-Aug-24 C-6390 - Structural Erection on the ground - Cell no 2 - 2 nd (snug bolting ONLY)
ONLY)
C-6390-ST-3300 C-6390 - Structural Erection on the ground - North 2nd (snug bolting ONLY) 2 07-Aug-24 08-Aug-24 C-6390 - Structural Erection on the ground - North 2nd (snug bolting ONLY)
C-6390-ST-3350 C-6390 - Structural Erection 2nd Floor 4 08-Aug-24 11-Aug-24 C-6390 - Structural Erection 2nd Floor
C-6390-ST-3400 C-6390 - Structural Erection on the ground - Stairs 3 rd (snug bolting ONLY) 2 09-Aug-24 10-Aug-24 C-6390 - Structural Erection on the ground - Stairs 3 rd (snug bolting ONLY)
C-6390-ST-3450 C-6390 - Structural Erection on the ground - Cell no 2 - 3 rd (snug bolting 2 11-Aug-24 12-Aug-24 C-6390 - Structural Erection on the ground - Cell no 2 - 3 rd (snug bolting ONLY)
ONLY)
C-6390-ST-3500 C-6390 - Structural Erection on the ground - North 3rd (snug bolting ONLY) 2 13-Aug-24 14-Aug-24 C-6390 - Structural Erection on the ground - North 3rd (snug bolting ONLY)
C-6390-ST-3550 C-6390 - Structural Erection 3rd Floor 4 14-Aug-24 17-Aug-24 C-6390 - Structural Erection 3rd Floor
C-6390-ST-3600 C-6390 - Plumbing and Torque (from Stair Case to Cell 01) 6 17-Aug-24 22-Aug-24 C-6390 - Plumbing and Torque (from Stair Case to Cell 01)
Mechanical 187 02-Aug-24 16-Feb-25 16-Feb-25, Mechanical
C-6390-CO-4060 C-6390 - Piping support fundations 10 02-Aug-24 11-Aug-24 C-6390 - Piping support fundations
C-6390-MC-3660 C-6390 - Mechanical - Pipe Support - ALL 6390 30 12-Aug-24 10-Sep-24 C-6390 - Mechanical - Pipe Support - ALL 6390
C-6390-MC-1005 6390 - Ultra-Fine Flotation Cell - Mechanical Labor 156 02-Sep-24 16-Feb-25 6390 - Ultra-Fine Flotation Cell - Mechanical Labor
C-6390-MC-3860 C-6390 - Commissionning 20 28-Jan-25 16-Feb-25 C-6390 - Commissionning
Piping 106 22-Oct-24 16-Feb-25 16-Feb-25, Piping
C-6390-PI-3000 C-6390 - Line 6390-300-SPR-L03-3016 14 22-Oct-24 04-Nov-24 C-6390 - Line 6390-300-SPR-L03-3016
C-6390-PI-3800 C-6390 - Line 6390-500-SPR-L03-3033 14 22-Oct-24 04-Nov-24 C-6390 - Line 6390-500-SPR-L03-3033
C-6390-PI-3400 C-6390 - Line 6390-300-SPR-L03-3016 14 28-Oct-24 10-Nov-24 C-6390 - Line 6390-300-SPR-L03-3016
C-6390-PI-3050 C-6390 - Line 6390-500-SPR-L03-3031 14 14-Nov-24 27-Nov-24 C-6390 - Line 6390-500-SPR-L03-3031
C-6390-PI-3100 C-6390 - Line 6390-450-SPR-L03-3047 7 14-Nov-24 20-Nov-24 C-6390 - Line 6390-450-SPR-L03-3047
C-6390-PI-3450 C-6390 - Line 6390-500-SPR-L03-3062 (Model 3D 3032) 5 16-Nov-24 20-Nov-24 C-6390 - Line 6390-500-SPR-L03-3062 (Model 3D 3032)
C-6390-PI-3850 C-6390 - Line 6390-350-SPR-L03-3051 5 19-Nov-24 23-Nov-24 C-6390 - Line 6390-350-SPR-L03-3051
C-6390-PI-3900 C-6390 - Line 6390-350-SPR-L03-3050 5 19-Nov-24 23-Nov-24 C-6390 - Line 6390-350-SPR-L03-3050
C-6390-PI-4150 C-6390 - Line 6390-300-SPR-L03-3026 7 19-Nov-24 25-Nov-24 C-6390 - Line 6390-300-SPR-L03-3026
C-6390-PI-3150 C-6390 - Line 6390-450-SPR-L03-3046 7 24-Nov-24 30-Nov-24 C-6390 - Line 6390-450-SPR-L03-3046
C-6390-PI-3500 C-6390 - Line 6390-450-SPR-L03-3049 7 24-Nov-24 30-Nov-24 C-6390 - Line 6390-450-SPR-L03-3049
C-6390-PI-3550 C-6390 - Line 6390-450-SPR-L03-3048 7 24-Nov-24 30-Nov-24 C-6390 - Line 6390-450-SPR-L03-3048
C-6390-PI-3200 C-6390 - Line 6390-450-SPR-L03-3004 4 04-Feb-25 07-Feb-25 C-6390 - Line 6390-450-SPR-L03-3004
C-6390-PI-3300 C-6390 - Line 6390-500-SPR-L03-3002 3 04-Feb-25 06-Feb-25 C-6390 - Line 6390-500-SPR-L03-3002
C-6390-PI-3250 C-6390 - Line 6390-450-SPR-L03-3005 4 07-Feb-25 10-Feb-25 C-6390 - Line 6390-450-SPR-L03-3005
C-6390-PI-3350 C-6390 - Line 6390-500-SPR-L03-3003 3 07-Feb-25 09-Feb-25 C-6390 - Line 6390-500-SPR-L03-3003
C-6390-PI-3600 C-6390 - Line 6390-500-SPR-L03-3014 4 08-Feb-25 11-Feb-25 C-6390 - Line 6390-500-SPR-L03-3014
C-6390-PI-3700 C-6390 - Line 6390-500-SPR-L03-3012 3 08-Feb-25 10-Feb-25 C-6390 - Line 6390-500-SPR-L03-3012
C-6390-PI-3950 C-6390 - Line 6390-400-SPR-L03-3024 4 09-Feb-25 12-Feb-25 C-6390 - Line 6390-400-SPR-L03-3024
C-6390-PI-4050 C-6390 - Line 6390-450-SPR-L03-3022 4 09-Feb-25 12-Feb-25 C-6390 - Line 6390-450-SPR-L03-3022
