CONSTRUCTION MANAGEMENT MAIN CONTRACTOR PROJECT

DAILY REPORT
( DRP )
Project : INDONESIA 1
Wheather C C C C C C C C C C O O O O O O O O C C C
Date : 20/08/2016
Temp. : 21 C Time
o
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4

MAN POWER QTY ACTIVITY / DONE (TODAY)


1. MANAGEMENT
Project Director 1
Project Manager 2 TC Erection (North TC) exacavation work CB
Site Engineer 4 Material moving: PVC pice and cement CB-I D-Wall demolitio
QS 2 Daily Joint Inspection (CM, RE, QC, SO, Const) rainforced concrete C
QC 5 Installation of formwork earthwork B01-Excav
Supervisor 4 Preparation for concreting
Surveyor 7 Instalation of rebar
Administration & Finance 23 Joint Survey existing Pile
Logistic & Storage 15 Make mock up of of Dwal hacking
HSE Officer 3 Genareal cleaning Nort Side
Security 25
TOTAL 91
2. SKILLED WORKER
Operator TC 4
Riger 2
Other Heavy Eqpt Operator 8
Maintenance -
Welder 2
Foremen -
Mandor 3
TOTAL 19 PROBLEM OCCURRED SOLUTION / REMEDY
3. WORKER
Carpenter/Formwork 21 Electricity is not available due to Cable Feeder Instalation Use genset
Masonry/Stone - Pump cannot used
Steel/rebar 25 Water stagnate at many area at site project Pump have to be rea
Electrical 4 Mechanic officer
Mechanical 4 Have to be standby a
Paint 4 Rebar not move yet covered by soil & dirty water Ceklist to box electric
Cut & Fill - Safety sign not enough
Cleaning 9 Bridge for worker not safe
Waterproofing - Heavy rain, no electricity
Finishing -
Helper 2
Dewatering 15
Other
TOTAL 84
MAIN EQUIPMENT

Item Unit Item Unit Item

EXSAVATOR /PC 200 3 BAR CUTTER 1 STEEL dia. 3

3 PVC pipe (De


PC BRAKER

CRANE 50 T 1
DRILL 1
COMPRESSOR 1
BAR BENDER 1
REMARKS / HIGHLIGHT ITEM or ACTIVITY
Crane 50 ton (north side) on site
Feeder installtion for temporer electricity
Hacking Dwall
General cleaning on site

Prepared by Field Coordinator Verified by Site Engineer Acknowledg


Signature

Name Kasdi Syahrul Dedi Agus


Date 18/08/2016 18/08/2016 18/08/2016
PROJECT EMPLOYER

CHINA SONANGOL
MEDIA INVESTMENT

REPORT
RP )
C : Clear D : Drizzling
C C C C
O : Overcast
5 6 7 8R : Rain

PLAN (TOMORROW)

exacavation work CB-I and CB-J


CB-I D-Wall demolition
rainforced concrete CB-B-RC Work
earthwork B01-Excavation work for z-a1 Z-A1 AND Z-A2

SOLUTION / REMEDY

Pump have to be ready on site

Have to be standby at site


Ceklist to box electrical on site elcb must work properly

MAIN MATERIAL
Unit
STEEL dia. 32,22,25,16,13,10

PVC pipe (Dewatering)


Acknowledge by Construction Manager

18/08/2016
(R.00 - 05082016)
MAIN CONTRACTOR MAIN CONTRACTOR PROJECT

DAILY REPORT
( DRP )
Project : INDONESIA 1
Wheather O O O O O O O O O O O O O
Date :21 AGUSTUS 21016
Temp. : 21 C Time
o
8 9 10 11 12 13 14 15 16 17 18 20 21

MAN POWER QTY DONE (TODAY)


1. MANAGEMENT
Project Director
Project Manager 1 Daily Joint Inspection (CM, RE, QC, SO, Const)
Site Engineer 2 Make mock up of of Dwal hacking
QS 4 Genareal cleaning Nort Side
QC 2 Braker operation demolitionn Dwall
Supervisor 5 cleaning cheaping bim
Surveyor 4 instal rubber at west site
Administration & Finance 7 neatness excavation at sowest
Logistic & Storage 23 moving landfill by subcont acset this start 21.00 until 04.00
HSE Officer 15
Security 3
TOTAL 25
2. SKILLED WORKER 91
Operator TC 4
Riger 2
Other Heavy Eqpt Operator 8
Maintenance -
Welder 2
Foremen -
Mandor 3
TOTAL 19 PROBLEM OCCURRED
3. WORKER
Carpenter/Formwork 21 Safety sign not enough
Masonry/Stone - Bridge for worker not safe
Steel/rebar 25
Electrical 4
Mechanical 4
Paint 4
Cut & Fill -
Cleaning 9
Waterproofing -
Finishing -
Helper 2
Dewatering 15
Other
TOTAL 84
MAIN EQUIPMENT
Item Unit Item
EXSAVATOR /PC 200 4
PC BRAKER 3
CRANE 50 T 1
BOR 1
BAR BENDER 1
BARCUTTER 1
REMARKS / HIGHLIGHT ITEM or ACTIVITY

Crane 50 ton (north side) on site


Hacking Dwall
General cleaning on site
Exavator pc 200 west side on site

Prepared by Field Coordinator Verified by Site Engineer


Signature

Name KASDI SAHRUL


Date 18 AGUSTUS 2016 18 AGUSTUS 2016
PROJECT EMPLOYER

CHINA SONANGOL
MEDIA INVESTMENT

ORT
S : Sunny D : Drizzling
O O O S S S S S S S
O : Overcast
22 23 24 1 2 3 4 5 6 7R : Rain

PLAN (TOMORROW)

exavator pc 78 braker cheaping at norwth side


instal tc 2 at north
inspektion tc 50 at south by depnaker

SOLUTION / REMEDY

Ceklist to box electrical on site elcb must work properly

MAIN MATERIAL
Unit Item Unit
BESI STEEL DIA { 32,16,13,11 }
PVC DEWATERING

Acknowledge by Construction Manager

DEDI AGUS
18 AGUSTUS 2016
(R.00 - 05082016)