SITGES

LIFTING PLAN
1. GENERAL
Project PMPHSA (PROJEK MAKMAL PATOLOGI HSA JB JOHOR)
Location of lifting operation BLOK PATOLOGI
Contractor carrying out the -SITGES ENGINEERING Date/ time of lifting 29/12/2021 @ 8.00 AM
lifting operation SDN BHD / operation
-SBI TERAS VENTURES Validity period of lifting 1 HARI
SDN BHD 29/12/2021 @ 5.00PM
operation
2. DETAILS OF THE LOAD/S
Description of load/s Blower pipe
Overall dimensions 300mm x meter
Weight of load 10 x 60kg = 600 Kg /ton Known weight Estimated weight
Centre of gravity  Obvious Estimated Determined by drawing
3. DETAILS OF THE LIFTING EQUIPMENT / LIFTING GEARS
Type of lifting equipment: MOBILE CRANE GC = NC+HB+SB+ RM = 600 + 750 + 120 + 80 = 1550 KG
Maximum SWL as certified on 25 TAN Date of last 30/6/2022
the LM cert: certification:
Max boom / Jib length: At LOAD = 9.050 Ton Fly jib / offset: No need
BOOM Length = 39.6 M
Intended load radius: Distance load and crane SWL at this radius: F.O.S = load = 9.05 = 12.07 TON
AT LOAD 9.050 Ton (Not more than 75%) 75% 75%
RADIUS = 12.0 M So, SWL = 12.07 TON
Type of lifting gears: Slings / webbing / chains / shackles / spreader beam / receptacle
Combined weight of the lifting HB = 750KG, RM = 80KG Certification of lifting SWL Lifting Gear :
gears: SB = 120KG gears: Hook = 5 T Shackle = 5T
TOTAL = 950 kg, @ 0.95 ton Yes No Sling = 5T Eye Bolt = 5T
SWL of LG: 5.0 TON Kg / tonne
Crane Capacity % maximum: Crane capacity: < 75% Safety Factor: > 1.33 Max Capacity at load chart = 12.10 ton
= load = 9.05 ton = 74.79% SWL = 12.10 = 1.34 Max Boom Length = 45.70 m
SWL 12.10 ton < 75% Max Working Radius = 9.5 m
LOAD 9.05 > 1.33
4. MEANS OF COMMUNICATIONS
Can the operator see the loading and unloading point for the load from his position?
Yes No
What are the means of communication between the lifting crew?
Standard hand signals Radio Others_________________________
5. PERSONNEL INVOLVED IN LIFTING OPERATION
Position Name Qualification/ Experience
Site Supervisor AMIR SUPERVISOR
Lifting Supervisor MOHAMAD NIZAM COMPETENT LS
Crane Operator
Rigger ABDUL MANNAN TRAINED RIGGER
Signalman MOHD JAKIR TRAINED SIGNALMAN
Others (please state) HARMAN BIN USMAN M&E COORDINATOR
6. PHYSICAL AND ENVIRONMENTAL CONSIDERATION (please include any details in the space provided)
Ground conditions Is the ground made safe (e.g., placing steel plate)? Yes No
Are the outriggers evenly extended? Yes No
Obstacles Are there any overhead obstacles such as power lines? Yes No
Are there nearby buildings or structure, equipment or stacked materials that Yes No
may obstruct lifting operation from being carried out safely?
Lighting Is the lighting condition adequate? Yes No
Demarcation Has the zone of operation been barricaded (with warning signs and barriers) to Yes No
prevent unauthorised access?
Environment Do not proceed with the lifting operation under the following circumstances:
Thunder storm and lightning strikes in the area. The ground condition must be
checked after a thunderstorm
Strong winds that may sway the suspended load. Warning (12 knot), Stop Work (15 knot)
Other circumstances (please specify) :
SITGES
7. SEQUENCE / SPECIAL PRECAUTIONS
TBM (TOOL BOX MEETING) FOR LIFTING WORK
BARRICADE & SIGNAGE SURROUND LIFTING ZONE
INSPECTION CHECKLIST : RELATED PERSONNEL / LIFTING ZONE / LIFTING EQUIPMENT / LIFTING GEAR
VALID PTW ( PERMIT TO WORK ) FOR LIFTING WORK
ERP – EMERGENCY RESPONSE PLAN / EMT – EMERGENCY MANAGEMENT TEAM
COLOUR CODING INSPECTION / PASSED STICKER
RISK ASSESSMENT – JHA / JSA / HRA / HIRARC / CHRA
CLEARING ALL OBSTACLES – EQUIPMENT / MATERIAL / DIVERT ACCESS
OTHERS :
OTHERS :

8. SKETCH OF THE ZONE OF OPERATION AND CRANE

If the crane capacity is less the < 75%, So, Crane Capacity = Gross Capacity = 9050.00kg = 12066.66 kg
75% 75%

i. 8100
Weight of the load:_________ kg
ii. 80
Weight of Rigging Materials: __________kg
iii. 750
Weight of main block: _________kg
iv. 120
Weight of Aux Block : _________kg
v. 9050
Total Weight (Gross Capacity):_______kg
vi. 45.70
Boom Length :__________m 120 kg 5.8
Aux: ________ (weight)? Capacity: _______
vii. 9.5
Working Radius :________m ton
viii. 70 º
Boom Angle: _______
ix. 12100
SWL at Load Chart :________kg
x. 74.79
Crane Capacity :_________%
xi. 1.34
Safety Factor : _______
Boom Length = 45.70
________
meter

750 kg (weight)? : _______


Main: ________ 50 ton

SWL 5 TON
Sling: __________
KATO NK50VR

Shackle: SWL 5 TON


_________

Load : _________

Rigging Type : direct hitch Crane capacity (%)


= LOAD = 9050kg = 74.79%
SWL 12100 kg
SAFETY FACTOR
Note: 9.5 meter
Working Radius = ________ SWL = 12100 kg = 1.34
Crane Capacity : < 75%
Safety Factor : > 1.33
LOAD 9050 kg

Applied by: SBI TERAS VENTURE Signature: Date: 15/11/2021


Name: MOHD AIMAN Time: 11.00AM
Prepared by: LIFTING SUPERVISOR Signature: Date: 15/11/2021
Name: MOHD NIZAM ADUN Time: 11.30 AM
Assessed by: SAFETY OFFICER Signature: Date: 15/11/2021
Name: KHAIRUL AZMAN Time: 2.00 PM
Approved by: PROJECT MANAGER Signature: Date: 15/11/2021
Name: MOHD AZHAR ZAINAL Time: 5.00PM