C-6390-PI-3650 C-6390 - Line 6390-500-SPR-L03-3015 4 11-Feb-25 14-Feb-25 C-6390 - Line 6390-500-SPR-L03-3015
C-6390-PI-3750 C-6390 - Line 6390-500-SPR-L03-3013 3 11-Feb-25 13-Feb-25 C-6390 - Line 6390-500-SPR-L03-3013
C-6390-PI-4000 C-6390 - Line 6390-16-SPR-L03-3025 4 13-Feb-25 16-Feb-25 C-6390 - Line 6390-16-SPR-L03-3025
C-6390-PI-4100 C-6390 - Line 6390-450-SPR-L03-3023 4 13-Feb-25 16-Feb-25 C-6390 - Line 6390-450-SPR-L03-3023
Electrical & Instrumentation
Instrumentati 183 18-Aug-24 01-Mar-25 01-Mar-25, Electrical & Instrumentation
C-6390-EL-3000 6390 - Ultra-Fine Flotation Cell - Cable Tray 60 18-Aug-24 16-Oct-24 6390 - Ultra-Fine Flotation Cell - Cable Tray
C-6390-EL-3050 6390 - Ultra-Fine Flotation Cell - Cable Pulling 50 30-Oct-24 19-Dec-24 6390 - Ultra-Fine Flotation Cell - Cable Pulling
C-6390-EL-3100 6390 - Ultra-Fine Flotation Cell - Connection 10 09-Nov-24 19-Nov-24 6390 - Ultra-Fine Flotation Cell - Connection
C-6390-EL-3150 6390 - Ultra-Fine Flotation Cell - Motor Bumping and Start up 10 23-Nov-24 02-Dec-24 6390 - Ultra-Fine Flotation Cell - Motor Bumping and Start up
C-6390-IN-3000 6390 - Ultra-Fine Flotation Cell - Programmation 40 20-Jan-25 01-Mar-25 6390 - Ultra-Fine Flotation Cell - Programmation
C-6390-IN-3010 6390 - Ultra-Fine Flotation Cell - 6390-LIT-0121/0221/0321 - Instrumentation 40 20-Jan-25 01-Mar-25 6390 - Ultra-Fine Flotation Cell - 6390-LIT-0121/0221/0321 - Instrumentation
C-6390-IN-3020 6390 - Ultra-Fine Flotation - 40 20-Jan-25 01-Mar-25 6390 - Ultra-Fine Flotation - 6390-FE/FT-0138/0148/0238/0248/0338/0348/0618/0628/0285/0619/0465/0134/0540/0955/0472/0334
6390-FE/FT-0138/0148/0238/0248/0338/0348/0618/0628/0285/0619/0465/013
C-6390-IN-1020 6390 - Ultra-Fine Flotation Cell - Valves - Instrumentation 40 20-Jan-25 01-Mar-25 6390 - Ultra-Fine Flotation Cell - Valves - Instrumentation
Structural Tie-In 4 17-Aug-24 20-Aug-24 20-Aug-24, Structural Tie-In
C-6390-ST-2080 TIP 6390-001 Strucure and Concrete Slab Primary - ST 4 17-Aug-24 20-Aug-24 TIP 6390-001 Strucure and Concrete Slab Primary - ST
Instrumentation Tie-In 10 10-Sep-24 19-Sep-24 19-Sep-24, Instrumentation Tie-In
C-6390-IN-2110 TIP 6390-004 Cleaner Scalper Cell (6390-FCL-003) - IN 5 10-Sep-24 14-Sep-24 TIP 6390-004 Cleaner Scalper Cell (6390-FCL-003) - IN
C-6390-IN-2090 TIP 6390-002 Rougher Feed Scalper Cell (6390-FCL-001) - IN 5 15-Sep-24 19-Sep-24 TIP 6390-002 Rougher Feed Scalper Cell (6390-FCL-001) - IN
C-6390-IN-2100 TIP 6390-003 Rougher Tailings Cell (6390-FCL-002) - IN 5 15-Sep-24 19-Sep-24 TIP 6390-003 Rougher Tailings Cell (6390-FCL-002) - IN
Mechanical - Lower Section
Sectio 86 02-Sep-24 26-Nov-24 26-Nov-24, Mechanical - Lower Section
Mechanical 86 02-Sep-24 26-Nov-24 26-Nov-24, Mechanical
C-6390-MC-3600 C-6390 - Mechanical - 1 - Platework - Pumpbox - Rougher Scalper 15 02-Sep-24 16-Sep-24 C-6390 - Mechanical - 1 - Platework - Pumpbox - Rougher Scalper
C-6390-MC-3620 C-6390 - Mechanical - 2 - Platework - Pumpbox - Rougher Tail 15 02-Sep-24 16-Sep-24 C-6390 - Mechanical - 2 - Platework - Pumpbox - Rougher Tail
C-6390-MC-3640 C-6390 - Mechanical - 3 - Platework - Pumpbox - Cleaner Scalper 15 02-Sep-24 16-Sep-24 C-6390 - Mechanical - 3 - Platework - Pumpbox - Cleaner Scalper
C-6390-MC-3720 C-6390 - Mechanical - Slurry Pumps 6390-PSL-001-002 4 14-Nov-24 17-Nov-24 C-6390 - Mechanical - Slurry Pumps 6390-PSL-001-002
C-6390-MC-3780 C-6390 - Mechanical - Slurry Pumps 6390-PSL-005-006 4 18-Nov-24 21-Nov-24 C-6390 - Mechanical - Slurry Pumps 6390-PSL-005-006
C-6390-MC-3840 C-6390 - Mechanical - Slurry Pumps 6390-PSL-009-010 4 23-Nov-24 26-Nov-24 C-6390 - Mechanical - Slurry Pumps 6390-PSL-009-010
Mechanical - Middle Section
Sectio 11 30-Aug-24 09-Sep-24 09-Sep-24, Mechanical - Middle Section
Mechanical 11 30-Aug-24 09-Sep-24 09-Sep-24, Mechanical
C-6390-MC-3680 C-6390 - Mechanical - Platework - Cleaner Scalper Cell External Recycle 6 30-Aug-24 04-Sep-24 C-6390 - Mechanical - Platework - Cleaner Scalper Cell External Recycle Mechanism 6390-TNK-001
Mechanism 6390-TNK-001
C-6390-MC-3740 C-6390 - Mechanical - Platework - Cleaner Scalper Cell External Recycle 6 01-Sep-24 06-Sep-24 C-6390 - Mechanical - Platework - Cleaner Scalper Cell External Recycle Mechanism 6390-TNK-002
Mechanism 6390-TNK-002
C-6390-MC-3800 C-6390 - Mechanical - Platework - Cleaner Scalper Cell External Recycle 6 04-Sep-24 09-Sep-24 C-6390 - Mechanical - Platework - Cleaner Scalper Cell External Recycle Mechanism 6390-TNK-003
Mechanism 6390-TNK-003
Mechanical - Upper Section
Sectio 11 04-Sep-24 14-Sep-24 14-Sep-24, Mechanical - Upper Section
Mechanical 11 04-Sep-24 14-Sep-24 14-Sep-24, Mechanical
C-6390-MC-3820 C-6390 - Mechanical - Platework - Cleaner Scalper 6390-FLC-003 6 04-Sep-24 09-Sep-24 C-6390 - Mechanical - Platework - Cleaner Scalper 6390-FLC-003
C-6390-MC-3700 C-6390 - Mechanical - Platework - Cleaner Scalper 6390-FLC-001 6 09-Sep-24 14-Sep-24 C-6390 - Mechanical - Platework - Cleaner Scalper 6390-FLC-001
C-6390-MC-3760 C-6390 - Mechanical - Platework - Cleaner Scalper 6390-FLC-002 6 09-Sep-24 14-Sep-24 C-6390 - Mechanical - Platework - Cleaner Scalper 6390-FLC-002
6400 - PreLeach/Leach/CIL & Concentration 263 09-Jun-24 A 13-Mar-25 13-Mar-25, 6400 - PreLeach/Leach/CIL & Concentration
6410 - Pre-Leach Thickener 26 07-Dec-24 13-Jan-25 13-Jan-25, 6410 - Pre-Leach Thickener
Area Milestones 21 11-Dec-24 13-Jan-25 13-Jan-25, Area Milestones
C-6410-MA-1010 6410 - Pre-Leach Thickener - Civil Complete 0 11-Dec-24 6410 - Pre-Leach Thickener - Civil Complete
C-6410-MA-1030 6410 - Pre-Leach Thickener - Mechanical Complete 0 08-Jan-25 6410 - Pre-Leach Thickener - Mechanical Complete
C-6410-MA-1040 6410 - Pre-Leach Thickener - Piping Complete 0 09-Jan-25 6410 - Pre-Leach Thickener - Piping Complete
C-6410-MA-1000 6410 - Pre-Leach Thickener - Complete 0 13-Jan-25 6410 - Pre-Leach Thickener - Complete
C-6410-MA-1060 6410 - Pre-Leach Thickener - Instrumentation Complete 0 13-Jan-25 6410 - Pre-Leach Thickener - Instrumentation Complete
Civil 5 07-Dec-24 11-Dec-24 11-Dec-24, Civil
C-6410-CI-1000 6410 - Pre-Leach Thickener - Civil 5 07-Dec-24 11-Dec-24 6410 - Pre-Leach Thickener - Civil
Mechanical 5 04-Jan-25 08-Jan-25 08-Jan-25, Mechanical
C-6410-MC-1000 6410 - Pre-Leach Thickener - Mechanical 5 04-Jan-25 08-Jan-25 6410 - Pre-Leach Thickener - Mechanical
Electrical & Instrumentation
Instrumentati 5 09-Jan-25 13-Jan-25 13-Jan-25, Electrical & Instrumentation
C-6410-IN-1020 6410 - PreLeach/Leach Thickner - Valves - Instrumentation 5 09-Jan-25 13-Jan-25 6410 - PreLeach/Leach Thickner - Valves - Instrumentation
Pipe Tie-In 1 09-Jan-25 09-Jan-25 09-Jan-25, Pipe Tie-In
C-6410-PI-2120 TIP 6410-001 ILR Area Sump Pump (6260-PSU-001) Primary - PI 1 09-Jan-25 09-Jan-25 TIP 6410-001 ILR Area Sump Pump (6260-PSU-001) Primary - PI
6420 - (CIL) Carbon in Leach 85 07-Dec-24 13-Mar-25 13-Mar-25, 6420 - (CIL) Carbon in Leach
Area Milestones 80 11-Dec-24 13-Mar-25 13-Mar-25, Area Milestones
C-6420-MA-1010 6420 - (CIL) Carbon in Leach - Civil Complete 0 11-Dec-24 6420 - (CIL) Carbon in Leach - Civil Complete
C-6420-MA-1020 6420 - (CIL) Carbon in Leach - Steel Structure Complete 0 18-Jan-25 6420 - (CIL) Carbon in Leach - Steel Structure Complete
C-6420-MA-1030 6420 - (CIL) Carbon in Leach - Mechanical Complete 0 16-Feb-25 6420 - (CIL) Carbon in Leach - Mechanical Complete
C-6420-MA-1040 6420 - (CIL) Carbon in Leach - Piping Complete 0 26-Feb-25 6420 - (CIL) Carbon in Leach - Piping Complete
C-6420-MA-1050 6420 - (CIL) Carbon in Leach - Electrical Complete 0 13-Mar-25 6420 - (CIL) Carbon in Leach - Electrical Complete
C-6420-MA-1000 6420 - (CIL) Carbon in Leach - Complete 0 13-Mar-25 6420 - (CIL) Carbon in Leach - Complete
C-6420-MA-1060 6420 - (CIL) Carbon in Leach - Instrumentation Complete 0 13-Mar-25 6420 - (CIL) Carbon in Leach - Instrumentation Complete
Civil 5 07-Dec-24 11-Dec-24 11-Dec-24, Civil
C-6420-CI-1040 C - 6420 - CIL Carbon in Leach - Civil 5 07-Dec-24 11-Dec-24 C - 6420 - CIL Carbon in Leach - Civil
Structure 30 07-Dec-24 18-Jan-25 18-Jan-25, Structure
C-6420-ST-1030 C - 6420 - CIL Carbon in Leach - Structure 30 07-Dec-24 18-Jan-25 C - 6420 - CIL Carbon in Leach - Structure
Mechanical 44 04-Jan-25 16-Feb-25 16-Feb-25, Mechanical
C-6420-MC-1050 C - 6420 - CIL Carbon in Leach - 6420-PSL-007/008 30 04-Jan-25 02-Feb-25 C - 6420 - CIL Carbon in Leach - 6420-PSL-007/008
C-6420-MC-1030 6420 - Mechanical - CIL Feed Trash Screen & Components 30 18-Jan-25 16-Feb-25 6420 - Mechanical - CIL Feed Trash Screen & Components
Piping 19 08-Feb-25 26-Feb-25 26-Feb-25, Piping
C-6420-PI-1050 6420 - CIL Carbon in Leach - Piping 19 08-Feb-25 26-Feb-25 6420 - CIL Carbon in Leach - Piping
Electrical & Instrumentation
Instrumentati 14 28-Feb-25 13-Mar-25 13-Mar-25, Electrical & Instrumentation
C-6420-EL-1040 C - 6420 - CIL Carbon in Leach - Electrical 14 28-Feb-25 13-Mar-25 C - 6420 - CIL Carbon in Leach - Electrical
C-6420-IN-1000 6420 - CIL Carbon in Leach - Instrumentation 14 28-Feb-25 13-Mar-25 6420 - CIL Carbon in Leach - Instrumentation
C-6420-IN-1020 6420 - CIL Carbon in Leach - Valves - Instrumentation 14 28-Feb-25 13-Mar-25 6420 - CIL Carbon in Leach - Valves - Instrumentation
Mechanical Tie-In 5 18-Jan-25 22-Jan-25 22-Jan-25, Mechanical Tie-In
C-6420-MC-2160 TIP 6420-001 Feed CIL Metallurgical Sampler (6420-SAM-001) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-001 Feed CIL Metallurgical Sampler (6420-SAM-001) Primary - MC
C-6420-MC-2170 TIP 6420-002 Interstage Screen #1 (6420-SCT-001) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-002 Interstage Screen #1 (6420-SCT-001) Primary - MC
C-6420-MC-2180 TIP 6420-003 Interstage Screen #2 (6420-SCT-002) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-003 Interstage Screen #2 (6420-SCT-002) Primary - MC
C-6420-MC-2190 TIP 6420-004 Interstage Screen #3 (6420-SCT-003) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-004 Interstage Screen #3 (6420-SCT-003) Primary - MC
C-6420-MC-2200 TIP 6420-005 Interstage Screen #4 (6420-SCT-004) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-005 Interstage Screen #4 (6420-SCT-004) Primary - MC
C-6420-MC-2210 TIP 6420-006 Interstage Screen #5 (6420-SCT-005) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-006 Interstage Screen #5 (6420-SCT-005) Primary - MC
C-6420-MC-2220 TIP 6420-007 Interstage Screen #6 (6420-SCT-006) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-007 Interstage Screen #6 (6420-SCT-006) Primary - MC
C-6420-MC-2230 TIP 6420-008 CIL Tailings Pump Box (6420-PPB-001) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-008 CIL Tailings Pump Box (6420-PPB-001) Primary - MC
C-6420-MC-2240 TIP 6420-009 CIL Tailings Pump #1 (6420-PSL-007) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-009 CIL Tailings Pump #1 (6420-PSL-007) Primary - MC
C-6420-MC-2250 TIP 6420-010 CIL Tailings Pump #2 (6420-PSL-008) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-010 CIL Tailings Pump #2 (6420-PSL-008) Primary - MC
C-6420-MC-2300 TIP 6420-017 CIL Feed Trash Screen #2 (6420-SCS-004) Secondary - MC 5 18-Jan-25 22-Jan-25 TIP 6420-017 CIL Feed Trash Screen #2 (6420-SCS-004) Secondary - MC
C-6420-MC-2310 TIP 6420-018 Trash Screens Distrubution Box (6420-DIB-004) Secondary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-018 Trash Screens Distrubution Box (6420-DIB-004) Secondary - MC
C-6420-MC-2320 TIP 6420-019 Interstage Screen #7 (6420-SCT-007) Primary - MC 1 18-Jan-25 18-Jan-25 TIP 6420-019 Interstage Screen #7 (6420-SCT-007) Primary - MC
C-6420-MC-2340 TIP 6420-021 CIL Trash Screen #1 Feed Box (6420-DIB-003) Secondary - MC 5 18-Jan-25 22-Jan-25 TIP 6420-021 CIL Trash Screen #1 Feed Box (6420-DIB-003) Secondary - MC
C-6420-PI-2140 TIP 6420-001 Feed CIL Metallurgical Sampler (6420-SAM-001) Primary - PI 1 18-Jan-25 18-Jan-25 TIP 6420-001 Feed CIL Metallurgical Sampler (6420-SAM-001) Primary - PI
C-6420-PI-2150 TIP 6420-001 Feed CIL Metallurgical Sampler (6420-SAM-001) Primary - PI 1 18-Jan-25 18-Jan-25 TIP 6420-001 Feed CIL Metallurgical Sampler (6420-SAM-001) Primary - PI
C-6420-PI-2260 TIP 6420-013 CIL Tailings Pumps (6420-PSL-008) Primary - PI 1 18-Jan-25 18-Jan-25 TIP 6420-013 CIL Tailings Pumps (6420-PSL-008) Primary - PI
C-6420-PI-2270 TIP 6420-014 CIL Tailings Pumps (6420-PSL-007) Primary - PI 1 18-Jan-25 18-Jan-25 TIP 6420-014 CIL Tailings Pumps (6420-PSL-007) Primary - PI
C-6420-PI-2290 TIP 6420-016 50-WTR-C02-0492 Primary - PI 1 18-Jan-25 18-Jan-25 TIP 6420-016 50-WTR-C02-0492 Primary - PI
C-6420-PI-2330 TIP 6420-020 CIL Dsitributor Tank (6420-DIB-001) - PI 5 18-Jan-25 22-Jan-25 TIP 6420-020 CIL Dsitributor Tank (6420-DIB-001) - PI
C-6420-PI-2350 TIP 6420-027 CIL Feed Trash Screen (6420-SCS-001) Primary - PI 1 18-Jan-25 18-Jan-25 TIP 6420-027 CIL Feed Trash Screen (6420-SCS-001) Primary - PI
C-6420-PI-2360 TIP 6420-044 CIL Tailings Pump Box (6420-PPB-001) Primary - PI 1 18-Jan-25 18-Jan-25 TIP 6420-044 CIL Tailings Pump Box (6420-PPB-001) Primary - PI
C-6420-PI-2370 TIP 6420-044 CIL Tailings Pump #2 (6420-PSL-008) Primary - PI 1 18-Jan-25 18-Jan-25 TIP 6420-044 CIL Tailings Pump #2 (6420-PSL-008) Primary - PI
C-6420-PI-2380 TIP 6420-045 CIL Tailings Pump Box (6420-PPB-001) Primary - PI 1 18-Jan-25 18-Jan-25 TIP 6420-045 CIL Tailings Pump Box (6420-PPB-001) Primary - PI
C-6420-PI-2390 TIP 6420-045 CIL Tailings Pump #1 (6420-PSL-007) Primary - PI 1 18-Jan-25 18-Jan-25 TIP 6420-045 CIL Tailings Pump #1 (6420-PSL-007) Primary - PI
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 6 of 7 28-Jun-24 ECFN-3 Master schedule weekly report - for information MF
Actual Level of Effort Critical Remaining Work
TASK filters: so_changes_not_red, so_show_into_report.
Actual Work Milestone
Fruta del Norte 3
Master Schedule Draft
Activity ID Activity Name Remaining Start Finish 2024 2025
Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
C-6420-ST-2280 TIP 6420-015 Structure for new/modified equipment Primary - ST 4 14-Jan-25 18-Jan-25 TIP 6420-015 Structure for new/modified equipment Primary - ST
C-6460-MA-1020 6460 - Au Concentrate Thickening - Steel Structure Complete 0 18-Jan-25 6460 - Au Concentrate Thickening - Steel Structure Complete
C-6460-MA-1000 6460 - Au Concentrate Thickening - Complete 0 18-Jan-25 6460 - Au Concentrate Thickening - Complete
Mechanical 10 27-Aug-24 05-Sep-24 05-Sep-24, Mechanical
C-6460-MC-1000 6460 - Au Concentrate Thickening - Mechanical 10 27-Aug-24 05-Sep-24 6460 - Au Concentrate Thickening - Mechanical
Piping 1 05-Sep-24 05-Sep-24 05-Sep-24, Piping
C-6460-PI-1000 6460 - Au Concentrate Thickening - Piping 1 05-Sep-24 05-Sep-24 6460 - Au Concentrate Thickening - Piping
Electrical & Instrumentation
Instrumentati 99 06-Sep-24 14-Dec-24 14-Dec-24, Electrical & Instrumentation
C-6460-IN-1000 6460 - Au Concentrate Thickening - Instrumentation 10 06-Sep-24 15-Sep-24 6460 - Au Concentrate Thickening - Instrumentation
C-6460-IN-1020 6460 - Au Concentrate Thickening - Valves - Instrumentation 10 04-Dec-24 14-Dec-24 6460 - Au Concentrate Thickening - Valves - Instrumentation
C-6470-CO-1100 6470 - Au Concentrate Filtration & Handling - Civil Labor 56 14-Jun-24 08-Aug-24 6470 - Au Concentrate Filtration & Handling - Civil Labor
C-6470-CO-3100 6470 - Au Concentrate Filtration & Handling - Formwork and Rebars - 0 17-Jun-24 A 21-Jun-24 A 6470 - Au Concentrate Filtration & Handling - Formwork and Rebars - Foundation - Footing
Foundation - Footing
C-6470-CO-3150 6470 - Au Concentrate Filtration & Handling - Footing Concrete Pour 0 22-Jun-24 A 22-Jun-24 A 6470 - Au Concentrate Filtration & Handling - Footing Concrete Pour
C-6470-CO-3250 6470 - Au Concentrate Filtration & Handling - Formwork and Rebars - 18 23-Jun-24 A 29-Jun-24 6470 - Au Concentrate Filtration & Handling - Formwork and Rebars - Foundation - Piers and Wall Phase 01
Foundation - Piers and Wall Phase 01
C-6470-CO-3200 6470 - Au Concentrate Filtration & Handling - Curing 0 23-Jun-24 A 23-Jun-24 A 6470 - Au Concentrate Filtration & Handling - Curing
C-6470-CO-3300 6470 - Au Concentrate Filtration & Handling - Piers & Wall Concrete Pour 1 01-Jul-24 01-Jul-24 6470 - Au Concentrate Filtration & Handling - Piers & Wall Concrete Pour
C-6470-CO-3350 6470 - Au Concentrate Filtration & Handling - Curing 8 01-Jul-24 08-Jul-24 6470 - Au Concentrate Filtration & Handling - Curing
C-6470-CO-3400 6470 - Au Concentrate Filtration & Handling - Formwork Removal 2 04-Jul-24 05-Jul-24 6470 - Au Concentrate Filtration & Handling - Formwork Removal
C-6470-CO-3850 6470 - Au Concentrate Filtration & Handling - Structural Backfill - Outside Wall 6 05-Jul-24 10-Jul-24 6470 - Au Concentrate Filtration & Handling - Structural Backfill - Outside Wall (check)
(check)
C-6470-CO-3450 6470 - Au Concentrate Filtration & Handling - Formwork and Rebars - 6 06-Jul-24 11-Jul-24 6470 - Au Concentrate Filtration & Handling - Formwork and Rebars - Foundation - Piers and Wall Phase 02
Foundation - Piers and Wall Phase 02
C-6470-CO-3650 6470 - Au Concentrate Filtration & Handling - Structural Backfill to Slab Level 4 11-Jul-24 14-Jul-24 6470 - Au Concentrate Filtration & Handling - Structural Backfill to Slab Level
C-6470-CO-3500 6470 - Au Concentrate Filtration & Handling - Piers & Wall Concrete Pour 1 12-Jul-24 12-Jul-24 6470 - Au Concentrate Filtration & Handling - Piers & Wall Concrete Pour
C-6470-CO-3550 6470 - Au Concentrate Filtration & Handling - Curing 3 13-Jul-24 15-Jul-24 6470 - Au Concentrate Filtration & Handling - Curing
C-6470-CO-3050 6470 - Au Concentrate Filtration & Handling - Demolition and cleaning existing 6 15-Jul-24* 20-Jul-24 6470 - Au Concentrate Filtration & Handling - Demolition and cleaning existing wall (option to cut the walls)
wall (option to cut the walls)
C-6470-CO-3600 6470 - Au Concentrate Filtration & Handling - Formwork Removal 2 15-Jul-24 16-Jul-24 6470 - Au Concentrate Filtration & Handling - Formwork Removal
C-6470-CO-3700 6470 - Au Concentrate Filtration & Handling - Formwork and Rebars - 6 17-Jul-24 22-Jul-24 6470 - Au Concentrate Filtration & Handling - Formwork and Rebars - Foundation - Slab on Grade
Foundation - Slab on Grade
C-6470-CO-3750 6470 - Au Concentrate Filtration & Handling - Slab on Grade Concrete Pour 1 23-Jul-24 23-Jul-24 6470 - Au Concentrate Filtration & Handling - Slab on Grade Concrete Pour
C-6470-CO-3800 6470 - Au Concentrate Filtration & Handling - Curing 4 24-Jul-24 27-Jul-24 6470 - Au Concentrate Filtration & Handling - Curing
C-6470-CO-3900 6470 - Au Concentrate Filtration & Handling - Compressor slabs & other landing 6 24-Jul-24 29-Jul-24 6470 - Au Concentrate Filtration & Handling - Compressor slabs & other landing stairs Concrete works (chk)
stairs Concrete works (chk)
C-6470-CO-3950 6470 - Au Concentrate Filtration & Handling - Formwork and Rebars - 6 29-Jul-24 03-Aug-24 6470 - Au Concentrate Filtration & Handling - Formwork and Rebars - Foundation - Filter Operation Floor
Foundation - Filter Operation Floor
C-6470-CO-4000 6470 - Au Concentrate Filtration & Handling - Filter Operation Floor Concrete 1 04-Aug-24 04-Aug-24 6470 - Au Concentrate Filtration & Handling - Filter Operation Floor Concrete Pour
Pour
C-6470-CO-4050 6470 - Au Concentrate Filtration & Handling - Curing 4 05-Aug-24 08-Aug-24 6470 - Au Concentrate Filtration & Handling - Curing
Structure 125 26-Jul-24 27-Nov-24 27-Nov-24, Structure
C-6470-ST-3000 6470 - Au Concentrate Filtration & Handling - Structural Erection 1st Floor 17 26-Jul-24 11-Aug-24 6470 - Au Concentrate Filtration & Handling - Structural Erection 1st Floor (Including Decking)
(Including Decking)
C-6470-ST-3050 6470 - Au Concentrate Filtration & Handling - Structural Erection 2nd Phase 17 06-Nov-24 22-Nov-24 6470 - Au Concentrate Filtration & Handling - Structural Erection 2nd Phase
C-6470-ST-3100 6470 - Au Concentrate Filtration & Handling - Structural Roof 2 22-Nov-24 23-Nov-24 6470 - Au Concentrate Filtration & Handling - Structural Roof
C-6470-ST-3150 6470 - Au Concentrate Filtration & Handling - Structural Walls and Opening 4 24-Nov-24 27-Nov-24 6470 - Au Concentrate Filtration & Handling - Structural Walls and Opening
C-6470-MC-3100 6470 - Au Concentrate Filtration & Handling - Compressor Installation 20 17-Oct-24 05-Nov-24 6470 - Au Concentrate Filtration & Handling - Compressor Installation
C-6470-MC-2005 6470 - Au Concentrate Filtration & Handling- Mechanical Labor 58 17-Oct-24 13-Dec-24 6470 - Au Concentrate Filtration & Handling- Mechanical Labor
C-6470-MC-2000 6470 - Au Concentrate Filtration & Handling- Mechanical - Plate work - 30 05-Nov-24 04-Dec-24 6470 - Au Concentrate Filtration & Handling- Mechanical - Plate work - 6470-CFD-007/008/009 6470-TNK-009
6470-CFD-007/008/009 6470-TNK-009
C-6470-MC-3200 6470 - Au Concentrate Filtration & Handling - Filter Press Mechanical Final 20 05-Nov-24 24-Nov-24 6470 - Au Concentrate Filtration & Handling - Filter Press Mechanical Final adjustment
adjustment
C-6470-MC-2010 6470 - Au Concentrate Filtration & Handling- Mechanical - 6470-PSL-004 - 30 14-Nov-24 13-Dec-24 6470 - Au Concentrate Filtration & Handling- Mechanical - 6470-PSL-004 - Installation
Installation
C-6470-MC-2020 6470 - Au Concentrate Filtration & Handling - Mechanical - 6470-PSL-005 - 30 14-Nov-24 13-Dec-24 6470 - Au Concentrate Filtration & Handling - Mechanical - 6470-PSL-005 - Installation
Installation
C-6470-MC-3250 6470 - Au Concentrate Filtration & Handling - Commissionning 15 03-Dec-24 17-Dec-24 6470 - Au Concentrate Filtration & Handling - Commissionning
Piping 15 15-Oct-24 29-Oct-24 29-Oct-24, Piping
C-6470-PI-3000 6470 - Au Concentrate Filtration & Handling - Line 6390-xxx-SPR-L03-3024 15 15-Oct-24 29-Oct-24 6470 - Au Concentrate Filtration & Handling - Line 6390-xxx-SPR-L03-3024
C-6470-EL-3050 6470 - Au Concentrate Filtration & Handling - Cable Pulling 25 13-Nov-24 07-Dec-24 6470 - Au Concentrate Filtration & Handling - Cable Pulling
C-6470-EL-3100 6470 - Au Concentrate Filtration & Handling - Connection 10 23-Nov-24 02-Dec-24 6470 - Au Concentrate Filtration & Handling - Connection
C-6470-IN-3010 6470 - Au Concentrate Filtration & Handling - 6470-PIT-0461 - Instrumentation 30 23-Nov-24 03-Jan-25 6470 - Au Concentrate Filtration & Handling - 6470-PIT-0461 - Instrumentation
C-6470-IN-3000 6470 - Au Concentrate Filtration & Handling - Programmation 15 03-Dec-24 17-Dec-24 6470 - Au Concentrate Filtration & Handling - Programmation
C-6470-IN-1020 6470 - Au Concentrate Filtration & Handling - Valves - Instrumentation 30 20-Jan-25 19-Feb-25 6470 - Au Concentrate Filtration & Handling - Valves - Instrumentation
C-6470-MC-2560 TIP 6470-014 Filter Press Air Receiver (6470-AIR-003) Secondary - MC 5 20-Nov-24 24-Nov-24 TIP 6470-014 Filter Press Air Receiver (6470-AIR-003) Secondary - MC
C-6470-MC-2570 TIP 6470-015 Filter Press Air Receiver (6470-AIR-004) Secondary - MC 5 20-Nov-24 24-Nov-24 TIP 6470-015 Filter Press Air Receiver (6470-AIR-004) Secondary - MC
C-6470-MC-2480 TIP 6470-006 Concentrate Filter Feed Pump (6470-PSL-004) Primary - MC 1 24-Nov-24 24-Nov-24 TIP 6470-006 Concentrate Filter Feed Pump (6470-PSL-004) Primary - MC
C-6470-MC-2490 TIP 6470-007 Concentrate Filter Feed Pump (6470-PSL-005) Primary - MC 1 24-Nov-24 24-Nov-24 TIP 6470-007 Concentrate Filter Feed Pump (6470-PSL-005) Primary - MC
C-6470-PI-2450 TIP 6470-003 Concentrate Filter Feed Tank (6470-TNK-001) Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6470-003 Concentrate Filter Feed Tank (6470-TNK-001) Primary - PI
C-6470-PI-2460 TIP 6470-004 25-WGS-C02-1582 Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6470-004 25-WGS-C02-1582 Primary - PI
C-6470-PI-2470 TIP 6470-005 25-WGS-C02-1523 Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6470-005 25-WGS-C02-1523 Primary - PI
C-6470-PI-2500 TIP 6470-008 Filter Tank (6470-TNK-002) Primary - PI 1 15-Oct-24 15-Oct-24 TIP 6470-008 Filter Tank (6470-TNK-002) Primary - PI
C-6470-PI-2510 TIP 6470-009 Filter Tank (6470-TNK-002) Primary - PI 5 15-Oct-24 19-Oct-24 TIP 6470-009 Filter Tank (6470-TNK-002) Primary - PI
C-6470-PI-2520 TIP 6470-010 Filter Tank (6470-TNK-002) Primary - PI 5 15-Oct-24 19-Oct-24 TIP 6470-010 Filter Tank (6470-TNK-002) Primary - PI
C-6470-PI-2540 TIP 6470-012 100-WPR-C02-2441 Primary - PI 5 15-Oct-24 19-Oct-24 TIP 6470-012 100-WPR-C02-2441 Primary - PI
C-6470-PI-2580 TIP 6470-016 Concentrate Filter Feed Tank (6470-TNK-001) - PI 5 15-Oct-24 19-Oct-24 TIP 6470-016 Concentrate Filter Feed Tank (6470-TNK-001) - PI
C-6720-MC-4320 TIP 6720-004-M Tailings Feed Pump 2nd Stage (6720-PSL-002) -MC 5 21-Nov-24 25-Nov-24 TIP 6720-004-M Tailings Feed Pump 2nd Stage (6720-PSL-002) -MC
C-6720-MC-4340 TIP 6720-005-M Tailings & Paste Plant Feed Pump 1st Stage 5 21-Nov-24 25-Nov-24 TIP 6720-005-M Tailings & Paste Plant Feed Pump 1st Stage (6720-PSL-005)-MC
(6720-PSL-005)-MC
C-6720-MC-4360 TIP 6720-006-M Tailings & Paste Plant Feed Pump 2nd Stage 5 21-Nov-24 25-Nov-24 TIP 6720-006-M Tailings & Paste Plant Feed Pump 2nd Stage (6720-PSL-006)-MC
(6720-PSL-006)-MC
C-6720-MC-4370 TIP 6720-007 Tailings Cyclone Cluster Feed Pump Box (6720-PPB-002)-MC 5 21-Nov-24 25-Nov-24 TIP 6720-007 Tailings Cyclone Cluster Feed Pump Box (6720-PPB-002)-MC
C-6720-EL-4310 TIP 6720-004-E Tailings Feed Pump 2nd Stage (6720-PSL-002) -EL 5 21-Nov-24 25-Nov-24 TIP 6720-004-E Tailings Feed Pump 2nd Stage (6720-PSL-002) -EL
C-6720-EL-4330 TIP 6720-005-E Tailings & Paste Plant Feed Pump 1st Stage 5 21-Nov-24 25-Nov-24 TIP 6720-005-E Tailings & Paste Plant Feed Pump 1st Stage (6720-PSL-005)-EL
(6720-PSL-005)-EL
C-6720-EL-4350 TIP 6720-006-E Tailings & Paste Plant Feed Pump 2nd Stage 5 21-Nov-24 25-Nov-24 TIP 6720-006-E Tailings & Paste Plant Feed Pump 2nd Stage (6720-PSL-006)-EL
(6720-PSL-006)-EL
6730 - Cyanide Destruction 20 11-Dec-24 11-Jan-25 11-Jan-25, 6730 - Cyanide Destruction
Area Milestones 0 11-Jan-25 11-Jan-25 11-Jan-25, Area Milestones
C-6730-MA-1040 6730 - Cyanide Destruction - Piping Complete 0 11-Jan-25 6730 - Cyanide Destruction - Piping Complete
C-6730-MA-1030 6730 - Cyanide Destruction - Mechanical Complete 0 11-Jan-25 6730 - Cyanide Destruction - Mechanical Complete
C-6730-MA-1000 6730 - Cyanide Destruction - Complete 0 11-Jan-25 6730 - Cyanide Destruction - Complete
Mechanical 20 11-Dec-24 11-Jan-25 11-Jan-25, Mechanical
C-6730-MC-1000 6730 - Cyanide Destruction - Mechanical 20 11-Dec-24 11-Jan-25 6730 - Cyanide Destruction - Mechanical
Mechanical Tie-In 1 11-Jan-25 11-Jan-25 11-Jan-25, Mechanical Tie-In
C-6730-MC-2620 TIP 6730-002 CIL Tails Metallurgical Sampler (6730-SAM-001) Primary - MC 1 11-Jan-25 11-Jan-25 TIP 6730-002 CIL Tails Metallurgical Sampler (6730-SAM-001) Primary - MC
6800 - Plant Services 133 28-Jun-24 A 21-Oct-24 21-Oct-24, 6800 - Plant Services
6810 - Plant Air 133 28-Jun-24 A 21-Oct-24 21-Oct-24, 6810 - Plant Air
Area Milestones 2 19-Oct-24 21-Oct-24 21-Oct-24, Area Milestones
C-6810-MA-1040 6810 - Plant Air - Piping Complete 0 19-Oct-24 6810 - Plant Air - Piping Complete
C-6810-MA-1030 6810 - Plant Air - Mechanical Complete 0 21-Oct-24 6810 - Plant Air - Mechanical Complete
C-6810-MA-1000 6810 - Plant Air - Complete 0 21-Oct-24 6810 - Plant Air - Complete
Civil 22 28-Jun-24 A 02-Jul-24 02-Jul-24, Civil
C-6810-CI-2640 TIP 6810-001 Filter Press Air Compressor #1 Foundation 22 28-Jun-24 A 02-Jul-24 TIP 6810-001 Filter Press Air Compressor #1 Foundation
C-6810-CI-2650 TIP 6810-001 Filter Press Air Compressor #1 (6810-DDC-004) Primary - 22 28-Jun-24 A 02-Jul-24 TIP 6810-001 Filter Press Air Compressor #1 (6810-DDC-004) Primary - Foundation
Foundation
Mechanical Tie-In 5 17-Oct-24 21-Oct-24 21-Oct-24, Mechanical Tie-In
C-6810-MC-2640 TIP 6810-001 Filter Press Air Compressor #1 (6810-DDC-004) Primary - MC 5 17-Oct-24 21-Oct-24 TIP 6810-001 Filter Press Air Compressor #1 (6810-DDC-004) Primary - MC
C-6810-MC-2650 TIP 6810-002 Filter Press Air Compressor #2 (6810-DDC-005) Primary - MC 5 17-Oct-24 21-Oct-24 TIP 6810-002 Filter Press Air Compressor #2 (6810-DDC-005) Primary - MC
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 7 of 7 28-Jun-24 ECFN-3 Master schedule weekly report - for information MF
Actual Level of Effort Critical Remaining Work
TASK filters: so_changes_not_red, so_show_into_report.
Actual Work Milestone